Adtec Pre No.19 Mac 09

Loading...

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

0 comments

Post a comment

    Post a comment
    Embed Video
    Edit your comment Cancel

    Favorites, Groups & Events

    Adtec Pre No.19 Mac 09 - Presentation Transcript

    1. LAPORAN KEMAJUAN PROJEK NO.19 ‘MAC 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B
    2. ADTEC TAIPING LOKASI PROJEK
    3. BANGUNAN PENTADBIRAN BENGKEL TEK. MAKLUMAT & JAMIN KUALITI DEWAN BESAR PUSAT SUMBER DEWAN KULIAH LOBI UTAMA KAFETERIA MIKRO ELEKTRONIK KOMPOSIT PLASTIK M&E PLANT ROOM 1 TNB SUB STATION SERAMIK M&E PLANT ROOM 2 GARAJ KENDERAAN ASRAMA LELAKI ASRAMA PEREMPUAN DEWAN MAKAN SURAU KELAS F KELAS G KUARTERS B, C, C&D PELAN TAPAK ADTEC TAIPING
    4. KEMAJUAN KERJA FIZIKAL JADUAL : 84.22% SEBENAR : 68.03% KESELURUHAN : -16.19% TARIKH LAPORAN : 11 MAC 2009
    5. KEMAJUAN KERJA KEWANGAN JADUAL : 86.30% SEBENAR : 68.81% KESELURUHAN : -17.49% @ 136 HARI (LEWAT ) TARIKH LAPORAN : 11 MAC 2009
    6.  
    7. KEMAJUAN KERJA FIZIKAL - DEWAN BESAR BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 97.222% 65.52% - 31.70% MAC 09’ 99.12% 74.17% - 24.95% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 50.00% FIRE FIGHTING 100.00% 39.77% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 85.00% SUBMAIN CABLE 100.00% 75.00% DB 100.00% 0.00% LUMINAIRE 100.00% 0.00% MAIN S/BOARD 100.00% 0.00% LPS NA NA PA 100.00% 31.81% SMATV 100.00% 25.00% CCTV NA NA ICT 100.00% 0.00%
    8. DEWAN BESAR
    9. DEWAN BESAR
    10. KEMAJUAN KERJA FIZIKAL – LOBI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 82.83% 78.68% -4.15% MAC 09’ 95.00% 89.22% -5,78% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 0.00% LUMINAIRE 100.00% 0.00% MAIN S/BOARD NA NA LPS NA NA PA 100.00% 65.37% SMATV NA NA CCTV 100.00% 65.37% ICT NA NA
    11. LOBI UTAMA
    12. KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 83.03% 66.39% -16.64% MAC 09’ 94.20% 74.34% -19.87% MECHANICAL PLANNED ACTUAL AIR COND 62.86% 75.00% FIRE FIGHTING 86.64% 3.87% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 56.25% 75.00% DB 100.00% 0.00% LUMINAIRE 0.00% 50.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 83.13% PA 100.00% 28.96% SMATV NA NA CCTV NA NA ICT 100.00% 0.00%
    13. DEWAN KULIAH UTAMA
    14. KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 93.37% 84.41% -8.96% MAC 09’ 96.79% 85.99% -10.80% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 75.00% FIRE FIGHTING 79.40% 29.24% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 0.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 77.33% PA 100.00% 41.75% SMATV 100.00% 68.59% CCTV NA NA ICT 40.84% 0.00%
    15. PUSAT SUMBER / PERPUSTAKAAN
    16. KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBER BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 91.35% 77.52% -13.83% MAC 09’ 96.07% 83.49% -12.58% MECHANICAL PLANNED ACTUAL AIR COND 95.68% 50.00% FIRE FIGHTING 81.99% 40.30% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 77.50% SUBMAIN CABLE 100.00% 75.00% DB 100.00% 0.00% LUMINAIRE 100.00% 30.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 72.59% PA 100.00% 19.15% SMATV 100.00% 62.46% CCTV 99.86% 2.13% ICT 82,62% 0.00%
    17. BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
    18. KEMAJUAN KERJA FIZIKAL - KAFETARIA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 84.36% 89.11% -4.75% MAC 09’ 94.82% 93.88% -0.95% MECHANICAL PLANNED ACTUAL AIR COND 76.19% 0.00% FIRE FIGHTING 14.60% 6.32% KITCHEN EQUIP. 45.48% 0.00% LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 0.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD NA NA LPS 75.13% 66.47% PA 100.00% 27.35% SMATV 99.59% 60.35% CCTV NA NA ICT 100.00% 0.00%
    19. KAFETERIA
    20. KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMAT BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 85.84% 81.62% -4.22% MAC 09’ 95.07% 84.50% -10.56% MECHANICAL PLANNED ACTUAL AIR COND 57.23% 50.00% FIRE FIGHTING 100.00% 15.93% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 50.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 87.01% PA 100.00% 42.43% SMATV 100.00% 70.94% CCTV 97.59% 33.71% ICT 29.05% 0.00%
    21. BENGKEL TEKNOLOGI MAKLUMAT
    22. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 78.05% 86.03% 7.98% MAC 09’ 88.52% 90.27% 1.75% MECHANICAL PLANNED ACTUAL AIR COND 56.66% 75.00% FIRE FIGHTING 49.72% 34.03% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 62.86% 75.00% DUST CONTROL NA NA PROCESS COOLING 35.30% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 47.06% 85.00% DB 0.00% 0.00% LUMINAIRE 0.00% 75.00% MAIN S/BOARD 0.00% 0.00% LPS 86.70% 91.49% PA 85.81% 56.22% SMATV NA NA CCTV 77.25% 49.69% ICT 17.49% 1.34%
    23. BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
    24. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 79.39% 83.64% 4.25% MAC 09’ 87.48% 91.18% 3.70% MECHANICAL PLANNED ACTUAL AIR COND 62.87% 75.00% FIRE FIGHTING 67.96% 32.95% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 68.57% 75.00% DUST CONTROL 48.77% 23.77% PROCESS COOLING 50.33% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 58.22% 85.00% DB 0.00% 0.00% LUMINAIRE 35.71% 75.00% MAIN S/BOARD 35.71% 0.00% LPS 81.02% 82.52% PA 83.73% 48.47% SMATV NA NA CCTV 92.94% 50.54% ICT 15.86% 1.16%
    25. BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
    26. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 76.14% 79.96% 3.82% MAC 09’ 81.17% 90.55% 9.38% MECHANICAL PLANNED ACTUAL AIR COND 41.99% 75.00% FIRE FIGHTING 43.45% 33.30% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 77.14% 75.00% DUST CONTROL 16.46% 8.86% PROCESS COOLING 41.29% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 72.22% 85.00% DB 0.00% 0.00% LUMINAIRE 0.00% 75.00% MAIN S/BOARD 0.00% 0.00% LPS 76.32% 89.38% PA 97.72% 49.95% SMATV NA NA CCTV 74.79% 57.16% ICT 23.12% 1.58%
    27. BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
    28. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 80.11% 77.74% -2.37% MAC 09’ 91.91% 83.93% -7.97% MECHANICAL PLANNED ACTUAL AIR COND 53.50% 55.00% FIRE FIGHTING 79.89% 14.81% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 100.00% 75.00% DUST CONTROL 71.70% 19.13% PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 82.50% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 85.00% LUMINAIRE 14.29% 45.00% MAIN S/BOARD 100.00% 0.00% LPS 91.41% 81.69% PA 100.00% 33.28% SMATV 98.53% 40.97% CCTV 86.29% 40.48% ICT 28.12% 0.00%
    29. BENGKEL KEJ. JAMINAN KUALITI
    30. KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIK BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 79.37% 78.27% -1.10% MAC 09’ 89.92% 87.86% -2.06% MECHANICAL PLANNED ACTUAL AIR COND 58.27% 50.00% FIRE FIGHTING 36.20% 11.16% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 94.29% 75.00% DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 90.48% 85.00% DB 0.00% 7.00% LUMINAIRE 0.00% 45.00% MAIN S/BOARD 0.00% 0.00% LPS 83.20% 84.16% PA 98.98% 39.69% SMATV 80.65% 55.50% CCTV 88.56% 52.62% ICT 31.59% 0.00%
    31. BENGKEL MIKRO ELEKTRONIK
    32. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 90.43% 95.76% 5.33% MAC 09’ 95.86% 96.63% 0.77% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 90.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 90.40% PA NA NA SMATV 100.00% 32.27% CCTV 100.00% 34.02% ICT 100.00% 90.00%
    33. KUARTERS KELAS ‘B’
    34. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 88.42% 95.12% 6.70% MAC 09’ 95.03% 96.71% 1.68% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 90.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 0.00% LPS 98.44% 90.63% PA NA NA SMATV 100.00% 24.75% CCTV NA NA ICT 100.00% 62.02%
    35. KUARTERS KELAS ‘C’
    36. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 84.31% 94.25% 9.94% MAC 09’ 92.69% 96.33% 3.63% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 90.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 91.85% PA NA NA SMATV 100.00% 32.27% CCTV NA NA ICT 100.00% 90.00%
    37. KUARTERS KELAS ‘C’ + ‘D’
    38. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 77.45% 91.08% 13.63% MAC 09’ 85.15% 94.13% 8.98% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 52.38% 90.00% DB 0.00% 90.00% LUMINAIRE 0.00% 90.00% MAIN S/BOARD 0.00% 0.00% LPS 100.00% 88.80% PA NA NA SMATV 100.00% 73.58% CCTV NA NA ICT 100.00% 65.58%
    39. KUARTERS KELAS ‘F’ ( 4 TINGKAT )
    40. KUARTERS KELAS ‘F’ ( 5 TINGKAT )
    41. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G (1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 77.88% 92.63% 14.75% MAC 09’ 86.68% 93.87% 7.19% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 44.44% 90.00% LUMINAIRE 0.00% 90.00% MAIN S/BOARD 26.67% 0.00% LPS 100.00% 88.80% PA NA NA SMATV 100.00% 73.58% CCTV NA NA ICT 100.00% 69.85%
    42. KUARTERS KELAS ‘G’ ( 5 TINGKAT )
    43. KUARTERS KELAS ‘G’ ( 4 TINGKAT )
    44. KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 98.16% 94.87% -3.29% MAC 09’ 98.39% 96.95% -1.44% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 75.00% FIRE FIGHTING 100.00% 12.24% KITCHEN EQUIP. 42.73% 0.00% LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 50.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 88.67% PA 100.00% 51.18% SMATV 100.00% 60.35% CCTV NA NA ICT 100.00% 0.00%
    45. DEWAN MAKAN
    46. KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & B BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 86.42% 91.05% 4.63% MAC 09’ 92.69% 95.69% 3.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 10.00% FIRE FIGHTING 100.00% 29.58% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 89.29% 86.25% SUBMAIN CABLE 0.00% 85.00% DB 0.00% 50.00% LUMINAIRE 0.00% 75.00% MAIN S/BOARD 0.00% 0.00% LPS 93.12% 85.86% PA 60.31% 54.28% SMATV 60.53% 54.88% CCTV 42.12% 31.69% ICT 98.57% 78.12%
    47. ASRAMA LELAKI A & B
    48. KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & D BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 81.04% 93.81% 12.77% MAC 09’ 90.09% 96.91% 6.82% MECHANICAL PLANNED ACTUAL AIR COND 17.86% 10.00% FIRE FIGHTING 46.33% 20.18% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 50.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD 100.00% 0.00% LPS 93.12% 85.86% PA 60.31% 54.28% SMATV 60.53% 54.88% CCTV 42.12% 31.69% ICT 98.57% 78.12%
    49. ASRAMA PEREMPUAN C & D
    50. KEMAJUAN KERJA FIZIKAL - SURAU BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 77.94% 78.73% 0.79% MAC 09’ 86.10% 84.06% -2.04% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 57.14% 0.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 75.00% SUBMAIN CABLE 41.67% 75.00% DB NA NA LUMINAIRE 0.00% 0.00% MAIN S/BOARD 0.00% 0.00% LPS 65.01% 81.70% PA 87.81% 22.89% SMATV NA NA CCTV NA NA ICT NA NA
    51. SURAU
    52. KEMAJUAN KERJA FIZIKAL - ASTAKA BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 91.60% 87.62% 3.98% MAC 09’ 99.03% 98.95% -0.45% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 0.00% 0.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 0.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD 100.00% 0.00% LPS 69.22% 37.93% PA 100.00% 28.62% SMATV NA NA CCTV NA NA ICT NA NA
    53. BANGUNAN SOKONGAN ASTAKA
    54. KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 91.00% 99.77% 8.77% MECHANICAL PLANNED ACTUAL AIR COND 94.03% 77.59% FIRE FIGHTING 79.72% 0.00% KITCHEN EQUIP. NA NA LPG INSTALL. 0.00% 0.00% COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 75.00% DB 100.00% 0.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD 100.00% 0.00% LPS NA NA PA NA NA SMATV NA NA CCTV NA NA ICT NA NA
    55. BANGUNAN SOKONGAN M&E PLANT ROOM – PUSAT SUMBER
    56. BANGUNAN SOKONGAN M&E PLANT ROOM - BENGKEL
    57. DECORATIVE FENCE
    58. BANGUNAN SOKONGAN GARAJ KENDERAAN
    59. ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
    60. WAKAF
    61. LALUAN BERBUMBUNG
    62. OPEN PLAZA
    63. KERJA INFRA – JALAN UTAMA
    64. GELANGGANG PERMAINAN
    65. M&E INSTALLATION
    66. M&E INSTALLATION
    67. M&E INSTALLATION
    68. BENGKEL MIKROELEKTRONIK – CLEAN ROOM
    69. BENGKEL MIKROELEKTRONIK – CLEAN ROOM
      • SEKIAN TERIMA KASIH
    SlideShare Zeitgeist 2009

    + Muhammad  ArkamMuhammad Arkam Nominate

    custom

    271 views, 0 favs, 1 embeds more stats

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 271
      • 268 on SlideShare
      • 3 from embeds
    • Comments 0
    • Favorites 0
    • Downloads 2
    Most viewed embeds
    • 3 views on http://www.arkamonline.com

    more

    All embeds
    • 3 views on http://www.arkamonline.com

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories