Adtec Pre No.21   Mei 09
Upcoming SlideShare
Loading in...5
×
 

Like this? Share it with your network

Share

Adtec Pre No.21 Mei 09

on

  • 976 views

 

Statistics

Views

Total Views
976
Views on SlideShare
958
Embed Views
18

Actions

Likes
0
Downloads
1
Comments
0

3 Embeds 18

http://www.arkamonline.com 16
https://www.mturk.com 1
http://arkamonline2.blogspot.com 1

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

Adtec Pre No.21 Mei 09 Presentation Transcript

  • 1. LAPORAN KEMAJUAN PROJEK NO.22 ‘APRIL 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B
  • 2. ADTEC TAIPING LOKASI PROJEK
  • 3. BANGUNAN PENTADBIRAN BENGKEL TEK. MAKLUMAT & JAMIN KUALITI DEWAN BESAR PUSAT SUMBER DEWAN KULIAH LOBI UTAMA KAFETERIA MIKRO ELEKTRONIK KOMPOSIT PLASTIK M&E PLANT ROOM 1 TNB SUB STATION SERAMIK M&E PLANT ROOM 2 GARAJ KENDERAAN ASRAMA LELAKI ASRAMA PEREMPUAN DEWAN MAKAN SURAU KELAS F KELAS G KUARTERS B, C, C&D PELAN TAPAK ADTEC TAIPING
  • 4. KEMAJUAN KERJA FIZIKAL JADUAL : 85.16 % SEBENAR : 87.59 % KESELURUHAN : 2.43 % TARIKH LAPORAN : 12 JUN 2009
  • 5. KEMAJUAN KERJA KEWANGAN JADUAL : 85.09 % SEBENAR : 86.12 % KESELURUHAN : 1.03 % TARIKH LAPORAN : 12 JUN 2009
  • 6.  
  • 7. KEMAJUAN KERJA FIZIKAL - DEWAN BESAR BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 88.35% 92.38% 4.03% JUN 09’ 94.21% 96.74% 2.53% MECHANICAL PLANNED ACTUAL AIR COND 94.85% 95.50% FIRE FIGHTING 81.61% 95.74% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 95.00% LPS NA NA PA 94.88% 67.17% SMATV 83.38% 86.79% CCTV NA NA ICT 3.31% 74.25%
  • 8. DEWAN BESAR
  • 9. DEWAN BESAR
  • 10. KEMAJUAN KERJA FIZIKAL – LOBI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 98.92% 94.90% -4.02% JUN 09’ 99.68% 99.72% 0.04% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 95.90% 100.00% SUBMAIN CABLE 94.17% 100.00% DB 75.00% 100.00% LUMINAIRE 87.89% 100.00% MAIN S/BOARD NA NA LPS NA NA PA NA NA SMATV NA NA CCTV 88.68% 92.58% ICT NA NA
  • 11. LOBI UTAMA
  • 12. KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 92.24% 91.71% -0.52% JUN 09’ 98.54% 98.19% -0.35% MECHANICAL PLANNED ACTUAL AIR COND 96.19% 95.00% FIRE FIGHTING 81.51% 86.04% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 75.00% 100.00% LUMINAIRE 91.65% 95.00% MAIN S/BOARD 75.00% 95.00% LPS 90.51% 92.01% PA 37.88% 65.71% SMATV NA NA CCTV NA NA ICT 0.91% 74.48%
  • 13. DEWAN KULIAH UTAMA
  • 14. KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 95.30% 95.38% 0.09% JUN 09’ 97.50% 98.54% 1.04% MECHANICAL PLANNED ACTUAL AIR COND 93.54% 85.18% FIRE FIGHTING 39.81% 81.59% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 97.53% 97.00% SUBMAIN CABLE 93.31% 98.00% DB 85.00% 100.00% LUMINAIRE 92.27% 98.00% MAIN S/BOARD 85.00% 95.00% LPS 91.25% 96.92% PA 44.70% 69.69% SMATV 94.54% 88.33% CCTV NA NA ICT 18.16% 23.36%
  • 15. PUSAT SUMBER / PERPUSTAKAAN
  • 16. KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBER BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 92.72% 92.73% 0.01% JUN 09’ 96.42% 96.51% 0.09% MECHANICAL PLANNED ACTUAL AIR COND 91.09% 94.96% FIRE FIGHTING 47.94% 74.24% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 99.48% 97.00% SUBMAIN CABLE 97.32% 98.00% DB 85.00% 100.00% LUMINAIRE 82.78% 95.00% MAIN S/BOARD 75.00% 95.00% LPS 87.80% 90.85% PA 63.70% 58.92% SMATV 95.99% 88.07% CCTV 73.69% 70.43% ICT 24.87% 51.37%
  • 17. BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
  • 18. KEMAJUAN KERJA FIZIKAL - KAFETARIA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 98.36% 98.71% 0.08% JUN 09’ 99.58% 99.23% -0.35% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING 90.22% 74.56% KITCHEN EQUIP. 65.55% 69.00% LPG INSTALL. 40.84% 48.50% COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD NA NA LPS 100.00% 88.81% PA 94.53% 62.91% SMATV 92.47% 87.44% CCTV NA NA ICT 0.00% 75.00%
  • 19. KAFETERIA
  • 20. KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMAT BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 93.95% 95.49% 1.54% JUN 09’ 98.05% 98.01% -0.05% MECHANICAL PLANNED ACTUAL AIR COND 86.90% 91.36% FIRE FIGHTING 31.85% 63.60% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 99.23% 96.00% SUBMAIN CABLE 98.21% 100.00% DB 97.27% 100.00% LUMINAIRE 92.51% 100.00% MAIN S/BOARD 75.00% 95.00% LPS 100.00% 96.80% PA 100.00% 73.49% SMATV 95.09% 89.00% CCTV 79.13% 291.22% ICT 8.53% 19.28%
  • 21. BENGKEL TEKNOLOGI MAKLUMAT
  • 22. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 96.82% 95.67% -1.14% JUN 09’ 98.42% 98.30% -0.12% MECHANICAL PLANNED ACTUAL AIR COND 93.36% 93.41% FIRE FIGHTING 45.37% 72.69% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 87.25% 85.00% DUST CONTROL NA NA PROCESS COOLING 41.53% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 75.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 75.00% 95.00% LPS 92.90% 96.80% PA 62.47% 75.48% SMATV 75.18% 74.39% CCTV 83.97% 93.08% ICT 26.23% 23.86%
  • 23. BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
  • 24. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 97.05% 95.65% -1.40% JUN 09’ 98.46% 98.41% -0.05% MECHANICAL PLANNED ACTUAL AIR COND 80.73% 78.34% FIRE FIGHTING 43.93% 69.10% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 87.25% 85.00% DUST CONTROL 31.69% 77.29% PROCESS COOLING 38.45% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 95.00% LPS 97.29% 93.25% PA 92.78% 72.21% SMATV 75.26% 75.20% CCTV 86.10% 92.75% ICT 21.23% 18.81%
  • 25. BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
  • 26. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 95.12% 94.67% -0.46% JUN 09’ 97.15% 97.14% -0.02% MECHANICAL PLANNED ACTUAL AIR COND 91.33% 92.19% FIRE FIGHTING 44.40% 69.54% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 87.25% 85.00% DUST CONTROL 11.65% 72.95% PROCESS COOLING 21.79% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 99.29% 100.00% DB 78.00% 100.00% LUMINAIRE 96.30% 100.00% MAIN S/BOARD 85.00% 95.00% LPS 90.20% 96.49% PA 96.64% 72.96% SMATV 73.29% 74.70% CCTV 90.23% 93.97% ICT 33.22% 27.44%
  • 27. BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
  • 28. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 94.30% 95.17% -0.87% JUN 09’ 96.50% 96.99% 0.48% MECHANICAL PLANNED ACTUAL AIR COND 82.68% 59.54% FIRE FIGHTING 26.16% 63.17% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 87.25% 85.00% DUST CONTROL 38.25% 80.74% PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 97.67% 96.00% SUBMAIN CABLE 95.02% 97.00% DB 95.02% 95.00% LUMINAIRE 77.98% 90.00% MAIN S/BOARD 57.17% 95.00% LPS 86.74% 96.20% PA 42.25% 68.68% SMATV 87.59% 85.36% CCTV 80.71% 90.90% ICT 7.17% 18.61%
  • 29. BENGKEL KEJ. JAMINAN KUALITI
  • 30. KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIK BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 92.86% 94.80% 1.94% JUN 09’ 95.58% 95.59% 0.01% MECHANICAL PLANNED ACTUAL AIR COND 93.43% 91.50% FIRE FIGHTING 22.33% 59.71% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 87.25% 85.00% DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 96.00% SUBMAIN CABLE 96.67% 95.00% DB 72.68% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 95.00% LPS 92.34% 96.70% PA 52.92% 72.02% SMATV 91.26% 86.86% CCTV 84.11% 91.21% ICT 6.84% 22.94%
  • 31. BENGKEL MIKRO ELEKTRONIK
  • 32. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 100.00% 100.00% 0.00% JUN 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 100.00% LPS 100.00% 95.68% PA NA NA SMATV 84.58% 68.14% CCTV 79.71% 93.15% ICT 100.00% 90.00%
  • 33. KUARTERS KELAS ‘B’
  • 34. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 100.00% 100.00% 0.00% JUN 09’ 100.00% 100.00% 100.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 95.78% PA NA NA SMATV 82.56% 46.09% CCTV NA NA ICT 100.00% 84.06%
  • 35. KUARTERS KELAS ‘C’
  • 36. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 100.00% 100.00% 0.00% JUN 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 96.33% PA NA NA SMATV 84.58% 86.14% CCTV NA NA ICT 100.00% 90.00%
  • 37. KUARTERS KELAS ‘C’ + ‘D’
  • 38. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 97.14% 98.49% 1.36% JUN 09’ 98.63% 98.85% 0.12% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 93.30% 96.98% PA NA NA SMATV 95.77% 93.31% CCTV NA NA ICT 96.04% 92.34%
  • 39. KUARTERS KELAS ‘F’ ( 4 TINGKAT )
  • 40. KUARTERS KELAS ‘F’ ( 5 TINGKAT )
  • 41. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G (1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 97.58% 98.48% 0.90% JUN 09’ 99.57% 99.58% 0.01% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 96.98% PA NA NA SMATV 95.77% 93.31% CCTV NA NA ICT 100.00% 98.37%
  • 42. KUARTERS KELAS ‘G’ ( 5 TINGKAT )
  • 43. KUARTERS KELAS ‘G’ ( 4 TINGKAT )
  • 44. KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 99.42% 99.60% 0.18% JUN 09’ 99.83% 96.63% 0.01% MECHANICAL PLANNED ACTUAL AIR COND 90.95% 100.00% FIRE FIGHTING 57.40% 72.89% KITCHEN EQUIP. 65.55% 69.00% LPG INSTALL. 40.84% 48.50% COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 98.00% DB 100.00% 95.00% LUMINAIRE 100.00% 80.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 97.32% PA 56.87% 73.23% SMATV 92.47% 90.79% CCTV NA NA ICT 100.00% 75.35%
  • 45. DEWAN MAKAN
  • 46. KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & B BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 98.70% 99.43% 0.73% JUN 09’ 99.39% 99.55% 0.16% MECHANICAL PLANNED ACTUAL AIR COND 89.66% 100.00% FIRE FIGHTING 39.31% 84.41% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 99.33% 100.00% SUBMAIN CABLE 94.80% 97.00% DB 100.00% 90.00% LUMINAIRE 100.00% 95.00% MAIN S/BOARD 100.00% 90.00% LPS 98.56% 97.48% PA 64.19% 76.16% SMATV 72.72% 89.94% CCTV 79.47% 92.93% ICT 97.72% 92.43%
  • 47. ASRAMA LELAKI A & B
  • 48. KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & D BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 98.95% 99.37% 0.52% JUN 09’ 99.44% 99.50% 0.06% MECHANICAL PLANNED ACTUAL AIR COND 76.12% 100.00% FIRE FIGHTING 81.16% 85.89% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 99.23`% 100.00% SUBMAIN CABLE 98.85% 97.00% DB 94.81% 90.00% LUMINAIRE 92.21% 95.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 97.64% PA 60.31% 74.66% SMATV 72.35% 89.94% CCTV 84.84% 92.62% ICT 99.49% 91.62%
  • 49. ASRAMA PEREMPUAN C & D
  • 50. KEMAJUAN KERJA FIZIKAL - SURAU BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 95.20% 92.10% 0.69% JUN 09’ 96.94% 96.63% -0.31% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 100.00% 75.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 76.89% 100.00% MAIN S/BOARD 85.00% 95.00% LPS 91.35% 96.24% PA 30.52% 64.71% SMATV NA NA CCTV NA NA ICT NA NA
  • 51. SURAU
  • 52. KEMAJUAN KERJA FIZIKAL - ASTAKA BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 99.80% 99.83% 0.04% JUN 09’ 99.99% 99.83% -0.16% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 100.00% 75.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 97.85% 93.89% PA 38.16% 67.38% SMATV NA NA CCTV NA NA ICT NA NA
  • 53. BANGUNAN SOKONGAN ASTAKA
  • 54. KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY JUN 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 99.53% FIRE FIGHTING 32.54% 90.34% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 97.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 0.00% LUMINAIRE 92.72% 90.00% MAIN S/BOARD 54.00% 100.00% LPS NA NA PA NA NA SMATV NA NA CCTV NA NA ICT NA NA
  • 55. BANGUNAN SOKONGAN M&E PLANT ROOM – PUSAT SUMBER
  • 56. BANGUNAN SOKONGAN M&E PLANT ROOM - BENGKEL
  • 57. DECORATIVE FENCE
  • 58. BANGUNAN SOKONGAN GARAJ KENDERAAN
  • 59. ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
  • 60. RUMAH SAMPAH
  • 61. LALUAN BERBUMBUNG
  • 62. OPEN PLAZA
  • 63. KERJA INFRA – JALAN UTAMA
  • 64. GELANGGANG PERMAINAN
  • 65. GELANGGANG PERMAINAN
  • 66. GELANGGANG PERMAINAN
  • 67. BENGKEL MIKRO - CLEANROON
  • 68. M&E : FIRE FIGHTING
  • 69. STAGE : DEWAN KULIAH
  • 70. BENGKEL JAMINAN KULITI
  • 71. KITCHEN HOOD : CAFETERIA
  • 72. M&E
  • 73.
    • SEKIAN TERIMA KASIH