Gilgel Gibe III dam Ethiopia: technical, engineering and economic feasibility study report.

Loading...

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

12 comments

Comments 1 - 10 of 12 previous next Post a comment

  • + damted Ted Warren 4 months ago
    Hi Anthony and thanks for your prompt responce. Thanks for updating the report. I would be happy to help with this project and it’s feasability. Networking is the answer. I wil post a CV and update my profile as needed. Feel free to contact me directly at damted2000@yahoo.com I will keep in touch.
    Ted
  • + anthony_mitchell Anthony Mitchell 4 months ago
    In reply to damted, the answer is yes, the facility design was changed from rockfill to RCC and is being constructed as such. The report above is being revised to reflect that change.
  • + damted Ted Warren 4 months ago
    Does anybody Know if Gibe III will be a RCC Dam. I am an RCC specialist and would be interested in assisting with the project. I have been involved with over 15 RCC dams in 7 countries since the early 1990,s
  • + anthony_mitchell Anthony Mitchell 5 months ago
    The comments below (ending in the comment titled ‘Public debate hindered’) were originally written as a stand-alone article. They may be reprinted in your publication or blog (hint, hint), provided that an HTML link is included back to this web page.
  • + anthony_mitchell Anthony Mitchell 5 months ago
    Gibe III Dam Heralds Climate Change Conflicts in Africa

    The Gibe III dam will become the tallest rock-filled dam in the world if construction is completed on the Omo River in southwestern Ethiopia. The dam is generating controversy because of technical and engineering questions, environmental and social issues, and the lack of transparency that led the World Bank to decline Ethiopia’s application for financial support for the project.

    The African Development Bank has tentatively approved Ethiopia’s request for funding Gibe III through the government-owned Ethiopian Electric Power Corporation (EEPCo).

    International banks and EEPCo are relying on an environmental and social impact analysis (ESIA) prepared by Centro Elletrotecnico Sperimentale Italiano (CESI), an Italian company whose owners include vendors who stand to benefit from the project. This conflict of interest is not disclosed in the impact statement.

    The impact statement presents Gibe III as a modern roller compacted concrete (RCC) gravity dam. The impact statement was completed in March 2009, after the project had been designed and construction began.

    EEPCo’s prime contractor at Gibe III is the Italian company Salini Costruttori S.p.A. Salini states that they are building a low-technology rock-fill structure. When asked to explain the discrepancy between the impact assessment for a RCC structure and Salini’s plans to build a rock-fill dam, the CESI team leader for the impact statement, Dr. Guiseppe Paolo Stigliano wrote on May 7:

    “I don’t notice any discrepancy inside the ESIA.
    “In any case, for further explanations please make directly reference to EEPCo for which the ESIA has been prepared.”

    Emails sent to the EEPCo contacts listed in the ESIA bounced back as undeliverable. EEPCo’s main website www.eepco.gov.et was found to be propagating ‘Silent love China’ computer attacks that attempt to install Trojan software on visitors’ computers and steal passwords. The Chinese are responsible for building the Tekeze dam in Ethiopia.

    From the outside, it is now known whether EEPCo’s computers have been breached by deliberate acts of espionage by government agencies within the Peoples’ Republic of China or by Chinese criminal groups. The nature of the breach at EEPCo, which purposely avoids infecting PRC government websites, suggests the former.
  • + anthony_mitchell Anthony Mitchell 5 months ago
    Role of the United States

    The United States has the most number of votes in the bank and is the largest contributor of funds to the African Development Fund or ADF. The ADF is the low-interest loan facility that countries (including Ethiopia) are allowed to borrow from at subsidized loan rates because their credit ratings are inadequate to obtain commercial loans.

    Ethiopia relies on civilian and military assistance from the United States, which in turn relies on Ethiopia for security assistance in the region. In fiscal year (FY) 2008, the United States government gave Ethiopia $455 million in civilian aid and an additional $550 million in food assistance.

    International Rivers [http://internationalrivers.org/node/3773], a non-governmental organization (NGO) based in Berkeley, CA, estimates that Ethiopia relies on foreign aid for most of its national budget, which in 2008 was $4.586 billion, while expenditures were approximately $5.729 billion. Imports in 2008 were $6.218 billion, while exports were $1.439 billion.

    Coffee is Ethiopia’s largest export, followed by the drug qat, gold, leather products, live animals and oilseeds. Per-capita gross domestic product remained at $800 in both 2007 and 2008. One in four Ethiopians lives on less than $1 per day.

    In December, 2005, the International Monetary Fund (IMF) forgave Ethiopia’s debt to that institution. On January 23, 2009, Ethiopia’s request for an emergency loan of $50 million from the IMF was approved by the IMF’s executive board. The loan was provided under the rapid-access component of the IMF’s Exogenous Shocks Facility.

    The Gibe III dam project is one of several big dam projects in Ethiopia. At a cost of $1.7 billion, Gibe III exceeds that country’s annual exports. The financial risks posed by undertaking Gibe III can be seen in the context of Ethiopia’s success with previous dam projects.
  • + anthony_mitchell Anthony Mitchell 5 months ago
    Recent Dams Failed to Meet Expectations

    Gibe I and Gibe II are located upstream from Gibe III and are also Salini projects. Gibe II is an extension of Gibe I, which has been completed. Work on Gibe II halted after an unexpected geological event that was not predicted by geological investigations before construction began. The design needed to be changed and construction plans altered, increasing costs.

    Gibe II is funded by the Italian government, which provided Ethiopia with the biggest Italian aid credit ever granted since the creation of the Italian development revolving fund: EUR 220 million. In March, 2006 Italian prosecutors began a criminal investigation into the granting and use of those funds.

    Later in 2006, the Campagna per la Riforma della Banca Mondiale [http://crbm.org/] (CRBM), an Italian NGO, initiated its own investigation. On November 16-30, 2007 CRBM members undertook a joint fact finding mission in Ethiopia with representatives from International Rivers, in cooperation with the CEE Bankwatch Network. The report issued by CRBM in 2008 on the three Gibe dam projects is titled the Gilgel Gibe Affair [http://bankwatch.org/documents/gibe_study.pdf].

    The Tekeze dam, built by the Chinese in the north of Ethiopia, was recognized on its first anniversary in February 2009 by Ethiopia’s Prime Minister Meles Zenawi. At 185 meters high, the Tekeze dam is 10 meters higher than the Three Gorges dam in China. In comparison, Gibe III will be 240 meters tall.

    On its first anniversary, Meles announced that the Tekeze dam had run out of water and could not generate electricity. The reservoir was too low, Meles declared. Information on revised generating capacity from the Tekeze dam, if any, has not been released. Nor has there been a public discussion of liability allocation.

    As with Gibe II, Tekeze’s construction had been delayed due to unexpected geological conditions that led to additional costs. A thorough pre-construction investigation was apparently not done at the Tekeze dam site, leading to unexpected events.

    Site conditions at Gibe III are no less complex than at other dam sites in Ethiopia. Three meters of volcanic ash have been found underneath the dam site. Ash creates unstable conditions for construction projects and has poor load bearing properties.

    Despite its location in an active earthquake region, there is no evidence that a seismic risk modeling study was conducted for the current Gibe III dam design. An independent technical and engineering study of Gibe III [http://www.slideshare.net/anthony_mitchell/gilgel-gibe-iii-hydroelectric-dam-ethiopia-technical-engineering-and-economic-feasibility-study-report] by this author raises additional questions about risks posed by the dam.
  • + anthony_mitchell Anthony Mitchell 5 months ago
    Gibe III Investigation Requested

    International Rivers, the Solidarity Movement for a New Ethiopia [http://solidaritymovement.org/], CRBM, Indigenous Peoples of Africa Coordinating Committee [http://www.ipacc.org.za/] and the Bank Information Center [http://bicusa.org/en/index.aspx] have jointly requested that the African Development Bank’s Compliance Review Mechanism Unit (CRMU) investigate the Bank’s decision to support Gibe III. The CRMU has until May 25 to respond to the request.

    The request is based on the following findings by the NGOs:

    • A lack of consultation with civil society groups and the 200,000 people downstream who depend on existing water flows through the UNESCO World Heritage Site that is the Lower Omo Valley.
    • Inconsistencies with Ethiopian law, including anti-corruption statutes.
    • The delayed and technically insufficient ESIA.
    • Environmental, health and social impacts.
    • Financial risks for Ethiopia.

    The Kenyan conservationist and paleontologist Richard Leakey [http://richardleakey.wildlifedirect.org/2009/03/26/the-gibe-iii-dam-must-be-stopped/] has spoken out against Gibe III because it would permanently decrease water levels in Lake Turkana. This high desert lake is downstream from Gibe III and provides drinking water and food that supports 300,000 people. A Kenyan NGO called the Friends of Lake Turkana [http://www.friendsoflaketurkana.org/] is urging the Kenyan government to take a stronger role in protecting the lake.

    Article 2(2) of the United Nations Convention on Civil and Political Rights (ratified by Ethiopia) states “in no case may a people be deprived of its own means of subsistence.” The NGOs believe that Gibe III and the mineral, oil exploration and biofuels projects planned by the Ethiopian government in the Omo River basin will violate that UN convention and jeopardize the survival of the tribes who live downstream.

    Even if Gibe III is not built, the region will face problems due to resource constraints that are accelerating because of global warming. The NGOs would like the international community to take a fresh look at development and conservation issues in the Horn of Africa.

    Following the end of the civil war in Southern Sudan, combatants from Ethiopia who participated in the conflict returned home—with their weapons. Peter Greste, a BBC reporter who traveled down the Omo River earlier this year to film a documentary [http://news.bbc.co.uk/2/hi/africa/7959444.stm] on Gibe III, found that disruptions in water flows could lead to outbreaks of violence.

    In 2008, Ekwe Ethuro, a member of the Kenyan parliament from the area of Lake Turkana, questioned why the Kenyan Government had not followed Egypt’s example in threatening to go to war with any country which might tamper with the Nile’s source.
  • + anthony_mitchell Anthony Mitchell 5 months ago
    Public Debate Hindered

    International Rivers obtained a field investigation report prepared by the United States Agency for International Development (USAID) on Gibe III. The report found that public debate in Ethiopia about Gibe III had been limited by political conditions in that country. The report states:

    “The current political landscape for civil society/NGOs remains difficult in the aftermath of the May 2005 parliamentary elections. This political environment discourages public discourse on development issues, including both energy policy and projects to implement the policy.

    “The absence of a free debate in the media also compounds concerns associated with the lack of public discourse. There appears to be tight government control of the media with no questions openly asked concerning national development issues and policies. This further restricts the limited amount of political space civil society has to engage in with the government.”

    Open public discourse is not encouraged by Meles Zenawi, who has led Ethiopia since 1991. Meles has been recognized for his anti-poverty efforts and for allowing Eritreans to vote on whether or not to remain within Ethiopia or form their own country, which they did in 1993.

    Violence and intimidation of opposition supporters following the May 2005 election brought condemnation from election observers and human rights groups. The Carter Center sent observers and reported that the period following May 15 was marked by highly charged political tensions, several days of protests and electoral violence, delays in vote tabulation, a large number of electoral complaints, and a prolonged and problematic electoral dispute resolution process.

    Observers from the Carter Center were allowed to remain in Ethiopia during the 2005 elections. However, the Carter Center’s report on the election noted that three US-based non-governmental organizations (NDI, IRI, and IFES), which could have provided assistance to the electoral process, were expelled in the months prior to the election.

    On March 22, 2009, Parade Magazine ranked Meles Zenawi in 16th place in its World’s Worst Dictators list [http://www.parade.com/dictators/2009/more-of-the-worlds-worst-dictators.html?index=6].

    According to Peter Bosshard [http://internationalrivers.org/blog/peter-bosshard], policy director for International Rivers, the United States is in a position to encourage environmentally sustainable development for all countries in the region, all of which face similar challenges and all of which have a stake in the allocation and conservation of water resources. Complex challenges surround the colonial-era agreements that govern rights to water from the Nile.

    Ethiopia’s development of water from the Omo River does not face sanctions from Egypt, which has been accused of supporting Al Shabaab’s military activities against Ethiopian interests in Somalia. Egypt has threatened to invade Ethiopia if Ethiopia dams the Blue Nile. The Blue Nile originates in Ethiopia and supplies 56% of the surface water entering Egypt.

    Tanzania appears to be disregarding treaties governing Egypt’s allocation of waters from the Nile and is unilaterally withdrawing water to support its own development efforts.

    “Conflicts over water rights in the region will increase with global climate change and development pressures,” Bosshard said. “The United States is in a unique position to play a constructive role in the region.”
  • + anthony_mitchell Anthony Mitchell 6 months ago
    Gibe III will result in permanently reduced flows to the Omo River because of the hydrogeology of the site of the artificial lake. In the existing river bed upstream of the dam site, groundwater flow direction is most likely to be predominantly horizontal or upward flowing.

    The geology of the remainder of the valley (which the lake will occupy) is predicted to be characterized by groundwater flow direction that is predominantly horizontal or downward flowing. Surface and groundwater are interconnected. It will be impossible to forestall outflows from the lake into the surrounding geology.

    The lake will raise the groundwater table in the region around the dam, resulting in considerable evapotranspiration and decreasing the amount of water passing through the dam and available for downstream use. This will inevitably result in a permanent reduction in the size of Lake Turkana.

    On a personal note, I believe Ethiopia should build additional dams, but should focus on smaller projects that are planned in accordance with commonly accepted international practices. Smaller dams do not have the same impacts or risks as huge projects.

    Ethiopia’s major hydro resource is the Blue Nile, which provides 56% of the surface water that flows into Egypt from the Nile. Run-of-the-river generation facilities can be designed without large artificial lakes and consequent water loss.

Comments 1 - 10 of 12 previous next

Post a comment
Embed Video
Edit your comment Cancel

1 Favorite

Gilgel Gibe III dam Ethiopia: technical, engineering and economic feasibility study report. - Presentation Transcript

  1. Gilgel Gibe III Economic, Technical and Engineering Feasibility Desk Study Report Submitted to the African Development Bank By Anthony Mitchell, April 15, 2009 http://AnthonyMitchell.com Background This report presents the results of an independent study of the feasibility of completing construction and beginning operations at the Gilgel Gibe III hydro-electric project in Ethiopia’s Omo River basin. The Gibe III dam is slated to be 240 meters tall and has a projected generation capacity of 1,870 megawatts of electricity. While the Nurek Dam in Tajikistan stands 60 meters taller than the planned height of Gibe III, in conducting research for this report, no previous example of any dam of Gibe III’s rockfill design with a concrete external liner was found to have been constructed anywhere in the world to the height proposed for Gibe III. A list of other big dam projects is included herein. This report identifies economic, technical and engineering issues at Gibe III. The report finds six areas in need of additional attention to fully assess the feasibility of Gibe III. In describing those six areas, the report suggests priorities for further research and review. The report draws on the findings of an earlier review conducted by the same author in support of a workplan created in 2008 for the World Bank as part of a proposal to assess the feasibility of the Bank providing financial assistance to the Gibe III project. Citing a lack of transparency and the absence of a competitive bidding process in the selection of a prime contractor, the World Bank opted not to proceed with a full review of the funding application for Gibe III. A full-scale economic and technical feasibility study was therefore not conducted. The World Bank’s feasibility study would have provided opportunities for site access and record reviews that are beyond the scope of a desk study. It is not known whether any qualified independent review teams have been given adequate access to the Gibe III project site and project records to date. Construction of the dam has begun with Ethiopian sponsorship and is slated for completion in 2011-2012. Construction is supported in part by the issuance of hard-currency, domestically tax- exempt Millennium bonds marketed to the Ethiopian diaspora at a reported maximum 5% rate of interest. The bonds carry the risks of a premature call and uncertain currency repatriation rights. There is no secondary market for Ethiopian bonds. Ethiopia’s currency does not trade freely on global markets. The Millennium bonds have not been found to be marketed with provisions for independent audits of the bond issue or of subsequent fund distributions or bond repayments. To those uncertainties can be added issues regarding currency repatriation (whether repayments will ultimately be made in Ethiopian currency and at artificial exchange rates), taxation, and the interest to be paid in the event of premature repayment (a “call”). This desk study does not include conclusions or recommendations on whether to provide financial support for Gibe III. It does identify economic, technical and engineering issues regarding the feasibility of the Gibe III project—but not environmental issues because the scope of Gibe III Independent Feasibility Report 1
  2. the World Bank’s proposed economic and technical assessment did not encompass environmental impacts. The results of this study can be used to structure additional research and create decision tools for financial institutions, policy makers and bond analysts. A summary of findings is presented first, with six categories of issues. Detailed findings are then presented for each category. Summary of Findings Permeability: The structural integrity of dams depends in part on the ability of the dam structure to minimize permeability through the structure itself. Some seepage is inevitable, but permeability risks are compounded by the dam’s design and dimensions. Primary permeability is distinguished from more critical issues of secondary permeability, i.e., permeability through joints and cracks in the concrete liner installed on the rockfill dam structure. Secondary permeability rates will govern at Gibe III. The dam will create an artificial lake 150 kilometers long. The lake will retain 11 billion cubic meters of water. That amount of water will exert considerable hydrostatic pressure on the dam structure. If water builds up inside the base of the dam, it will make the facility more unstable and vulnerable to deformation and structural failure during seismic events. Structural stability: Structural stability is initially achieved on the basis of the peak strength of the materials used to construct the dam. After the dam and its foundations have settled and experienced one or more seismic events, materials in the dam may shift beyond the capability of peak strength to hold them in place. Once this occurs, the dam begins to rely on residual strength for its structural stability. Volcanic ash has been a problem at other civil engineering projects in the region. If ash or other low-load-bearing soils are present in the dam or its foundations, then the risk of catastrophic failure will be heightened. The Gibe III contractor’s prior performance at Gibe II provides cause for concern, thanks to the failure of the original design and construction plan to identify and address the presence of weak soils. The risk of catastrophic failure of the dam at Gibe III is not insignificant. Shear strength: Pre-construction measurement and testing of the shear strength of materials to be installed in a dam assists in calculating when and how structural failure or deformation could occur. In assessing Gibe III’s engineering designs, it is important to examine how shear strength was measured. Two principal measurement techniques are contrasted here. Shear-block tests are equated with peak strength. Ring-shear tests can Gibe III Independent Feasibility Report 2
  3. measure both peak strength and residual strength. No evidence was found that appropriate strength testing has been conducted at Gibe III. Monitoring and planning: Dam construction involves more than simply moving rocks around. It involves ongoing and diligent construction oversight, materials testing and laboratory analysis. Is independent construction oversight occurring at Gibe III? • Monitoring devices need to be installed during construction. • Monitoring and contingency plans need to be developed to detect and respond to seepage, shifting, pressure buildup, deformation, movement of the dam and other scenarios during facility operation. • Potential facility failure modes need to be identified and surveillance and monitoring systems put into place for each of them. • Mitigation and emergency response capabilities need to be institutionalized and readied for quick deployment. Economic feasibility: The economic feasibility of a hydro-electric facility is determined in part by power sale arrangements and the performance of electrical generators. Gibe III’s rate structures and performance projections are called into question. Given existing indicators regarding tariff structures in Ethiopia, the electrical power generated at Gibe III could prove to be unaffordable for many of the residential customers for whom the dam is ostensibly being constructed. Economic externalities: The costs and impacts of building and operating a dam often extend beyond the dam site itself. Negative economic externalities can be created where changes in physical resources occur. At Gibe III, physical changes will extend upstream and downstream. So too will economic impacts, which include disruptions in food production and drinking water access. Despite their significance, these impacts do not appear to have been quantified or adequately considered in assessing the economic and technical feasibility of Gibe III. Detailed Findings Permeability In examining the permeability of the dam structure, two types of permeability need to be distinguished. Primary permeability is the rate at which liquids pass through consolidated soil or other materials. Secondary permeability is the rate at which liquids pass through the voids (and highly permeable material) that may exist between more impermeable, consolidated substances. Gibe III Independent Feasibility Report 3
  4. In calculating permeability rates, secondary permeability governs the speed at which liquids travel through materials (where secondary permeability exists) such as highly fractured masses of rock. Published descriptions of Gibe III characterize the dam as a rockfill structure with a concrete exterior liner. Concrete is intended to provide an impermeable barrier, which the dam’s rockfill mass itself cannot do because the voids between the rocks are highly permeable. If properly constructed and maintained, concrete’s low primary permeability can allow it to serve as an effective water barrier for long periods of time, especially in small structures protected from extreme temperature differentials. Concrete’s primary impermeability is limited by the size of each contiguous concrete mass or slab. Filler material placed in the joints between slabs is designed to allow concrete to expand and contract without cracking. However, seam fillers are vulnerable to damage and deterioration. Cracks and other failures within concrete slabs can create voids that allow for high rates of secondary permeability to negate concrete’s low primary permeability. In a structure as tall as Gibe III there is a risk that the concrete liner will be damaged by differential settling and other structural shifts within the dam and its foundations. These shifts could be aggravated by risks from: 1. Soils containing volcanic ash present under or adjacent to the dam. A bridge in the region reportedly failed because it had been built over volcanic ash that was not strong enough to support the loads placed upon it. 2. Impurities in the water used to make concrete. 3. Differential compaction and uneven settling of the dam structure. 4. Uneven cooling and contraction of the concrete during construction. 5. Heat expanding the concrete and causing it to crack following construction. 6. Seismic activity, for which southwestern Ethiopia is known. See: http://www.ethiopians.com/ earthquake_engineering_resources.htm. The weight of the 11 billion cubic meters of water retained by the dam could trigger seismic events. 7. Excessive moisture inside the base of the dam is liable to make the facility more unstable and vulnerable to liquefaction, deformation and structural failure during seismic events. Detailed engineering reviews of the site’s geology and the dam’s design and construction should assess the risks to the concrete liner failing and reducing the structural integrity to the rockfill structure. A dam failure will not necessarily result in the complete release of all impounded water. Risks of failure at Gibe III need to be considered in the context of the dam’s slope and scale. At 240 meters in height, Gibe III will exceed the height of these existing dams: • The Three Gorges Dam in China, at 101 meters in height • Cahora Bassa Dam, Zambezi River, Mozambique, 171 meters • Hoover Dam in the United States, 221 meters • Guri Dam or Central Hidroeléctrica Simón Bolívar in Venezuela, 162 meters • Itaipu Dam on the border between Brazil and Paraguay, 196 meters • Grand Coulee Dam in the United States, 168 meters Structural stability Gibe III Independent Feasibility Report 4
  5. The stability of the dam depends on the strength of materials at their weakest points, which is often found where materials join together, such as rocks-to-rocks or concrete on top of rocks. Calculations of sheer strength would or should have served as a basis for determining the dam’s dimensions. An outside engineering review needs to examine how those calculations were made and how the sheer strength of the dam was modeled under static loading and different (and repeated) seismic events. Two types of sheer strength can be distinguished: • Peak strength • Residual strength When you dislodge a rock and begin to move it, peak strength is the energy needed to start the rock moving. Once the rock has begun to move, residual strength may be all that is needed to keep the rock moving. As the dam weighs down soils within and beneath the structure or is jolted by seismic events, peak strength could be exceeded in portions of the facility. This will leave the structure’s integrity reliant on residual strength. Given the nature of the local soils, voids present within the rockfill structure, repeated seismic activity in the area and pressures exerted by the mass of water that will build up behind the dam, an engineering study needs to assess the consequences of peak strength being exceeded during the dam’s lifecycle and then how the dam structure could react under different scenarios. The Gibe III prime contractor’s level of previous experience with dam projects the size of Gibe III, and the contractor’s inclination to perform pre-construction engineering studies (as evidenced by the interruption of work at Gibe II due to a failure to adequately perform pre-construction geological testing) underscores the importance of examining whether and how residual strength was measured and factored into the Gibe III design. Measurement of shear strength The strength of two materials where they come together can be measured using sheer block tests and ring sheer tests. Sheer blocks: A sheer block test places a sample on a block and pushes it laterally over another sample. While sheer blocks can be used to measure peak strength, the fact that fresh, untouched base material is constantly being encountered on the lower portion of the test unit’s slip surface makes sheer block tests unsuitable for assessing the residual strength of slip surfaces because they consistently over-state calculations of residual strength. Ring sheer: A ring sheer test has the upper test substance rotated over the base substance in a circular, ring-like motion that enables both test surfaces to achieve full contact before residual strength is determined. Ring sheer tests can provide accurate data on both peak strength (at the beginning of a test sequence) and residual strength—once peak strength has been exceeded. Gibe III Independent Feasibility Report 5
  6. An independent engineering assessment should examine how sheer strength was measured at Gibe III and seek to assess the extent to which the design will remain stable once peak strength has been exceeded. Monitoring and planning Monitoring and contingency planning is important in all phases of a dam’s lifecycle. It is critical during construction. The adequacy of oversight of the construction process needs to be evaluated as part of an independent engineering and technical study. The oversight capabilities and practices of the Ethiopian Electric Power Corporation (EEPCo) and government regulatory agencies in Ethiopia to oversee the design and construction of the Gibe dams should be evaluated. Technical expertise (supported by adequate oversight procedures, training, laboratory analysis capabilities and resources for onsite monitoring) are needed to ensure that proper engineering practices were followed by Salini Costruttori, the prime contractor at Gibe III and the previous two Gibe hydroelectric projects. Sound engineering and construction practices can be employed to reduce structural risks at big dam projects but not eliminate them. Hence the need for monitoring and contingency planning. Monitoring plans at Gibe III need to be reviewed for adequacy in detecting and responding to seepage, movement of the dam structure, excessive pressure on the dam structure and other indications of failure. Proper placement of instrumentation needs to be planned prior to facility construction and subject to independent outside review. During construction, the following should be installed: • Observation wells and piezometers • Plumb lines • Load cells • Strain gauges A list of potential problems with the facility needs to be developed and contingency plans readied, tested and institutionalized for each potential problem. Potential failure modes need to be identified, with monitoring and response plans organized for each failure scenario identified. Mitigation and emergency response capabilities need to be built up, monitored and kept ready for launch. Contingency planning needs to be extended to potentially impacted areas downstream, paid for by the dam operator. Periodic reviews need to be initiated of actions taken to reduce the likelihood and consequences of dam failure. Reviews should include: • Facility designs • Design and placement of monitoring systems • Data collection and analysis procedures • Dam operation procedures • Risk-reduction measures Gibe III Independent Feasibility Report 6
  7. • Structural remediation capabilities • Contingency plans and capabilities • Downstream impact reduction • Communication capabilities and procedures Economic feasibility The economic feasibility of the Gibe III project is an open question that would need to take into account the rate structures for selling power generated from the facility and the service agreement with the dam operator. Global climate change and diminished water supplies are reducing power generated at hydro-electric facilities elsewhere in the world and appear likely to do so at Gibe III. Liability exposure and allocation in the event of unanticipated outcomes at the Gibe projects needs to be clarified and examined. Unanticipated events could interfere with loan repayments and the supply of electricity to residential consumers in the franchise areas served by the Gibe hydro-electric projects. Tariff structures for selling electricity from the Gibe projects and the service agreements with the electrical utility and the contractors engaged in the Gibe projects need to be examined to assess whether and how investors and bond holders can be repaid under a variety of performance scenarios. Rate structures and service agreements need to be examined to determine whether they are equitable, reasonable, and conform to general principles of fairness, soundness and best utility-rate-practices. The viability, independence and fairness of systems for resolving tariff disputes should also be examined. National and local governments (and many international organizations) lack the expertise and resources to conduct rate studies and to adequately and fairly respond to subsequent rate disputes and rate appeals. These institutional and systemic shortcomings have led to unexpected economic burdens from utility projects in many areas of the world, including Western countries where such expertise is more readily available. Tariff systems commonly operate outside of normal government channels for taxation and appropriation. Their frequent lack of transparency and their ability to generate significant recurrent revenues makes utility franchises an attractive vehicle for private enrichment at public expense. The larger the infrastructure project, the greater the opportunities for kick-backs and diversion of funds away from purposes that are used and useful to rate payers. Even where instances of outright fraud and corruption are low, poor decisions in utility infrastructure planning and financing can exercise profound, long term negative economic effects. EEPCo’s existing tariff and electrical distribution policies are reputed to favor large industrial and commercial users over residential consumers. Cross subsidization of industrial and commercial users by residential customers, who pay disproportionally higher rates for the same amount of electricity, can unreasonably benefit industrial and commercial users, while under serving residential consumers whose lack of access to electricity originally served to justify public investments in the Gibe dam projects. Gibe III Independent Feasibility Report 7
  8. The affordability and equitability of electrical tariffs can be reduced in the event that generation capacity falters due to unplanned events such as water shortages and maintenance problems. It is not known whether or how power sale agreements may favor specific customers or classes of customers in the event of generation shortfalls or cost increases involving the Gibe projects. While wholesale customers may be provided with guaranteed supplies of power at relatively low cost, it is possible that EEPCo’s rate structures could allocate responsibility for cost increases and generation shortfalls to categories of rate payers least able to afford it. Contract terms, oversight arrangements and tariff-dispute-resolution systems may neither allow nor encourage adequate control of costs once Gibe III becomes operational. Contract terms and oversight arrangements may allow costs to be passed on for expenses that are not used or useful to some classes of rate payers, thereby violating central principles of equity and fairness in utility rate systems. Electrical power from Gibe III could be unaffordable to substantial numbers of residential customers for whom the dam project is ostensibly being built. Residential customers appear likely to subsidize the electricity used by commercial and industrial customers. Considerable attention needs to be devoted to assessing the financial aspects of the Gibe III project and the institutional factors surrounding tariff-system administration. When neglected, the financial terms and conditions of electrical projects can exercise long-term negative effects on some economic sectors, interfere with debt servicing and divert resources away from productive purposes. The allocation of liabilities at Gibe III deserves attention in light of the nature and extent of the risks inherent in the Gibe III project and the manner in which risks have been monitored and controlled to date. The need for a new approach to risk management at EEPCo is underscored by the fact that research activities to support the preparation of this report were repeatedly hindered by EEPCo’s website. EEPCo’s main website www.eepco.gov.et was found to be propagating ‘Silent love China’ computer attacks that attempt to install Trojan software on visitors’ computers and steal passwords. It is recommended that www.eepco.gov.et not be visited until corrective actions have been taken. Security breaches within EEPCo’s computer systems need to be investigated and corrected immediately, with enhanced security monitoring and response capabilities instituted and maintained. Independent outside auditing of EEPCo’s computer security practices should also be instituted and maintained. From the outside, it is now known whether EEPCo has been breached by deliberate acts of espionage by government agencies within the Peoples’ Republic of China or by Chinese criminal groups. The nature of the breach at EEPCo, which purposely avoids infecting PRC government websites, suggests the former. Given their commercial interests at stake in Ethiopia, one would have expected that the Italian government and Salini would have defended their interests and sought to prevent Chinese interference at EEPCo, regardless of whether security breaches stemmed from PRC government agencies or private parties. Actual responsibility for defending EEPCo’s interests rests with EEPCo itself, notwithstanding EEPCo’s inability or unwillingness to do so. Economic externalities Gibe III Independent Feasibility Report 8
  9. In addition to the aforementioned economic considerations regarding Gibe III, the following negative externalities appear as costs to populations who will bear disproportionately negative economic and quality-of-life impacts as a result of Gibe III. Economic losses are likely to be experienced from increases in disease caused by the dam’s impacts on the physical environment. Specifically: • Increases in schistosomiasis (also known as bilharzia or snail fever) are expected upstream of the dam. According to the United States Centers for Disease Control and Prevention: Children who are repeatedly infected can develop anemia, malnutrition, and learning difficulties. After years of infection, the parasite can also damage the liver, intestines, lungs, and bladder. Rarely, eggs are found in the brain or spinal cord and can cause seizures, paralysis, or spinal cord inflammation. Symptoms of schistosomiasis are caused by the body's reaction to the eggs produced by worms, not by the worms themselves. • Malaria rates are likely increase around the artificial lake, especially among children, as indicated by a study of malaria rates at Gibe I completed in 2008. Gibe III’s impact on malaria rates downstream should also be examined. Downstream economic losses do not appear to have been adequately examined in the host nation’s planning activities and reviews of the dam conducted to date. In order to meet electricity sales targets, water withholdings in excess of publicly announced levels may occur. Impacts from evapotranspiration, evaporation and ground water recharge from the artificial lake created by Gibe III have not been found to be adequately recognized in the official plans for Gibe III. These water losses will expand the need for additional water withholdings from the Omo River and will inevitably lead to decreases in water released downstream. Loss of water in the Omo River basin will translate into reduced flows into Lake Turkana, shrinking the size of the lake and altering the lake’s chemistry. Lake Turkana is a high desert lake largely located in Kenya. The lake is the destination of the Omo River. The lake is a source of potable water and food (from fishing). It reportedly provides support for 300,000 people, many of whom have no viable economic alternatives. Lake Turkana is already stressed. The lake has been receding and becoming more alkaline, which threatens to make its water undrinkable. Resources for securing alternate potable water supplies have not been identified. Gibe III would contribute additional stress and lower economic outputs from the lake and the Omo River basin. “Stopping the periodic inundations that replenish floodplains in the R Omo and its delta region will have a direct effect on several commercial [fish] species that depend on those areas as nurseries,” said Dr. Peter B. Bayley, Department of Fisheries & Wildlife, Oregon State University, who has conducted research on fisheries in the Omo River basin. Eliminating periodic inundations in the Omo River basin will disrupt food supplies for downstream communities that have developed sophisticated agricultural practices that depend on existing water Gibe III Independent Feasibility Report 9
  10. supplies and flow cycles. Disruptions in food supplies do not appear to have been fully taken into account in planning for the dam, nor have adequate mitigation measures reportedly begun to be implemented downstream. Changes in water supplies will accelerate resource competitions among tribes downstream and could lead to armed conflicts. Adversely impacted individuals and localities do not appear to have been granted adequate legal standing and enabling resources that would allow them to participate at key junctures of the dam’s permitting, licensing and funding processes. Nor does the existing permitting and licensing process appear to have been conducted independently from the process of pro-actively arranging for the Gibe III project to be implemented. A lack of independent outside participation in planning, regulatory and technical matters has deprived all three Gibe hydro-electric projects of valuable inputs that would have reduced risks for project sponsors, investors and electrical rate payers. As demonstrated by the failure of Gibe II to be implemented as planned, the lack of independent oversight and meaningful stakeholder participation has contributed to cost over runs, project delays and wasted allocations of public resources. In the case of Gibe III, the stakes are higher, notably in regard to engineering and financial risks and impacts on populations whose survival depends on maintaining access to existing natural resources. END Gibe III Independent Feasibility Report 10

+ Anthony MitchellAnthony Mitchell, 6 months ago

custom

4533 views, 1 favs, 1 embeds more stats

Gilgel Gibe III hydro-electric dam, Ethiopia: techn more

More info about this document

© All Rights Reserved

Go to text version

  • Total Views 4533
    • 4523 on SlideShare
    • 10 from embeds
  • Comments 12
  • Favorites 1
  • Downloads 57
Most viewed embeds
  • 10 views on http://medeshi-medeshi.blogspot.com

more

All embeds
  • 10 views on http://medeshi-medeshi.blogspot.com

less

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

Cancel
File a copyright complaint
Having problems? Go to our helpdesk?

Categories