Your SlideShare is downloading. ×
0
Everything you need to know about broadband towers and land use issues
Everything you need to know about broadband towers and land use issues
Everything you need to know about broadband towers and land use issues
Everything you need to know about broadband towers and land use issues
Everything you need to know about broadband towers and land use issues
Everything you need to know about broadband towers and land use issues
Everything you need to know about broadband towers and land use issues
Everything you need to know about broadband towers and land use issues
Everything you need to know about broadband towers and land use issues
Upcoming SlideShare
Loading in...5
×

Thanks for flagging this SlideShare!

Oops! An error has occurred.

×
Saving this for later? Get the SlideShare app to save on your phone or tablet. Read anywhere, anytime – even offline.
Text the download link to your phone
Standard text messaging rates apply

Everything you need to know about broadband towers and land use issues

591

Published on

Published in: Education, Business, Technology
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
591
On Slideshare
0
From Embeds
0
Number of Embeds
1
Actions
Shares
0
Downloads
0
Comments
0
Likes
0
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. Facility Installation – FiberJames T. Burroughs
  • 2. Linear Construction Project
    Crosses all imaginable types of property ownership and triggers all conceivable land use permitting issues
  • 3. Project Description
    Trench
    Plow
    Rock cutting
    Bridge attach
    Usually not aerial (for security and facility protection purposes)
    Signal regeneration stations
    Marker posts (aesthetic issue sometimes)
  • 4. Right-of-way issues
  • 5. Typical Project Team
    Engineers
    ROW agents
    Environmental consultants
    Lawyers
  • 6. Permitting Agencies-Depends
    County/City CUP
    Water crossings
    Listed species
    State-owned land
    Federally-owned land
    Coastal Commission
    Flood control districts and their conveyance facilities
    Usually notAQMD
  • 7. CEQA Compliance
    Lead agency
    “Binding" on responsible agencies for MND's and EIRs
    Typical Issues
    Typical mitigation
  • 8. Permitting Timeline
    Depending on the length and complexity of the project:
    45-60 days with a CatEx
    6-12 months with a MND
    12-24 months with EIR
  • 9. Litigation
    Relatively rare
    Challenge to control costs and deliver the fiber product on a timely basis

×