SlideShare a Scribd company logo
1 of 8
Download to read offline
Building Economy ARE 431
Dr. Mohammad A. Hassanain 1
1
Assemblies Estimating - Approach
Assemblies estimating – also called Systems Estimating – is
best accomplished concurrently with the design phase of a
project.
This estimate is prepared by working with the system or
assembly unit of a project.
In a ROM estimate a gross unit is established, for example
the number of hospital beds required.
In square foot estimating the estimator works with the
project area.
In assemblies estimating the estimator will use more
detailed units such as: (square feet of partition wall, number
of plumbing fixtures, or square feet of carpet).
2
Assemblies Estimating - Approach
Since the units are detailed, the estimate becomes more
flexible and accurate, but it requires greater input from the
designer, and therefore takes longer to prepare.
In an assemblies estimate quality is now treated by the
specific material or design method chosen, and no longer by
using ranges as ¼ or ¾ .
Provided good data is available, the designer should be able
to look at the costs of different alternatives and make a
selection based on:
Cost.
Durability.
Owner requirements for quality.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 2
3
Assemblies Estimating - Approach
Example:
Decide which type of floor covering to use in an office building:
Floor area = 10,000 sq. ft.
The three best alternatives are: Total
Woven wool carpet (42 oz) with padding = $6.68/sq. ft. $66,680
Nylon carpet (26 oz) = $3.06/sq. ft. $30,600
Resilient asphalt tile = $1.57/sq. ft. $15,700
As can be seen, the project cost savings of choosing resilient
flooring over the high quality carpet is over $50,000. However, initial
cost is only one factor to consider.
There are also ongoing maintenance issues to consider, along with
aesthetics.
4
Assemblies Estimating - Approach
The systems estimate provides a basis for the comparison
of the costs of different subsystems within a project.
Example:
A commercial building project is estimated by following what
is called the uniformat breakdown (see Figure 5-11).
By comparing the twelve divisional calculated costs with the
average for past projects, the estimator can verify the
estimate’s accuracy both overall and by division.
If a division (as a percent of the project total) is much higher
than normal, the estimator should investigate why.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 3
5
Assemblies Estimating - Approach
The table in figure 5-12 provides a typical twelve-division
breakdown for a general commercial building.
Many projects are large and are designed by large design
teams.
The process of using the systems estimate to check and
verify the design to date should serve to keep the project
balanced and within budget and responsive to the owner’s
needs.
6
Assemblies Estimating - Data
The information needed for a systems estimate must be
available in a form that can be quickly itemized on a system
by system basis.
Example:
Using interior partition as an example, the interior partition
which will be estimated per square foot, must include:
The cost of the metal studs.
Drywall installation.
Taping and finishing.
It would be useful to have in the company database partition
options including:
Different fire ratings.
Insulated vs. non-insulated partitions.
Partitions finished both sides vs. only one side.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 4
7
Assemblies Estimating - Data
The R. S. Means Company publishes an Assemblies Data
book on an annual basis (See Figure 5-13 as an example).
The book is organized in accordance with the twelve
uniformat divisions.
Referencing Figures 5-13 and 5-14, notice the information
illustrated for an interior drywall partition system.
The estimator must:
1. Identify the partition system that will be used.
2. Determine the number of square feet of partition
that will be needed.
8
Assemblies Estimating - Data
The estimator in conjunction with the designer must decide
between:
Wood vs. metal studs.
Fire resistant vs. water resistant drywall on the face
of the layer.
Base layer dry wall type.
Stud spacing.
Whether or not insulation will be used.
The corresponding cost for installation and material for each
option can be read to the right.
These costs are the installation costs including overhead and
profit for the installing contractor.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 5
9
Assemblies Estimating - Data
Example:
Assume that the drywall specified in line #6.1-510-1450 from
the table in Figure 5-13 was selected for use in a 10,000
sq.ft. office area. At this point :
If drawings are available, the estimator can
measure the partition square footage (linear foot x
height).
By using an approximation or estimating aid such
as Figure 5-15, arrive at the quantity of dry wall
necessary for the project.
10
Assemblies Estimating - Data
Example:
Assuming a two-story 10,000 square foot building, and using
the numbers from Figure 5-15:
10,000 sq. ft. / 20 sq. ft. per lf = 500 lf of partition
70% drywall = 350 lf
30% block = 150 lf
Assume a 12` height:
Sq.ft. drywall = 350 lf x 12` = 4,200 sq.ft.
Sq.ft block = 150 lf x 12` = 1,800 sq.ft.
Total drywall cost = Quantity drywall in sq.ft. x Cost per sq.ft.
Total drywall cost = 4,200 sq.ft. x $4.14 per sq.ft. = $17,388
Building Economy ARE 431
Dr. Mohammad A. Hassanain 6
11
Assemblies Estimating - Data
Existing drawings and/or estimating tools would be used to
determine the quantities for all the components in a project.
Assembly cost data would be taken from company historical
records, from data books such as Means, from suppliers and
vendors, or would be created by the estimator by the use of
unit prices.
Once all of the quantities and system unit prices are
determined, the total assembly estimate can be produced.
12
Assemblies Estimating – Compilation and Adjustment
Each of the major elements of the project would be quantified and
priced by its major assemblies as the interior partition example.
For a commercial building project, the assemblies would be
summarized as shown in Figure 5-16.
Excavation, roadways and parking, and landscapingSite WorkDiv 12
Architectural equipments and furnishingsSpecialtiesDiv 11
General ConditionsGeneral ConditionsDiv 10
Service, power and lightingElectricalDiv 9
Plumbing, heating and cooling, and fire protectionMechanicalDiv 8
Elevators, escalators, and dumbwaitersConveyingDiv 7
Partitions, interior doors, finish floors, and ceilingsInterior ConstructionDiv 6
Roofing – membrane, insulation, and flashingRoofingDiv 5
Building envelope – windows, doors and wallsExterior ClosureDiv 4
Floor and roof structures and superstructuresSuperstructureDiv 3
Slab on gradeSubstructureDiv 2
Foundations and excavationFoundationDiv 1
Building Economy ARE 431
Dr. Mohammad A. Hassanain 7
13
Assemblies Estimating – Compilation and Adjustment
For projects other than commercial buildings the divisions
would be organized differently, in accordance to the method
in which the project is structured.
A highway project for example, might be organized along
major elements such as:
Clearing and grading.
Paving.
Drainage.
As shown on the worksheet in Figure 5-16, the project
should be adjusted for location as well as time.
If the estimate needs to reflect total project cost to the
owner, the designer’s fee needs to be added in as well.
Project contingency would be added in at the end to allow
some room for adjustment in owner scope.
14
Assemblies Estimating - Presentation
An assemblies estimate might be done several times
throughout the course of the design and should be an
integral part of the design process.
A formal review of the estimate should occur at:
The end of schematic design and
The end of the design development phase.
It is important in the estimate presentation to highlight the
design elements that are generating the greatest project
cost, particularly work items that have some degree of
flexibility as to owner choice.
Identifying these elements early provides the opportunity for
cost savings or an early adjustments in the project’s focus
that may end up providing the owner greater value at less
cost.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 8
15
Assemblies Estimating - Presentation
Required code items would have little flexibility, whereas
other items such as fine millwork, high end carpet, or high
speed elevator systems may have alternate options.
The key, is to get an accurate, early budget for the project,
verifying that the design is within or that it exceeds the
owner’s budget.
If the design exceeds the owner’s budget:
Design alternatives may be investigated.
The scope of the project may be reduced.
Additional funding may be pursued.
The earlier and more accurate the estimate, the greater the
opportunity for such decisions to be made.

More Related Content

What's hot

M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sumEst
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Jamal Nelson, CCM
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
Construction management
Construction managementConstruction management
Construction managementvhjadhav
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
Construction accidents and safety management
Construction accidents and safety managementConstruction accidents and safety management
Construction accidents and safety managementSwarna Rajan
 
Valuation Format
Valuation FormatValuation Format
Valuation FormatRohit Digra
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Valuation - professional prractice and valuation
Valuation - professional prractice and valuationValuation - professional prractice and valuation
Valuation - professional prractice and valuationKavin Raval
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequenceRanjith Kumar
 
Estimation introduction - Estimation, Costing and Valuation (ECV)
Estimation introduction - Estimation, Costing and Valuation (ECV)Estimation introduction - Estimation, Costing and Valuation (ECV)
Estimation introduction - Estimation, Costing and Valuation (ECV)Shanmugasundaram N
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
Construction Project Process Flow
Construction Project Process FlowConstruction Project Process Flow
Construction Project Process FlowRajasekar M
 
Valuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringValuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 

What's hot (20)

M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sum
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Construction management
Construction managementConstruction management
Construction management
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Construction accidents and safety management
Construction accidents and safety managementConstruction accidents and safety management
Construction accidents and safety management
 
Valuation Format
Valuation FormatValuation Format
Valuation Format
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Valuation - professional prractice and valuation
Valuation - professional prractice and valuationValuation - professional prractice and valuation
Valuation - professional prractice and valuation
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequence
 
Estimation introduction - Estimation, Costing and Valuation (ECV)
Estimation introduction - Estimation, Costing and Valuation (ECV)Estimation introduction - Estimation, Costing and Valuation (ECV)
Estimation introduction - Estimation, Costing and Valuation (ECV)
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Construction Project Process Flow
Construction Project Process FlowConstruction Project Process Flow
Construction Project Process Flow
 
Valuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringValuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation Engineering
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 

Similar to 4.3 assemblies estimating

06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdfJunaidMughal34
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONAr Naveen Naveen
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Shabaz Khan
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to EstimationMuthanna Abbu
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - BriefKai Yun Pang
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxSudipBalLama
 
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...IOSR Journals
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01hlksd
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).pptNaumanIjaz12
 

Similar to 4.3 assemblies estimating (20)

5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
3 estimate considerations
3 estimate considerations3 estimate considerations
3 estimate considerations
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 
2 types of estimates
2 types of estimates2 types of estimates
2 types of estimates
 
PEPD MODULE 1.pdf
PEPD MODULE 1.pdfPEPD MODULE 1.pdf
PEPD MODULE 1.pdf
 
4.1 conceptual estimates
4.1 conceptual estimates4.1 conceptual estimates
4.1 conceptual estimates
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
5.2 unit pricing
5.2 unit pricing5.2 unit pricing
5.2 unit pricing
 
Eca workshop
Eca workshopEca workshop
Eca workshop
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
 
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 
5.3 estimate setup
5.3 estimate setup5.3 estimate setup
5.3 estimate setup
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 

More from Ali Juma Albahrani

More from Ali Juma Albahrani (13)

10 depreciation and depletion
10 depreciation and depletion10 depreciation and depletion
10 depreciation and depletion
 
9 benefit to cost ratio method
9 benefit to cost ratio method9 benefit to cost ratio method
9 benefit to cost ratio method
 
8.the rate of return method
8.the rate of return method8.the rate of return method
8.the rate of return method
 
7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method
 
7.1 present worth method
7.1 present worth method7.1 present worth method
7.1 present worth method
 
7.0 life cycle costing
7.0 life cycle costing7.0 life cycle costing
7.0 life cycle costing
 
6.4 multiple factors
6.4 multiple factors6.4 multiple factors
6.4 multiple factors
 
6.3 use of interest tables
6.3 use of interest tables6.3 use of interest tables
6.3 use of interest tables
 
6.2 cash flow - time diagrams
6.2 cash flow - time diagrams6.2 cash flow - time diagrams
6.2 cash flow - time diagrams
 
6.1 simple versus compound interest
6.1 simple versus compound interest6.1 simple versus compound interest
6.1 simple versus compound interest
 
5.0 detailed estimating
5.0 detailed estimating5.0 detailed estimating
5.0 detailed estimating
 
4.0 pre-construction estimates
4.0 pre-construction estimates4.0 pre-construction estimates
4.0 pre-construction estimates
 
1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimating
 

Recently uploaded

Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfNainaShrivastava14
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfManish Kumar
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfDrew Moseley
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.elesangwon
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionSneha Padhiar
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsResearcher Researcher
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdfAkritiPradhan2
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Erbil Polytechnic University
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming languageSmritiSharma901052
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodManicka Mamallan Andavar
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 

Recently uploaded (20)

Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdf
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based question
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending Actuators
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming language
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument method
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 

4.3 assemblies estimating

  • 1. Building Economy ARE 431 Dr. Mohammad A. Hassanain 1 1 Assemblies Estimating - Approach Assemblies estimating – also called Systems Estimating – is best accomplished concurrently with the design phase of a project. This estimate is prepared by working with the system or assembly unit of a project. In a ROM estimate a gross unit is established, for example the number of hospital beds required. In square foot estimating the estimator works with the project area. In assemblies estimating the estimator will use more detailed units such as: (square feet of partition wall, number of plumbing fixtures, or square feet of carpet). 2 Assemblies Estimating - Approach Since the units are detailed, the estimate becomes more flexible and accurate, but it requires greater input from the designer, and therefore takes longer to prepare. In an assemblies estimate quality is now treated by the specific material or design method chosen, and no longer by using ranges as ¼ or ¾ . Provided good data is available, the designer should be able to look at the costs of different alternatives and make a selection based on: Cost. Durability. Owner requirements for quality.
  • 2. Building Economy ARE 431 Dr. Mohammad A. Hassanain 2 3 Assemblies Estimating - Approach Example: Decide which type of floor covering to use in an office building: Floor area = 10,000 sq. ft. The three best alternatives are: Total Woven wool carpet (42 oz) with padding = $6.68/sq. ft. $66,680 Nylon carpet (26 oz) = $3.06/sq. ft. $30,600 Resilient asphalt tile = $1.57/sq. ft. $15,700 As can be seen, the project cost savings of choosing resilient flooring over the high quality carpet is over $50,000. However, initial cost is only one factor to consider. There are also ongoing maintenance issues to consider, along with aesthetics. 4 Assemblies Estimating - Approach The systems estimate provides a basis for the comparison of the costs of different subsystems within a project. Example: A commercial building project is estimated by following what is called the uniformat breakdown (see Figure 5-11). By comparing the twelve divisional calculated costs with the average for past projects, the estimator can verify the estimate’s accuracy both overall and by division. If a division (as a percent of the project total) is much higher than normal, the estimator should investigate why.
  • 3. Building Economy ARE 431 Dr. Mohammad A. Hassanain 3 5 Assemblies Estimating - Approach The table in figure 5-12 provides a typical twelve-division breakdown for a general commercial building. Many projects are large and are designed by large design teams. The process of using the systems estimate to check and verify the design to date should serve to keep the project balanced and within budget and responsive to the owner’s needs. 6 Assemblies Estimating - Data The information needed for a systems estimate must be available in a form that can be quickly itemized on a system by system basis. Example: Using interior partition as an example, the interior partition which will be estimated per square foot, must include: The cost of the metal studs. Drywall installation. Taping and finishing. It would be useful to have in the company database partition options including: Different fire ratings. Insulated vs. non-insulated partitions. Partitions finished both sides vs. only one side.
  • 4. Building Economy ARE 431 Dr. Mohammad A. Hassanain 4 7 Assemblies Estimating - Data The R. S. Means Company publishes an Assemblies Data book on an annual basis (See Figure 5-13 as an example). The book is organized in accordance with the twelve uniformat divisions. Referencing Figures 5-13 and 5-14, notice the information illustrated for an interior drywall partition system. The estimator must: 1. Identify the partition system that will be used. 2. Determine the number of square feet of partition that will be needed. 8 Assemblies Estimating - Data The estimator in conjunction with the designer must decide between: Wood vs. metal studs. Fire resistant vs. water resistant drywall on the face of the layer. Base layer dry wall type. Stud spacing. Whether or not insulation will be used. The corresponding cost for installation and material for each option can be read to the right. These costs are the installation costs including overhead and profit for the installing contractor.
  • 5. Building Economy ARE 431 Dr. Mohammad A. Hassanain 5 9 Assemblies Estimating - Data Example: Assume that the drywall specified in line #6.1-510-1450 from the table in Figure 5-13 was selected for use in a 10,000 sq.ft. office area. At this point : If drawings are available, the estimator can measure the partition square footage (linear foot x height). By using an approximation or estimating aid such as Figure 5-15, arrive at the quantity of dry wall necessary for the project. 10 Assemblies Estimating - Data Example: Assuming a two-story 10,000 square foot building, and using the numbers from Figure 5-15: 10,000 sq. ft. / 20 sq. ft. per lf = 500 lf of partition 70% drywall = 350 lf 30% block = 150 lf Assume a 12` height: Sq.ft. drywall = 350 lf x 12` = 4,200 sq.ft. Sq.ft block = 150 lf x 12` = 1,800 sq.ft. Total drywall cost = Quantity drywall in sq.ft. x Cost per sq.ft. Total drywall cost = 4,200 sq.ft. x $4.14 per sq.ft. = $17,388
  • 6. Building Economy ARE 431 Dr. Mohammad A. Hassanain 6 11 Assemblies Estimating - Data Existing drawings and/or estimating tools would be used to determine the quantities for all the components in a project. Assembly cost data would be taken from company historical records, from data books such as Means, from suppliers and vendors, or would be created by the estimator by the use of unit prices. Once all of the quantities and system unit prices are determined, the total assembly estimate can be produced. 12 Assemblies Estimating – Compilation and Adjustment Each of the major elements of the project would be quantified and priced by its major assemblies as the interior partition example. For a commercial building project, the assemblies would be summarized as shown in Figure 5-16. Excavation, roadways and parking, and landscapingSite WorkDiv 12 Architectural equipments and furnishingsSpecialtiesDiv 11 General ConditionsGeneral ConditionsDiv 10 Service, power and lightingElectricalDiv 9 Plumbing, heating and cooling, and fire protectionMechanicalDiv 8 Elevators, escalators, and dumbwaitersConveyingDiv 7 Partitions, interior doors, finish floors, and ceilingsInterior ConstructionDiv 6 Roofing – membrane, insulation, and flashingRoofingDiv 5 Building envelope – windows, doors and wallsExterior ClosureDiv 4 Floor and roof structures and superstructuresSuperstructureDiv 3 Slab on gradeSubstructureDiv 2 Foundations and excavationFoundationDiv 1
  • 7. Building Economy ARE 431 Dr. Mohammad A. Hassanain 7 13 Assemblies Estimating – Compilation and Adjustment For projects other than commercial buildings the divisions would be organized differently, in accordance to the method in which the project is structured. A highway project for example, might be organized along major elements such as: Clearing and grading. Paving. Drainage. As shown on the worksheet in Figure 5-16, the project should be adjusted for location as well as time. If the estimate needs to reflect total project cost to the owner, the designer’s fee needs to be added in as well. Project contingency would be added in at the end to allow some room for adjustment in owner scope. 14 Assemblies Estimating - Presentation An assemblies estimate might be done several times throughout the course of the design and should be an integral part of the design process. A formal review of the estimate should occur at: The end of schematic design and The end of the design development phase. It is important in the estimate presentation to highlight the design elements that are generating the greatest project cost, particularly work items that have some degree of flexibility as to owner choice. Identifying these elements early provides the opportunity for cost savings or an early adjustments in the project’s focus that may end up providing the owner greater value at less cost.
  • 8. Building Economy ARE 431 Dr. Mohammad A. Hassanain 8 15 Assemblies Estimating - Presentation Required code items would have little flexibility, whereas other items such as fine millwork, high end carpet, or high speed elevator systems may have alternate options. The key, is to get an accurate, early budget for the project, verifying that the design is within or that it exceeds the owner’s budget. If the design exceeds the owner’s budget: Design alternatives may be investigated. The scope of the project may be reduced. Additional funding may be pursued. The earlier and more accurate the estimate, the greater the opportunity for such decisions to be made.