The Non-intuitive Impact of Software Defects  on Development Efforts Time Estimates                Copyrights (c) 2011-201...
Motivation• Many software development projects rely on software  implementation time estimates provided by the  developmen...
Equation Variables• R = number of requirements that need to be  implemented in the software• I = mean implementation rate ...
Defect Ratio• Many factors influence the value of the Defect  ratio such as  – Misunderstanding of requirements from the  ...
Defect Ratio• The Defect ratio we are talking about is an  average value.• This average (or mean) value can be  determined...
Defect Ratio• The Defect ratio can also be determined as the  probability that an implemented requirement  generates a def...
The Equation• T = time needed to implement a set of R  software requirements. It is given by this  equation [E]:          ...
Equation Interpretation• When the defect ratio is D = 0 then the time  needed to implement R software requirements is:    ...
Equation Illustration• Assume that R=100 requirements need to be  implemented at a rate I=10 requirements per  week• The c...
Equation Chart  Copyrights (c) 2011-2013 Pragmatic                                       10         Cohesion Consulting
Equation Illustration• In this example, when D=0 it takes 10 weeks  to implement the 100 requirements. This is  the common...
Non-intuitive Impact of Defects• With a 20% Defect ratio, the implementation  time of the 100 requirements goes from 10  w...
Impact of High Defect Ratios• As the Defect ratio approaches 100%, the  Implementation time grows at a faster rate  toward...
Impact on Software Requirements        Implementation Rate• Lets examine again the case where the Defect  ratio is D=0%. I...
Impact on Software Requirements       Implementation Rate• An implementation rate of I = 14.2  requirements/week can be ob...
Impact on Software Requirements Size• With the Defect ratio D=30%, if we had to  keep the same development team size, the ...
For Comments and Questions contact didier@pragmaticohesion.com                      Copyrights (c) 2011-2013 Pragmatic    ...
Upcoming SlideShare
Loading in...5
×

The non intuitive impact of software defects on development efforts time estimates

358

Published on

We have derived a simple equation that can be used to more accurately estimate the time needed to implement a set of R software requirements given an average Defect ratio .
The equation results can also be used to adjust the development team work schedule, the number of developers, or the project number of software requirements.

Published in: Technology
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
358
On Slideshare
0
From Embeds
0
Number of Embeds
1
Actions
Shares
0
Downloads
8
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

The non intuitive impact of software defects on development efforts time estimates

  1. 1. The Non-intuitive Impact of Software Defects on Development Efforts Time Estimates Copyrights (c) 2011-2013 Pragmatic 1 Cohesion Consulting
  2. 2. Motivation• Many software development projects rely on software implementation time estimates provided by the development team to forecast the total duration of a software implementation effort.• This presentation takes a rational look at the non-intuitive impact of software defects on development time estimates.• We have derived a simple equation that can be used to more accurately estimate the time needed to implement a set of R software requirements .• The equation results can also be used to adjust the development team work schedule, the number of developers, or the project number of software requirements to implement. Copyrights (c) 2011-2013 Pragmatic 2 Cohesion Consulting
  3. 3. Equation Variables• R = number of requirements that need to be implemented in the software• I = mean implementation rate of software requirements. I unit is in Requirements per time unit (for example 23 requirements per week)• D = mean implemented requirements defect ratio. For example if D=20% then for every 10 implemented requirements, 2 of them are not properly implemented. Copyrights (c) 2011-2013 Pragmatic 3 Cohesion Consulting
  4. 4. Defect Ratio• Many factors influence the value of the Defect ratio such as – Misunderstanding of requirements from the designer and/or developer resulting in software behavior that does not fully fulfill the requirements – Errors in software code• The reader can refer to the Wikipedia article on software bug for more details. Copyrights (c) 2011-2013 Pragmatic 4 Cohesion Consulting
  5. 5. Defect Ratio• The Defect ratio we are talking about is an average value.• This average (or mean) value can be determined through historical metrics gathered by the software development organization or team over an appropriate timespan and over a set of past development efforts. Copyrights (c) 2011-2013 Pragmatic 5 Cohesion Consulting
  6. 6. Defect Ratio• The Defect ratio can also be determined as the probability that an implemented requirement generates a defect at any point in time during an entire software development project.• The reader can refer to our SlideShare presentation “The dynamic interaction of passed and failed requirements during software testing” for further details on how to calculate such probabilities. Copyrights (c) 2011-2013 Pragmatic 6 Cohesion Consulting
  7. 7. The Equation• T = time needed to implement a set of R software requirements. It is given by this equation [E]: 𝑅 𝑇= 𝐼(1 − 𝐷) Copyrights (c) 2011-2013 Pragmatic 7 Cohesion Consulting
  8. 8. Equation Interpretation• When the defect ratio is D = 0 then the time needed to implement R software requirements is: 𝑅 𝑇= 𝐼• “I (1-D)” represents an adjusted Implementation rate that decreases in direct proportion to the defect ratio. It captures the effect of rework efforts that slow down production throughput.• As the defect ratio varies from 0 to 1 , the time needed to implement the set of R software requirements increases in a non-linear way. Copyrights (c) 2011-2013 Pragmatic 8 Cohesion Consulting
  9. 9. Equation Illustration• Assume that R=100 requirements need to be implemented at a rate I=10 requirements per week• The chart of T (time needed to implement the 100 requirements) as a function of D (implemented requirements defect ratio) is presented on the next slide Copyrights (c) 2011-2013 Pragmatic 9 Cohesion Consulting
  10. 10. Equation Chart Copyrights (c) 2011-2013 Pragmatic 10 Cohesion Consulting
  11. 11. Equation Illustration• In this example, when D=0 it takes 10 weeks to implement the 100 requirements. This is the common way of estimating implementation time where defects rework is not taken into account.• Equation [E] explicitly incorporates the impact of defects on the total time needed for implementing the set of R requirements. Copyrights (c) 2011-2013 Pragmatic 11 Cohesion Consulting
  12. 12. Non-intuitive Impact of Defects• With a 20% Defect ratio, the implementation time of the 100 requirements goes from 10 weeks to 12.5 weeks which is a 25% increase.• A 30% Defect ratio results in 42% increase in implementation time: T goes from 10 weeks to 14.2 weeks!• A 50% defect ratio results in 100% increase in implementation time: T goes from 10 weeks to 20 weeks! Copyrights (c) 2011-2013 Pragmatic 12 Cohesion Consulting
  13. 13. Impact of High Defect Ratios• As the Defect ratio approaches 100%, the Implementation time grows at a faster rate towards infinity.• This behavior can be intuitively understood if one considers that with 100% defect nothing gets properly implemented and every requirement needs to be re-implemented over and over again leading to an infinite implementation time.• What is not so easily understood is the non-linear increasing rate of growth in Implementation time as the Defect ratio increases. Copyrights (c) 2011-2013 Pragmatic 13 Cohesion Consulting
  14. 14. Impact on Software Requirements Implementation Rate• Lets examine again the case where the Defect ratio is D=0%. It would take 10 weeks to implement the 100 requirements at a rate of 10 requirements/week.• If the defect ratio is actually 30%, it now takes 14.2 weeks to implement the 100 requirements. To implement the 100 requirements in the initial 10 weeks, the Implementation rate must increase. Using [E]:  T = 10 = 100/(I x (1-0.3)  I = 100/(10 x 0.7) = 14.2 requirements/week Copyrights (c) 2011-2013 Pragmatic 14 Cohesion Consulting
  15. 15. Impact on Software Requirements Implementation Rate• An implementation rate of I = 14.2 requirements/week can be obtained in several ways: – If the development team remains the same size, then we must increase its weekly hours by 42% – If weekly hours cannot be increased then we must increase the size of the development team by 42%, so if we had initially 5 developers we now need 2 more developers to have 7 developers! Copyrights (c) 2011-2013 Pragmatic 15 Cohesion Consulting
  16. 16. Impact on Software Requirements Size• With the Defect ratio D=30%, if we had to keep the same development team size, the same implementation rate, and the same implementation time, then we must reduce the number of requirements from 100 to:  T = 10 = R /(10 x (1-0.3)  R = 10 x 10 x 0.7 = 70 Requirements! Copyrights (c) 2011-2013 Pragmatic 16 Cohesion Consulting
  17. 17. For Comments and Questions contact didier@pragmaticohesion.com Copyrights (c) 2011-2013 Pragmatic 17 Cohesion Consulting