1. MEASUREMENT OF QUANTITIES
● Mat Naim bin Abdullah @ Mohd Asmoni
● Diploma QS (UTM), BSc. QS (Glasgow
Caledonian University), M.Eng. Construction
(UTM), PhD Facilities Management (UTM)
● matnaim@utm.my
● amn871969@yahoo.com
● C04-308
● 019-7573760
www.utm.my innovative ● entrepreneurial ● global 1
2. MEASUREMENT OF QUANTITIES
Assumption No. 1: Total land area = 10m x 10m
Project Title: Construction and completion of
guard house
Owner: Panicsonic Sdn Bhd
Architect: A to Z Sdn Bhd
Drawing Title: Ground beam and foundation plan
-------------------------------------------------------------------------
Drawn by: Sheila
Checked by: Aaron
www.utm.my innovative ● entrepreneurial ● global 2
4. MEASUREMENT OF QUANTITIES
Construction Method
1. Preliminaries (Initial site works) - % of total cost
2. Site clearance and earthwork
3. Foundation construction (E.g. Piling and footing)
4. Work below lowest floor finish
5. Frame
6. Staircase
7. Upper Floor
8. Roof
9. Wall and partition
10. Door and window
11. Finishes
12. Sundries (Built-in furniture)
13. Building services (M&E, ICT etc)
14. External works (Water reticulation, landscape etc)
www.utm.my innovative ● entrepreneurial ● global 4
5. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
1) Site clearance
1.1) Clear the site including grubbing of Area of the site:
trees, shrubs and demolish any 10 x 10 = 100m2
existing structure and cart away
and dump to the specified
location.
10.00
10.00
----------
100.00 100 m2
----------
www.utm.my innovative ● entrepreneurial ● global 5
7. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
2) Foundation
2.1) Piling including all related works Area of the building:
Length = 3048 + 3048 = 6096
6.10 Width = 3048 + 3048 = 6096
6.10
----------
37.21 37 m2
----------
www.utm.my innovative ● entrepreneurial ● global 7
8. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
2) Foundation
2.2) Excavation for pile cap Size of pile cap = 1219 x 1219
Depth of excavation:
9/1.22 1524 + 50 (lean concrete) = 1574
1.22
1.57
----------
21.03 21 m3
----------
www.utm.my innovative ● entrepreneurial ● global 8
10. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
2) Foundation
2.3) Reinforced concrete Grade 30 for Size of pile cap:
pile cap Length = 1219
Width = 1219
9/1.22 Thickness = 305
1.22
0.31
----------
4.15 4 m3
----------
www.utm.my innovative ● entrepreneurial ● global 10
11. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
2) Foundation
2.4) 50mm thick lean concrete Grade Size of pile cap:
15 for pile cap Length = 1219
Width = 1219
9 / 1.22
1.22
----------
13.40 13 m2
----------
www.utm.my innovative ● entrepreneurial ● global 11
13. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
2) Foundation
2.5) Formwork for pile cap Size of pile cap:
Length = 1219
9 / 4 /1.22 Width = 1219
0.31 Thickness = 305
----------
13.62 14 m2 9/2/1.22
---------- 0.31 6.81
9/2/1.50
0.31 8.37
15.18 15m2
www.utm.my innovative ● entrepreneurial ● global 13
14. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
2) Foundation
2.6) Reinforcement bar Y12 for pile cap Length:
a c
9/2/ 12/ 1.53
---------- b
330.48m x 0.89 kg/m = 294.13kg = a + b + c – cover
---------- = 305 + 1219 + 305 – 6(50)
= 294 kg = 1829 – 300
= 1529
a=305-50-50=205 No. of bars:
b=1219-50-50=1119 = (b/100) + 1
c=305-50-50=205 = ((1219 – 2(50)cover )/100 )+1
A+B+C=1529 = 12 nos.
www.utm.my innovative ● entrepreneurial ● global 14
16. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF Taker off : Checked by:
3.1) Column stump Size of column stump:
3.1.1) Reinforced concrete Grade 30 Length = 229
for column stump Width = 229
Height = 1524 – 305 thickness of pile
9/0.23 cap – (351/2) Half of beam’s
0.23 thickness
1.04 = 1043.50
----------
0.50 1 m3
----------
www.utm.my innovative ● entrepreneurial ● global 16
17. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.1) Column stump Size of column stump:
3.1.2) Formwork for column stump Length = 229
Width = 229
9/4/0.23 Height = 1524 – 305 thickness of pile
1.04 cap – (351/2) Half of beam’s
---------- thickness
8.61 9 m2 = 1043.50
----------
www.utm.my innovative ● entrepreneurial ● global 17
18. MEASUREMENT OF QUANTITIES
Height of column stump
@100 c/c
www.utm.my innovative ● entrepreneurial ● global 18
19. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.1) Column stump Length = a + half beam’s thickness –
3.1.3) Reinforcement bar Y12 for cover + 2 laps
column stump lap
9/4/2.97
---------- a
106.92m x 0.89kg/m = 95.16kg
---------- lap
95kg
= 1524 + (351/2) – 50 + (660x2)
= 2969.50
www.utm.my innovative ● entrepreneurial ● global 19
21. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.1) Column stump Length of link: (length of CS– 2cover) x
3.1.4) R6 link in for column stump 4 +hook Hook
9/6/0.62
----------
33.48m x 0.22kg/m = 7.36kg =(229-100)+(229-100)+(229-100)+(229-
---------- 100)+100=616
7kg
No. of link:
Height of column stump = 1043.50
=(1043.50/229)+1
= 6 nos.
www.utm.my innovative ● entrepreneurial ● global 21
22. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.2) Ground beam Size of ground beam:
3.2.1) Excavation for ground beam Length=3048+3048=6096
Width = 229
2/3/6.10 Thickness = 351
0.23
0.35
----------
2.95m3
----------
3m3
www.utm.my innovative ● entrepreneurial ● global 22
23. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.2) Ground beam Size of ground beam:
3.2.2) Reinforced concrete Grade 30 for Length=3048+3048=6096
ground beam Width = 229
Thickness = 351
2/3/6.10
0.23
0.35
----------
2.95m3
----------
3m3
www.utm.my innovative ● entrepreneurial ● global 23
24. MEASUREMENT OF QUANTITIES
Assumption No. 1: Total land area = 10m x 10m
Project Title: Construction and completion of
guard house
Owner: Panicsonic Sdn Bhd
Architect: A to Z Sdn Bhd
Drawing Title: Ground beam and foundation plan
-------------------------------------------------------------------------
Drawn by: Sheila
Checked by: Aaron
www.utm.my innovative ● entrepreneurial ● global 24
25. MEASUREMENT OF QUANTITIES
Height of column stump
@100 c/c
www.utm.my innovative ● entrepreneurial ● global 25
26. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.2) Ground beam Size of ground beam:
3.2.3) Formwork for ground beam Length=3048+3048=6096
Width = 229
Thickness = 351
2/3/2/6.10
0.35
----------
25.62 26m2
----------
www.utm.my innovative ● entrepreneurial ● global 26
27. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.2) Ground beam Length = (length–2cover)+(2bend-
3.2.4) Reinforcement bar Y10 for 2cover)
ground beam =(6096-(2x50))+(2x351)-(4x50)
= 6498
2/3/4/6.50
----------
156.00m x 0.62kg/m = 96.72kg
----------
97kg
www.utm.my innovative ● entrepreneurial ● global 27
28. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.2) Ground beam Length of stirrup:
3.2.5) R6 stirrup for ground beam Hook
2/3/28/0.86
---------- =(229-100)+(351-100)+(229-100)+(351-
144.48m x 0.22kg/m = 31.79kg 100)+100
---------- =860
32kg
No. of stirrup:
Length of grd beam= 6096
=(6096/229)+1
= 28 nos.
www.utm.my innovative ● entrepreneurial ● global 28
29. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab = length x width
3.3.1) Excavation for ground slab Depth of excavation = 500mm
150mm thick
concrete slab
6.10
6.10 BRC A8
0.50 50mm thick
sand
---------- 300mm thick
18.61m3 hardcore
---------- DPM
19 m3
www.utm.my innovative ● entrepreneurial ● global 29
30. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab = length x width
3.3.2) Reinforced concrete G30 in Depth of excavation = 500mm
ground slab 150mm thick
concrete slab
6.10 BRC A8
6.10 50mm thick
0.15 sand
---------- 300mm thick
hardcore
5.58m3
---------- 6 m3 DPM
www.utm.my innovative ● entrepreneurial ● global 30
31. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab = length x width
3.3.3) Formwork for ground slab Depth of excavation = 500mm
150mm thick
concrete slab
4/6.10
0.15 BRC A8
---------- 50mm thick
sand
3.66m2 300mm thick
---------- hardcore
4 m2 DPM
www.utm.my innovative ● entrepreneurial ● global 31
32. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab = length x width
3.3.4) BRC A8 for ground slab Depth of excavation = 500mm
150mm thick
concrete slab
6.10
6.10 BRC A8
---------- 50mm thick
37.21m2 sand
---------- 300mm thick
hardcore
37 m2
DPM
www.utm.my innovative ● entrepreneurial ● global 32
33. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab = length x width
3.3.5) DPM for ground slab Depth of excavation = 500mm
150mm thick
concrete slab
6.10
6.10 BRC A8
---------- 50mm thick
37.21m2 sand
---------- 300mm thick
hardcore
37 m2
DPM
www.utm.my innovative ● entrepreneurial ● global 33
34. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab = length x width
3.3.6) 50mm sand blinding for ground Depth of excavation = 500mm
slab 150mm thick
concrete slab
6.10 BRC A8
6.10 50mm thick
---------- sand
37.21m2 300mm thick
hardcore
----------
37 m2 DPM
www.utm.my innovative ● entrepreneurial ● global 34
35. MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab = length x width
3.3.7) Hardcore for ground slab Depth of excavation = 500mm
150mm thick
concrete slab
6.10
6.10 BRC A8
0.30 50mm thick
---------- sand
11.16m3 300mm thick
hardcore
----------
11 m3 DPM