    1. LAPORAN KEMAJUAN PROJEK NO.22 ‘JUN 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B
    2. ADTEC TAIPING LOKASI PROJEK
    3. BANGUNAN PENTADBIRAN BENGKEL TEK. MAKLUMAT & JAMIN KUALITI DEWAN BESAR PUSAT SUMBER DEWAN KULIAH LOBI UTAMA KAFETERIA MIKRO ELEKTRONIK KOMPOSIT PLASTIK M&E PLANT ROOM 1 TNB SUB STATION SERAMIK M&E PLANT ROOM 2 GARAJ KENDERAAN ASRAMA LELAKI ASRAMA PEREMPUAN DEWAN MAKAN SURAU KELAS F KELAS G KUARTERS B, C, C&D PELAN TAPAK ADTEC TAIPING
    4. KEMAJUAN KERJA FIZIKAL JADUAL : 85.16 % SEBENAR : 87.59 % KESELURUHAN : 2.43 % TARIKH LAPORAN : 12 JUN 2009
    5. KEMAJUAN KERJA KEWANGAN JADUAL : 85.09 % SEBENAR : 86.12 % KESELURUHAN : 1.03 % TARIKH LAPORAN : 12 JUN 2009
    6.  
    7. KEMAJUAN KERJA FIZIKAL - DEWAN BESAR BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 88.35% 92.38% 4.03% JUN 09’ 94.21% 96.74% 2.53% MECHANICAL PLANNED ACTUAL AIR COND 94.85% 95.50% FIRE FIGHTING 81.61% 95.74% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 95.00% LPS NA NA PA 94.88% 67.17% SMATV 83.38% 86.79% CCTV NA NA ICT 3.31% 74.25%
    8. DEWAN BESAR
    9. DEWAN BESAR
    10. KEMAJUAN KERJA FIZIKAL – LOBI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 98.92% 94.90% -4.02% JUN 09’ 99.68% 99.72% 0.04% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 95.90% 100.00% SUBMAIN CABLE 94.17% 100.00% DB 75.00% 100.00% LUMINAIRE 87.89% 100.00% MAIN S/BOARD NA NA LPS NA NA PA NA NA SMATV NA NA CCTV 88.68% 92.58% ICT NA NA
    11. LOBI UTAMA
    12. KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 92.24% 91.71% -0.52% JUN 09’ 98.54% 98.19% -0.35% MECHANICAL PLANNED ACTUAL AIR COND 96.19% 95.00% FIRE FIGHTING 81.51% 86.04% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 75.00% 100.00% LUMINAIRE 91.65% 95.00% MAIN S/BOARD 75.00% 95.00% LPS 90.51% 92.01% PA 37.88% 65.71% SMATV NA NA CCTV NA NA ICT 0.91% 74.48%
    13. DEWAN KULIAH UTAMA
    14. KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 95.30% 95.38% 0.09% JUN 09’ 97.50% 98.54% 1.04% MECHANICAL PLANNED ACTUAL AIR COND 93.54% 85.18% FIRE FIGHTING 39.81% 81.59% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 97.53% 97.00% SUBMAIN CABLE 93.31% 98.00% DB 85.00% 100.00% LUMINAIRE 92.27% 98.00% MAIN S/BOARD 85.00% 95.00% LPS 91.25% 96.92% PA 44.70% 69.69% SMATV 94.54% 88.33% CCTV NA NA ICT 18.16% 23.36%
    15. PUSAT SUMBER / PERPUSTAKAAN
    16. KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBER BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 92.72% 92.73% 0.01% JUN 09’ 96.42% 96.51% 0.09% MECHANICAL PLANNED ACTUAL AIR COND 91.09% 94.96% FIRE FIGHTING 47.94% 74.24% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 99.48% 97.00% SUBMAIN CABLE 97.32% 98.00% DB 85.00% 100.00% LUMINAIRE 82.78% 95.00% MAIN S/BOARD 75.00% 95.00% LPS 87.80% 90.85% PA 63.70% 58.92% SMATV 95.99% 88.07% CCTV 73.69% 70.43% ICT 24.87% 51.37%
    17. BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
    18. KEMAJUAN KERJA FIZIKAL - KAFETARIA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 98.36% 98.71% 0.08% JUN 09’ 99.58% 99.23% -0.35% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING 90.22% 74.56% KITCHEN EQUIP. 65.55% 69.00% LPG INSTALL. 40.84% 48.50% COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD NA NA LPS 100.00% 88.81% PA 94.53% 62.91% SMATV 92.47% 87.44% CCTV NA NA ICT 0.00% 75.00%
    19. KAFETERIA
    20. KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMAT BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 93.95% 95.49% 1.54% JUN 09’ 98.05% 98.01% -0.05% MECHANICAL PLANNED ACTUAL AIR COND 86.90% 91.36% FIRE FIGHTING 31.85% 63.60% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 99.23% 96.00% SUBMAIN CABLE 98.21% 100.00% DB 97.27% 100.00% LUMINAIRE 92.51% 100.00% MAIN S/BOARD 75.00% 95.00% LPS 100.00% 96.80% PA 100.00% 73.49% SMATV 95.09% 89.00% CCTV 79.13% 291.22% ICT 8.53% 19.28%
    21. BENGKEL TEKNOLOGI MAKLUMAT
    22. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 96.82% 95.67% -1.14% JUN 09’ 98.42% 98.30% -0.12% MECHANICAL PLANNED ACTUAL AIR COND 93.36% 93.41% FIRE FIGHTING 45.37% 72.69% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 87.25% 85.00% DUST CONTROL NA NA PROCESS COOLING 41.53% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 75.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 75.00% 95.00% LPS 92.90% 96.80% PA 62.47% 75.48% SMATV 75.18% 74.39% CCTV 83.97% 93.08% ICT 26.23% 23.86%
    23. BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
    24. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 97.05% 95.65% -1.40% JUN 09’ 98.46% 98.41% -0.05% MECHANICAL PLANNED ACTUAL AIR COND 80.73% 78.34% FIRE FIGHTING 43.93% 69.10% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 87.25% 85.00% DUST CONTROL 31.69% 77.29% PROCESS COOLING 38.45% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 95.00% LPS 97.29% 93.25% PA 92.78% 72.21% SMATV 75.26% 75.20% CCTV 86.10% 92.75% ICT 21.23% 18.81%
    25. BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
    26. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 95.12% 94.67% -0.46% JUN 09’ 97.15% 97.14% -0.02% MECHANICAL PLANNED ACTUAL AIR COND 91.33% 92.19% FIRE FIGHTING 44.40% 69.54% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 87.25% 85.00% DUST CONTROL 11.65% 72.95% PROCESS COOLING 21.79% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 99.29% 100.00% DB 78.00% 100.00% LUMINAIRE 96.30% 100.00% MAIN S/BOARD 85.00% 95.00% LPS 90.20% 96.49% PA 96.64% 72.96% SMATV 73.29% 74.70% CCTV 90.23% 93.97% ICT 33.22% 27.44%
    27. BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
    28. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 94.30% 95.17% -0.87% JUN 09’ 96.50% 96.99% 0.48% MECHANICAL PLANNED ACTUAL AIR COND 82.68% 59.54% FIRE FIGHTING 26.16% 63.17% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 87.25% 85.00% DUST CONTROL 38.25% 80.74% PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 97.67% 96.00% SUBMAIN CABLE 95.02% 97.00% DB 95.02% 95.00% LUMINAIRE 77.98% 90.00% MAIN S/BOARD 57.17% 95.00% LPS 86.74% 96.20% PA 42.25% 68.68% SMATV 87.59% 85.36% CCTV 80.71% 90.90% ICT 7.17% 18.61%
    29. BENGKEL KEJ. JAMINAN KUALITI
    30. KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIK BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 92.86% 94.80% 1.94% JUN 09’ 95.58% 95.59% 0.01% MECHANICAL PLANNED ACTUAL AIR COND 93.43% 91.50% FIRE FIGHTING 22.33% 59.71% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 87.25% 85.00% DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 96.00% SUBMAIN CABLE 96.67% 95.00% DB 72.68% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 95.00% LPS 92.34% 96.70% PA 52.92% 72.02% SMATV 91.26% 86.86% CCTV 84.11% 91.21% ICT 6.84% 22.94%
    31. BENGKEL MIKRO ELEKTRONIK
    32. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 100.00% 100.00% 0.00% JUN 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 100.00% LPS 100.00% 95.68% PA NA NA SMATV 84.58% 68.14% CCTV 79.71% 93.15% ICT 100.00% 90.00%
    33. KUARTERS KELAS ‘B’
    34. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 100.00% 100.00% 0.00% JUN 09’ 100.00% 100.00% 100.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 95.78% PA NA NA SMATV 82.56% 46.09% CCTV NA NA ICT 100.00% 84.06%
    35. KUARTERS KELAS ‘C’
    36. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 100.00% 100.00% 0.00% JUN 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 96.33% PA NA NA SMATV 84.58% 86.14% CCTV NA NA ICT 100.00% 90.00%
    37. KUARTERS KELAS ‘C’ + ‘D’
    38. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 97.14% 98.49% 1.36% JUN 09’ 98.63% 98.85% 0.12% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 93.30% 96.98% PA NA NA SMATV 95.77% 93.31% CCTV NA NA ICT 96.04% 92.34%
    39. KUARTERS KELAS ‘F’ ( 4 TINGKAT )
    40. KUARTERS KELAS ‘F’ ( 5 TINGKAT )
    41. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G (1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 97.58% 98.48% 0.90% JUN 09’ 99.57% 99.58% 0.01% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 96.98% PA NA NA SMATV 95.77% 93.31% CCTV NA NA ICT 100.00% 98.37%
    42. KUARTERS KELAS ‘G’ ( 5 TINGKAT )
    43. KUARTERS KELAS ‘G’ ( 4 TINGKAT )
    44. KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 99.42% 99.60% 0.18% JUN 09’ 99.83% 96.63% 0.01% MECHANICAL PLANNED ACTUAL AIR COND 90.95% 100.00% FIRE FIGHTING 57.40% 72.89% KITCHEN EQUIP. 65.55% 69.00% LPG INSTALL. 40.84% 48.50% COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 98.00% DB 100.00% 95.00% LUMINAIRE 100.00% 80.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 97.32% PA 56.87% 73.23% SMATV 92.47% 90.79% CCTV NA NA ICT 100.00% 75.35%
    45. DEWAN MAKAN
    46. KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & B BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 98.70% 99.43% 0.73% JUN 09’ 99.39% 99.55% 0.16% MECHANICAL PLANNED ACTUAL AIR COND 89.66% 100.00% FIRE FIGHTING 39.31% 84.41% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 99.33% 100.00% SUBMAIN CABLE 94.80% 97.00% DB 100.00% 90.00% LUMINAIRE 100.00% 95.00% MAIN S/BOARD 100.00% 90.00% LPS 98.56% 97.48% PA 64.19% 76.16% SMATV 72.72% 89.94% CCTV 79.47% 92.93% ICT 97.72% 92.43%
    47. ASRAMA LELAKI A & B
    48. KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & D BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 98.95% 99.37% 0.52% JUN 09’ 99.44% 99.50% 0.06% MECHANICAL PLANNED ACTUAL AIR COND 76.12% 100.00% FIRE FIGHTING 81.16% 85.89% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 99.23`% 100.00% SUBMAIN CABLE 98.85% 97.00% DB 94.81% 90.00% LUMINAIRE 92.21% 95.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 97.64% PA 60.31% 74.66% SMATV 72.35% 89.94% CCTV 84.84% 92.62% ICT 99.49% 91.62%
    49. ASRAMA PEREMPUAN C & D
    50. KEMAJUAN KERJA FIZIKAL - SURAU BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 95.20% 92.10% 0.69% JUN 09’ 96.94% 96.63% -0.31% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 100.00% 75.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 76.89% 100.00% MAIN S/BOARD 85.00% 95.00% LPS 91.35% 96.24% PA 30.52% 64.71% SMATV NA NA CCTV NA NA ICT NA NA
    51. SURAU
    52. KEMAJUAN KERJA FIZIKAL - ASTAKA BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 99.80% 99.83% 0.04% JUN 09’ 99.99% 99.83% -0.16% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 100.00% 75.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 97.85% 93.89% PA 38.16% 67.38% SMATV NA NA CCTV NA NA ICT NA NA
    53. BANGUNAN SOKONGAN ASTAKA
    54. KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY JUN 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 99.53% FIRE FIGHTING 32.54% 90.34% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 97.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 0.00% LUMINAIRE 92.72% 90.00% MAIN S/BOARD 54.00% 100.00% LPS NA NA PA NA NA SMATV NA NA CCTV NA NA ICT NA NA
    55. BANGUNAN SOKONGAN M&E PLANT ROOM – PUSAT SUMBER
    56. BANGUNAN SOKONGAN M&E PLANT ROOM - BENGKEL
    57. DECORATIVE FENCE
    58. BANGUNAN SOKONGAN GARAJ KENDERAAN
    59. ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
    60. RUMAH SAMPAH
    61. LALUAN BERBUMBUNG
    62. OPEN PLAZA
    63. KERJA INFRA – JALAN UTAMA
    64. GELANGGANG PERMAINAN
    65. GELANGGANG PERMAINAN
    66. GELANGGANG PERMAINAN
    67. BENGKEL MIKRO - CLEANROON
    68. M&E : FIRE FIGHTING
    69. STAGE : DEWAN KULIAH
    70. BENGKEL JAMINAN KULITI
    71. KITCHEN HOOD : CAFETERIA
    72. M&E
      • SEKIAN TERIMA KASIH
    SlideShare Zeitgeist 2009

    + Muhammad  ArkamMuhammad Arkam Nominate

    custom

    235 views, 0 favs, 1 embeds more stats

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 235
      • 234 on SlideShare
      • 1 from embeds
    • Comments 0
    • Favorites 0
    • Downloads 0
    Most viewed embeds
    • 1 views on https://www.mturk.com

    more

    All embeds
    • 1 views on https://www.mturk.com

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories