Phase 2A<br />In this slide show: <br />West Canopy & Interior Work<br />July 8, 2011<br />
New west side canopy completed with all lighting installed.  <br />
New copper gutter installed on north canopy adjacent to Plaza. <br />
A large roll-up door installed on the west wall. <br />
The future baggage area gets a new door with brass fixtures and restored windows that allow plenty of light. <br />
This beautiful marble counter was reinstalled.<br />
The freshly refurbished grand staircase steps and new stainlessness rail.  <br />
Mechanical systems under the plaza in the final stage of installation. <br />
Communications equipment room under construction.<br />
Staircase and lift door (right of stair) to mezzanine space above future Amtrak offices. <br />
At the mezzanine level this area will serve as restrooms and locker rooms. <br />
Future Amtrak break room on the mezzanine level. <br />
Additional interior partitions installed for future use. <br />
This space, under the northeast corner of the plaza, will be the recycling room. Metallic, automatic roll-up doors provide...
A new steel guard plate installed to protect Jackson Street structural wall. <br />
On the station’s west side crews installed 31 additional geothermal wells expanding the efficient, sustainable heating and...
Upcoming SlideShare
Loading in...5
×

7.6.11 West Canopy & Interior Work

2,003

Published on

Published in: Art & Photos, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
2,003
On Slideshare
0
From Embeds
0
Number of Embeds
3
Actions
Shares
0
Downloads
1
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

7.6.11 West Canopy & Interior Work

  1. 1. Phase 2A<br />In this slide show: <br />West Canopy & Interior Work<br />July 8, 2011<br />
  2. 2. New west side canopy completed with all lighting installed. <br />
  3. 3. New copper gutter installed on north canopy adjacent to Plaza. <br />
  4. 4. A large roll-up door installed on the west wall. <br />
  5. 5. The future baggage area gets a new door with brass fixtures and restored windows that allow plenty of light. <br />
  6. 6. This beautiful marble counter was reinstalled.<br />
  7. 7. The freshly refurbished grand staircase steps and new stainlessness rail. <br />
  8. 8. Mechanical systems under the plaza in the final stage of installation. <br />
  9. 9. Communications equipment room under construction.<br />
  10. 10. Staircase and lift door (right of stair) to mezzanine space above future Amtrak offices. <br />
  11. 11. At the mezzanine level this area will serve as restrooms and locker rooms. <br />
  12. 12. Future Amtrak break room on the mezzanine level. <br />
  13. 13. Additional interior partitions installed for future use. <br />
  14. 14. This space, under the northeast corner of the plaza, will be the recycling room. Metallic, automatic roll-up doors provide convenient access. <br />
  15. 15. A new steel guard plate installed to protect Jackson Street structural wall. <br />
  16. 16. On the station’s west side crews installed 31 additional geothermal wells expanding the efficient, sustainable heating and cooling systems.<br />
  1. A particular slide catching your eye?

    Clipping is a handy way to collect important slides you want to go back to later.

×