SlideShare a Scribd company logo
1 of 117
2010
Automation Spring/Wire Form
               Assembly Line
                Working Plan




                   Project Managers:
                   Lydia Ross
                   Hector Rodriguez
                   Automotive Parts, Inc
                   Master Capstone Project
                   Keller School of Management
                   6/16/2010
Contents
1     Executive Summary ...............................................................................................................................................6
    1.1       Project Baseline ............................................................................................................................................6
    1.2       Project Variance ...........................................................................................................................................8
    1.3       Project Expansion .........................................................................................................................................8
2     Technical Proposal ................................................................................................................................................9
    2.1       Project Purpose ............................................................................................................................................9
      2.1.1       Background ..............................................................................................................................................9
      2.1.2       The Need ..................................................................................................................................................9
      2.1.3       Objectives and Goals .............................................................................................................................10
    2.2       Project Benefits ..........................................................................................................................................10
      2.2.1       Stakeholders ..........................................................................................................................................10
      2.2.2       Benefits ..................................................................................................................................................11
    2.3       Statement of work .....................................................................................................................................12
      2.3.1       Project Summary ...................................................................................................................................12
      2.3.2       Scope .....................................................................................................................................................12
      2.3.3       Phases and Milestones ..........................................................................................................................12
      2.3.4       Schedule of Rates - Labor ......................................................................................................................13
      2.3.5       Equipment and Materials ......................................................................................................................13
      2.3.6       General Administration, Contingency, Others .......................................................................................14
      2.3.7       Summary of Total Cost ...........................................................................................................................14
      2.3.8       Payment terms.......................................................................................................................................15
      2.3.9       Statement of work – Assumptions.........................................................................................................16
      2.3.10          Change Management Process ...........................................................................................................17
      2.3.11          Engagement Related Expenses..........................................................................................................17
      2.3.12          Acceptance and authorization...........................................................................................................18
    2.4       Project Plan ................................................................................................................................................19
      2.4.1       Technical Description of New System ....................................................................................................19
      2.4.2       Facility Design and Simulation ...............................................................................................................20
      2.4.3       Future Process .......................................................................................................................................20
      2.4.4       Detailed Project Schedule - Modified ....................................................................................................21
      2.4.5       Specific Challenges .................................................................................................................................22
      2.4.6       Risk Management Matrix .......................................................................................................................22
      2.4.7       Top Risk Recommended Action Plans ....................................................................................................24
    2.5       Project Completion Plan.............................................................................................................................27
      2.5.1       Deliverables ...........................................................................................................................................27



                                                                                                                                                            2|Page
Keller School of Management- Capstone PM600
2.5.2       Acceptance Test ....................................................................................................................................28
      2.5.3       Acceptance Sign-off Cart........................................................................................................................29
3     Management Proposal ........................................................................................................................................30
    3.1       Corporate Organizational Structure ...........................................................................................................30
      3.1.1       Corporate Roles and Responsibilities ....................................................................................................31
    3.2       Project Organizational plan ........................................................................................................................34
      3.2.1       Work Breakdown Structure ...................................................................................................................34
      3.2.2       Project Organizational Structure ...........................................................................................................35
      3.2.3       Project Team ..........................................................................................................................................36
      3.2.4       Responsibility Matrix ............................................................................................................................38
4     Management Systems ........................................................................................................................................40
    4.1       Supplier, Selection and Management ........................................................................................................40
      4.1.1       Overview - Procurement of Automated Machines and Robots .............................................................40
      4.1.2       Production-Line Equipment Vendors .....................................................................................................41
      4.1.3       Computer Vendors.................................................................................................................................43
      4.1.4       Contract Close-Out ................................................................................................................................43
    4.2       Monitoring Cost and Schedule ...................................................................................................................44
      4.2.1       Overview ................................................................................................................................................44
      4.2.2       Labor Cost and Schedule........................................................................................................................45
      4.2.3       Major Equipment Cost and Schedule ....................................................................................................47
      4.2.4       Contingency, Administration and Others Cost ......................................................................................47
    4.3       Management of Scope and Change Orders ...............................................................................................48
      4.3.1       Overview ................................................................................................................................................48
      4.3.2       Development of Scope ...........................................................................................................................49
      4.3.3       Out-of-Scope Items ................................................................................................................................50
      4.3.4       Documentation of Change of Scope ......................................................................................................51
    4.4       Quality Management .................................................................................................................................52
      4.4.1       Overview ................................................................................................................................................52
      4.4.2       Work Package Identification ..................................................................................................................54
      4.4.3       Work Package Inputs, Process and Outputs ..........................................................................................55
      4.4.4       Determining Possible Defects ................................................................................................................56
      4.4.5       Prevention of Defects ............................................................................................................................56
      4.4.6       Indentification of Defects ......................................................................................................................58
5     Project Cost Estimate ..........................................................................................................................................61
    5.1       Project Cost ................................................................................................................................................61
      5.1.1       Total Project Cost ...................................................................................................................................61



                                                                                                                                                          3|Page
Keller School of Management- Capstone PM600
5.1.2       Breakdown of Project Costs ...................................................................................................................62
      5.1.3       Progress Payments.................................................................................................................................63
      5.1.4       Monthly Payment Distribution ..............................................................................................................64
      5.1.5       Earned Value Control ............................................................................................................................65
      5.1.6       Control Performance Index (CPI) & Schedule Performance Index (SPI) ................................................66
      5.1.7       Estimate at Completion (EAC) and Variance at Completion (VAC) ........................................................67
    5.2       Customer-Provide Resources .....................................................................................................................68
    5.3       Terms and Conditions ................................................................................................................................69
6     Unexpected Event ...............................................................................................................................................73
    6.1       Problem ......................................................................................................................................................73
      6.1.1       General Description ...............................................................................................................................73
      6.1.2       Current Status ........................................................................................................................................74
    6.2       Alternative Solutions ..................................................................................................................................79
      6.2.1       Overview ................................................................................................................................................79
      6.2.2       Continuing Contract ...............................................................................................................................79
      6.2.3       Contract Modification ............................................................................................................................79
      6.2.4       Pursuing another OEM...........................................................................................................................80
    6.3       Proposed Action .........................................................................................................................................80
7     Scope Expansion .................................................................................................................................................83
    7.1       Project Description .....................................................................................................................................83
    7.2       Initial Planning............................................................................................................................................85
    7.3       Scope ..........................................................................................................................................................87
    7.4       Schedule .....................................................................................................................................................89
    7.5       Budget ........................................................................................................................................................91
      7.5.1       Schedule of Rates - Labor ......................................................................................................................91
      7.5.2       Equipment and Materials ......................................................................................................................92
      7.5.3       General Administration, Contingency, Others .......................................................................................92
      7.5.4       Summary of Total Cost ...........................................................................................................................93
      7.5.5       WBS/ Cost Breakdown ...........................................................................................................................95
8     Appendixes .........................................................................................................................................................98
    8.1       Appendix A – Risk Assessment Matrix .......................................................................................................98
    8.2       Appendix B – Schedule of Rates ...............................................................................................................100
    8.3       Appendix C – Weekly Payments Progress ................................................................................................102
    8.4       Appendix D – Value Stream Maps ............................................................................................................103
    8.5       Appendix E – Change Request Form ........................................................................................................105
    8.6       Appendix F – Baseline Schedule ...............................................................................................................106



                                                                                                                                                             4|Page
Keller School of Management- Capstone PM600
8.7          Appendix G – Earned Value Analysis Week 14 .........................................................................................107
     8.8          Appendix H – Contract Close Out Checklist .............................................................................................108
     8.9          Appendix I ................................................................................................................................................112
9      Tables ................................................................................................................................................................115
10         Figures ..............................................................................................................................................................116
11     Works Cited .......................................................................................................................................................117




                                                                                                                                                                 5|Page
Keller School of Management- Capstone PM600
1 Executive Summary
1.1 Project Baseline
          Automated Parts Inc, (API) a coil spring, wire forming, subassembly automotive parts company is
          facing a lost in market share due to its inability to increase its production rate of manufactured
          parts while keeping competitive prices to customers. The company is currently stable with its
          current production but would like to increase market share with the coil spring and wire forms
          and increase production of value added parts. The value added parts will provide for a bigger
          profit margin. In order to meet these needs, API, Inc. as engaged its project management
          department to automate the coil spring, wire forming and welding equipment production lines.

          The automation of the production of parts and subassembly lines require the acquisition of new
          equipment, redesign of the production area, training of existing personnel, and in some cases the
          job placement of existing personnel in other organizations. The project management
          department has developed the team, planned the project, prepared the risk assessment and
          engaged engineering, procurement, finance and manufacturing to implement the plan. API as
          provided $2.5 million dollars for the entire plan which includes risk management and contingency
          plans and all cost associated with the project. The project is scheduled for a 43 week duration,
          starting on May 5th 2010. The Project is divided in four different phases:


                                                Table 1.1 Project Phases


                                        Phase                              Completion date
                                                                                   rd
                  1. Project Planning Phase                                   June 3 , 2010
      .           2.Manufacturing Design Phase- Execution
                                                                                        t
                                                                           September 7 , 2010
                                                                                        st
                  3.Procurement Phase-Execution                            December 21 , 2010
                                                                                   nd
                  4.Production/Validation Phase –Completion                  Marc 2 , 2011


          The project is defined in terms of quality that will increase production as well as make the
          production process more efficient in time, cost and the percentage of accurate first time
          production of parts. A team of 18 new skilled operators will be trained to operate the new
          equipment, while current labor consisting of 42 workers needs to be reassigned for future labor
          needs and placement. Figure No.1 describes the time, cost and accuracy rates the organization
          estimates it can achieve with the implementation of this project.




                                                                                                 6|Page
Keller School of Management- Capstone PM600
Figure 1.1: Process Performance Metrics (Ross & Rodriguez, 2010)



                       Current Process                                                                         Future Process

                  Variable                               Measure                                    Variable                                       Measure


 Lead Production Time                            428 Minutes                               Lead Production Time                            <200 Minutes
                        1
 Value Added Time                                246 Minutes                               Value Added Time                                >150 Minutes

 Non-Value Added Time                            48 Minutes                                Non-Value Added Time                            0-10 Minutes

                                                                                           Inventory Time ( waiting Time)                  <50 Minutes
 Inventory Time ( waiting Time)                  134 Minutes
                                                                                           Takt Time (seconds/part)                        <20 seconds/part
 Takt Time (seconds/part)                        28.8 seconds/part

 First Time Quality :                            58%                                       First Time Quality :                            90%

 Change-Over time:                               60 Minutes                                Change-Over time:                               <30 Minutes



 Lead time: the time needed to complete an activity from start to finis
 Value Added Time: Activities that contributes to the production of final Product, transforms material and information
 Non-Value Added time: waste time, activities that does not add value to the final product. Activities creating no value but which cannot be eliminated
  based on current state of technology or thinking
 Inventory Time: waiting time to be process material, batch delays, and process delays.
 Takt Time : total time available for work time per day divided by customer-demand per day – sets the pace of production to match rate of demand
  Source: The Lean Memory Jogger, Richard L. Macinnes.




                      The new process will require automated equipment for the Wire Gauge Checking, Wire Forming
                      and Robotic Welding for an investment of $1,700,000. Turnkey installation service and
                      specialized training will be provided to our team of engineers and production operators by the
                      selected Vendor. The Automation of Spring and Wire Form assembly line will bring numerous
                      benefits to API including improvement in precision manufacturing of parts, flexible
                      manufacturing, better quality control systems, empowered employees, improvement in
                      ergonomics and safety in the operations, increase of production capacity, and reduction of Takt
                      time and reduction of production cost by a range of 20%. Finally the automation of the coil
                      spring/wire form production line will set the grounds for Lean Manufacturing and Just in Time
                      Inventory as future corporate projects. It also will set the ground for new product development
                      and more specialty sub-assembly products.

            1
                Value added operations are for example those operations which require some welding or subassembly



                                                                                                                                            7|Page
            Keller School of Management- Capstone PM600
The success of the project is paramount to API, therefore risk management and contingency
          plans are in place to overcome every possible foreseeable problem.

1.2 Project Variance
          One problem that occurred during the working plan of the project was the vendor of the coil
          springs and wire forms equipment became financially unstable and was threatening bankruptcy.
          Since project management anticipated a possible financial concern during vendor selection, the
          next highest scored vendor’s proposal specifications and the first phase of contract negotiations
          had been conducted in case the first vendor was unable to fulfill the negotiated contract.
          Project management defined the risk scenarios and contingency plan to overcome the risk. The
          risk contingency plans that were developed due to the vendor’s financial dilemmas included the
          following:

            1. Stay with the vendor and receive the equipment without service or maintenance.
            2. Wait for Vendor to be taken over by another company and renegotiate the contract.
            3. Go with another OEM and continue with the project.
          Section 6 of this plan will describe all of the impacts of choosing one of the above scenarios. In
          order to maintain the integrity of the project in terms of time and cost the decision to pick
          another OEM was employed. In this scenario, the President of API, Owen French could stay with
          his initial goal of gaining more of the market share.

1.3 Project Expansion
          To achieve increased market share as quickly as possible, an expansion of the automation project
          was presented to project management which included new product development, as well as,
          acquiring consignment parts of subassemblies. Marketing research determined coil springs for
          military tanks, wire forms for NASA aerospace and subassemblies for the department of defense
          were new products developments the company would pursue. These new product
          developments will be launched in three separate timeframes during the project to ensure
          maximum efficiency and quality. Section 7.0 of this plan describes the expansion to the
          automation project.

                                              Table 1.2: Product Development Program


                                       Project                           Completion date
                                                                                 th
                  1. Wire Forms Aerospace                                   June 8 , 2011
      .           2.Coil for Tanks Defense
                                                                                      st
                                                                           August 1 , 2011
                                                                                       th
                  3.Subassemblies Defense                                 January 16 , 2012




                                                                                                 8|Page
Keller School of Management- Capstone PM600
2 Technical Proposal
2.1 Project Purpose
2.1.1 Background
         Automotive Parts Inc. (API) is a small manufacturer of coil springs and wire forms. API’s
         customers include suppliers of mechanical and electrical subassemblies to automobile, truck,
         over-the-road vehicle OEMs (Original Equipment Manufacturer) and the OEMs themselves.
         These types of customers include such clients as Dana, Arvin Meritor, Ford, GM and Toyota. API
         is providing coil springs, wire forms and subassemblies that include welded parts for these
         important clients. In order to provide better service to its clients, API also offers unique
         prototypes and fast turnaround of its coil springs and wire forms. The manufacturing process to
         produce the photo types, coil spring and wire forms require several steps.

          The manufacturing processes involved in producing springs and flexible wire forms are wire
         gauge checking, wire forming, and welding. Wire gage checking is a complex process which also
         includes inspections for imperfections in the wire. Other operations in the manufacturing
         process include the value added operations. Value added operations are those operations
         which require some welding or subassembly. For example, the ends of a formed-wire piece
         may be welded to a small metal base plate for screw-mounting within a vehicle, or for applying a
         spring’s force over a larger area to hold another part in place. Value-added operations
         represent bigger margin work than wire form and coil springs. Therefore the Company’s goal is
         to increase business in the value added operations area.



2.1.2 The Need
         The Company needs to get its cost in-line to stay competitive. Currently API is losing market
         share because of its inability to meet the prices of its major competitors. The aim is to automate
         the current manufacturing process of Wire Gauge checking, Wire formers and Welding. By
         automating these processes, API can produce parts much quicker as well as increase its capacity.

         The Company is prepared to spend $2.5 million for the automation project of its production
         lines. To achieve its goals, the company will buy automated equipment for Electronic Wire
         Gauge Checkers, Automated Wire Formers and Robotic Welders. In addition to the automated
         resources, there will be labor resources including 2 operators for the wire gauge checking
         operations, 10 operators for the wire forming operation and 4 operators for the robotic welding
         operation.




                                                                                               9|Page
Keller School of Management- Capstone PM600
2.1.3 Objectives and Goals
         The objectives of the Automation of the Coil/Springs production Line is to deliver better quality
         parts, with an updated production process that will make Automotive Parts, Inc more
         competitive in the market and increase its market share, while reducing production cost.

                                        Table 2.1: Goals & Objectives (Ross & Rodriguez, 2010)

              Goals                           Objectives            Method                       Measures of Success
                                                              Invest in new
  Have top notch Production             Update Process        Electronic Wire Gauge       The Process in full operation with
  Facility for Springs and Wire         with Automated        Checkers, Automated         100% Installation and Start-up for
  Forms                                 Equipment             Wire Formers and            Production ready in 10 months
                                                              Robotic Welders
                                                              Study Current Process
  Become a Cost oriented
                                        Reduce                Check for Inefficiencies
  operation that contributes                                                              Reduce Production Cost by 20%
                                        Production Cost       and Cost Reduction
  to the profit margin
                                                              Opportunities
                                                                                          Decrease Takt Time
                                                              Increase Peak Capacity
   Produce the best Quality             Increase Quality                                  (time to process a part) from 28.8
                                                              as a strategic
  Products with high First              Increase                                          sec/piece to less than 20
                                                              advantage.
  Time Quality                          Production                                        seconds/piece
                                                              Trim down the Quality
  ( FTQ)                                Capacity                                          Raise First Time Quality (FTQ)
                                                              Inspection Process
                                                                                          from 58% to bigger tan 90%.
                                                              Release work force
  Have the most qualified,                                    from Mechanical
                                        Provide New                                       Increase the welding and value
  motivated and committed                                     Operations to include
                                        Value Added                                       added production throughput
  teams adding more value to                                  more value added
                                        Operations                                        between 25% an 50%.
  the Operation                                               operations – Ready to
                                                              Assemble Parts


2.2 Project Benefits
2.2.1 Stakeholders
         Figure 2.1 lists the most important stakeholders; we have divided them into external and
         internal suppliers or customers.

                                     Figure 2.1: Stakeholders (Ross & Rodriguez, 2010)
                                External Suppliers
                                                                 External Customers
                                   Wire Supplier
                                                                   OEM’ Suppliers
                               Metal Parts Suppliers
                                                                       OEM’s
                           Other Parts in Consignment

                                                      Process
                                                Manufacturing Eng.
                                                   Product Eng.
                                                Quality / Production
                                                                 Internal Customers
                                Internal Suppliers             Operations Department
                          Human Resource Department             Finance Department
                             Purchasing Department              Sales and Marketing
                                                                    Department



                                                                                                        10 | P a g e
Keller School of Management- Capstone PM600
2.2.2 Benefits
                     The project benefits are classified in the five categories of the Global Manufacturing System
                     (GMS): People, Quality, Response Capacity, Cost and Environment

                                                 Figure 2.2: Benefits (Ross & Rodriguez, 2010)




                                                              Response
   People                         Quality                                                        Cost             Environment
                                                              Capacity
                                                                                                                      1. Cleaner/Safer
                                                                                                                           working
    1. Increase                                                                                                      environment, less
                                                                                         1. Savings in the cost     lubricants, grease,
   Professional                                                   1. Increase
Development of the                                                                         of production by         production debris.
                                                             Production Volume                                       2. Use less energy
    labor force                  1. Improve FTQ for                Capacity                       20%
                                 production process                                                                      and fluids in
   2. Elevate the                                            2.Increase product              2. Opportunity              production
technical level of the               2. Increase                   Portfolio                Cost to product          3. Less noise and
    labor force                   productivity and           3. Add value added           more value added           distraction in the
                                  efficiency of the           components, and                    parts              production process
3. Add better paying                                                                     3. Motivate Wokers
                                  production line                 assemblies                                          4. Reduction of
        jobs                                                                             for Cost Reduction
                                                             4. Add Flexible Mfg.                                       Incidents and
    4. Increase                                                  Production                      Ideas                    Accidents
   Empowerment                                                                                                            5. Improve
                                                                                                                      Ergonomic and
                                                                                                                           Working
                                                                                                                        Environment
                                                                                                                          Conditions




                                                              HOW
                                                             The new Equipment
  The new assembly
                                                                  will increase
    line will require                                          productivity and
sophisticated , state                                        production capacity.
of the art automated           The new automated             The new equipment
   equipment, with                equipment will             will allow release of         Include automated         Implement a Lean
     better control,              contribute to a                                           equipment in the         and Clean flow of
                                                              the labor force to
  technical skills and            more stable and              add new added              wire gauge checking,      materials. Introduce
      management                precise production             value processes,             wire forming and          the automated
 decision. The labor           process giving better                                      welding production           equipment to
                                                                 increasing the
      force will be             quality of parts at a         product portfolio.          stations to decrease      reduce mechanical
 involved in this and            faster production            Develop a Flexible          production takt time          operations.
       future cost                      rate.                Operations design to
 reduction initiative                                        produce for a variety
with bonus pays per
                                                                  of parts and
   suggestion ideas.                                                volumes.




                                                                                                                  11 | P a g e
          Keller School of Management- Capstone PM600
2.3 Statement of work
2.3.1 Project Summary
                                          Table 2.2: Project Description

                  Client/Vendor name                   Production Department

             Client/Vendor’s administrator             PMO
                                                       Automation of Spring/Wire Form
                      Project name
                                                       Production Line
                 Engagement duration                   43 Weeks
                                                             th
                        Begin date                     May 5 , 2010
                                                                  nd
                           End date                    March 2 , 2011


2.3.2 Scope
         The project will design, develop and implement the automation of the Springs and Wire Forms
         assembly line within a $2.5million budget in a 43 week period. The Project will include facility
         design, equipment and process design, procurement of new equipment, installation of
         equipment, accommodations of assembly line space, training and manufacturing validation of
         the new production assembly line. More details on the scope development will be explained on
         section 4.3.

2.3.3 Phases and Milestones
                      Table 2.3: Phases and Milestones (Ross & Rodriguez, 2010)

      Pase                                                             Completion date
                                                                        Pase
                                                                               rd
      Project Planning Phase                                             June 3 , 2010
                                                                               rd
      Program Initiation                                                 June 3 , 2010
                                                                                         th
      Manufacturing Design Phase- Execution                        September 7 , 2010
                                                                                th
      Layout Design                                                     June 30 , 2010
                                                                               th
      Equipment Design                                                   July 14 , 2010
                                                                                nd
      Engineering Data Release                                          August 2 , 2010
                                                                                         st
      Procurement Phase-Execution                                 December 21 , 2010
                                                                                     st
      Purchase Orders                                             September 1 , 2010
                                                                                         st
      Equipment Development and Shipping                          December 21 , 2010
                                                                               nd
      Production/Validation Phase –Completion                          March 2 , 2011
                                                                                    st
      Installation of Equipment                                        January 26 , 2011
                                                                                nd
      Validation of Equipment                                           March 2 , 2011




                                                                                              12 | P a g e
Keller School of Management- Capstone PM600
2.3.4 Schedule of Rates - Labor
           Additional overtime hours are required for professional staff to account for action plan in procurement,
           engineering and installation of new equipment from Vendor B. See section 6 for more details. (Detailed
           information on each labor resource is provided in Appendix B).

                              Table 2.4: Schedule of Rates (Ross & Rodriguez, 2010)
         Item description              Quantity          Avg.           Delivery             Cost             Cost
                                                      Rate/hour        schedule            Baseline         Baseline
                                                                      (Man - ours)                          Modified
                                                                              2
Professional Staff                        18           $29.14           7,417             $199,706         $216,141
(Engineers, Managers,
Supervisors)
Operations Staff                          16           $16.50            4,800            $79,233           $79,233
(Line Operators)
Current Operations Staff                  42           $15.42           12,600            $194,319         $194,319
( Line Operators, Inspectors)
Totals                                                                                   $473,258.58      $489,693.24




2.3.5 Equipment and Materials
           A 5% increase on price for new equipment: Wire Gauge Checkers and Wire Forming CNC, is to be added
           to the modified Baseline once the negotiations are revised with Vendor B. See section 6 for more details.
           (Detailed information on Equipment and Materials is provided in Appendix B).

                                   Table 2.5: Equipment Rates (Ross & Rodriguez, 2010)

                                                           3               Cost                        Cost
    Item description        Quantity           Rate/unit
                                                                         Baseline                    Baseline
                                                                                                     Modified
Computer                       5                    $2,000.00                $10,000.00                  $10,000.00
Terminal
Wire Gauge                     2                  $ 150,000.00              $300,000.00                 $315,000.00
Checkers
Wire Forming CNC               5                  $ 210,000.00            $1,050,000.00                $1,102,500.00

Robotic Welders                2                  $ 205,000.00              $410,000.00                 $410,000.00


Totals                                                                       $1,770,000                  $1,837,500




2
 Delivery Schedule for Baseline was 6,290 hours not including additional hours for unexpected event (section 6)
3
  Rates/Units for modified baseline increased 5% for Wire Gauge Checkers ($157,500) and Wire Formers
($220,500)



                                                                                                         13 | P a g e
Keller School of Management- Capstone PM600
2.3.6 General Administration, Contingency, Others
                 Additional cost for trips, General Administration/Overhead are included as part of this project
                 only.


                                                Table 2.6: Other Costs (Ross & Rodriguez, 2010)
                                Item Description                           Cost             Cost
                                                                         Baseline         Baseline
                                                                                         Modified
                                General Administration                  $109,123         109,123

                                Trips                                    $10,000         $10,000

                                Contingency                             $215,127         $131,191

                                Totals                                  $334,250         $250,314




        2.3.7 Summary of Total Cost
                 The total cost (modified) did not changed. All action plans cost to activate new Vendor B will be
                 absorbed by the Contingency Budget, hence reducing this contingency figure to $131,192.00
                 .(Detailed information on cost on Section 4)




Figure 2.3:Cost Distribution Chart (Ross & Rodriguez, 2010)




                                                                       Table 2.7 : Summary Cost Structure (Ross & Rodriguez, 2010)

                                                                                                              14 | P a g e
        Keller School of Management- Capstone PM600
2.3.8 Payment terms
         No including contingency. Project Manager’s professional fees are prorated on the overall project.
         (Detailed information on Payments is provided in Appendix C)


                             Table 2.8: Payment Schedule (Ross & Rodriguez, 2010)

                     Pase                       Completion date      Payments due         Payments due
                                                                        Baseline        Baseline Modified
                                                       rd
Project Planning Phase                           June 3 , 2010           $1,320              $1,320
                                                            th
Manufacturing Design Phase- Execution         September 7 , 2010        $48,845              $48,845

Procurement Phase-Execution                    December 21, 2010       $1,353,065          $1,419,573
                                                       nd
Operations/Validation Phase –Completion          Marc 2 , 2011          $781,228            $798,655




                                                                                                      15 | P a g e
Keller School of Management- Capstone PM600
2.3.9 Statement of work – Assumptions
                                                  Table 2.9: Assumptions (Ross & Rodriguez, 2010)
          Product                     Operations/              Quality        uman Resources               IT              Management-
        Engineering                Production/Supply                                                                     Presidency/Finance
 Small to Mid-Size Springs       Intension to Keep New       Current First    Higher Tecnical          Current ERP        Top Management
 and Wire Forms Products            Production Rate,        Time Quality is   Labor Force will       System in place        Endorsement
                                    Desire to increase           58%           be demanded          for Material and
                                   Production Capacity                                                Cost control
      Material Sapes &            Current Operations 3      There are two      This is a Non-       DesignCAD/CAM       VSM Worksop Results
 Specifications: .004 inches       Shifts – 8 hours. The    Six Sigma Belts    Union Facility       systems in Place.   for improvement and
       to 2.0 inches in           two lines will produce                                                Simulation           opportunities
    diameter,round wire          simultaneously during                                                 Production
 ,square wire , rectangular              validation                                                 Systems in Place
  wire, special section wire
  Body Types open-coiled ,        Lead Average Time to      Will follow the         Future         New Computer,        The Project will Follow
helical shaped usually coiled     Produce One Part is 8      Quality Valve      Placement of       CNC systems will           the Global
 with a constant diameter,               hours              Review – Stage     Employees will          need to be        Development Plan of
     though they can be                                       Gate Plan          be required.        installed and          the Company
produced in hourglass, cone                                                       HR Plan is      callibrated. Added
      and barrel shapes                                                         required. Less     to the TPM plan
                                                                               labor force will
                                                                                 be required
Materials spring steel ,high       Current Production           Quality       Must keep some      New Equipment           Payments Plan for
  carbon steel, low carbon        Average is 3000 Parts      Inspection of    part of the labor   will be syncronize         Equipment
 steel , nickel plated carbon           per day              Production in     force for value       with Andon            25% @Deposit
steel, stainless alloys, non-                                    place              added             Production          25% @ Reception
   ferrous metals: elgiloy,                                                       operations            System            25% @ Validation
  astelloy, monel, inconel,                                                                                               25% @Installation
            Titanium
Presence of testing Lab with         No Space Layout        Will work along    Must identify
   Materials an Durability             Constraints           with Product      high and low
          Equipment                                         Engineering for     performers
                                                                Product
                                                             Validation on
                                                            new production
                                                              Equipment
                                 Equipmet Cost already                         higher paying
                                   includes Insurance                         rates will come
                                     and Freigt Cost                             after new
                                                                                equipment
                                                                              installation for
                                                                                 Operators
                                   Turnkey ( in-service)
                                 installation by supplier
                                  through validation of
                                        production
                                  New Automated and
                                      Development
                                    Equipment will be
                                  declared and covered
                                      by FloorShop
                                  Insurance Equipment
                                           Policy



                                                                                                                    16 | P a g e
           Keller School of Management- Capstone PM600
2.3.10 Change Management Process

         The change management process will follow three internal procedures:

         1. Engineering/Process Change Notifications, release per engineering system
         2. Freeze Design Dates – Red Zone will be in the project Schedule to submit changes to the
            Project Council during the Red Zone Stage
         3. Scope Change – Any change in scope will be submitted to the PMO office and presented to
            the Project Council for approval

              For more detailed Change Management process refer to section 4.4



2.3.11 Engagement Related Expenses


           General Administration Expenses


         All payments and disbursement of money will be done through our Finance Department. All
         checks and bank transferred will need to be authorized and audited by our Finance department
         which will be the only entity authorized to release the funds. All Administration expenses will
         be accounted for in the Project Budget and will be released accordingly. Other departments may
         enter their cost, materials, resource request on our ERP (Enterprise Resource Planning) system
         for financial calculations and Finance approval and release.

           Payroll


         Payments of Payroll will be generated by the human Resource Department depending on the
         numbers of hours reported on the project. Finance will authorize and release payments for
         payroll purposes.

           Materials


         Material and Equipment payments will be generated by the Purchasing Department into the ERP
         system, and submitted for approval to Finance Department, which will be authorizing and
         releasing funds according to terms of payments agreed between Supplier and the Company.
         Any payment contract arrangements needs to be prepared and reviewed by the Purchasing
         Department and presented to the Finance Department for planning and provision purposes.




                                                                                            17 | P a g e
Keller School of Management- Capstone PM600
2.3.12 Acceptance and authorization



                   The terms and conditions of the Professional Services Agreement apply in full to the
                   services and products provided under this Statement of Work.

                   IN WITNESS WEREOF, the parties here to each acting with proper authority will
                   authorize the execution of this Statement of Work.




                 Full name                                             Full name



                 CEO – Automotive Parts, Inc                           Project Manager - PMO
                 Title                                                 Title




                 Signature                                             Signature




                 Date                                                  Date




                                                                                              18 | P a g e
Keller School of Management- Capstone PM600
2.4 Project Plan
2.4.1 Technical Description of New System
         API conducted a Value Stream Mapping workshop to identify the opportunities for improvement
         and to streamline the production of springs and wire forms.

         Current Process


         A SIPOC (Supplier, Inputs, Process, Output and Customer) depicts the current process and flow
         of materials and information. A more detailed Value Stream Map of the current System is
         shown on Appendix D. The Value Stream Map shows clearly where the inventory (waste) time
         is, and finds where the Wiring Gauging, Wire Forming and Welding stations become
         bottlenecks in the production process.


                               Figure 2.4: SIPOC Current Process (Ross & Rodriguez, 2010)




                                                                                            19 | P a g e
Keller School of Management- Capstone PM600
2.4.2 Facility Design and Simulation
           In order to avoid future errors and rework, we will be using AutoCAD and other Simulation Tools
           to design the new shop floor and simulate the production flow with the new equipment in
           place. Both the old and the new assembly line will run simultaneously for the period of the
           Manufacturing Validation Build of the new assembly Line. After production is validated the old
           equipment needs to be sold or scrapped within six month of project completion (this activity is
           considered out of the scope of the project)

 2.4.3 Future Process
           The high Inventory time (waste) before wire inspection, wire forming and welding stations is
           creating bottlenecks, increasing the lead time of the production process. These three stations
           will be automated in order to increase throughput and production flow.

           To reduce the Lead Production Time and specially the Inventory Time and Changeover Time, the
           future process will incorporate three major automated equipments, which include CNC
           (Computer Numerical Control). These equipments will help release the inventory bottlenecks in
           the Gauge Checking, Wire Forming and Welding, making a more productive and efficient
           production flow.

           2Electronic Wire Gauge Checkers
           5Automated Wire Formers
           2Robotic Welders

                 Current and Future Value Stream Maps are shown in Appendix D. Figure 2.5
           summarizes the main metrics from Current and Future Process.



           Current Process                                                        Future Process

           Variable                            Measure                           Variable               Measure


Lead Production Time                  428 Minutes                 Lead Production Time                 <200 Minutes

Value Added Time                      246 Minutes                 Value Added Time                     >150 Minutes

Non-Value Added Time                  48 Minutes                  Non-Value Added Time                 0-10 Minutes

Inventory Time ( waiting Time)        134 Minutes                 Inventory Time ( waiting Time)       <50 Minutes

Takt Time (seconds/part)              28.8 seconds/part           Takt Time (seconds/part)             <20 seconds/part

First Time Quality :                  58%                         First Time Quality :                 90%

Change-Over time:                     60 Minutes                  Change-Over time:                    <30 Minutes




                                 Figure 2.5: Process Performance Metrics (Ross & Rodriguez, 2010)
                                                Figure 5: Process Metrics

                                                                                                    20 | P a g e
 Keller School of Management- Capstone PM600
2.4.4 Detailed Project Schedule - Modified
         Figure 2.6 shows the progress of schedule when 26% of the worked has been completed. The
         Black Bar shows the Baseline Schedule; The Blue Bar shows Baseline Modified Schedule ; The
         Red Bar shows the Critical Path for the Baseline Modified Schedule


                             Figure 2.6: Baseline Modified Schedule (Ross & Rodriguez, 2010)




                                                                                               21 | P a g e
Keller School of Management- Capstone PM600
2.4.5 Specific Challenges
                 Specific challenges in the following areas of: Supply, Communication, Operations, Systems,
                 People, Legal and Quality were all identified in our Risk Assessment, and included in our Risk
                 Assessment Matrix, with Contingency plans.

       2.4.6 Risk Management Matrix
                 The Project Team will follow recommendations according to the detailed Risk Management
                 Matrix considering the major and top risks on the projects and contingency action plans. Top
                 Risks considered while developing the project schedule are shown in Table 2.10.
                 The Baseline Modified Risk Assessment includes the new risk and contingency for Supplier
                 Selection, and the current contingency plan that is currently in progress. Figure 2.7
                 summarizes the Risk Assessment considerations. Section 2.4.7 addresses action plans for
                 Shipping and Hiring/Placement risks. Top major risks considered during project planning phase.
                 Baseline Risk Matrix per activity attached on Appendix A.

                                    Table 2.10: Risk Matrix (Modified) (Ross & Rodriguez, 2010)

Risk                                                                           Severity
                Activity                        Risk          Type4   Prob.      1=Low      Rank             Contingency
 #                                                                               5=High
 1     Shipping of Equipment         Delays in Shipping for                                         Avoid winter season by pulling
                                     Winter Season                                                  ahead project with overtime in
                                                              SUP      85%         5         4.25
                                                                                                    the Design Phase

 2     Supplier Selection            Late Change of                                                 Ensure suppliers are ranked
                                     Suppliers, limited                                             among top Suppliers in the
                                     Suppliers                SUP      75%         5         3.75   Industry. Have a Backup
                                                                                                    Supplier Plan Ready in Case
                                                                                                    selected Supplier fails to comply

 3     Hiring/Placement              Labor Conflicts for                                            Avoid Labor Conflicts and
                                     new Entrants due to                                            Stoppage by preparing an HR
                                     Potential Layoffs -        R      65%         5         3.25   Placement Plan Ahead and
                                     Strike                                                         Presenting to Production
                                                                                                    Management
 4     Displacement of Old           Damage of production                                           Avoid Damages by
       Equipment                     Equipment                                                      Using Experts in Transportation,
                                                              OPE      65%         5         3.25   Include Equipment in Insurance
                                                                                                    Coverage before acquisition

 5     Design Changes                Late Design Changes                                            Use ECN and Change
       Engineering                                                                                  Management Process for
                                                                                                    Engineering Change
                                                              ENG      75%         4         3.00   Communication. Implement Red
                                                                                                    Zone and Freeze Date for
                                                                                                    Engineering Changes



       4
           SUP=Supply, HR=Human Resource, OPE=Operations, ENG=Engineering, QUA=Quality



                                                                                                           22 | P a g e
       Keller School of Management- Capstone PM600
Risk                                                                                                                     Severity
                Activity                                  Risk                          Type            Prob.               1=Low            Rank                             Contingency
 #                                                                                                                          5=High
 6     Install/Calibration of               Delays on installation                                                                                          Invite Supplier to Installation.
       Equipment                            due to complexity                               OPE         55%                   5              2.75           Turnkey In Service Installation

 7     Construction                         Safety Regulations not                                                                                          Revision of legal, permits and
       Requirements                         in Compliance                                   ENG         50%                   5                 2.5         safety by Safety Committee

 8     Engineering Testing                  Parts fails to Product                                                                                          Prepare Six Sigma Teams for
                                            Engineering/Quality                          QUA            50%                   5                 2.5         Action Plans
                                            Validation Compliance
 9     Negotiations                                                                                                                                         Set Target Price, Benchmark and
                                            Negotiations exceed
                                                                                            SUP         75%                   3              2.25                 3 Quotation Process
                                            Budget
10     Equip. Fabrication                   Delays of fabrication                                                                                           Select Expert Suppliers and Visit
                                            due to complex                                                                                                   of Manufacturing Engineering
                                            customization                                                                                                   Development, include overtime
                                                                                            SUP         55%                   4                 2.2           to pull ahead development
                                                                                                                                                             dates. Have Two Alternatives
                                                                                                                                                             Suppliers ready for contracts

11     Production Validation                Worker’s absence due                                                                                                 Prepare a list of Floater Pool
                                            to winter and lack of                           OPE         50%                   4                 2               workers as part of the HR Plan
                                            motivation



                                   Figure 2.7: Risk Summary Chart - Modified (Ross & Rodriguez, 2010)



                                                              Risk Assessment Summary

                                       5            5            5            5                           5            5           5


                                4.25         4.25                                            4                                                              4             4


                                                          3.25         3.25                                                                     3
                                                                                        3
                                                                                                   2.75
                                                                                                                 2.5         2.5
                                                                                                                                         2.25         2.2
                                                                                                                                                                      2



                            85%            75%                                    75%                                                  75%
                                                        65%          65%                         55%          50%          50%                      55%         50%




                                                                                  Prob           Rank         Severity



                                                                                                                                                                          23 | P a g e
       Keller School of Management- Capstone PM600
2.4.7 Top Risk Recommended Action Plans
          1. Shipping/Weather Risk

                                 Table 2.11: Weather/Shipping Action Plan (Ross & Rodriguez, 2010)

                       CURRENT                                                         ALTERNATIVE
  Shipping of new equipment will be planned from                 Plan for overtime work during the Design and Purchasing
November 2010 through February 2011, which is in the             Activities will mitigate Shipping Risk, pulling ahead Project
middle of winter Season, delaying the installation and            Schedule almost 1 Month ahead and reducing total cost
                      training                                     of the project due to MVB1 and MVB2 synchronization
                                                    COSTS (Only Project )
      Project Cost – Expected                                         Project Cost – Expected
                                               $2,232,654                                                     $2,184,458
           w/o Overtime                                                   with Overtime
                                                                     Project Cost – Pessimistic
    Project Cost – Pessimistic-
                                                  2,557,217        with Overtime + Winter Storm               $2,389,912
   w/o Overtime + Winter Storm

    Contingency Cost- Risk                     $324,563               Contingency Cost - Risk                 $205,454
                                                                  Extra Overtime Cost – 342 ours                $11,970
                                                           BENEFITS
           Delays and bigger Inbound Cost                                       Better Working Shipping Schedule
                  higher Shipping Fees                                                 Lower Shipping Fees
       Installation and Training over Christmas                             Avoid Christmas holidays work overlapping
      Expected Finish Project in March 28, 2011                              Expected Finish Project in Marc 3,2011
           Late Finish Risk August 10, 2011                                       Late Finish Risk April 26, 2011




          Labor Overtime Plan to Mitigate Shipping Risk


                              Table 2.12: Overtime Proposal (Ross & Rodriguez, 2010)

               Tasks                           Resource          Overtime           Rate        Total
                                                                   hrs                          Labor
 Layout Design                         Facility Engineer              80             35            $2800
 Equipment Design                      Process Engineer               54             35            $1890
 Equipment Design                      Systems Engineer               20             35             $700
 Equipment Design                      Material Engineer              27             35             $945
 Procurement                           Buyer                          81             35            $2835
 Equipment Development                 Manufacturing Engineer         40             35            $1400
 Equipment Development                 Supplier                       40             35            $1400
 Total                                                                342                       $11,970




                                                                                                           24 | P a g e
 Keller School of Management- Capstone PM600
2. Hiring/Placement Risk

                             Table 2.13: Labor Conflicts Action Plan (Ross & Rodriguez, 2010)

                      CURRENT                                                     ALTERNATIVE
                  Total: 42 Workers                                                Total : 16 Workers
8 Wire Gauge Checkers                                           2 Gauge Operators
3 Gauge Inspectors                                              5 Wire Forming Operators Shift 1
10 Wire Forming Operators Shift 1                               5 Wire Forming Operators Shift 2
8 Wire Forming Operators Shift 2                                2 Welders Operators Shift 1
4 Wire Forming Operators Shift 3                                2 Welders Operators Shift 2
5 Welders Shift 1                                                                           +
3 Welders Shift 2                                               HR Distribution of 26 Workers:
1 Welders Shift 3                                               46% - 12 Workers Placement with Suppliers and OEM’s
                                                                15% - 4 Floaters
                                                                27% - 7 Workers Trained for Value Added Operations
                                                                12% - 3 Workers Low Performers
                                                           COSTS
Cost/Mont                                     $103,636          Cost/Mont                               $42,257
Probability of Work                                             Probability of Work
                                                %65                                                       <%20
Stoppage                                                        Stoppage
                                                         BENEFITS
                  Mechanical Labor                                          Automated and Controlled Labor
         High Risk to incidents and accidents,                            Reduce the incidents and accidents,
               Safety and Health issues                                           Increase ergonomics
                   Higher Fixed Cost                                                Lower Fixed cost
             Technical Skills Development                                 Professional Technical Development
           High Takt time, low Productivity                                Low Takt time, higher Productivity
            Professional Career Stagnation                          Career Growth Opportunities in Top Companies
   High gaps to negotiate placement of labor force                  Close gap to negotiate placement of labor force


          Human Resource Action Plan to Mitigate Risk


                              Table 2.14: Replacement Proposal (Ross & Rodriguez, 2010)
                                    Identify job opportunities with higher paying salaries for those employees that
                                     will be released from their duties.
Placement                           Employees should not be laid off until an acceptable position in a OEM’s or
                                     Supplier has been arranged and contracted

                                    Identify those employees who will remain in the organization as on-call in the
                                     organization.
Floater                             These group of employees can rotate in different positions as required, and can
                                                            rd
                                     be prepare for future 3 shift or production increments

                                    Identified High Performer Workers to remain in the organization and trained for
Trainees                             value added operations.

                                    Workers who will need to be laid off due to their low performance
Low Performers




                                                                                                         25 | P a g e
Keller School of Management- Capstone PM600
3. Automated Equipment


         The Project intends to install state of the art new equipment for the facility. However, this new
         equipment is sophisticated and should be calibrated by experts. There is a risk to delay the
         installation, setup and validation of equipment, assuming proper training and assistance is not in
         place. It is recommended to close a Turnkey in Service installation from Equipment Supplier.
         This means the supplier will accompany the team of engineers during the installation, training,
         setup and validation of production. With this action it is intended to mitigate the uncertainty of
         setup, functioning and operation of new equipment, while training the group of engineers for
         future control, operation and maintenance of new equipment. The New Equipment will have
         period of guarantee of 90 days and will require maintenance assistance from the Vendor
         periodically. A new Contingency Plan for OEM Supplier Change is explained on section 6.0




                                                                                              26 | P a g e
Keller School of Management- Capstone PM600
2.5 Project Completion Plan
2.5.1 Deliverables




                                                                                                                     27 | P a g e
Keller School of Management- Capstone PM600




                                              Figure 2.8: Project Completion/Deliverables (Ross & Rodriguez, 2010)
2.5.2 Acceptance Test
         The Project will follow the Program Quality and Readiness Review (PQRR) as a Stage Gate
         Model. Different Review Valves will allow for checking of metrics, deliverables and buying off
         before proceeding to the next Stage of the Project. There are nine (9) Review Valves as follow:

                                    Table 2.15: Stage Gate Reviews (Ross & Rodriguez, 2010)

         Gate Name                            Initials Objectives
    1.   Preliminary Plan Review                PP       Test Preliminary Project Information
    2.   Program Initiation Review              PI       Test Project Plan, Team Structure and Initiation
    3.   Manufacturing Engineering              MP       Test Engineering Design and R Planning
         Review
    4.   Verify Data Release Review             VDR      Validate Engineering Documentation for Procurement
    5.   Contract Sign-Off                      CSO      Validated Procurement and Contract with External Suppliers
    6.   Production/ Operations                 POD      Test readiness of Operations/ Production
         Review
    7.   Manufacturing Validation              MVB       Validation new equipment and parts out of new production line
         Build I                                 I
    8.   Manufacturing Validation              MVB       Validation new equipment and parts out of new production line
         Build II                                II
    9.   Start of Regular Production           SORP      Final Approval and Sign-off to regular production, Cost validation


         Figure 2.9 represents the Acceptance Test to define when a PQRR Valve should be Approved,
         Revised or Stopped.

                                              Figure 2.9: Acceptance Test Chart (Motors, 2006)




                                                                                                            28 | P a g e
Keller School of Management- Capstone PM600
2.5.3 Acceptance Sign-off Cart
         Figure 2.10 shows a check list of items to be completed at each Review Valve




                                              Figure 2.10: Acceptance Criteria/Sign-0ff Chart (Ross & Rodriguez, 2010)
                                                                                                                         29 | P a g e
Keller School of Management- Capstone PM600
3 Management Proposal
                      3.1 Corporate Organizational Structure
                               API has a Matrix Organization structured based on Projects. The Project Team will report directly to the Project Manager for task related
                               projects, also they will report to operations and functional managers from different departments.

                                                                          Figure 3.1: Corporate Organizational Chart (Ross & Rodriguez, 2010)


                                                                                                             President
                                                                                                               CEO
                                                                                                              Owen
                                                                                                              French

Project Monitoring               Director of                                             Director of                                                         Supply and    Director of        Sales and       Finance
   & Controlling                 Engineering                                             Operations                                                         Procurement     Human             Marketing       Director
Director, Dick Ives                                                                                                                                           Director     Resources           Director
                           Product      Manufacturing      Quality        Materials                                      Production
                                                                                                                                                              Purchasing                                      Finance
                         Engineering     Engineering       Manager        Manager                                         Manager                                          HR Manager       Sales/Marketing
                          Manager                                                                                                                              Manager                                        Manager
                                          Manager                                                                                                                                               Manager

                                                                Quality      Materials        Production       Production                         Safety                                                         Finance
     Project                 Product         Facility                                         Supervisor                         Maintenance                    Buyer             HR
                                                               Engineer      Engineer                          Supervisor                      Ergonomics                                                        Auditor
    Manager A                Engineer       Engineer                                            Shift 1                           Engineer                                     Specialist       Salesperson
                                                                                                                 Shift 2                       Supervisor

                              Testing       Industrial                                          Production        Production                                                                    Marketing
                             Engineer       Engineer                                             Workers           Workers                                                                      Specialist

                                            Product
                                            Engineer

                                             System
                                            Engineer

                                               Manufacturing
                                                 Engineer




                                                                                                                                                                                                  30 | P a g e
                      Keller School of Management- Capstone PM600
3.1.1 Corporate Roles and Responsibilities
         The purpose of the Corporate Responsibility Matrix ( table 3.1) is to assign departments or
         individuals to activity categories, define role responsibilities, and define relationships between
         groups. This matrix should be completed before detailed resource allocating or scheduling. The
         goals of the roles and responsibilities matrix are to:
              Define roles and responsibilities of project stakeholders.
              Improve overall project team and stakeholder communication.
              Proactively identify gaps in assignments, accountability, or resources.
              Clarify cross-functional interactions between project team members.
              Document project interdependencies with other enterprise initiatives.
              Define project team interactions with supporting resources and departments.

                                      Table 3.1: Corporate Responsibility Matrix (Ross & Rodriguez, 2010)

                                                            Project Activity (Spring Automation)
         Organization Title                                                               Project
                                   Requirements         Design            Test                         Training
                                                                                       Communication

     Project Management:
     Monitoring &                        R                 C               S               A/R              S
     Controlling

     Engineering
                                       A/R/C            A/R/C             R/C               C                S

     Finance
                                          S                                                 C

     Operations/
     Production/                          S                S                S               S/C             R
     Manufacturing

     Supply and
                                        A/C                S                                C/S
     Procurement

     Human Resources
                                                                                            C/S             A/R

         KEY:
         A – Accountable for successful completion of task.
         R – Responsible for completion of task. (Task can be delegated to this person.)
         S – Supports task.
         C – Requirements communication about the task.




                                                                                                       31 | P a g e
Keller School of Management- Capstone PM600
Table 3.2: Corporate Roles & Responsibilities (Ross & Rodriguez, 2010)

           Title                                  Role                                       Responsibilities
 Project Manager             The Project Manager is responsible for            Project Plan
                             developing, in conjunction with the Project       Manage and lead the project team.
                             Sponsor, the project charter. The Project
                                                                               Manage the coordination of the partners
                             Manager ensures that the project is delivered
                                                                                and the working groups.
                             on time, within budget, and to the required
                             quality standards.                                Develop and maintain a detailed project
                                                                                plan.

 Engineering                 The Engineering department’s role is to             Layout, Facility Design
                             Perform as a manager or project systems             Construction Plan and Requirements
                             engineer for a complex project (e.g. several
                                                                                 Regulations and Permits
                             distinct subsystems or other defined services,
                             capabilities, or products and their associated      Requirement and Specs. Development
                             interfaces).                                        Process Assembly Instructions
                                                                                 Tools and Equipment Requirement Specs.
                                                                                 Standard Procedures Operation Sheets
                                                                                 Visual Aids
                                                                                 Simulation of Production
                                                                                 Testing
                                                                                 Total Productive Maintenance
                                                                                 Quality/Engineering Product Testing Plan
                                                                                 Engineering Review Valve

 Finance                     Once the organization as established goals     Audits of Financials
                             and associated strategies (or ways to reach
                             the goals), funds are set aside for the
                             resources and labor to the accomplish goals
                             and tasks. As the money is spent, statements
                             are changed to reflect what was spent, how it
                             was spent and what it obtained. Review of
                             financial statements is one of the more
                             common methods to monitor the progress of
                             programs and plans. The most common
                             financial statements include the balance
                             sheet, income statement and cash flow
                             statement.
                             The major work of the                               Installation Plan
                             Project accomplished (i.e., design,
 Operations/                                                                     Simultaneous Production Plan
                             development, construction, production,
 Production/                 testing, system activation, etc.).                  Manufacturing Validation Plan
                                                                                 Training




                                                                                                         32 | P a g e
Keller School of Management- Capstone PM600
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper
API Project Capstone Paper

More Related Content

What's hot

Friction loss tables
Friction loss tablesFriction loss tables
Friction loss tablesbeqs
 
Strategic Asset Management - Water Utilities
Strategic Asset Management - Water UtilitiesStrategic Asset Management - Water Utilities
Strategic Asset Management - Water Utilitiesjpfeliciano
 
top 10 events assistant interview questions and answers
 top 10 events assistant interview questions and answers top 10 events assistant interview questions and answers
top 10 events assistant interview questions and answerscreatjonh
 
Thermo problem set no. 2
Thermo problem set no. 2Thermo problem set no. 2
Thermo problem set no. 2Yuri Melliza
 
Difference Between Quality Control Inspection and Commissioning Inspection
Difference Between Quality Control Inspection and Commissioning InspectionDifference Between Quality Control Inspection and Commissioning Inspection
Difference Between Quality Control Inspection and Commissioning InspectionOlivia Wilson
 
Bahan Paparan Inspeksi Teknis, Pemeriksaan Keselamatan dan PLO Pertagas.pptx
Bahan Paparan Inspeksi Teknis, Pemeriksaan Keselamatan dan PLO Pertagas.pptxBahan Paparan Inspeksi Teknis, Pemeriksaan Keselamatan dan PLO Pertagas.pptx
Bahan Paparan Inspeksi Teknis, Pemeriksaan Keselamatan dan PLO Pertagas.pptxTSulistomo
 
Thermodynamics problems
Thermodynamics problemsThermodynamics problems
Thermodynamics problemsYuri Melliza
 
Design of air preheater for solar dryer for drying cereals
Design of air preheater for solar dryer for drying cerealsDesign of air preheater for solar dryer for drying cereals
Design of air preheater for solar dryer for drying cerealsSumit Dharmarao
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxhesham ismail
 
Case History of ISO 14224 Application in the QGOG Offshore Drilling Fleet
Case History of ISO 14224 Application in the QGOG Offshore Drilling FleetCase History of ISO 14224 Application in the QGOG Offshore Drilling Fleet
Case History of ISO 14224 Application in the QGOG Offshore Drilling FleetTony Ciliberti PE
 
M.V/H.V Cable trays earthing systems
M.V/H.V Cable trays earthing systemsM.V/H.V Cable trays earthing systems
M.V/H.V Cable trays earthing systemsMohamed Azzam
 
Design of machine elements - Spur gears
Design of machine elements - Spur gearsDesign of machine elements - Spur gears
Design of machine elements - Spur gearsAkram Hossain
 
Boiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridgedBoiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridgedBryan Haywood
 
Dynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and TurnaroundsDynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and TurnaroundsEJ (Ted) Lister
 
Procedural due process
Procedural due processProcedural due process
Procedural due processRoi Xcel
 

What's hot (20)

Friction loss tables
Friction loss tablesFriction loss tables
Friction loss tables
 
Strategic Asset Management - Water Utilities
Strategic Asset Management - Water UtilitiesStrategic Asset Management - Water Utilities
Strategic Asset Management - Water Utilities
 
top 10 events assistant interview questions and answers
 top 10 events assistant interview questions and answers top 10 events assistant interview questions and answers
top 10 events assistant interview questions and answers
 
Thermo problem set no. 2
Thermo problem set no. 2Thermo problem set no. 2
Thermo problem set no. 2
 
Difference Between Quality Control Inspection and Commissioning Inspection
Difference Between Quality Control Inspection and Commissioning InspectionDifference Between Quality Control Inspection and Commissioning Inspection
Difference Between Quality Control Inspection and Commissioning Inspection
 
Bahan Paparan Inspeksi Teknis, Pemeriksaan Keselamatan dan PLO Pertagas.pptx
Bahan Paparan Inspeksi Teknis, Pemeriksaan Keselamatan dan PLO Pertagas.pptxBahan Paparan Inspeksi Teknis, Pemeriksaan Keselamatan dan PLO Pertagas.pptx
Bahan Paparan Inspeksi Teknis, Pemeriksaan Keselamatan dan PLO Pertagas.pptx
 
Thermodynamics problems
Thermodynamics problemsThermodynamics problems
Thermodynamics problems
 
Inspection of-pressure-vessels
Inspection of-pressure-vesselsInspection of-pressure-vessels
Inspection of-pressure-vessels
 
Design of air preheater for solar dryer for drying cereals
Design of air preheater for solar dryer for drying cerealsDesign of air preheater for solar dryer for drying cereals
Design of air preheater for solar dryer for drying cereals
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptx
 
Case History of ISO 14224 Application in the QGOG Offshore Drilling Fleet
Case History of ISO 14224 Application in the QGOG Offshore Drilling FleetCase History of ISO 14224 Application in the QGOG Offshore Drilling Fleet
Case History of ISO 14224 Application in the QGOG Offshore Drilling Fleet
 
M.V/H.V Cable trays earthing systems
M.V/H.V Cable trays earthing systemsM.V/H.V Cable trays earthing systems
M.V/H.V Cable trays earthing systems
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Design of machine elements - Spur gears
Design of machine elements - Spur gearsDesign of machine elements - Spur gears
Design of machine elements - Spur gears
 
Elements 1 checked
Elements 1 checkedElements 1 checked
Elements 1 checked
 
Boiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridgedBoiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridged
 
Collective Negotiation Agreement
Collective Negotiation AgreementCollective Negotiation Agreement
Collective Negotiation Agreement
 
Dynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and TurnaroundsDynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and Turnarounds
 
TPI - Example Report.
TPI - Example Report.TPI - Example Report.
TPI - Example Report.
 
Procedural due process
Procedural due processProcedural due process
Procedural due process
 

Similar to API Project Capstone Paper

Strategic Technology Roadmap Houston Community College 2005
Strategic Technology Roadmap Houston Community College 2005Strategic Technology Roadmap Houston Community College 2005
Strategic Technology Roadmap Houston Community College 2005schetikos
 
Project Implementation Plan
Project Implementation PlanProject Implementation Plan
Project Implementation PlanAjjaWalker
 
WebIT2 Consultants Proposal
WebIT2 Consultants ProposalWebIT2 Consultants Proposal
WebIT2 Consultants ProposalSarah Killey
 
Strategy Field Project Report
Strategy Field Project ReportStrategy Field Project Report
Strategy Field Project ReportSaritaMishra62
 
SSTRM - StrategicReviewGroup.ca - Workshop 2: Power/Energy and Sustainability...
SSTRM - StrategicReviewGroup.ca - Workshop 2: Power/Energy and Sustainability...SSTRM - StrategicReviewGroup.ca - Workshop 2: Power/Energy and Sustainability...
SSTRM - StrategicReviewGroup.ca - Workshop 2: Power/Energy and Sustainability...Phil Carr
 
Sap hr implementation config rc - Aditi Tarafdar
Sap hr implementation config rc - Aditi TarafdarSap hr implementation config rc - Aditi Tarafdar
Sap hr implementation config rc - Aditi TarafdarAditi Tarafdar
 
BizTalk Practical Course Preview
BizTalk Practical Course PreviewBizTalk Practical Course Preview
BizTalk Practical Course PreviewMoustafaRefaat
 
Qs2 consultants manual
Qs2 consultants manualQs2 consultants manual
Qs2 consultants manualkhayer
 
Solmanfocusedbuild
SolmanfocusedbuildSolmanfocusedbuild
SolmanfocusedbuildGhassen B
 
BIMplement inc_proposal
BIMplement inc_proposalBIMplement inc_proposal
BIMplement inc_proposalAnkit Singhai
 
It Handbook On Mergers Acqui 130975
It Handbook On Mergers Acqui 130975It Handbook On Mergers Acqui 130975
It Handbook On Mergers Acqui 130975Kellermann Robert
 
Invest plus user manual
Invest plus user manualInvest plus user manual
Invest plus user manualInvest Plus
 
Business proposal coffee shop in Canada
Business proposal coffee shop in CanadaBusiness proposal coffee shop in Canada
Business proposal coffee shop in CanadaNewGate India
 

Similar to API Project Capstone Paper (20)

It project development fundamentals
It project development fundamentalsIt project development fundamentals
It project development fundamentals
 
Strategic Technology Roadmap Houston Community College 2005
Strategic Technology Roadmap Houston Community College 2005Strategic Technology Roadmap Houston Community College 2005
Strategic Technology Roadmap Houston Community College 2005
 
Project Implementation Plan
Project Implementation PlanProject Implementation Plan
Project Implementation Plan
 
Coinaid earth pilot
Coinaid earth pilotCoinaid earth pilot
Coinaid earth pilot
 
Business Plan
Business PlanBusiness Plan
Business Plan
 
WebIT2 Consultants Proposal
WebIT2 Consultants ProposalWebIT2 Consultants Proposal
WebIT2 Consultants Proposal
 
Strategy Field Project Report
Strategy Field Project ReportStrategy Field Project Report
Strategy Field Project Report
 
SSTRM - StrategicReviewGroup.ca - Workshop 2: Power/Energy and Sustainability...
SSTRM - StrategicReviewGroup.ca - Workshop 2: Power/Energy and Sustainability...SSTRM - StrategicReviewGroup.ca - Workshop 2: Power/Energy and Sustainability...
SSTRM - StrategicReviewGroup.ca - Workshop 2: Power/Energy and Sustainability...
 
Sap hr implementation config rc - Aditi Tarafdar
Sap hr implementation config rc - Aditi TarafdarSap hr implementation config rc - Aditi Tarafdar
Sap hr implementation config rc - Aditi Tarafdar
 
BizTalk Practical Course Preview
BizTalk Practical Course PreviewBizTalk Practical Course Preview
BizTalk Practical Course Preview
 
Hcc procurement procedures 8 28-18
Hcc procurement procedures 8 28-18Hcc procurement procedures 8 28-18
Hcc procurement procedures 8 28-18
 
Qs2 consultants manual
Qs2 consultants manualQs2 consultants manual
Qs2 consultants manual
 
Solmanfocusedbuild
SolmanfocusedbuildSolmanfocusedbuild
Solmanfocusedbuild
 
BIMplement inc_proposal
BIMplement inc_proposalBIMplement inc_proposal
BIMplement inc_proposal
 
It Handbook On Mergers Acqui 130975
It Handbook On Mergers Acqui 130975It Handbook On Mergers Acqui 130975
It Handbook On Mergers Acqui 130975
 
Invest plus user manual
Invest plus user manualInvest plus user manual
Invest plus user manual
 
U M Lvs I D E F
U M Lvs I D E FU M Lvs I D E F
U M Lvs I D E F
 
E elt constrproposal
E elt constrproposalE elt constrproposal
E elt constrproposal
 
Business proposal coffee shop in Canada
Business proposal coffee shop in CanadaBusiness proposal coffee shop in Canada
Business proposal coffee shop in Canada
 
Scope management
Scope management Scope management
Scope management
 

More from Ryder System, Inc.

More from Ryder System, Inc. (13)

Resume functional automotive
Resume functional   automotiveResume functional   automotive
Resume functional automotive
 
Hybrid Systems Definitions/Concepts
Hybrid Systems Definitions/ConceptsHybrid Systems Definitions/Concepts
Hybrid Systems Definitions/Concepts
 
Battery Experience
Battery ExperienceBattery Experience
Battery Experience
 
Resumex
ResumexResumex
Resumex
 
GMV Values
GMV ValuesGMV Values
GMV Values
 
Lean Startups from LEI
Lean Startups  from LEILean Startups  from LEI
Lean Startups from LEI
 
Oci white paper general motors
Oci white paper   general motorsOci white paper   general motors
Oci white paper general motors
 
Profile Xt
Profile XtProfile Xt
Profile Xt
 
Kaizen Workshop - Sales & Marketing
Kaizen Workshop - Sales & MarketingKaizen Workshop - Sales & Marketing
Kaizen Workshop - Sales & Marketing
 
Lean Project Management Principles
Lean Project Management Principles Lean Project Management Principles
Lean Project Management Principles
 
Lsi Results And Circumplex Hector Rodriguez
Lsi Results And Circumplex Hector RodriguezLsi Results And Circumplex Hector Rodriguez
Lsi Results And Circumplex Hector Rodriguez
 
Value Stream Mapping
Value Stream Mapping Value Stream Mapping
Value Stream Mapping
 
Gm Job Description
Gm Job DescriptionGm Job Description
Gm Job Description
 

Recently uploaded

PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxShruti Mittal
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...ssuserf63bd7
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 

Recently uploaded (20)

PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptx
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 

API Project Capstone Paper

  • 1. 2010 Automation Spring/Wire Form Assembly Line Working Plan Project Managers: Lydia Ross Hector Rodriguez Automotive Parts, Inc Master Capstone Project Keller School of Management 6/16/2010
  • 2. Contents 1 Executive Summary ...............................................................................................................................................6 1.1 Project Baseline ............................................................................................................................................6 1.2 Project Variance ...........................................................................................................................................8 1.3 Project Expansion .........................................................................................................................................8 2 Technical Proposal ................................................................................................................................................9 2.1 Project Purpose ............................................................................................................................................9 2.1.1 Background ..............................................................................................................................................9 2.1.2 The Need ..................................................................................................................................................9 2.1.3 Objectives and Goals .............................................................................................................................10 2.2 Project Benefits ..........................................................................................................................................10 2.2.1 Stakeholders ..........................................................................................................................................10 2.2.2 Benefits ..................................................................................................................................................11 2.3 Statement of work .....................................................................................................................................12 2.3.1 Project Summary ...................................................................................................................................12 2.3.2 Scope .....................................................................................................................................................12 2.3.3 Phases and Milestones ..........................................................................................................................12 2.3.4 Schedule of Rates - Labor ......................................................................................................................13 2.3.5 Equipment and Materials ......................................................................................................................13 2.3.6 General Administration, Contingency, Others .......................................................................................14 2.3.7 Summary of Total Cost ...........................................................................................................................14 2.3.8 Payment terms.......................................................................................................................................15 2.3.9 Statement of work – Assumptions.........................................................................................................16 2.3.10 Change Management Process ...........................................................................................................17 2.3.11 Engagement Related Expenses..........................................................................................................17 2.3.12 Acceptance and authorization...........................................................................................................18 2.4 Project Plan ................................................................................................................................................19 2.4.1 Technical Description of New System ....................................................................................................19 2.4.2 Facility Design and Simulation ...............................................................................................................20 2.4.3 Future Process .......................................................................................................................................20 2.4.4 Detailed Project Schedule - Modified ....................................................................................................21 2.4.5 Specific Challenges .................................................................................................................................22 2.4.6 Risk Management Matrix .......................................................................................................................22 2.4.7 Top Risk Recommended Action Plans ....................................................................................................24 2.5 Project Completion Plan.............................................................................................................................27 2.5.1 Deliverables ...........................................................................................................................................27 2|Page Keller School of Management- Capstone PM600
  • 3. 2.5.2 Acceptance Test ....................................................................................................................................28 2.5.3 Acceptance Sign-off Cart........................................................................................................................29 3 Management Proposal ........................................................................................................................................30 3.1 Corporate Organizational Structure ...........................................................................................................30 3.1.1 Corporate Roles and Responsibilities ....................................................................................................31 3.2 Project Organizational plan ........................................................................................................................34 3.2.1 Work Breakdown Structure ...................................................................................................................34 3.2.2 Project Organizational Structure ...........................................................................................................35 3.2.3 Project Team ..........................................................................................................................................36 3.2.4 Responsibility Matrix ............................................................................................................................38 4 Management Systems ........................................................................................................................................40 4.1 Supplier, Selection and Management ........................................................................................................40 4.1.1 Overview - Procurement of Automated Machines and Robots .............................................................40 4.1.2 Production-Line Equipment Vendors .....................................................................................................41 4.1.3 Computer Vendors.................................................................................................................................43 4.1.4 Contract Close-Out ................................................................................................................................43 4.2 Monitoring Cost and Schedule ...................................................................................................................44 4.2.1 Overview ................................................................................................................................................44 4.2.2 Labor Cost and Schedule........................................................................................................................45 4.2.3 Major Equipment Cost and Schedule ....................................................................................................47 4.2.4 Contingency, Administration and Others Cost ......................................................................................47 4.3 Management of Scope and Change Orders ...............................................................................................48 4.3.1 Overview ................................................................................................................................................48 4.3.2 Development of Scope ...........................................................................................................................49 4.3.3 Out-of-Scope Items ................................................................................................................................50 4.3.4 Documentation of Change of Scope ......................................................................................................51 4.4 Quality Management .................................................................................................................................52 4.4.1 Overview ................................................................................................................................................52 4.4.2 Work Package Identification ..................................................................................................................54 4.4.3 Work Package Inputs, Process and Outputs ..........................................................................................55 4.4.4 Determining Possible Defects ................................................................................................................56 4.4.5 Prevention of Defects ............................................................................................................................56 4.4.6 Indentification of Defects ......................................................................................................................58 5 Project Cost Estimate ..........................................................................................................................................61 5.1 Project Cost ................................................................................................................................................61 5.1.1 Total Project Cost ...................................................................................................................................61 3|Page Keller School of Management- Capstone PM600
  • 4. 5.1.2 Breakdown of Project Costs ...................................................................................................................62 5.1.3 Progress Payments.................................................................................................................................63 5.1.4 Monthly Payment Distribution ..............................................................................................................64 5.1.5 Earned Value Control ............................................................................................................................65 5.1.6 Control Performance Index (CPI) & Schedule Performance Index (SPI) ................................................66 5.1.7 Estimate at Completion (EAC) and Variance at Completion (VAC) ........................................................67 5.2 Customer-Provide Resources .....................................................................................................................68 5.3 Terms and Conditions ................................................................................................................................69 6 Unexpected Event ...............................................................................................................................................73 6.1 Problem ......................................................................................................................................................73 6.1.1 General Description ...............................................................................................................................73 6.1.2 Current Status ........................................................................................................................................74 6.2 Alternative Solutions ..................................................................................................................................79 6.2.1 Overview ................................................................................................................................................79 6.2.2 Continuing Contract ...............................................................................................................................79 6.2.3 Contract Modification ............................................................................................................................79 6.2.4 Pursuing another OEM...........................................................................................................................80 6.3 Proposed Action .........................................................................................................................................80 7 Scope Expansion .................................................................................................................................................83 7.1 Project Description .....................................................................................................................................83 7.2 Initial Planning............................................................................................................................................85 7.3 Scope ..........................................................................................................................................................87 7.4 Schedule .....................................................................................................................................................89 7.5 Budget ........................................................................................................................................................91 7.5.1 Schedule of Rates - Labor ......................................................................................................................91 7.5.2 Equipment and Materials ......................................................................................................................92 7.5.3 General Administration, Contingency, Others .......................................................................................92 7.5.4 Summary of Total Cost ...........................................................................................................................93 7.5.5 WBS/ Cost Breakdown ...........................................................................................................................95 8 Appendixes .........................................................................................................................................................98 8.1 Appendix A – Risk Assessment Matrix .......................................................................................................98 8.2 Appendix B – Schedule of Rates ...............................................................................................................100 8.3 Appendix C – Weekly Payments Progress ................................................................................................102 8.4 Appendix D – Value Stream Maps ............................................................................................................103 8.5 Appendix E – Change Request Form ........................................................................................................105 8.6 Appendix F – Baseline Schedule ...............................................................................................................106 4|Page Keller School of Management- Capstone PM600
  • 5. 8.7 Appendix G – Earned Value Analysis Week 14 .........................................................................................107 8.8 Appendix H – Contract Close Out Checklist .............................................................................................108 8.9 Appendix I ................................................................................................................................................112 9 Tables ................................................................................................................................................................115 10 Figures ..............................................................................................................................................................116 11 Works Cited .......................................................................................................................................................117 5|Page Keller School of Management- Capstone PM600
  • 6. 1 Executive Summary 1.1 Project Baseline Automated Parts Inc, (API) a coil spring, wire forming, subassembly automotive parts company is facing a lost in market share due to its inability to increase its production rate of manufactured parts while keeping competitive prices to customers. The company is currently stable with its current production but would like to increase market share with the coil spring and wire forms and increase production of value added parts. The value added parts will provide for a bigger profit margin. In order to meet these needs, API, Inc. as engaged its project management department to automate the coil spring, wire forming and welding equipment production lines. The automation of the production of parts and subassembly lines require the acquisition of new equipment, redesign of the production area, training of existing personnel, and in some cases the job placement of existing personnel in other organizations. The project management department has developed the team, planned the project, prepared the risk assessment and engaged engineering, procurement, finance and manufacturing to implement the plan. API as provided $2.5 million dollars for the entire plan which includes risk management and contingency plans and all cost associated with the project. The project is scheduled for a 43 week duration, starting on May 5th 2010. The Project is divided in four different phases: Table 1.1 Project Phases Phase Completion date rd 1. Project Planning Phase June 3 , 2010 . 2.Manufacturing Design Phase- Execution t September 7 , 2010 st 3.Procurement Phase-Execution December 21 , 2010 nd 4.Production/Validation Phase –Completion Marc 2 , 2011 The project is defined in terms of quality that will increase production as well as make the production process more efficient in time, cost and the percentage of accurate first time production of parts. A team of 18 new skilled operators will be trained to operate the new equipment, while current labor consisting of 42 workers needs to be reassigned for future labor needs and placement. Figure No.1 describes the time, cost and accuracy rates the organization estimates it can achieve with the implementation of this project. 6|Page Keller School of Management- Capstone PM600
  • 7. Figure 1.1: Process Performance Metrics (Ross & Rodriguez, 2010) Current Process Future Process Variable Measure Variable Measure Lead Production Time 428 Minutes Lead Production Time <200 Minutes 1 Value Added Time 246 Minutes Value Added Time >150 Minutes Non-Value Added Time 48 Minutes Non-Value Added Time 0-10 Minutes Inventory Time ( waiting Time) <50 Minutes Inventory Time ( waiting Time) 134 Minutes Takt Time (seconds/part) <20 seconds/part Takt Time (seconds/part) 28.8 seconds/part First Time Quality : 58% First Time Quality : 90% Change-Over time: 60 Minutes Change-Over time: <30 Minutes  Lead time: the time needed to complete an activity from start to finis  Value Added Time: Activities that contributes to the production of final Product, transforms material and information  Non-Value Added time: waste time, activities that does not add value to the final product. Activities creating no value but which cannot be eliminated based on current state of technology or thinking  Inventory Time: waiting time to be process material, batch delays, and process delays.  Takt Time : total time available for work time per day divided by customer-demand per day – sets the pace of production to match rate of demand Source: The Lean Memory Jogger, Richard L. Macinnes. The new process will require automated equipment for the Wire Gauge Checking, Wire Forming and Robotic Welding for an investment of $1,700,000. Turnkey installation service and specialized training will be provided to our team of engineers and production operators by the selected Vendor. The Automation of Spring and Wire Form assembly line will bring numerous benefits to API including improvement in precision manufacturing of parts, flexible manufacturing, better quality control systems, empowered employees, improvement in ergonomics and safety in the operations, increase of production capacity, and reduction of Takt time and reduction of production cost by a range of 20%. Finally the automation of the coil spring/wire form production line will set the grounds for Lean Manufacturing and Just in Time Inventory as future corporate projects. It also will set the ground for new product development and more specialty sub-assembly products. 1 Value added operations are for example those operations which require some welding or subassembly 7|Page Keller School of Management- Capstone PM600
  • 8. The success of the project is paramount to API, therefore risk management and contingency plans are in place to overcome every possible foreseeable problem. 1.2 Project Variance One problem that occurred during the working plan of the project was the vendor of the coil springs and wire forms equipment became financially unstable and was threatening bankruptcy. Since project management anticipated a possible financial concern during vendor selection, the next highest scored vendor’s proposal specifications and the first phase of contract negotiations had been conducted in case the first vendor was unable to fulfill the negotiated contract. Project management defined the risk scenarios and contingency plan to overcome the risk. The risk contingency plans that were developed due to the vendor’s financial dilemmas included the following: 1. Stay with the vendor and receive the equipment without service or maintenance. 2. Wait for Vendor to be taken over by another company and renegotiate the contract. 3. Go with another OEM and continue with the project. Section 6 of this plan will describe all of the impacts of choosing one of the above scenarios. In order to maintain the integrity of the project in terms of time and cost the decision to pick another OEM was employed. In this scenario, the President of API, Owen French could stay with his initial goal of gaining more of the market share. 1.3 Project Expansion To achieve increased market share as quickly as possible, an expansion of the automation project was presented to project management which included new product development, as well as, acquiring consignment parts of subassemblies. Marketing research determined coil springs for military tanks, wire forms for NASA aerospace and subassemblies for the department of defense were new products developments the company would pursue. These new product developments will be launched in three separate timeframes during the project to ensure maximum efficiency and quality. Section 7.0 of this plan describes the expansion to the automation project. Table 1.2: Product Development Program Project Completion date th 1. Wire Forms Aerospace June 8 , 2011 . 2.Coil for Tanks Defense st August 1 , 2011 th 3.Subassemblies Defense January 16 , 2012 8|Page Keller School of Management- Capstone PM600
  • 9. 2 Technical Proposal 2.1 Project Purpose 2.1.1 Background Automotive Parts Inc. (API) is a small manufacturer of coil springs and wire forms. API’s customers include suppliers of mechanical and electrical subassemblies to automobile, truck, over-the-road vehicle OEMs (Original Equipment Manufacturer) and the OEMs themselves. These types of customers include such clients as Dana, Arvin Meritor, Ford, GM and Toyota. API is providing coil springs, wire forms and subassemblies that include welded parts for these important clients. In order to provide better service to its clients, API also offers unique prototypes and fast turnaround of its coil springs and wire forms. The manufacturing process to produce the photo types, coil spring and wire forms require several steps. The manufacturing processes involved in producing springs and flexible wire forms are wire gauge checking, wire forming, and welding. Wire gage checking is a complex process which also includes inspections for imperfections in the wire. Other operations in the manufacturing process include the value added operations. Value added operations are those operations which require some welding or subassembly. For example, the ends of a formed-wire piece may be welded to a small metal base plate for screw-mounting within a vehicle, or for applying a spring’s force over a larger area to hold another part in place. Value-added operations represent bigger margin work than wire form and coil springs. Therefore the Company’s goal is to increase business in the value added operations area. 2.1.2 The Need The Company needs to get its cost in-line to stay competitive. Currently API is losing market share because of its inability to meet the prices of its major competitors. The aim is to automate the current manufacturing process of Wire Gauge checking, Wire formers and Welding. By automating these processes, API can produce parts much quicker as well as increase its capacity. The Company is prepared to spend $2.5 million for the automation project of its production lines. To achieve its goals, the company will buy automated equipment for Electronic Wire Gauge Checkers, Automated Wire Formers and Robotic Welders. In addition to the automated resources, there will be labor resources including 2 operators for the wire gauge checking operations, 10 operators for the wire forming operation and 4 operators for the robotic welding operation. 9|Page Keller School of Management- Capstone PM600
  • 10. 2.1.3 Objectives and Goals The objectives of the Automation of the Coil/Springs production Line is to deliver better quality parts, with an updated production process that will make Automotive Parts, Inc more competitive in the market and increase its market share, while reducing production cost. Table 2.1: Goals & Objectives (Ross & Rodriguez, 2010) Goals Objectives Method Measures of Success Invest in new Have top notch Production Update Process Electronic Wire Gauge The Process in full operation with Facility for Springs and Wire with Automated Checkers, Automated 100% Installation and Start-up for Forms Equipment Wire Formers and Production ready in 10 months Robotic Welders Study Current Process Become a Cost oriented Reduce Check for Inefficiencies operation that contributes Reduce Production Cost by 20% Production Cost and Cost Reduction to the profit margin Opportunities Decrease Takt Time Increase Peak Capacity Produce the best Quality Increase Quality (time to process a part) from 28.8 as a strategic Products with high First Increase sec/piece to less than 20 advantage. Time Quality Production seconds/piece Trim down the Quality ( FTQ) Capacity Raise First Time Quality (FTQ) Inspection Process from 58% to bigger tan 90%. Release work force Have the most qualified, from Mechanical Provide New Increase the welding and value motivated and committed Operations to include Value Added added production throughput teams adding more value to more value added Operations between 25% an 50%. the Operation operations – Ready to Assemble Parts 2.2 Project Benefits 2.2.1 Stakeholders Figure 2.1 lists the most important stakeholders; we have divided them into external and internal suppliers or customers. Figure 2.1: Stakeholders (Ross & Rodriguez, 2010) External Suppliers External Customers Wire Supplier OEM’ Suppliers Metal Parts Suppliers OEM’s Other Parts in Consignment Process Manufacturing Eng. Product Eng. Quality / Production Internal Customers Internal Suppliers Operations Department Human Resource Department Finance Department Purchasing Department Sales and Marketing Department 10 | P a g e Keller School of Management- Capstone PM600
  • 11. 2.2.2 Benefits The project benefits are classified in the five categories of the Global Manufacturing System (GMS): People, Quality, Response Capacity, Cost and Environment Figure 2.2: Benefits (Ross & Rodriguez, 2010) Response People Quality Cost Environment Capacity 1. Cleaner/Safer working 1. Increase environment, less 1. Savings in the cost lubricants, grease, Professional 1. Increase Development of the of production by production debris. Production Volume 2. Use less energy labor force 1. Improve FTQ for Capacity 20% production process and fluids in 2. Elevate the 2.Increase product 2. Opportunity production technical level of the 2. Increase Portfolio Cost to product 3. Less noise and labor force productivity and 3. Add value added more value added distraction in the efficiency of the components, and parts production process 3. Add better paying 3. Motivate Wokers production line assemblies 4. Reduction of jobs for Cost Reduction 4. Add Flexible Mfg. Incidents and 4. Increase Production Ideas Accidents Empowerment 5. Improve Ergonomic and Working Environment Conditions HOW The new Equipment The new assembly will increase line will require productivity and sophisticated , state production capacity. of the art automated The new automated The new equipment equipment, with equipment will will allow release of Include automated Implement a Lean better control, contribute to a equipment in the and Clean flow of the labor force to technical skills and more stable and add new added wire gauge checking, materials. Introduce management precise production value processes, wire forming and the automated decision. The labor process giving better welding production equipment to increasing the force will be quality of parts at a product portfolio. stations to decrease reduce mechanical involved in this and faster production Develop a Flexible production takt time operations. future cost rate. Operations design to reduction initiative produce for a variety with bonus pays per of parts and suggestion ideas. volumes. 11 | P a g e Keller School of Management- Capstone PM600
  • 12. 2.3 Statement of work 2.3.1 Project Summary Table 2.2: Project Description Client/Vendor name Production Department Client/Vendor’s administrator PMO Automation of Spring/Wire Form Project name Production Line Engagement duration 43 Weeks th Begin date May 5 , 2010 nd End date March 2 , 2011 2.3.2 Scope The project will design, develop and implement the automation of the Springs and Wire Forms assembly line within a $2.5million budget in a 43 week period. The Project will include facility design, equipment and process design, procurement of new equipment, installation of equipment, accommodations of assembly line space, training and manufacturing validation of the new production assembly line. More details on the scope development will be explained on section 4.3. 2.3.3 Phases and Milestones Table 2.3: Phases and Milestones (Ross & Rodriguez, 2010) Pase Completion date Pase rd Project Planning Phase June 3 , 2010 rd Program Initiation June 3 , 2010 th Manufacturing Design Phase- Execution September 7 , 2010 th Layout Design June 30 , 2010 th Equipment Design July 14 , 2010 nd Engineering Data Release August 2 , 2010 st Procurement Phase-Execution December 21 , 2010 st Purchase Orders September 1 , 2010 st Equipment Development and Shipping December 21 , 2010 nd Production/Validation Phase –Completion March 2 , 2011 st Installation of Equipment January 26 , 2011 nd Validation of Equipment March 2 , 2011 12 | P a g e Keller School of Management- Capstone PM600
  • 13. 2.3.4 Schedule of Rates - Labor Additional overtime hours are required for professional staff to account for action plan in procurement, engineering and installation of new equipment from Vendor B. See section 6 for more details. (Detailed information on each labor resource is provided in Appendix B). Table 2.4: Schedule of Rates (Ross & Rodriguez, 2010) Item description Quantity Avg. Delivery Cost Cost Rate/hour schedule Baseline Baseline (Man - ours) Modified 2 Professional Staff 18 $29.14 7,417 $199,706 $216,141 (Engineers, Managers, Supervisors) Operations Staff 16 $16.50 4,800 $79,233 $79,233 (Line Operators) Current Operations Staff 42 $15.42 12,600 $194,319 $194,319 ( Line Operators, Inspectors) Totals $473,258.58 $489,693.24 2.3.5 Equipment and Materials A 5% increase on price for new equipment: Wire Gauge Checkers and Wire Forming CNC, is to be added to the modified Baseline once the negotiations are revised with Vendor B. See section 6 for more details. (Detailed information on Equipment and Materials is provided in Appendix B). Table 2.5: Equipment Rates (Ross & Rodriguez, 2010) 3 Cost Cost Item description Quantity Rate/unit Baseline Baseline Modified Computer 5 $2,000.00 $10,000.00 $10,000.00 Terminal Wire Gauge 2 $ 150,000.00 $300,000.00 $315,000.00 Checkers Wire Forming CNC 5 $ 210,000.00 $1,050,000.00 $1,102,500.00 Robotic Welders 2 $ 205,000.00 $410,000.00 $410,000.00 Totals $1,770,000 $1,837,500 2 Delivery Schedule for Baseline was 6,290 hours not including additional hours for unexpected event (section 6) 3 Rates/Units for modified baseline increased 5% for Wire Gauge Checkers ($157,500) and Wire Formers ($220,500) 13 | P a g e Keller School of Management- Capstone PM600
  • 14. 2.3.6 General Administration, Contingency, Others Additional cost for trips, General Administration/Overhead are included as part of this project only. Table 2.6: Other Costs (Ross & Rodriguez, 2010) Item Description Cost Cost Baseline Baseline Modified General Administration $109,123 109,123 Trips $10,000 $10,000 Contingency $215,127 $131,191 Totals $334,250 $250,314 2.3.7 Summary of Total Cost The total cost (modified) did not changed. All action plans cost to activate new Vendor B will be absorbed by the Contingency Budget, hence reducing this contingency figure to $131,192.00 .(Detailed information on cost on Section 4) Figure 2.3:Cost Distribution Chart (Ross & Rodriguez, 2010) Table 2.7 : Summary Cost Structure (Ross & Rodriguez, 2010) 14 | P a g e Keller School of Management- Capstone PM600
  • 15. 2.3.8 Payment terms No including contingency. Project Manager’s professional fees are prorated on the overall project. (Detailed information on Payments is provided in Appendix C) Table 2.8: Payment Schedule (Ross & Rodriguez, 2010) Pase Completion date Payments due Payments due Baseline Baseline Modified rd Project Planning Phase June 3 , 2010 $1,320 $1,320 th Manufacturing Design Phase- Execution September 7 , 2010 $48,845 $48,845 Procurement Phase-Execution December 21, 2010 $1,353,065 $1,419,573 nd Operations/Validation Phase –Completion Marc 2 , 2011 $781,228 $798,655 15 | P a g e Keller School of Management- Capstone PM600
  • 16. 2.3.9 Statement of work – Assumptions Table 2.9: Assumptions (Ross & Rodriguez, 2010) Product Operations/ Quality uman Resources IT Management- Engineering Production/Supply Presidency/Finance Small to Mid-Size Springs Intension to Keep New Current First Higher Tecnical Current ERP Top Management and Wire Forms Products Production Rate, Time Quality is Labor Force will System in place Endorsement Desire to increase 58% be demanded for Material and Production Capacity Cost control Material Sapes & Current Operations 3 There are two This is a Non- DesignCAD/CAM VSM Worksop Results Specifications: .004 inches Shifts – 8 hours. The Six Sigma Belts Union Facility systems in Place. for improvement and to 2.0 inches in two lines will produce Simulation opportunities diameter,round wire simultaneously during Production ,square wire , rectangular validation Systems in Place wire, special section wire Body Types open-coiled , Lead Average Time to Will follow the Future New Computer, The Project will Follow helical shaped usually coiled Produce One Part is 8 Quality Valve Placement of CNC systems will the Global with a constant diameter, hours Review – Stage Employees will need to be Development Plan of though they can be Gate Plan be required. installed and the Company produced in hourglass, cone HR Plan is callibrated. Added and barrel shapes required. Less to the TPM plan labor force will be required Materials spring steel ,high Current Production Quality Must keep some New Equipment Payments Plan for carbon steel, low carbon Average is 3000 Parts Inspection of part of the labor will be syncronize Equipment steel , nickel plated carbon per day Production in force for value with Andon 25% @Deposit steel, stainless alloys, non- place added Production 25% @ Reception ferrous metals: elgiloy, operations System 25% @ Validation astelloy, monel, inconel, 25% @Installation Titanium Presence of testing Lab with No Space Layout Will work along Must identify Materials an Durability Constraints with Product high and low Equipment Engineering for performers Product Validation on new production Equipment Equipmet Cost already higher paying includes Insurance rates will come and Freigt Cost after new equipment installation for Operators Turnkey ( in-service) installation by supplier through validation of production New Automated and Development Equipment will be declared and covered by FloorShop Insurance Equipment Policy 16 | P a g e Keller School of Management- Capstone PM600
  • 17. 2.3.10 Change Management Process The change management process will follow three internal procedures: 1. Engineering/Process Change Notifications, release per engineering system 2. Freeze Design Dates – Red Zone will be in the project Schedule to submit changes to the Project Council during the Red Zone Stage 3. Scope Change – Any change in scope will be submitted to the PMO office and presented to the Project Council for approval For more detailed Change Management process refer to section 4.4 2.3.11 Engagement Related Expenses General Administration Expenses All payments and disbursement of money will be done through our Finance Department. All checks and bank transferred will need to be authorized and audited by our Finance department which will be the only entity authorized to release the funds. All Administration expenses will be accounted for in the Project Budget and will be released accordingly. Other departments may enter their cost, materials, resource request on our ERP (Enterprise Resource Planning) system for financial calculations and Finance approval and release. Payroll Payments of Payroll will be generated by the human Resource Department depending on the numbers of hours reported on the project. Finance will authorize and release payments for payroll purposes. Materials Material and Equipment payments will be generated by the Purchasing Department into the ERP system, and submitted for approval to Finance Department, which will be authorizing and releasing funds according to terms of payments agreed between Supplier and the Company. Any payment contract arrangements needs to be prepared and reviewed by the Purchasing Department and presented to the Finance Department for planning and provision purposes. 17 | P a g e Keller School of Management- Capstone PM600
  • 18. 2.3.12 Acceptance and authorization The terms and conditions of the Professional Services Agreement apply in full to the services and products provided under this Statement of Work. IN WITNESS WEREOF, the parties here to each acting with proper authority will authorize the execution of this Statement of Work. Full name Full name CEO – Automotive Parts, Inc Project Manager - PMO Title Title Signature Signature Date Date 18 | P a g e Keller School of Management- Capstone PM600
  • 19. 2.4 Project Plan 2.4.1 Technical Description of New System API conducted a Value Stream Mapping workshop to identify the opportunities for improvement and to streamline the production of springs and wire forms. Current Process A SIPOC (Supplier, Inputs, Process, Output and Customer) depicts the current process and flow of materials and information. A more detailed Value Stream Map of the current System is shown on Appendix D. The Value Stream Map shows clearly where the inventory (waste) time is, and finds where the Wiring Gauging, Wire Forming and Welding stations become bottlenecks in the production process. Figure 2.4: SIPOC Current Process (Ross & Rodriguez, 2010) 19 | P a g e Keller School of Management- Capstone PM600
  • 20. 2.4.2 Facility Design and Simulation In order to avoid future errors and rework, we will be using AutoCAD and other Simulation Tools to design the new shop floor and simulate the production flow with the new equipment in place. Both the old and the new assembly line will run simultaneously for the period of the Manufacturing Validation Build of the new assembly Line. After production is validated the old equipment needs to be sold or scrapped within six month of project completion (this activity is considered out of the scope of the project) 2.4.3 Future Process The high Inventory time (waste) before wire inspection, wire forming and welding stations is creating bottlenecks, increasing the lead time of the production process. These three stations will be automated in order to increase throughput and production flow. To reduce the Lead Production Time and specially the Inventory Time and Changeover Time, the future process will incorporate three major automated equipments, which include CNC (Computer Numerical Control). These equipments will help release the inventory bottlenecks in the Gauge Checking, Wire Forming and Welding, making a more productive and efficient production flow. 2Electronic Wire Gauge Checkers 5Automated Wire Formers 2Robotic Welders Current and Future Value Stream Maps are shown in Appendix D. Figure 2.5 summarizes the main metrics from Current and Future Process. Current Process Future Process Variable Measure Variable Measure Lead Production Time 428 Minutes Lead Production Time <200 Minutes Value Added Time 246 Minutes Value Added Time >150 Minutes Non-Value Added Time 48 Minutes Non-Value Added Time 0-10 Minutes Inventory Time ( waiting Time) 134 Minutes Inventory Time ( waiting Time) <50 Minutes Takt Time (seconds/part) 28.8 seconds/part Takt Time (seconds/part) <20 seconds/part First Time Quality : 58% First Time Quality : 90% Change-Over time: 60 Minutes Change-Over time: <30 Minutes Figure 2.5: Process Performance Metrics (Ross & Rodriguez, 2010) Figure 5: Process Metrics 20 | P a g e Keller School of Management- Capstone PM600
  • 21. 2.4.4 Detailed Project Schedule - Modified Figure 2.6 shows the progress of schedule when 26% of the worked has been completed. The Black Bar shows the Baseline Schedule; The Blue Bar shows Baseline Modified Schedule ; The Red Bar shows the Critical Path for the Baseline Modified Schedule Figure 2.6: Baseline Modified Schedule (Ross & Rodriguez, 2010) 21 | P a g e Keller School of Management- Capstone PM600
  • 22. 2.4.5 Specific Challenges Specific challenges in the following areas of: Supply, Communication, Operations, Systems, People, Legal and Quality were all identified in our Risk Assessment, and included in our Risk Assessment Matrix, with Contingency plans. 2.4.6 Risk Management Matrix The Project Team will follow recommendations according to the detailed Risk Management Matrix considering the major and top risks on the projects and contingency action plans. Top Risks considered while developing the project schedule are shown in Table 2.10. The Baseline Modified Risk Assessment includes the new risk and contingency for Supplier Selection, and the current contingency plan that is currently in progress. Figure 2.7 summarizes the Risk Assessment considerations. Section 2.4.7 addresses action plans for Shipping and Hiring/Placement risks. Top major risks considered during project planning phase. Baseline Risk Matrix per activity attached on Appendix A. Table 2.10: Risk Matrix (Modified) (Ross & Rodriguez, 2010) Risk Severity Activity Risk Type4 Prob. 1=Low Rank Contingency # 5=High 1 Shipping of Equipment Delays in Shipping for Avoid winter season by pulling Winter Season ahead project with overtime in SUP 85% 5 4.25 the Design Phase 2 Supplier Selection Late Change of Ensure suppliers are ranked Suppliers, limited among top Suppliers in the Suppliers SUP 75% 5 3.75 Industry. Have a Backup Supplier Plan Ready in Case selected Supplier fails to comply 3 Hiring/Placement Labor Conflicts for Avoid Labor Conflicts and new Entrants due to Stoppage by preparing an HR Potential Layoffs - R 65% 5 3.25 Placement Plan Ahead and Strike Presenting to Production Management 4 Displacement of Old Damage of production Avoid Damages by Equipment Equipment Using Experts in Transportation, OPE 65% 5 3.25 Include Equipment in Insurance Coverage before acquisition 5 Design Changes Late Design Changes Use ECN and Change Engineering Management Process for Engineering Change ENG 75% 4 3.00 Communication. Implement Red Zone and Freeze Date for Engineering Changes 4 SUP=Supply, HR=Human Resource, OPE=Operations, ENG=Engineering, QUA=Quality 22 | P a g e Keller School of Management- Capstone PM600
  • 23. Risk Severity Activity Risk Type Prob. 1=Low Rank Contingency # 5=High 6 Install/Calibration of Delays on installation Invite Supplier to Installation. Equipment due to complexity OPE 55% 5 2.75 Turnkey In Service Installation 7 Construction Safety Regulations not Revision of legal, permits and Requirements in Compliance ENG 50% 5 2.5 safety by Safety Committee 8 Engineering Testing Parts fails to Product Prepare Six Sigma Teams for Engineering/Quality QUA 50% 5 2.5 Action Plans Validation Compliance 9 Negotiations Set Target Price, Benchmark and Negotiations exceed SUP 75% 3 2.25 3 Quotation Process Budget 10 Equip. Fabrication Delays of fabrication Select Expert Suppliers and Visit due to complex of Manufacturing Engineering customization Development, include overtime SUP 55% 4 2.2 to pull ahead development dates. Have Two Alternatives Suppliers ready for contracts 11 Production Validation Worker’s absence due Prepare a list of Floater Pool to winter and lack of OPE 50% 4 2 workers as part of the HR Plan motivation Figure 2.7: Risk Summary Chart - Modified (Ross & Rodriguez, 2010) Risk Assessment Summary 5 5 5 5 5 5 5 4.25 4.25 4 4 4 3.25 3.25 3 3 2.75 2.5 2.5 2.25 2.2 2 85% 75% 75% 75% 65% 65% 55% 50% 50% 55% 50% Prob Rank Severity 23 | P a g e Keller School of Management- Capstone PM600
  • 24. 2.4.7 Top Risk Recommended Action Plans 1. Shipping/Weather Risk Table 2.11: Weather/Shipping Action Plan (Ross & Rodriguez, 2010) CURRENT ALTERNATIVE Shipping of new equipment will be planned from Plan for overtime work during the Design and Purchasing November 2010 through February 2011, which is in the Activities will mitigate Shipping Risk, pulling ahead Project middle of winter Season, delaying the installation and Schedule almost 1 Month ahead and reducing total cost training of the project due to MVB1 and MVB2 synchronization COSTS (Only Project ) Project Cost – Expected Project Cost – Expected $2,232,654 $2,184,458 w/o Overtime with Overtime Project Cost – Pessimistic Project Cost – Pessimistic- 2,557,217 with Overtime + Winter Storm $2,389,912 w/o Overtime + Winter Storm Contingency Cost- Risk $324,563 Contingency Cost - Risk $205,454 Extra Overtime Cost – 342 ours $11,970 BENEFITS Delays and bigger Inbound Cost Better Working Shipping Schedule higher Shipping Fees Lower Shipping Fees Installation and Training over Christmas Avoid Christmas holidays work overlapping Expected Finish Project in March 28, 2011 Expected Finish Project in Marc 3,2011 Late Finish Risk August 10, 2011 Late Finish Risk April 26, 2011 Labor Overtime Plan to Mitigate Shipping Risk Table 2.12: Overtime Proposal (Ross & Rodriguez, 2010) Tasks Resource Overtime Rate Total hrs Labor Layout Design Facility Engineer 80 35 $2800 Equipment Design Process Engineer 54 35 $1890 Equipment Design Systems Engineer 20 35 $700 Equipment Design Material Engineer 27 35 $945 Procurement Buyer 81 35 $2835 Equipment Development Manufacturing Engineer 40 35 $1400 Equipment Development Supplier 40 35 $1400 Total 342 $11,970 24 | P a g e Keller School of Management- Capstone PM600
  • 25. 2. Hiring/Placement Risk Table 2.13: Labor Conflicts Action Plan (Ross & Rodriguez, 2010) CURRENT ALTERNATIVE Total: 42 Workers Total : 16 Workers 8 Wire Gauge Checkers 2 Gauge Operators 3 Gauge Inspectors 5 Wire Forming Operators Shift 1 10 Wire Forming Operators Shift 1 5 Wire Forming Operators Shift 2 8 Wire Forming Operators Shift 2 2 Welders Operators Shift 1 4 Wire Forming Operators Shift 3 2 Welders Operators Shift 2 5 Welders Shift 1 + 3 Welders Shift 2 HR Distribution of 26 Workers: 1 Welders Shift 3 46% - 12 Workers Placement with Suppliers and OEM’s 15% - 4 Floaters 27% - 7 Workers Trained for Value Added Operations 12% - 3 Workers Low Performers COSTS Cost/Mont $103,636 Cost/Mont $42,257 Probability of Work Probability of Work %65 <%20 Stoppage Stoppage BENEFITS Mechanical Labor Automated and Controlled Labor High Risk to incidents and accidents, Reduce the incidents and accidents, Safety and Health issues Increase ergonomics Higher Fixed Cost Lower Fixed cost Technical Skills Development Professional Technical Development High Takt time, low Productivity Low Takt time, higher Productivity Professional Career Stagnation Career Growth Opportunities in Top Companies High gaps to negotiate placement of labor force Close gap to negotiate placement of labor force Human Resource Action Plan to Mitigate Risk Table 2.14: Replacement Proposal (Ross & Rodriguez, 2010)  Identify job opportunities with higher paying salaries for those employees that will be released from their duties. Placement  Employees should not be laid off until an acceptable position in a OEM’s or Supplier has been arranged and contracted  Identify those employees who will remain in the organization as on-call in the organization. Floater  These group of employees can rotate in different positions as required, and can rd be prepare for future 3 shift or production increments  Identified High Performer Workers to remain in the organization and trained for Trainees value added operations.  Workers who will need to be laid off due to their low performance Low Performers 25 | P a g e Keller School of Management- Capstone PM600
  • 26. 3. Automated Equipment The Project intends to install state of the art new equipment for the facility. However, this new equipment is sophisticated and should be calibrated by experts. There is a risk to delay the installation, setup and validation of equipment, assuming proper training and assistance is not in place. It is recommended to close a Turnkey in Service installation from Equipment Supplier. This means the supplier will accompany the team of engineers during the installation, training, setup and validation of production. With this action it is intended to mitigate the uncertainty of setup, functioning and operation of new equipment, while training the group of engineers for future control, operation and maintenance of new equipment. The New Equipment will have period of guarantee of 90 days and will require maintenance assistance from the Vendor periodically. A new Contingency Plan for OEM Supplier Change is explained on section 6.0 26 | P a g e Keller School of Management- Capstone PM600
  • 27. 2.5 Project Completion Plan 2.5.1 Deliverables 27 | P a g e Keller School of Management- Capstone PM600 Figure 2.8: Project Completion/Deliverables (Ross & Rodriguez, 2010)
  • 28. 2.5.2 Acceptance Test The Project will follow the Program Quality and Readiness Review (PQRR) as a Stage Gate Model. Different Review Valves will allow for checking of metrics, deliverables and buying off before proceeding to the next Stage of the Project. There are nine (9) Review Valves as follow: Table 2.15: Stage Gate Reviews (Ross & Rodriguez, 2010) Gate Name Initials Objectives 1. Preliminary Plan Review PP Test Preliminary Project Information 2. Program Initiation Review PI Test Project Plan, Team Structure and Initiation 3. Manufacturing Engineering MP Test Engineering Design and R Planning Review 4. Verify Data Release Review VDR Validate Engineering Documentation for Procurement 5. Contract Sign-Off CSO Validated Procurement and Contract with External Suppliers 6. Production/ Operations POD Test readiness of Operations/ Production Review 7. Manufacturing Validation MVB Validation new equipment and parts out of new production line Build I I 8. Manufacturing Validation MVB Validation new equipment and parts out of new production line Build II II 9. Start of Regular Production SORP Final Approval and Sign-off to regular production, Cost validation Figure 2.9 represents the Acceptance Test to define when a PQRR Valve should be Approved, Revised or Stopped. Figure 2.9: Acceptance Test Chart (Motors, 2006) 28 | P a g e Keller School of Management- Capstone PM600
  • 29. 2.5.3 Acceptance Sign-off Cart Figure 2.10 shows a check list of items to be completed at each Review Valve Figure 2.10: Acceptance Criteria/Sign-0ff Chart (Ross & Rodriguez, 2010) 29 | P a g e Keller School of Management- Capstone PM600
  • 30. 3 Management Proposal 3.1 Corporate Organizational Structure API has a Matrix Organization structured based on Projects. The Project Team will report directly to the Project Manager for task related projects, also they will report to operations and functional managers from different departments. Figure 3.1: Corporate Organizational Chart (Ross & Rodriguez, 2010) President CEO Owen French Project Monitoring Director of Director of Supply and Director of Sales and Finance & Controlling Engineering Operations Procurement Human Marketing Director Director, Dick Ives Director Resources Director Product Manufacturing Quality Materials Production Purchasing Finance Engineering Engineering Manager Manager Manager HR Manager Sales/Marketing Manager Manager Manager Manager Manager Quality Materials Production Production Safety Finance Project Product Facility Supervisor Maintenance Buyer HR Engineer Engineer Supervisor Ergonomics Auditor Manager A Engineer Engineer Shift 1 Engineer Specialist Salesperson Shift 2 Supervisor Testing Industrial Production Production Marketing Engineer Engineer Workers Workers Specialist Product Engineer System Engineer Manufacturing Engineer 30 | P a g e Keller School of Management- Capstone PM600
  • 31. 3.1.1 Corporate Roles and Responsibilities The purpose of the Corporate Responsibility Matrix ( table 3.1) is to assign departments or individuals to activity categories, define role responsibilities, and define relationships between groups. This matrix should be completed before detailed resource allocating or scheduling. The goals of the roles and responsibilities matrix are to:  Define roles and responsibilities of project stakeholders.  Improve overall project team and stakeholder communication.  Proactively identify gaps in assignments, accountability, or resources.  Clarify cross-functional interactions between project team members.  Document project interdependencies with other enterprise initiatives.  Define project team interactions with supporting resources and departments. Table 3.1: Corporate Responsibility Matrix (Ross & Rodriguez, 2010) Project Activity (Spring Automation) Organization Title Project Requirements Design Test Training Communication Project Management: Monitoring & R C S A/R S Controlling Engineering A/R/C A/R/C R/C C S Finance S C Operations/ Production/ S S S S/C R Manufacturing Supply and A/C S C/S Procurement Human Resources C/S A/R KEY: A – Accountable for successful completion of task. R – Responsible for completion of task. (Task can be delegated to this person.) S – Supports task. C – Requirements communication about the task. 31 | P a g e Keller School of Management- Capstone PM600
  • 32. Table 3.2: Corporate Roles & Responsibilities (Ross & Rodriguez, 2010) Title Role Responsibilities Project Manager The Project Manager is responsible for  Project Plan developing, in conjunction with the Project  Manage and lead the project team. Sponsor, the project charter. The Project  Manage the coordination of the partners Manager ensures that the project is delivered and the working groups. on time, within budget, and to the required quality standards.  Develop and maintain a detailed project plan. Engineering The Engineering department’s role is to  Layout, Facility Design Perform as a manager or project systems  Construction Plan and Requirements engineer for a complex project (e.g. several  Regulations and Permits distinct subsystems or other defined services, capabilities, or products and their associated  Requirement and Specs. Development interfaces).  Process Assembly Instructions  Tools and Equipment Requirement Specs.  Standard Procedures Operation Sheets  Visual Aids  Simulation of Production  Testing  Total Productive Maintenance  Quality/Engineering Product Testing Plan  Engineering Review Valve Finance Once the organization as established goals  Audits of Financials and associated strategies (or ways to reach the goals), funds are set aside for the resources and labor to the accomplish goals and tasks. As the money is spent, statements are changed to reflect what was spent, how it was spent and what it obtained. Review of financial statements is one of the more common methods to monitor the progress of programs and plans. The most common financial statements include the balance sheet, income statement and cash flow statement. The major work of the  Installation Plan Project accomplished (i.e., design, Operations/  Simultaneous Production Plan development, construction, production, Production/ testing, system activation, etc.).  Manufacturing Validation Plan  Training 32 | P a g e Keller School of Management- Capstone PM600