Adtec Pre No.20 April 09

  1. 1. LAPORAN KEMAJUAN PROJEK NO.20 ‘APRIL 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B
  2. 2. ADTEC TAIPING LOKASI PROJEK
  3. 3. BANGUNAN PENTADBIRAN BENGKEL TEK. MAKLUMAT & JAMIN KUALITI DEWAN BESAR PUSAT SUMBER DEWAN KULIAH LOBI UTAMA KAFETERIA MIKRO ELEKTRONIK KOMPOSIT PLASTIK M&E PLANT ROOM 1 TNB SUB STATION SERAMIK M&E PLANT ROOM 2 GARAJ KENDERAAN ASRAMA LELAKI ASRAMA PEREMPUAN DEWAN MAKAN SURAU KELAS F KELAS G KUARTERS B, C, C&D PELAN TAPAK ADTEC TAIPING
  4. 4. KEMAJUAN KERJA FIZIKAL JADUAL : 99.14% SEBENAR : 73.45% KESELURUHAN : -25.69% TARIKH LAPORAN : 16 APRIL 2009
  5. 5. KEMAJUAN KERJA KEWANGAN JADUAL : 99.26% SEBENAR : 74.19% KESELURUHAN : -25.07% @ 182 HARI (LEWAT ) TARIKH LAPORAN : 16 APRIL 2009
  6. 7. KEMAJUAN KERJA FIZIKAL - DEWAN BESAR BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 99.12% 74.17% - 24.95% APRIL 09’ 100% 85.77% - 14.23% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 83.25% FIRE FIGHTING 100.00% 42.40% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 87.50% SUBMAIN CABLE 100.00% 80.00% DB 100.00% 0.00% LUMINAIRE 100.00% 55.00% MAIN S/BOARD 100.00% 0.00% LPS NA NA PA 100.00% 38.17% SMATV 100.00% 28.33% CCTV NA NA ICT 100.00% 0.00%
  7. 8. DEWAN BESAR
  8. 9. DEWAN BESAR
  9. 10. KEMAJUAN KERJA FIZIKAL – LOBI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 95.00% 89.22% -5.78% APRIL 09’ 100.00% 94.30% -5.70% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 87.00% DB 100.00% 0.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD NA NA LPS NA NA PA NA NA SMATV NA NA CCTV 100.00% 72.63% ICT NA NA
  10. 11. LOBI UTAMA
  11. 12. KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 94.20% 74.34% -19.87% APRIL 09’ 99.45% 81.81% -17.64% MECHANICAL PLANNED ACTUAL AIR COND 62.86% 82.50% FIRE FIGHTING 86.64% 7.73% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 56.25% 80.00% DB 100.00% 0.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 80.61% PA 100.00% 34.76% SMATV NA NA CCTV NA NA ICT 100.00% 0.00%
  12. 13. DEWAN KULIAH UTAMA
  13. 14. KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 96.79% 85.99% -10.80% APRIL 09’ 100.00% 91.94% -8.06% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 82.76% FIRE FIGHTING 100.00% 34.78% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 87.00% DB 100.00% 0.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 85.10% PA 100.00% 41.75% SMATV 100.00% 76.21% CCTV NA NA ICT 40.84% 4.84%
  14. 15. PUSAT SUMBER / PERPUSTAKAAN
  15. 16. KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBER BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 96.07% 83.49% -12.58% APRIL 09’ 100.00% 88.93% -11.07% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 82.44% FIRE FIGHTING 100.00% 40.30% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 0.00% LUMINAIRE 100.00% 55.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 79.94% PA 100.00% 19.15% SMATV 100.00% 69.40% CCTV 100.00% 2.36% ICT 100.00% 4.36%
  16. 17. BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
  17. 18. KEMAJUAN KERJA FIZIKAL - KAFETARIA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 94.82% 93.88% -0.95% APRIL 09’ 100.00% 96.14% -03.86% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 0.00% FIRE FIGHTING 100.00% 6.32% KITCHEN EQUIP. 82.89% 18.00% LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 10.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD NA NA LPS 100.00% 66.47% PA 100.00% 27.35% SMATV 100.00% 67.06% CCTV NA NA ICT 100.00% 0.00%
  18. 19. KAFETERIA
  19. 20. KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMAT BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 95.07% 84.50% -10.56% APRIL 09’ 99.67% 89.84% -9.82% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 66.97% FIRE FIGHTING 100.00% 15.93% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 84.62% PA 100.00% 50.29% SMATV 100.00% 78.82% CCTV 100.00% 37.46% ICT 100.00% 0.00%
  20. 21. BENGKEL TEKNOLOGI MAKLUMAT
  21. 22. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 88.52% 90.27% 1.75% APRIL 09’ 99.20% 94.41% -4.79% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 80.11% FIRE FIGHTING 100.00% 45.37% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 100.00% 75.00% DUST CONTROL NA NA PROCESS COOLING 100.00% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 0.00% LUMINAIRE 100.00% 85.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 91.49% PA 100.00% 56.22% SMATV NA NA CCTV 100.00% 55.21% ICT 89.05% 2.35%
  22. 23. BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
  23. 24. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 87.48% 91.18% 3.70% APRIL 09’ 99.13% 94.65% -4.48% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 78.34% FIRE FIGHTING 100.00% 32.95% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 100.00% 75.00% DUST CONTROL 100.00% 24.40% PROCESS COOLING 100.00% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 87.00% DB 100.00% 0.00% LUMINAIRE 100.00% 85.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 82.52% PA 100.00% 48.47% SMATV NA NA CCTV 100.00% 56.15% ICT 94.14% 1.16%
  24. 25. BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
  25. 26. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 81.17% 90.55% 9.38% APRIL 09’ 98.21% 92.30% -5.91% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 78.29% FIRE FIGHTING 98.01% 33.30% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 100.00% 75.00% DUST CONTROL 100.00% 9.09% PROCESS COOLING 100.00% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 0.00% LUMINAIRE 100.00% 85.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 89.38% PA 100.00% 49.95% SMATV NA NA CCTV 100.00% 63.51% ICT 100.00% 2.36%
  26. 27. BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
  27. 28. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 91.91% 83.93% -7.97% APRIL 09’ 99.71% 91.02% -8.70% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 59.54% FIRE FIGHTING 100.00% 21.39% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 100.00% 75.00% DUST CONTROL 100.00% 29.45% PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 55.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 81.69% PA 100.00% 39.94% SMATV 100.00% 45.52% CCTV 100.00% 44.98% ICT 100.00% 0.00%
  28. 29. BENGKEL KEJ. JAMINAN KUALITI
  29. 30. KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIK BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 89.92% 87.86% -2.06% APRIL 09’ 98.51% 90.05% -8.47% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 81.50% FIRE FIGHTING 100.00% 11.16% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 100.00% 75.00% DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 25.00% LUMINAIRE 100.00% 55.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 84.16% PA 100.00% 47.63% SMATV 100.00% 61.66% CCTV 100.00% 58.47% ICT 89.84% 0.00%
  30. 31. BENGKEL MIKRO ELEKTRONIK
  31. 32. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 95.86% 96.63% 0.77% APRIL 09’ 100.00% 96.79% -3.21% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 90.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 90.40% PA NA NA SMATV 100.00% 35.86% CCTV 100.00% 37.80% ICT 100.00% 90.00%
  32. 33. KUARTERS KELAS ‘B’
  33. 34. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 95.03% 96.71% 1.68% APRIL 09’ 100.00% 96.94% -3.06% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 90.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 90.63% PA NA NA SMATV 100.00% 27.51% CCTV NA NA ICT 100.00% 62.02%
  34. 35. KUARTERS KELAS ‘C’
  35. 36. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 92.69% 96.33% 3.63% APRIL 09’ 100.00% 96.38% -3.62% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 90.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 91.85% PA NA NA SMATV 100.00% 35.86% CCTV NA NA ICT 100.00% 90.00%
  36. 37. KUARTERS KELAS ‘C’ + ‘D’
  37. 38. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 85.15% 94.13% 8.98% APRIL 09’ 99.68% 94.20% -5.48% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 88.80% PA NA NA SMATV 100.00% 81.76% CCTV NA NA ICT 100.00% 67.18%
  38. 39. KUARTERS KELAS ‘F’ ( 4 TINGKAT )
  39. 40. KUARTERS KELAS ‘F’ ( 5 TINGKAT )
  40. 41. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G (1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 86.68% 93.87% 7.19% APRIL 09’ 99.33% 93.98% -5.35% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 77.27% 100.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 88.80% PA NA NA SMATV 100.00% 81.76% CCTV NA NA ICT 100.00% 69.85%
  41. 42. KUARTERS KELAS ‘G’ ( 5 TINGKAT )
  42. 43. KUARTERS KELAS ‘G’ ( 4 TINGKAT )
  43. 44. KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 98.39% 96.95% -1.44% APRIL 09’ 100.00% 97.34% -2.66% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 75.00% FIRE FIGHTING 100.00% 12.24% KITCHEN EQUIP. 82.98% 18.00% LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 75.00% LUMINAIRE 100.00% 80.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 88.67% PA 100.00% 51.18% SMATV 100.00% 67.06% CCTV NA NA ICT 100.00% 1.40%
  44. 45. DEWAN MAKAN
  45. 46. KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & B BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 92.69% 95.69% 3.00% APRIL 09’ 100.00% 97.10% -2.90% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 10.00% FIRE FIGHTING 100.00% 38.83% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 90.48% 90.00% DB 22.22% 50.00% LUMINAIRE 62.50% 90.00% MAIN S/BOARD 43.75% 0.00% LPS 100.00% 84.86% PA 100.00% 57.78% SMATV 100.00% 60.98% CCTV 100.00% 37.44% ICT 100.00% 73.53%
  46. 47. ASRAMA LELAKI A & B
  47. 48. KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & D BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 90.09% 96.91% 6.82% APRIL 09’ 99.99% 97.67% -2.32% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 10.00% FIRE FIGHTING 100.00% 46.61% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 55.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 85.86% PA 100.00% 54.28% SMATV 100.00% 60.98% CCTV 100.00% 35.21% ICT 100.00% 78.12%
  48. 49. ASRAMA PEREMPUAN C & D
  49. 50. KEMAJUAN KERJA FIZIKAL - SURAU BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 86.10% 84.06% -2.04% APRIL 09’ 98.65% 92.10% -6.55% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 100.00% 0.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB NA NA LUMINAIRE 92.31% 25.00% MAIN S/BOARD 100.00% 0.00% LPS 95.12% 81.70% PA 100.00% 27.47% SMATV NA NA CCTV NA NA ICT NA NA
  50. 51. SURAU
  51. 52. KEMAJUAN KERJA FIZIKAL - ASTAKA BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 99.03% 98.59% -0.45% APRIL 09’ 100.00% 98.86% -1.14% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 100.00% 0.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 0.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 0.00% LPS 96.86% 69.95% PA 100.00% 34.34% SMATV NA NA CCTV NA NA ICT NA NA
  52. 53. BANGUNAN SOKONGAN ASTAKA
  53. 54. KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 99.77% -0.23% MECHANICAL PLANNED ACTUAL AIR COND 98.48% 83.47% FIRE FIGHTING 100.00% 0.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 80.00% DB 100.00% 0.00% LUMINAIRE 100.00% 85.00% MAIN S/BOARD 100.00% 0.00% LPS NA NA PA NA NA SMATV NA NA CCTV NA NA ICT NA NA
  54. 55. BANGUNAN SOKONGAN M&E PLANT ROOM – PUSAT SUMBER
  55. 56. BANGUNAN SOKONGAN M&E PLANT ROOM - BENGKEL
  56. 57. DECORATIVE FENCE
  57. 58. BANGUNAN SOKONGAN GARAJ KENDERAAN
  58. 59. ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
  59. 60. WAKAF
  60. 61. LALUAN BERBUMBUNG
  61. 62. OPEN PLAZA
  62. 63. KERJA INFRA – JALAN UTAMA
  63. 64. GELANGGANG PERMAINAN
  64. 65. GELANGGANG PERMAINAN
  65. 66. M&E INSTALLATION
  66. 67. M&E INSTALLATION
  67. 68. M&E INSTALLATION
  68. 69. BENGKEL MIKROELEKTRONIK – CLEAN ROOM
  69. 70. BENGKEL MIKROELEKTRONIK – CLEAN ROOM
  70. 71. <ul><li>SEKIAN TERIMA KASIH </li></ul>

×