What Are Flexible Overhead Budgets? 17- A flexible budget is valid for  a  range of activity A static budget is based on a particular planned  level  of activity This range of activity is the relevant range A flexible overhead budget  is defined as a detailed plan  for controlling overhead cost valid in the firm’s relevant range of activity
Static Budget Versus Flexible Budget 17- Based on planned June production of 4,000 tents, at 1.5 machine hours per tent. We cannot tell from this budget what it would cost to make 3,000 tents. Based on only  ONE anticipated activity level Includes several possible activity levels Exh. 17-1
Advantages Of Flexible Budgets 17- Actual Electricity Cost Budgeted Electricity Cost (static budget) $1,050 $1,200 The manager is comparing the electricity cost incurred at the  ACTUAL  activity level (3,000 tents) with the budgeted electricity cost at the  PLANNED  activity level (4,000 tents). These activity levels are different, therefore we would expect the electricity cost to be different Cost Variance $150 Favorable
Advantages Of Flexible Budgets 17- Actual Electricity Cost Budgeted Electricity Cost (flexible budget) Cost Variance $1,050 $900 $150 Unfavorable The manager is comparing the electricity cost incurred at the  ACTUAL  activity level, 3,000 tents with the budgeted electricity  cost at the  ACTUAL   activity level, (3,000 tents x 1.5 machine hours) = 4,500 machine hours Electrical cost was greater than it should have been, given the actual  level of output
Activity Measure:  Based On Input Or Output 17- Output measures require different inputs Output measures can be used if you only make one product Flexible budget must be based on outputs that can be compared
Flexible Budgets:  Inputs Versus Outputs 17- 1.5 standard allowed machine  hours per tent Usually not a  meaningful measure in a multi-product firm because it would require us to add numbers of unlike products  Output is measured in terms of  the standard allowed input, given actual output
Formula Flexible Budget 17- If you recall, this is similar to the Predetermined Cost-Driver Rate discussed in Chapter 4. EXAMPLE Assume that the company needs flexible budget numbers for three activity levels: 4,500 hours, 6,000 hours, and 7,500 hours.  Also, assume that the Predetermined Budgeted Variable-Overhead Cost per Activity Unit is $6 per hour.  Budgeted Fixed-Overhead Cost for the month is $30,000. Flexible Budget? .
Formula Flexible Budget 17- The flexed total budgeted monthly overhead for each activity level can now be used effectively in planning and variance analysis.
Overhead Application - Normal Costing  17- Manufacturing Overhead Work-in-Process Inventory Actual overhead Applied overhead Actual hours Predetermined overhead rate X Applied overhead Actual hours Predetermined overhead rate X The Difference between Normal Costing and Standard  Costing lies in the quantity of hours used Exh. 17-4
Overhead Application - Standard Costing  17- Manufacturing Overhead Work-in-Process Inventory Actual overhead Applied overhead Standard allowed hours Predetermined or standard overhead rate X Applied overhead Standard allowed hours Predetermined or standard overhead rate X The Difference between Normal Costing and Standard  Costing lies in the quantity of hours used Exh. 17-4
Predetermined Overhead Rates 17- Both normal-costing and standard-costing systems use an overhead rate computed at the beginning of the accounting period (predetermined overhead rate) Computed annually Exh. 17-5
Choice Of Activity Measure ,[object Object],17- The variable overhead cost and the activity measure  should move together Direct labor time has traditionally been the most popular activity  measure in manufacturing firms As automation increases, more firms are  switching to machine hours  or process time Dollar measures, such as  direct-labor or material costs can be misleading because  they are subject to price-level changes and other fluctuations
Overhead Cost Variances 17- Koala manufactured 3,000 tree line tents X 1.5 machine hours per tent = standard allowed 4,500 machine hours Actual machine hours for June = 4,800 The total variable overhead variance for  June = Actual variable overhead  $30,480 Budget variable overhead  $27,000   $ 3,480  F For  standard allowed 4,500 machine hours the budget overhead (from  Exhibit 17-3) for June = Variable overhead  $27,000 Fixed overhead  $30,000 From the cost accounting records, the actual overhead  for June = Variable overhead  $30,480 Fixed overhead  $32,500   $62,980
Variable Overhead Variances 17- The VARIABLE-OVERHEAD SPENDING VARIANCE is the difference between the actual variable overhead cost and the product of the standard variable -overhead rate and the actual hours of an activity base  (or cost driver) Exh. 17-6 Actual variable overhead Actual machine  hours (AH) Actual rate  (AVR) Actual machine  hours (AH) Standard rate  (SVR) Actual machine hours × the standard rate ? ? ? ? 4,800 machine hours $6.35 per machine hour 4,800 machine  hours  $6.00 per  machine hour $30,480 $28,800 $1,680 Unfavorable Variable-overhead spending variance
Variable Overhead Variances 17- The VARIABLE-OVERHEAD EFFICIENCY VARIANCE is the difference between the actual and the  standard hours of an activity base (or cost driver) multiplied by the standard variable overhead rate  Flexible budget: variable overhead Standard allowed machine hours (SH) Standard rate  (SVR) Actual machine  hours (AH) Standard rate  (SVR) Actual machine hours times the standard rate Exh. 17-6 $27,000 $28,800 ? ? ? ? 4,500 machine hours $6.00 per machine hour 4,800 machine  hours  $6.00 per  machine hour $1,800 Unfavorable Variable-overhead efficiency variance
Variable Overhead Variances 17- The flexible budget amount for variable overhead $27,000 is the  amount that will be applied to Work-in-Process for product-costing purposes Flexible budget: variable overhead Standard allowed machine hours (SH) Standard rate  (SVR) Variable overhead applied to work in process Standard allowed machine hours (SH) Standard rate  (SVR) Exh. 17-6 ? ? ? ? $27,000 4,500 machine hours $6.00 per machine hour 4,500 machine hours $6.00 per machine hour No difference $27,000
How To Interpret The Variable Overhead Variances 17- ? The unfavorable variance resulting from using more machine hours than the standard  quantity, given actual output The actual labor rate per hour differs from the standard rate Efficiency variance Spending variance The variable overhead efficiency variance has  nothing to do with efficient or inefficient use of  variable overhead items An unfavorable variance means that the total actual cost of  variable overhead is > expected, after adjusting for the actual quantity of machine hours used The spending variance is the real control variance for variable  overhead
Fixed Overhead Budget Variance 17- The FIXED-OVERHEAD BUDGET VARIANCE is the difference between actual fixed overhead and budgeted fixed overhead Unfavorable variance of  $2,500, because we spent more than budgeted Fixed-overhead budget variance Actual Fixed overhead Budgeted fixed overhead = - Fixed-overhead budget variance Actual Fixed overhead = $32,500 Budgeted fixed overhead = $30,000 = -
Fixed Overhead Volume Variance 17- The FIXED-OVERHEAD VOLUME VARIANCE is the difference between budgeted fixed overhead and actual fixed overhead.  Assume that the predetermined fixed overhead per machine hour = $5 and that it is based on 4,500 machine hours. Variance = $7,500 U, because we produced less than budgeted. Fixed-overhead volume variance Budgeted fixed overhead Applied fixed overhead = - Applied fixed overhead = $22,500 Fixed-overhead volume variance Budgeted  fixed overhead = $30,000 = -
Managerial Interpretation Of Fixed-Overhead Variances 17- Budget Variance Volume Variance The real control  variance for fixed overhead  because it  compares actual expenditures with budgeted fixed  overhead costs   Reconciles  the two different purposes of the cost accounting system For cost-management  purposes, the cost- accounting system recognizes that fixed overhead does not change as production activity varies For product-costing  purposes, budgeted fixed overhead is divided by planned  activity to obtain a predetermined or standard fixed-overhead rate
Fixed Overhead Budget And Volume Variances 17- (1) Actual fixed O/H (2) Budgeted fixed O/H (3) Fixed overhead applied to work in process Standard allowed machine hours Standard fixed overhead rate X $30,000 $32,500 Fixed-overhead budget variance = $2,500 U Fixed-overhead volume variance = $7,500 U Exh. 17-8 4,500 machine hrs $5.00 per machine hr X $22,500
Budgeted Versus Applied Fixed Overhead 17- Exh. 17-9 Fixed overhead $30,000 $22,500 0 Applied fixed overhead ($5.00 per standard allowed machine  hour) Budgeted fixed overhead Machine hours Volume variance $7,500 4,500 Standard allowed hours, given actual output 6,000 Planned monthly activity Applied fixed  overhead in June
4-, 3-, & 2-way Variance Analysis 17- Four-way analysis Three-way analysis Two-way analysis Variable- overhead spending variance Fixed- overhead budget variance Variable- overhead efficiency variance Fixed- overhead volume variance $1,680 U $2,500 U $1,800 U $7,500 U Combined spending variance $4,180 U $1,800 U $7,500 U $5,980 U Combined budget variance Underapplied overhead  $7,500 U $62,980 actual overhead - overhead  applied to WIP, 49,500 = $13,480 Exh. 17-10
Using The Overhead Cost Performance Report In Cost Management 17- An Overhead Cost  Performance Report Shows the fixed overhead budget variance ,along with the actual and budgeted cost for each fixed overhead item. Shows the variable  overhead spending and efficiency variances, along with the actual and budgeted cost for each variable overhead item. The report would be used by management to exercise control over each of the overhead costs.
Using Standard Costs In Product Costing 17- Manufacturing Overhead Actual  $62,980 $49,500  Applied Credit: Indirect-material inventory  Wages payable  Utilities payable Accumulated depreciation Prepaid insurance and  property taxes Engineering salaries payable 19,350 32,610 2,170 1,300 1,050 6,500 Debit: Work-in-process inventory Applied overhead: $11.00 (predetermined  overhead rate) X 4,500 (standard allowed hours $49,500 $13,480 Debit: Cost of goods sold $13,480
Activity-Based Flexible Budget 17- An activity-based flexible budget may provide more useful cost management information than a conventional flexible budget The traditional budget Activity-based flexible budget Costs are categorized as variable based on volume measures Machine hours Direct labor hours Costs are categorized as variable based on several cost drivers Cost that may seem fixed with respect to a single volume-based cost driver may be variable with respect to other non-volume related  cost drivers
End of Chapter 17 17- I wish I could figure out how to  ……..  my paycheck!  FLEX

More Related Content

What's hot

Cost volume-profit analysis
Cost volume-profit analysisCost volume-profit analysis
Cost volume-profit analysisBabasab Patil
 
Chapter 11 : Activity Based Costing and Accounting Information
Chapter 11 : Activity Based Costing and Accounting InformationChapter 11 : Activity Based Costing and Accounting Information
Chapter 11 : Activity Based Costing and Accounting InformationPeleZain
 
Activity based costing
Activity based costingActivity based costing
Activity based costingKartik Bansal
 
Cost volume profit analysis
Cost volume profit analysisCost volume profit analysis
Cost volume profit analysiskamran
 
Cost terms, Concepts and classification-C1.ppt.pdf
Cost terms, Concepts and classification-C1.ppt.pdfCost terms, Concepts and classification-C1.ppt.pdf
Cost terms, Concepts and classification-C1.ppt.pdfBjrnIronside
 
COST-VOLUME-PROFIT (CVP) analysis
COST-VOLUME-PROFIT (CVP) analysis COST-VOLUME-PROFIT (CVP) analysis
COST-VOLUME-PROFIT (CVP) analysis AJ Raina
 
Capacity planning ppt @ bec doms
Capacity planning ppt @ bec domsCapacity planning ppt @ bec doms
Capacity planning ppt @ bec domsBabasab Patil
 
presentation on responsibility accounting
presentation on responsibility accountingpresentation on responsibility accounting
presentation on responsibility accountingNisha Singh
 
PPT on break even analysis
PPT on break even analysisPPT on break even analysis
PPT on break even analysisITC Limited
 
Cost classification
Cost classificationCost classification
Cost classificationpankajmaini
 
Standard costs and variance analysis
Standard costs and variance analysisStandard costs and variance analysis
Standard costs and variance analysisSumit Malhotra
 
Make or Buy Decisions
Make or Buy DecisionsMake or Buy Decisions
Make or Buy DecisionsRon McFarland
 
Standard costing and Variance Analysis
Standard costing and Variance AnalysisStandard costing and Variance Analysis
Standard costing and Variance AnalysisArunkumar Duna
 

What's hot (20)

Chap12 mc questions&answers
Chap12 mc questions&answersChap12 mc questions&answers
Chap12 mc questions&answers
 
Activity-Based Costing System
Activity-Based Costing SystemActivity-Based Costing System
Activity-Based Costing System
 
Cost volume-profit analysis
Cost volume-profit analysisCost volume-profit analysis
Cost volume-profit analysis
 
Chapter 11 : Activity Based Costing and Accounting Information
Chapter 11 : Activity Based Costing and Accounting InformationChapter 11 : Activity Based Costing and Accounting Information
Chapter 11 : Activity Based Costing and Accounting Information
 
Relevant+cost
Relevant+costRelevant+cost
Relevant+cost
 
Activity based costing
Activity based costingActivity based costing
Activity based costing
 
Activity-Based Costing System
Activity-Based Costing SystemActivity-Based Costing System
Activity-Based Costing System
 
Cost volume profit analysis
Cost volume profit analysisCost volume profit analysis
Cost volume profit analysis
 
Cost terms, Concepts and classification-C1.ppt.pdf
Cost terms, Concepts and classification-C1.ppt.pdfCost terms, Concepts and classification-C1.ppt.pdf
Cost terms, Concepts and classification-C1.ppt.pdf
 
COST-VOLUME-PROFIT (CVP) analysis
COST-VOLUME-PROFIT (CVP) analysis COST-VOLUME-PROFIT (CVP) analysis
COST-VOLUME-PROFIT (CVP) analysis
 
Capacity planning ppt @ bec doms
Capacity planning ppt @ bec domsCapacity planning ppt @ bec doms
Capacity planning ppt @ bec doms
 
presentation on responsibility accounting
presentation on responsibility accountingpresentation on responsibility accounting
presentation on responsibility accounting
 
PPT on break even analysis
PPT on break even analysisPPT on break even analysis
PPT on break even analysis
 
Budgeting
BudgetingBudgeting
Budgeting
 
Cost classification
Cost classificationCost classification
Cost classification
 
Standard costs and variance analysis
Standard costs and variance analysisStandard costs and variance analysis
Standard costs and variance analysis
 
Make or Buy Decisions
Make or Buy DecisionsMake or Buy Decisions
Make or Buy Decisions
 
ABC costing
ABC costing ABC costing
ABC costing
 
Variance analysis
Variance analysisVariance analysis
Variance analysis
 
Standard costing and Variance Analysis
Standard costing and Variance AnalysisStandard costing and Variance Analysis
Standard costing and Variance Analysis
 

Similar to Flexible budgets & overhead costs

Horngrenima14e ch13
Horngrenima14e ch13Horngrenima14e ch13
Horngrenima14e ch13Anchit Jain
 
Assignment Exercise 17–1 Variance AnalysisGreenview Hospital op.docx
Assignment Exercise 17–1 Variance AnalysisGreenview Hospital op.docxAssignment Exercise 17–1 Variance AnalysisGreenview Hospital op.docx
Assignment Exercise 17–1 Variance AnalysisGreenview Hospital op.docxssuser562afc1
 
Acc mgt noreen09 flexible budgets and overhead analysis
Acc mgt noreen09 flexible budgets and overhead analysisAcc mgt noreen09 flexible budgets and overhead analysis
Acc mgt noreen09 flexible budgets and overhead analysisJudianto Nugroho
 
3. Analisi delle Spese Generali e Budget Flessibile
3. Analisi delle Spese Generali e Budget Flessibile3. Analisi delle Spese Generali e Budget Flessibile
3. Analisi delle Spese Generali e Budget FlessibileManager.it
 
Manufacturinf overhead variance
Manufacturinf overhead varianceManufacturinf overhead variance
Manufacturinf overhead varianceemployee goverment
 
Example 17A Variance AnalysisOur variance analysis example and pr.docx
Example 17A Variance AnalysisOur variance analysis example and pr.docxExample 17A Variance AnalysisOur variance analysis example and pr.docx
Example 17A Variance AnalysisOur variance analysis example and pr.docxmodi11
 
Standard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures AndStandard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures Andafiali
 
Variances with examples
Variances with examplesVariances with examples
Variances with examplesAyesha Hamid
 
Cost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptx
Cost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptxCost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptx
Cost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptxObsaKamil
 
cost accounting chapter 6, fundamentals of product and service design
cost accounting chapter 6, fundamentals of product and service designcost accounting chapter 6, fundamentals of product and service design
cost accounting chapter 6, fundamentals of product and service designBeaDelaPenia1
 

Similar to Flexible budgets & overhead costs (20)

Horngrenima14e ch13
Horngrenima14e ch13Horngrenima14e ch13
Horngrenima14e ch13
 
Assignment Exercise 17–1 Variance AnalysisGreenview Hospital op.docx
Assignment Exercise 17–1 Variance AnalysisGreenview Hospital op.docxAssignment Exercise 17–1 Variance AnalysisGreenview Hospital op.docx
Assignment Exercise 17–1 Variance AnalysisGreenview Hospital op.docx
 
Cost_sample
Cost_sampleCost_sample
Cost_sample
 
Cost Sample
Cost SampleCost Sample
Cost Sample
 
Acc mgt noreen09 flexible budgets and overhead analysis
Acc mgt noreen09 flexible budgets and overhead analysisAcc mgt noreen09 flexible budgets and overhead analysis
Acc mgt noreen09 flexible budgets and overhead analysis
 
3. Analisi delle Spese Generali e Budget Flessibile
3. Analisi delle Spese Generali e Budget Flessibile3. Analisi delle Spese Generali e Budget Flessibile
3. Analisi delle Spese Generali e Budget Flessibile
 
Manufacturinf overhead variance
Manufacturinf overhead varianceManufacturinf overhead variance
Manufacturinf overhead variance
 
horngren_ima16_stppt13.ppt
horngren_ima16_stppt13.ppthorngren_ima16_stppt13.ppt
horngren_ima16_stppt13.ppt
 
Example 17A Variance AnalysisOur variance analysis example and pr.docx
Example 17A Variance AnalysisOur variance analysis example and pr.docxExample 17A Variance AnalysisOur variance analysis example and pr.docx
Example 17A Variance AnalysisOur variance analysis example and pr.docx
 
Hca14 sm ch08
Hca14 sm ch08Hca14 sm ch08
Hca14 sm ch08
 
Standard Costing
Standard Costing Standard Costing
Standard Costing
 
Standard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures AndStandard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures And
 
Costing system
Costing systemCosting system
Costing system
 
Managment accounting
Managment accountingManagment accounting
Managment accounting
 
Overhead-Costing
Overhead-Costing Overhead-Costing
Overhead-Costing
 
Variances with examples
Variances with examplesVariances with examples
Variances with examples
 
Absorption costing
Absorption costingAbsorption costing
Absorption costing
 
Week 6
Week 6Week 6
Week 6
 
Cost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptx
Cost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptxCost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptx
Cost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptx
 
cost accounting chapter 6, fundamentals of product and service design
cost accounting chapter 6, fundamentals of product and service designcost accounting chapter 6, fundamentals of product and service design
cost accounting chapter 6, fundamentals of product and service design
 

Recently uploaded

Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsKnowledgeSeed
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Types of Cyberattacks - ASG I.T. Consulting.pdf
Types of Cyberattacks - ASG I.T. Consulting.pdfTypes of Cyberattacks - ASG I.T. Consulting.pdf
Types of Cyberattacks - ASG I.T. Consulting.pdfASGITConsulting
 
14680-51-4.pdf Good quality CAS Good quality CAS
14680-51-4.pdf  Good  quality CAS Good  quality CAS14680-51-4.pdf  Good  quality CAS Good  quality CAS
14680-51-4.pdf Good quality CAS Good quality CAScathy664059
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdfMintel Group
 
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...ssuserf63bd7
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckHajeJanKamps
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
Data Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and TemplatesData Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and TemplatesAurelien Domont, MBA
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers referencessuser2c065e
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsIndiaMART InterMESH Limited
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreNZSG
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingrajputmeenakshi733
 

Recently uploaded (20)

Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applications
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Types of Cyberattacks - ASG I.T. Consulting.pdf
Types of Cyberattacks - ASG I.T. Consulting.pdfTypes of Cyberattacks - ASG I.T. Consulting.pdf
Types of Cyberattacks - ASG I.T. Consulting.pdf
 
14680-51-4.pdf Good quality CAS Good quality CAS
14680-51-4.pdf  Good  quality CAS Good  quality CAS14680-51-4.pdf  Good  quality CAS Good  quality CAS
14680-51-4.pdf Good quality CAS Good quality CAS
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
 
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deck
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptxThe Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
Data Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and TemplatesData Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and Templates
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan Dynamics
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource Centre
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketing
 

Flexible budgets & overhead costs

  • 1. Hilton • Maher • Selto
  • 2. 17 Flexible Budgets, Overhead Cost Management, and Activity-Based Budgeting McGraw-Hill/Irwin © 2003 The McGraw-Hill Companies, Inc., All Rights Reserved .
  • 3. What Are Flexible Overhead Budgets? 17- A flexible budget is valid for a range of activity A static budget is based on a particular planned level of activity This range of activity is the relevant range A flexible overhead budget is defined as a detailed plan for controlling overhead cost valid in the firm’s relevant range of activity
  • 4. Static Budget Versus Flexible Budget 17- Based on planned June production of 4,000 tents, at 1.5 machine hours per tent. We cannot tell from this budget what it would cost to make 3,000 tents. Based on only ONE anticipated activity level Includes several possible activity levels Exh. 17-1
  • 5. Advantages Of Flexible Budgets 17- Actual Electricity Cost Budgeted Electricity Cost (static budget) $1,050 $1,200 The manager is comparing the electricity cost incurred at the ACTUAL activity level (3,000 tents) with the budgeted electricity cost at the PLANNED activity level (4,000 tents). These activity levels are different, therefore we would expect the electricity cost to be different Cost Variance $150 Favorable
  • 6. Advantages Of Flexible Budgets 17- Actual Electricity Cost Budgeted Electricity Cost (flexible budget) Cost Variance $1,050 $900 $150 Unfavorable The manager is comparing the electricity cost incurred at the ACTUAL activity level, 3,000 tents with the budgeted electricity cost at the ACTUAL activity level, (3,000 tents x 1.5 machine hours) = 4,500 machine hours Electrical cost was greater than it should have been, given the actual level of output
  • 7. Activity Measure: Based On Input Or Output 17- Output measures require different inputs Output measures can be used if you only make one product Flexible budget must be based on outputs that can be compared
  • 8. Flexible Budgets: Inputs Versus Outputs 17- 1.5 standard allowed machine hours per tent Usually not a meaningful measure in a multi-product firm because it would require us to add numbers of unlike products Output is measured in terms of the standard allowed input, given actual output
  • 9. Formula Flexible Budget 17- If you recall, this is similar to the Predetermined Cost-Driver Rate discussed in Chapter 4. EXAMPLE Assume that the company needs flexible budget numbers for three activity levels: 4,500 hours, 6,000 hours, and 7,500 hours. Also, assume that the Predetermined Budgeted Variable-Overhead Cost per Activity Unit is $6 per hour. Budgeted Fixed-Overhead Cost for the month is $30,000. Flexible Budget? .
  • 10. Formula Flexible Budget 17- The flexed total budgeted monthly overhead for each activity level can now be used effectively in planning and variance analysis.
  • 11. Overhead Application - Normal Costing 17- Manufacturing Overhead Work-in-Process Inventory Actual overhead Applied overhead Actual hours Predetermined overhead rate X Applied overhead Actual hours Predetermined overhead rate X The Difference between Normal Costing and Standard Costing lies in the quantity of hours used Exh. 17-4
  • 12. Overhead Application - Standard Costing 17- Manufacturing Overhead Work-in-Process Inventory Actual overhead Applied overhead Standard allowed hours Predetermined or standard overhead rate X Applied overhead Standard allowed hours Predetermined or standard overhead rate X The Difference between Normal Costing and Standard Costing lies in the quantity of hours used Exh. 17-4
  • 13. Predetermined Overhead Rates 17- Both normal-costing and standard-costing systems use an overhead rate computed at the beginning of the accounting period (predetermined overhead rate) Computed annually Exh. 17-5
  • 14.
  • 15. Overhead Cost Variances 17- Koala manufactured 3,000 tree line tents X 1.5 machine hours per tent = standard allowed 4,500 machine hours Actual machine hours for June = 4,800 The total variable overhead variance for June = Actual variable overhead $30,480 Budget variable overhead $27,000 $ 3,480 F For standard allowed 4,500 machine hours the budget overhead (from Exhibit 17-3) for June = Variable overhead $27,000 Fixed overhead $30,000 From the cost accounting records, the actual overhead for June = Variable overhead $30,480 Fixed overhead $32,500 $62,980
  • 16. Variable Overhead Variances 17- The VARIABLE-OVERHEAD SPENDING VARIANCE is the difference between the actual variable overhead cost and the product of the standard variable -overhead rate and the actual hours of an activity base (or cost driver) Exh. 17-6 Actual variable overhead Actual machine hours (AH) Actual rate (AVR) Actual machine hours (AH) Standard rate (SVR) Actual machine hours × the standard rate ? ? ? ? 4,800 machine hours $6.35 per machine hour 4,800 machine hours $6.00 per machine hour $30,480 $28,800 $1,680 Unfavorable Variable-overhead spending variance
  • 17. Variable Overhead Variances 17- The VARIABLE-OVERHEAD EFFICIENCY VARIANCE is the difference between the actual and the standard hours of an activity base (or cost driver) multiplied by the standard variable overhead rate Flexible budget: variable overhead Standard allowed machine hours (SH) Standard rate (SVR) Actual machine hours (AH) Standard rate (SVR) Actual machine hours times the standard rate Exh. 17-6 $27,000 $28,800 ? ? ? ? 4,500 machine hours $6.00 per machine hour 4,800 machine hours $6.00 per machine hour $1,800 Unfavorable Variable-overhead efficiency variance
  • 18. Variable Overhead Variances 17- The flexible budget amount for variable overhead $27,000 is the amount that will be applied to Work-in-Process for product-costing purposes Flexible budget: variable overhead Standard allowed machine hours (SH) Standard rate (SVR) Variable overhead applied to work in process Standard allowed machine hours (SH) Standard rate (SVR) Exh. 17-6 ? ? ? ? $27,000 4,500 machine hours $6.00 per machine hour 4,500 machine hours $6.00 per machine hour No difference $27,000
  • 19. How To Interpret The Variable Overhead Variances 17- ? The unfavorable variance resulting from using more machine hours than the standard quantity, given actual output The actual labor rate per hour differs from the standard rate Efficiency variance Spending variance The variable overhead efficiency variance has nothing to do with efficient or inefficient use of variable overhead items An unfavorable variance means that the total actual cost of variable overhead is > expected, after adjusting for the actual quantity of machine hours used The spending variance is the real control variance for variable overhead
  • 20. Fixed Overhead Budget Variance 17- The FIXED-OVERHEAD BUDGET VARIANCE is the difference between actual fixed overhead and budgeted fixed overhead Unfavorable variance of $2,500, because we spent more than budgeted Fixed-overhead budget variance Actual Fixed overhead Budgeted fixed overhead = - Fixed-overhead budget variance Actual Fixed overhead = $32,500 Budgeted fixed overhead = $30,000 = -
  • 21. Fixed Overhead Volume Variance 17- The FIXED-OVERHEAD VOLUME VARIANCE is the difference between budgeted fixed overhead and actual fixed overhead. Assume that the predetermined fixed overhead per machine hour = $5 and that it is based on 4,500 machine hours. Variance = $7,500 U, because we produced less than budgeted. Fixed-overhead volume variance Budgeted fixed overhead Applied fixed overhead = - Applied fixed overhead = $22,500 Fixed-overhead volume variance Budgeted fixed overhead = $30,000 = -
  • 22. Managerial Interpretation Of Fixed-Overhead Variances 17- Budget Variance Volume Variance The real control variance for fixed overhead because it compares actual expenditures with budgeted fixed overhead costs Reconciles the two different purposes of the cost accounting system For cost-management purposes, the cost- accounting system recognizes that fixed overhead does not change as production activity varies For product-costing purposes, budgeted fixed overhead is divided by planned activity to obtain a predetermined or standard fixed-overhead rate
  • 23. Fixed Overhead Budget And Volume Variances 17- (1) Actual fixed O/H (2) Budgeted fixed O/H (3) Fixed overhead applied to work in process Standard allowed machine hours Standard fixed overhead rate X $30,000 $32,500 Fixed-overhead budget variance = $2,500 U Fixed-overhead volume variance = $7,500 U Exh. 17-8 4,500 machine hrs $5.00 per machine hr X $22,500
  • 24. Budgeted Versus Applied Fixed Overhead 17- Exh. 17-9 Fixed overhead $30,000 $22,500 0 Applied fixed overhead ($5.00 per standard allowed machine hour) Budgeted fixed overhead Machine hours Volume variance $7,500 4,500 Standard allowed hours, given actual output 6,000 Planned monthly activity Applied fixed overhead in June
  • 25. 4-, 3-, & 2-way Variance Analysis 17- Four-way analysis Three-way analysis Two-way analysis Variable- overhead spending variance Fixed- overhead budget variance Variable- overhead efficiency variance Fixed- overhead volume variance $1,680 U $2,500 U $1,800 U $7,500 U Combined spending variance $4,180 U $1,800 U $7,500 U $5,980 U Combined budget variance Underapplied overhead $7,500 U $62,980 actual overhead - overhead applied to WIP, 49,500 = $13,480 Exh. 17-10
  • 26. Using The Overhead Cost Performance Report In Cost Management 17- An Overhead Cost Performance Report Shows the fixed overhead budget variance ,along with the actual and budgeted cost for each fixed overhead item. Shows the variable overhead spending and efficiency variances, along with the actual and budgeted cost for each variable overhead item. The report would be used by management to exercise control over each of the overhead costs.
  • 27. Using Standard Costs In Product Costing 17- Manufacturing Overhead Actual $62,980 $49,500 Applied Credit: Indirect-material inventory Wages payable Utilities payable Accumulated depreciation Prepaid insurance and property taxes Engineering salaries payable 19,350 32,610 2,170 1,300 1,050 6,500 Debit: Work-in-process inventory Applied overhead: $11.00 (predetermined overhead rate) X 4,500 (standard allowed hours $49,500 $13,480 Debit: Cost of goods sold $13,480
  • 28. Activity-Based Flexible Budget 17- An activity-based flexible budget may provide more useful cost management information than a conventional flexible budget The traditional budget Activity-based flexible budget Costs are categorized as variable based on volume measures Machine hours Direct labor hours Costs are categorized as variable based on several cost drivers Cost that may seem fixed with respect to a single volume-based cost driver may be variable with respect to other non-volume related cost drivers
  • 29. End of Chapter 17 17- I wish I could figure out how to …….. my paycheck! FLEX