Deployment Plan for B2B Integrations
 

Deployment Plan for B2B Integrations

on

  • 1,640 views

This is a sample of the deployment plan on how to carry out the cut over activities for the migration from an old interface to web service interface with service providers.

This is a sample of the deployment plan on how to carry out the cut over activities for the migration from an old interface to web service interface with service providers.

Statistics

Views

Total Views
1,640
Views on SlideShare
1,636
Embed Views
4

Actions

Likes
0
Downloads
0
Comments
0

1 Embed 4

http://www.slideshare.net 4

Accessibility

Categories

Upload Details

Uploaded via

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    Deployment Plan for B2B Integrations Deployment Plan for B2B Integrations Presentation Transcript

    • Now until Day 0 Task Details Begin Time End Time Owner Status Soft Launch 1-Mar-09 Customer Dev Team Load Dbacklog Orders - Order Confirmed Date - 1/Nov/2008 - Backlog order 1-Mar-09 Customer Dev Team DRAGONfx 2.0 Change Ticket Change Ticket Preparation - Master CT - MQ CT - Control-M CT - DB CT Submit the CT - refer to CT & Contact tab 1-Mar-09 Customer Dev Team Upstream/Downstream Change Ticket Preparation Review Deployment Plan 1-Mar-09 Customer Review the Deployment Plan - Webservice Project Team / Business (Upstream/downstream) - Upstream/Downstream Systems Teams, IT - LSPs Day 1 Task Details Begin Time End Time Owner Status Change Ticket Review 2-Mar-09 Customer Change Ticket Review for Webservice Change Ticket and Upstream/Downtream systems Change Ticket (Upstream/downstream) Teams, IT Day 2 Task Details Begin Time End Time Owner Status Verify Webservice Connectivities LSP able to connect to Webservice thru https 9:00 AM 4:00 PM Customer IT, Vendor IT Copy/Verify OMI Master Data 9:00 AM 4:00 PM Customer Bussiness Support - Copy the OMI Master data from UAT - Verify the OMI Master data Pull/Verify DRAGON 1.0 Users Accounts 9:00 AM 4:00 PM Customer Logistics Business IT need to pull out now - Pull out the old applicaton 1.0 user accounts - Create the user accounts in application 2.0 Verify Master Data 9:00 AM 4:00 PM Customer Logistics / COM / - Review all the master data (especially on Part, Vendor Pull all the master data Part, etc) COC business, Logistics in xls file to the team. Business, Procurement, Customer IT Day 2 Task Details Begin Time End Time Owner Status Create User Accounts in Application 2.0 - Create the user accounts 9:00 AM 4:00 PM Customer Logistics Load/Verify Application 1.0 Final Orders 9:00 AM 10:00 PM Customer Procurement - Orders loaded up to that day same as Application 1.0 - Clear all the message fallout - Keep deployment day feed in webservice transaction table (example, SO / SOC / MN / etc) in case LSP required 9:00 AM 1:00 PM Vendor Business / IT Deploy LSP application ( no data interface - Deploy the changes in LSP system and point to Inventory quantity can to within lsp and Dell) Application 2.0 webservices send to us on Day 0 if - Physical inventory count for LSP (DMI / VMI) hub operation is stop Stop Application 2.0 - Stop the application 2.0 weblogic 9:30 AM 10:00 AM Customer IT
    • 10:00 AM 12:00 PM Customer IT Change Order Management batch jobs - Change the Order Management data feed to application and LSP Feed-in folder 1.0 and application 2.0 - Change the LSP feed-in folder to another new folder name Adjust Inventory 10:00 AM 11:30 AM Customer Logistics/Customer Inventory quantity can - Get the latest inventory info from Hub send to us on Day 0 if - Update/Adjust the Inventory table IT hub operation is stop Final turn application 2.0 orders - set the email account for application 2.0 email 10:00 AM 12:00 PM Customer IT notification - delete ETA_TMP table - - Keep deployment day feed in webservice transaction table (example, SO / SOC / MN / etc) in case LSP needed Change vendor currency conversion setting 9:00 AM 12:00 PM Customer Logistics Change vendor currency conversion setting Implement freight system changes Point to new application 2.0 DB view 9:00 AM 12:00 PM Customer IT Deploy the application 2.0 build scripts Run the deployment build scripts with all the jobs enable 10:00 AM 12:00 PM Customer IT 11:00 AM 1:00 PM Customer Logistics / COM / Confirm the master data and orders - Final verify all the master data and make sure non- COC business, Logistics intergrity. backlog orders set properly - Make sure no records in webservice_transaction table Business, Procurement, Customer IT Start the Weblogic for Backend/Frontend services 12:00 PM 1:00 PM Customer IT Turn on Application 2.0 application services Verify/Test order management Feed Files - Make sure application 1.0 and application 2.0 able to 12:00 PM 1:00 PM Customer IT load/process the orders and master data 4:00 PM Customer IT, Vendor IT Testing with LSP - Test with LSP on the webservices 1:00 PM Day 3 Verify/Test freight system changes Able to pull the existing application 2.0 orders thru DB 9:00 AM 4:00 PM Customer IT Implement Online Webfarm changes Point to new application 2.0 webservice 9:00 AM 4:00 PM Dell IT Verify/Test Online Webfarm 9:00 AM 4:00 PM Customer IT Able to pull the existing application 2.0 orders thru webservice Point to new application 2.0 DB 9:00 AM 4:00 PM Customer IT Implement Customer Care system changes Implement Datamart changes Point to new application 2.0 share folder 9:00 AM 4:00 PM Customer IT Implement Ebilling changes Point to new application 2.0 webservice 9:00 AM 4:00 PM Customer IT Monitor Application logs Monitor application logs 9:00 AM 4:00 PM Customer IT Verify/Test Customer Care system Able to pull the existing application 2.0 orders thru DB 9:00 AM 4:00 PM Customer IT Verify TNT status Make sure the in-factory/ex-factory status is correct 9:00 AM 4:00 PM Customer Logistics Verify OMI status Monitor the OMI calculated data and email status 9:00 AM 4:00 PM Customer Logistics / COM / COC business, Logistics Business, Procurement, Customer IT Verify Inventory Movement Able to perform Inventory movement from LSP 9:00 AM 4:00 PM Customer Logistics / COM / COC business, Logistics Business, Procurement, Customer IT
    • Verify Reports Verify Fulfillment, TNT, Inventory, OMI reports 9:00 AM 4:00 PM Customer Logistics / COM / COC business, Logistics Business, Procurement, Customer IT Verify other downstream/upstream Able to pull the existing application 2.0 orders 9:00 AM 4:00 PM Customer Logistics / COM / systems COC business, Logistics Business, Procurement, Customer IT Final verification Final verify all the testing results before Go/No-Go 4:00 PM 4:30 PM Customer Logistics / COM / COC business, Logistics Business, Procurement, Customer IT/Vendor Business, Vendor IT GO/NO-GO Meeting GO/NO-GO Meeting 4:30 PM 5:00 PM Customer Logistics / COM / COC business, Logistics Business, Procurement, Customer IT/Vendor Business, Vendor IT Day 4 onward Task Details Begin Time End Time Owner Status Close the Change Ticket Update and close the Change Ticket 9:00 AM 4:00 PM Customer IT Stabilization Start Monitor Trouble Ticket and route to project team 1-May-09 Customer Logistics/Customer IT
    • Day 3 Task Details Begin Time End Time Owner Status Stop application 2.0 6:30 PM 7:00 PM Customer IT Stop the application 2.0 application and change back to soft launch setting 7:00 PM 10:00 PM Customer IT Copy upstream/downstream feed files back to Copy the upstream/downstream feed files from application 2.0 application 1.0 back to application 1.0 Copy the TNT status from application 2.0 tables to application 1.0 7:00 PM 10:00 PM Customer IT Copy the TNT status / servicetag records from application 2.0 DB to application 1.0 DB Set the merge order in application 1.0 7:00 PM 10:00 PM Customer IT Base on the application 2.0 merge order and set the application 1.0 fulfillment table Adjust the Inventory 7:00 PM 10:00 PM Customer Logistics Business Base on the application 2.0 inventory and adjust back on application 1.0 Rollback MQ changes Change back to original MQ servers 7:00 PM 10:00 PM Customer IT Rollback upstream/downstream/LSP changes Rollback to their original application settings 7:00 PM 10:00 PM Customer Change Owner Verify back out result Verify back out result 10:00 PM 11:00 PM Customer Logistics/Customer IT Day 4 Task Details Begin Time End Time Owner Status Close the Change Ticket Update and close the Change Ticket 9:00 AM 4:00 PM Customer CT Implementer