Global Energy Group Presentation - Presentation Transcript
A presentation of the
Global Energy Group
April 2009
Mission Statement:
“We strive to be our clients first choice in the provision of integrated
management services and solutions”
Vision Statement:
“To develop the Global Energy Group into a world class provider of
client solutions whilst providing a safe and rewarding working
environment for our people.”
Roy MacGregor - Chairman
The Group
contracting and service-based company supporting the
International Energy Industry.
flexible approach to supporting clients, offering turnkey project
solutions or stand-alone services in:
project engineering
fabrication
specialist welding
inspection
supply-chain management
managed resources
construction
Whether we are supporting a segment of our clients project, or an
integrated delivery of service, our commitment to safety and
quality is without exception.
Background
Based in the UK (Scotland) – with worldwide operations
Employs in excess of 2200 staff and contract personnel
Dynamic Growth :
£28m by financial year end March 06
£65m by financial year end March 07
£96m by financial year end March 08
£130m by financial year end March 09 - forecast
Integrated Management System: 1SO 9001 Certified by DnV
Global Core Values
People Pioneers
People
Global’s People make our success possible
We will provide a secure, safe and challenging environment, promote a
positive attitude and encourage personal development
We will create a culture centred on care, respect and reward
Integrity
Global’s integrity is not negotiable
We will maintain the highest moral and ethical standards
We will honour our commitments and reflect respect and trust in all
relationships
Quality
Global’s quality is assured by performance excellence
We aim to deliver above and beyond our client‟s expectations
We will research and develop innovative solutions to remain best in class
Marketplace
CIVIL OFFSHORE
CONSTRUCTION DRILLING
UTILITIES & SUBSEA &
INFRASTRUCTURE MARINE
RENEWABLE PETROCHEM /
ENERGY LNG
Organisational
Chart
Corporate Company Secretary
Board of Directors
HSEQ Department Finance Director
Organisational
Development Technical Services
Group Business
Development Communications
Group Training
Global Global Global Global Global Energy Global
Resources Construction Inspection Fabrication Services Pipelines
Global Global Global Energy Global Pipeline
Reel Isleburn
Resources Construction Services Solutions
Les Taylor Global Project
Maris Subsea Sea Ocean
Construction Services
Global
Highland
Global SCS
Group Organisation Chart March 2009
Fabrication Fabrication
Oil & Gas Fabrication and Engineering
Oil & Gas Operators
Subsea Installation Contractors
Decommissioning Specialists
Mobile Drilling Rigs Operators
Renewable Energy
Offshore Wind Farms
Wave and tidal energy development
Nuclear
M & E Utilities; Infrastructure
Road & Rail Bridge construction and
installation
Replacement and refurbishment of Lock
Gates
Power Generation Site blasting and painting
Port facility enhancements
Single source for all disciplines
MOD Engineering solutions
Client : Subsea 7
Project : Jura Manifold / Towhead
Fabrication
Typical Project
420 tonne Manifold /
Towhead
Sales Value £3.0 M
Contract award to
completion 18 weeks
Project Scope
Procurement of structural materials, fabrication and painting.
Receipt of F.I Duplex piping materials and valves, fabrication, installation, painting,
flushing & pressure testing
Fabrication, fitting, integration with control panels, flushing & pressure testing of
small bore control tubing
Full FAT / SIT inside workshop
Transport from Nigg Workshop and load out to barge at Nigg Quayside
Client : ConocoPhillips
Project Britannia Satellites Topsides Skid Units
Fabrication
Typical Project
9 No Skid Units from 10 tonnes to
140 tonnes
Sales Value £3.6 M
Contract award to completion
12 months
Project Scope
Procurement of structural materials, fabrication
and painting.
Receipt of piping materials and equipment,
fabrication, installation, painting, insulation, flushing
& pressure testing
Electrical & Instrumentation installation and testing
FullzFAT / SIT inside workshop
Transport from Nigg Workshop and load out to ships
at Nigg Quayside
Client : MOD / DML
Project RAH – Reactor Handling Containment Module
Fabrication
Typical Project
600 tonne Module for refuelling of
nuclear submarines
Sales Value £5.4 M
Contract award to completion 24
months
Project Scope
Procurement of structural materials, fabrication and painting.
Outfitting of equipment and testing
Erection on barge and float out into drydock
Installation over drydock onto skidding system
Full load test and functional test
Client : Aquamarine
Project Prototype Wave Generator (Oyster)
Fabrication
Typical Project
Oyster Prototype Wave
Generator 240 tonnes
Sales Value £2.4 M
Contract award to completion
12 months
Project Scope
Procurement of structural materials, fabrication and painting.
Outfitting of equipment and testing
Trial operation in workshop
Pressure testing of system
Transport to quayside and load out
Inspection Inspection
REEL Group - Principle Services:
NDT – MPI and DPI Disciplines
NDT – Eddy Current and Ultrasonic Inspection
Lifting Equipment Inspection and Testing
Hoisting, Handling and Rotary Drilling Tool Inspection
Special Periodic Surveys (ABS, DNV, USCG)
Wall Thickness and Corrosion Monitoring Services
Drilling Derrick and Mast Inspection
DROPS Hazard Inspections
Rope Access Services
Electromagnetic Wire Rope Inspection
Wire Rope Services
Spooling Services
Diving Services
Client: Technip
Vessel: CSO Deep Pioneer
Project: Wire Rope NDT Inspection &
Inspection high pressure lubrication
Typical Project
In-service Maintenance project
2 NDT Wire Rope Examiners
Inspection carried out whilst operating
offshore Ghana, West Africa
Project Scope
NDT Inspection of main 120mm Dia VLS
Lift Wire
Pressure Lubrication of main 120mm Dia
VLS Lift Wire
Verify Rope is fit and safe for service in a
3:1 operating system
Ensuring correct spooling and running of
rope
Client: Bird Air
Location: Reliant Stadium
Project: Roof Replacement
Inspection
Typical Project
$ 2 Million Sales
38 Personnel
Nov 2008 to Mar 2009 (20 weeks) - Houston
Replace and repair roof after Hurricane Ike
Project Scope
Supply specialist rope access teams
Undertake repairs of existing roof
structure
Replace all roof material sections
Energy
Services
Energy Services - Drilling
Principle Services
Full Turnkey Projects
Project Specific Solutions
Services Capability
Project Management / Supervision
Survey, Workscope & Budget Development
Structural / Mechanical & Piping Engineering &
Draughting (Repair & Upgrade)
Specialist Equipment Sourcing & Procurement
Marine Systems Upgrade, Overhaul & Repair
Special Periodic Survey associated with Class
Approval
Construction & Commissioning of Structural /
Mechanical / Hydraulic / Pneumatic & Electrical
Systems
Accommodation Upgrade & New Build
Client: Essar Oil
Vessel: Essar Wildcat
Energy Project: Major Reactivation Program
Services
Typical Project
Turn-key Project (Reactivation)
£7 Million Sales
260 Personnel at peak (160 direct Global
Employee‟s)
Dec 2007 to Mar 2008 (10 weeks) - Invergordon
Project Scope
Inspection of Marine, Drilling & Subsea Equipment
Prepare detailed SOW, Budget & Project Plan
Liaise with DnV – Class Approval Recertification
Prepare & Manage Rig move from open waters to
dock-side facility
Undertake Repairs/Refurbishment /Overhaul of
Primary/Secondary Structure, Piping, Mechanical
Equipment, Electrical SCR‟s, & Accommodation
Undertake upgrade design, pre-fabrication,
installation & commissioning.
Client: Oceanrig A/S
Vessel: Leiv Eriksson
Energy Project: Major North Sea Upgrade
Services
Typical Project
Turn-key Project (North Sea Upgrade)
£5.5 Million Sales
160 Personnel at peak (145 direct Global Employee‟s)
Sep 2007 to Jan 2008 (17 weeks) – Tow from Angola to Las
Palmas, Las Palmas Yard & Tow to UKCS
Project Scope
Prepare detailed SOW, Budget & Project Plan
Subsea Systems Support Assemblies Installation
Design, Fabrication, Installation & Commissioning of 96,000
ltr Slop Tank (Gross Weight “Steel”: 30Te).
Design, Fabrication & Installation of New Bulkheads,
Enclosures & Associated Platforms
Design, Fabrication & Installation of Cantilevered W/C
ROV LARS
Fabrication, Installation (Re-route) Exhaust & Engine Air
Intake Vents
Energy
Services
Energy Services – Marine
Principle Service
Launch System Structural / Mechanical Design
Subsea Tooling Design
Topside Equipment Structural/Piping Integration
Mob/Demob Management & Execution
Service Specific Capability
Feasibility Study
Conceptual Design & Budget Proposal
Detailed Design & Analysis
Installation / Commissioning Procedure Development
Project Management
Project Delivery
Client: Subsea 7
Vessel: DSV Seven Sisters
Energy Project: ROV LARS Integration
Services
Typical Project
Shelter Deck Extension
Integrate 2 No W/C ROV LARS
£0.5 Million Sales
Oct 2007 to Mar 2008
Project Scope
Survey of Vessel, ROV Equipment and propose conceptual design solutions
Prepare detailed SOW, Budget & Project Plan
Detailed Design c/w relevant Structural /Mechanical Analysis & Drawings
Liaise with DnV – Class Approval Management
Develop Installation / Commissioning Procedures and relevant Risk Assessments
Provide Site Management & Engineering Support
Client: Integrated Subsea Services
Vessel: DSV Normand Tonjer
Energy Project: ROV & Air Dive LARS
Services Integration
Typical Project
New Mezzanine Deck
Integrate 4 No W/C ROV LARS
Integrate 1 No Air Dive LARS
£0.6 Million Sales
Oct 2007 to Mar 2008
Project Scope
Survey of Vessel, ROV & Air Dive Equipment and propose conceptual design solutions
Prepare detailed SOW, Budget & Project Plan
Detailed Design c/w relevant Structural /Mechanical Analysis & Drawings
Liaise with DnV – Class Approval Management
Develop Installation / Commissioning Procedures and relevant Risk Assessments
Provide Site Management & Engineering Support
Provide Site Installation Personnel for Installation
Energy Services
Global
Energy Downstream
Services
Principle Services
Specialist Welding Services
(semi / automatic / STT)
Pipespool Fabrication for Petrochem / LPG /
Power Generation
Mechanical / Electrical / Instrumentation /
Commissioning
Mechanical Contractor Support
Managed Site Services
Client: Whessoe / AMEC
Site: Milford Haven Wales
Energy Project: Dragon LNG Plant
Services
Typical Project
Construction of New Build LNG Plant
Project value £36 million
Construction phase for Global June
07 till June 09
Project Services workforce 315 peak
personnel
Project Scope
Provision of Site Project Managed Team
Provision of Specialist Welding services Tanks
Provision of Mechanical / Piping / Fabrication / Rigging / Welding services
Qualification of all WPQ‟S for Client
Provision of Equipment / Plant Hire and Material Consumable Purchase to Client
Project included Construction activities covering Fabrication, M&E, Commissioning
& Testing of Tanks / Jetty Head / PAR & PAU Units / Process Pipework.
Client: Vetco Aibel
Site: Haugesund Yard
Energy Project: Marathon Alviem FPSO
Services
Typical Project
Construction & Outfitting of Topside
Module Units for FPSO
Project Value £18million
Duration of Project 24 months
Project Services workforce 140
personnel peak
Project Scope
Yard provision of Supervisory / Multi Trades
Construction Fabrication activities
Specialist Welding services
Project included the Construction activities covering Fabrication of Topside Process
Module Units during Yard stay, through to Integration of Modules to Vessel.
Project included the Commissioning & Testing of associated M&E products during
Yard and Offshore execution activities.
Client: Aker Solutions/Fabricom
Site: Ormen Lange LPG
Global Project: Ormen Lange Project
Energy
Services
Typical Project
Construction of Gas Terminal for
Statoil
Project Value - £22M
Duration – 28 months
Project Services Workforce – 360
peak
Project Scope
Welding, Pipefitting to support PAU‟s
Full contract management workscope
Full logistics workscope
M /E & Instrumentation
Commissioning of Plant
Global
Pipelines &
Specialist Pipeline Solutions
Welding
Areas of Expertise include:
In-House Welding Research and Development.
Weld Procedure Development and Qualification
Manual, Semi-Automatic and Automatic welding systems, welding
techniques and associated processes.
Total site fabrication and construction solutions to include Welding, NDE, FJC
and Inspection Services (Utilising CRC-Evans FJC and NDE companies).
Management of all aspects associated with Spoolbase Operations – Project
Management, Commercial, Engineering, Operations (All disciplines).
Applications to include SCR‟s Flowlines, Bundles, Double Joints, Quad Joints,
Hex Joints, Spools, Risers, Pipe In Pipe, Cladded Flowlines and HDPE Linepipe.
Material Welding and Metallurgy to include Carbon Steel, Stainless Steel,
Duplex, Super Duplex, Inconel Clad, 5% Chrome, 13% Chrome and Titanium.
Services provided to both Onshore and Offshore pipeline construction
markets.
Expertise of working within Europe, Africa, Middle East, Russia, U.S.A and
South America
Client: Subsea 7
Site: Seven Oceans
Pipelines &
Specialist Project: Shell BC 10 (Brazil)
Welding
Typical Project
10” Diameter X up to 40mm WT
Very restrictive criteria to meet
Mechanised GTAW / GMAW Process
GPS Personnel requested for WPQ
Successful qualification of WPQ (inc.
fatigue)
Ongoing Welding onboard Subsea 7 Vessel
All welds to-date completed by GPS
4 Riser assemblies now installed
( 3 welds per assembly)
Work should continue till end May 2009
Client: Murphy’s Pipelines UK
Site: Brecon Beacon, Wales
Pipelines & Project: BG / Transco Main Trunkline
Specialist
Welding
Typical Project
10” Diameter X up to 40mm WT
Very restrictive criteria to meet
Mechanised GTAW / GMAW Process
GPS Personnel requested for WPQ
Successful qualification of WPQ (inc.
fatigue)
Ongoing Welding onboard Subsea 7
Vessel
All welds to-date completed by GPS
4 Riser assemblies now installed
( 3 welds per assembly)
Kupe Project
Pipelines &
Specialist
Welding
New Zealand Spool Base
Typical Project
.
28km of 12” rigid flow line including 2km of fatigue sensitive flow line
(SCR Standard) 300m of 12” dupex
Resource
Resource
Management
Management
Resource Management
Contract Recruitment
Staff Recruitment
Campaign Recruitment
Oil and Gas / Energy Sectors
Drilling
Subsea & Marine
Technical
Professional
Civil Construction Sector
Construction Management
Civil Engineering
Mechanical & Electrical
Surveying & Architecture
Trades & Labour
Global
Construction Construction
Principle Services
Full Turnkey Projects
Project Specific Solutions
Services Capability
Project Management / Supervision
Conceptual Design & Budget Proposals
Detailed Design & Build Contractor
Provision of Construction Trades Teams for Project
Execution
Service Sector
Commercial, Housing Associations, Energy
Companies, Utility Companies, Local & regional
Authorities, Private Industry & Power Companies
Global Construction
Energy
Services
Projects
Typical Project
Property Demolition/Conversion for Workshop to
Luxury Office Accommodation
£600k Sales
35 Personnel (Various Trades)
Construction Phase: Aug 08 to Jan 09
Project Scope
Survey and Proposal Development
Develop Conceptual / Detailed Design
Prepare Budget and Project Plan
Liaison with Statutory Authorities for Design Approval
Procurement
Provision of Project Management, Supervisory and
Trades Labour for demolition, construction and
commissioning
Global Construction
Construction Projects
Client: The Highland Council Client: The Highland Council
Duration: Sep 2005 – Oct 2006 Value: £290k
Value: £2.5 Million
Grantown Grammar School Sports Facility Braenock Bridge, Foyers
Major new sports hall and changing rooms, Demolition of existing old bridge and
complete with ground source heating system replacement with new insitu concrete bridge
and all Mechanical & Electrical Services. 50+ positioned over a river gorge whilst continuing
Personnel. the flow of traffic at all times.
Facilities
Global Energy Group
International Locations
Invergordon
Evanton
Haugesund Inverness Aberdeen
UK
Houston Cairo Glasgow
Trinidad
Pipelines &
Specialist Hartlepool
Welding
Berths 5 All Tidal Access
Depth of Water 8.5m LAT On berths
Depth of Water 5.0m LAT Approach Channel
Training
The Global Training Facility
Nigg
Trainees and Instructors at
the New Global Training
Academy
Recognition of Industry shortages
Retaining Industry experience and skills
Fast-track Modern Apprenticeship Programme
Welding, Fabrication & Pipefitting Training
Vocational „on the job‟ learning
Guaranteed job on successful completion of
training
Leadership & Management
Development
The people -
JV’s / MOU’s
Norwegian
Global
Energy JV Bergen Yards
Services
Forklifts 1,5-12 ton.
Terminal tractors and
hangers 20-100 ton.
Mobile cranes from 55-220TM
Approx. 100 ton scaffolding
Access control system
Stair towers
Global
Project Malta
Services
2090m x 50m x 6m graving dry-dock
Dockside cranes of 125T, 80T and 40T.
2 main quays with a total length of 500m
equipped with 2x 40T cranes, 1x 48T, 1x 40T
Main workshop, with covered area of
30,000m2 comprising:
unit assembly hall
block assembly
panel line bay
plasma and gas cutting machines
hydraulic presses up to 2000T
Other workshops including:
Machine shop
Joinery complex
Plate/profile treatment line
Corporate Support
HSEQ
Advice & Guidance on Legislation
Operational Involvement & Support
Auditing & Monitoring
Emergency Response Management
Training and Development & Competency
Human Resources
Advice on Employment Legislation
Well Developed and robust IR Policies
Information technology
State of the Art Systems
Global Network Capacity
Group Training
Occupational Development
Leadership & Management Development Programme
Financial
Commercial Advice
Payroll & Accounting Functions
Working with “Global”
We listen to our customer‟s business needs
We work in partnership to find appropriate solutions
We seek to deliver ongoing benefits
We provide an integrated services relationship
We help deliver improved performance and cost savings
We work to common objectives with clear lines of
responsibility and accountability
We allow our customers to focus on their core activities
0 comments
Post a comment