SlideShare a Scribd company logo
1 of 24
MANUFACTURING PROCESS OF 660 MW
TURBO GENERTOR STATOR WINDING
BAR
ABHISHEK SINGH
12ERDME004
AT BHEL HARIDWAR
INTRODUCTION
In 1956 India took a major step towards the establishment of its
heavy engineering industry when BHEL, the first heavy electrical
Manufacturing unit of the country was set up at Bhopal.
BHEL's Heavy Electrical Equipment Plant (HEEP) was set up
in technical collaboration with USSR, for the manufacturing of
power plant equipment.
In 1976, BHEL entered into a collaboration agreement with
M/s Kraftwerk Union, AG of Germany for design,
manufacturing, erection and commissioning of large size
steam turbines.
More than 40 percent of the country's electrical energy is
generated from the power equipment supplied by BHEL,
Haridwar.
MANUFACTURING BLOCKS:
.
BLOCK I: ELECTRICAL MACHINE BLOCK, IS DESIGNED TO
MANUFACTURING OF TURBOGENERATORS
BLOCK II: FABRICATION BLOCK
BLOCK III: TURBINE BLADE BLOCK
BLOCK IV: COIL & INSULATION MANUFACTURING &
APPARATUS & CONTROL GEAR MANUFACTURING
BLOCK
BLOCK V: FEEDER BLOCK AND KNOWN AS FABRICATION
AND FORGE BLOCK
BLOCK VI: STAMPING AND DIES MANUFACTURING BLOCK
BLOCK VII: WOODWORKING BLOCK
BLOCK VIII: HEAT EXCHANGER BLOCK, IS DESIGNED TO
MANUFACTURE HEAT EXCHANGER UNIT FOR
STEAM TURBINES.
COIL & INSULATION MANUFACTURING
SHOP (BLOCK-IV)
Block-4 is designed to manufacture stator winding
bars of Turbo & Hydro generator and coil like DC
Armature coil ,main pole coil , equalizer coil etc.
There are three BAYS in this block each bay
manufactures stator bars and coils for different
machines
BAY-I: Bar winding shop: manufacturing of stator winding
bars of generator
BAY-II: Manufacturing of heavy duty generator stator bars
with New CNC M/c
BAY-III: Insulation detail shop: Manufacturing of hard
insulation & machining of hares insulation part (Glass Textolite)
such as packing, washer, insulation box, wedges etc
Bar Shop: This shop is meant for manufacturing of stator
winding coils of turbo-generator and hydro generator
Layout of CIM, Block-IV
It is quite difficult (rather impossible) to manufacture, handle
and wind in the stator slot of generator of higher generation
capacity because of its bigger size and heavy weight. That is
why we make coil in two parts. One part its bottom part of coil
called bottom or lower bar and other part of coil is called top
bar or upper bar.
Why do we call it bar?
Manufacturing Process
• For the manufacturing of stator bars insulated
copper conductors are brought from Bangalore,
it’s of two type’s i.e. solid copper conductor &
hollow copper conductors which are used in
water cooled stator layer glass insulation.
• solid bar for 600/660/700 MW
volume - 9.5X1.2
• Hollow copper for 600/660/700
Volume – 8.0x 4.6x1.3
Cutting
This process is done by automatic 3-444CNC machine. In
this process the pre insulated copper conductor is cut into
number of required length. Insulation is removed from both
ends of the conductor cut.
Transposition
Transposition means changing/shifting of position of
each conductor in active core (slot) part.
After cutting the required number of conductors, the
conductors are arranged on the comb in staggered
manner and then bends are given to the conductors with
the help of bending die at required distance.
Then the conductor are taken out from the comb & die
and placed with their ends in a line and transposition is
carried out.
Need of transposition.
1. To reduce eddy current losses.
2. Equalize the voltage generator.
3. To minimize skin effect of ac current
Cross Over Insulation
• The pre insulation of the copper conductor may get damaged
due to mechanical bending in die during transposition, hence
the insulating spacers are provided at the crossover portion
of the conductors. A filler material (insulating putty or
moulding micanite) is provided along the height of the bar to
maintain the rectangular shape and to cover the difference of
level of conductors.
Stack Pressing
• The core part of bar stack is pressed in under the pressure b/w
70kg to 80 kg and Temperature b/w 90 C to160 C for given
period. Four bar is pressed in one time and six to eight plate
are used for pressing .after that the consolidated stack is
withdraw from the press.
Inter Stand Short Test
The consolidated stack is tested for the short between any
two conductors in the bar, if found then it has to be
rectified.This is done to ensure that no local current is flowing
due to short circuit between conductors.(300 A/C supply)
Forming
• This process of forming is very important as in this process the
bars are bending from both the ends of the bar i.e. at exciter
side and turbine side at specific angles and shape as per
design. This process is done manually. First the former is set
according to the design making different angles at different
positions. The straight bar stack is formed as per overhang
profile (as per design), The overhang portion is consolidated
after forming.
. Pickling process
After the forming and cutting process of the bar and due to the
transportation of the bar, there accumulate very minute particles
of dust on the ends of the bar. These particles may cause at
the time of brazing and may create some air gaps. So, in order
to remove these unwanted particles, basically the oil particles
pickling process is performed.
Contact Sleeve Mounting
• After the pickling process is complete, contact
sleeve and water box bottom parts are mounted on
both the ends of the bar. it is a rectangular sleeve
which is used to make contact between upper and
lower bars . All the solid conductors are cut from
the ends of the bar after the contact sleeve except
the outer solid conductors. The water box is
mounted in two halves; first the water box bottom
part is mounted after the contact sleeve keeping
some distance between them.
• Brazing is basically the process of fixation of
both the contact sleeve and water box.
• Brazing is suitable for small parts , when high
joint strength is required.In brazing alloy is
mixed with water.
Brazing
• Nitrogen gas is the main constituent of the test. This test is
similar to puncture test that is inflated tube is dipped in water for
any leakage, the air bubbles gives us the exact position of the
puncture.
Nitrogen test
Thermal Shock Test
Thermal shock test is performed to check whether the bar can
withstand extreme conditions i.e. when the generator is
working or running at about 3000 Rpm. This is achieved by
thermal shock test. Thermal shock test consist of series of hot
water & cold water cycles alternatively. So firstly hot water at
temperature of about 90ºC is passed through the bar and then
cold water at about room temperature 27ºC approx. is flowed
inside the bar alternatively. This process is repeated again and
again.
Helium Leakage Test
• After thermal shock test bar is tested for any leakage with
help of Helium gas. Helium test is the most important test of
all, because helium test is performed to check any minute
leakage within the bar and at the brazed portion. because
helium is one of the lightest gases.
Reforming
• After all the previous processes which had undergone on the
bar. That the shape of the bar is deformed from its original
shape due to handling of the bar from one place to another for
different processes. So to keep the shape of the bar as per
design, the bar is checked if it is found distorted then it is
reformed in the previous former machine by placing the bar on
the former .
Insulation
• The stator bars are insulated with Micalastic (trade name)
insulation.
• Insulation is basically done to prevent any kind of short circuit
between the bar and the stator core when the bar is assembled
in the stator of the machine
Impregnation and Baking
• Micalastic System : In case of poor resin system the
insulated bars are heated under vacuum and the
impregnated (dipped) in heated resin so that all the air
gaps are filled, layer by layer, with resin.
• After impregnation the bars are pressed to bring them
back to the original dimensions.
HIGH VOLTAGE TEST
•When the bar is dried it is wrapped with aluminum sheet to make
outer surface of the bar conducting so that H.V. (High voltage
test) can be performed. After this tests the coating of red gel is
applied at both the ends of the bar.
•In this test the bar which is already wrapped with aluminum is
used.
•High voltage is applied to the bar using auto-transformer and it is
increased in steps according to the working voltage of the
generator. If the insulation is weak the bar will puncture at the
place of weaker insulation.
•If any of the bar fails this test i.e. bar is punctured at any point
then the bar is sent back for re-insulation and all the processes
are repeated again
Finishing
• The baked and dimensionally correct bars are
sanded-off to smoothen the edges and the
surface is calibrated, if required, for the
dimension.
Dispatched for winding
• The bars preserved with polythene sleeves to
protect from dust, dirt, oil, rain etc are send to Block-I
(Electric Machines Production Block - I, Turbo
Generators and Hydro Generators) for winding
Picture Of Bars
THANK YOU

More Related Content

What's hot

Power scenario in india
Power scenario in indiaPower scenario in india
Power scenario in indiaAnkur Mahajan
 
bhel report file on turbine shop & blade
 bhel report file on turbine shop & blade bhel report file on turbine shop & blade
bhel report file on turbine shop & bladeABHISHEK SINGH
 
BHEL INDUSTRIAL TRAINNING REPORT
BHEL INDUSTRIAL TRAINNING REPORTBHEL INDUSTRIAL TRAINNING REPORT
BHEL INDUSTRIAL TRAINNING REPORTSai Chandu Chandu
 
MANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATOR
MANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATORMANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATOR
MANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATORAnurag Verma
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipatpratikguptateddy
 
BHEL VOCATIONAL TRAINING REPORT
BHEL VOCATIONAL TRAINING REPORT BHEL VOCATIONAL TRAINING REPORT
BHEL VOCATIONAL TRAINING REPORT Eshver chandra
 
BHEL Vocational training report Haridwar
BHEL Vocational training report HaridwarBHEL Vocational training report Haridwar
BHEL Vocational training report HaridwarIshant Gautam.
 
kota super thermal Power station training report
kota super thermal Power station training reportkota super thermal Power station training report
kota super thermal Power station training reportEr. Aman Agrawal
 
Bhel haridwar vocational training report block 1
Bhel haridwar vocational training report block 1Bhel haridwar vocational training report block 1
Bhel haridwar vocational training report block 1khemraj298
 
A best ppt on kota super thermal power station
A best ppt on kota super thermal power stationA best ppt on kota super thermal power station
A best ppt on kota super thermal power stationNaveen Kumar
 
training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...Sagar Mehta
 
6 weeks summer Training report on thermal power plant in DCPP
6 weeks summer Training report on thermal power plant in DCPP6 weeks summer Training report on thermal power plant in DCPP
6 weeks summer Training report on thermal power plant in DCPPAmit Bansal
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Ajeet Chaurasia
 
Project report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGCProject report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGCGirish Gupta
 

What's hot (20)

Bhel training report
Bhel training reportBhel training report
Bhel training report
 
Bhel presentation
 Bhel presentation Bhel presentation
Bhel presentation
 
Power scenario in india
Power scenario in indiaPower scenario in india
Power scenario in india
 
bhel report file on turbine shop & blade
 bhel report file on turbine shop & blade bhel report file on turbine shop & blade
bhel report file on turbine shop & blade
 
BHEL INDUSTRIAL TRAINNING REPORT
BHEL INDUSTRIAL TRAINNING REPORTBHEL INDUSTRIAL TRAINNING REPORT
BHEL INDUSTRIAL TRAINNING REPORT
 
MANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATOR
MANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATORMANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATOR
MANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATOR
 
BHEL HARIDWAR
BHEL HARIDWARBHEL HARIDWAR
BHEL HARIDWAR
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
 
Summer traning report
Summer traning reportSummer traning report
Summer traning report
 
BHEL VOCATIONAL TRAINING REPORT
BHEL VOCATIONAL TRAINING REPORT BHEL VOCATIONAL TRAINING REPORT
BHEL VOCATIONAL TRAINING REPORT
 
BHEL Vocational training report Haridwar
BHEL Vocational training report HaridwarBHEL Vocational training report Haridwar
BHEL Vocational training report Haridwar
 
kota super thermal Power station training report
kota super thermal Power station training reportkota super thermal Power station training report
kota super thermal Power station training report
 
Bhel haridwar vocational training report block 1
Bhel haridwar vocational training report block 1Bhel haridwar vocational training report block 1
Bhel haridwar vocational training report block 1
 
A best ppt on kota super thermal power station
A best ppt on kota super thermal power stationA best ppt on kota super thermal power station
A best ppt on kota super thermal power station
 
training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...
 
6 weeks summer Training report on thermal power plant in DCPP
6 weeks summer Training report on thermal power plant in DCPP6 weeks summer Training report on thermal power plant in DCPP
6 weeks summer Training report on thermal power plant in DCPP
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
 
400 kv nelmangala
400 kv nelmangala400 kv nelmangala
400 kv nelmangala
 
BHEL Final Report
BHEL Final ReportBHEL Final Report
BHEL Final Report
 
Project report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGCProject report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGC
 

Viewers also liked

BHEL summer training report on ROLE OF CNC MACHINE IN MANUFACTURING OF 500/60...
BHEL summer training report on ROLE OF CNC MACHINE IN MANUFACTURING OF 500/60...BHEL summer training report on ROLE OF CNC MACHINE IN MANUFACTURING OF 500/60...
BHEL summer training report on ROLE OF CNC MACHINE IN MANUFACTURING OF 500/60...Nawneet Thakur
 
ELB044 Lecture 18. Introduction to Induction Machines
ELB044 Lecture 18. Introduction to Induction MachinesELB044 Lecture 18. Introduction to Induction Machines
ELB044 Lecture 18. Introduction to Induction MachinesFrancisco Gonzalez-Longatt
 
Manufacturing process of 500/600MW stator winding bar
Manufacturing process of 500/600MW stator winding barManufacturing process of 500/600MW stator winding bar
Manufacturing process of 500/600MW stator winding barAvinash Kumar
 
Mechanical Vibrations all slides
Mechanical Vibrations all slidesMechanical Vibrations all slides
Mechanical Vibrations all slidesEbrahim Hanash
 

Viewers also liked (10)

Design of wind generator
Design of wind generatorDesign of wind generator
Design of wind generator
 
Harshit agarwal
Harshit agarwalHarshit agarwal
Harshit agarwal
 
Seminar report
Seminar reportSeminar report
Seminar report
 
BHEL summer training report on ROLE OF CNC MACHINE IN MANUFACTURING OF 500/60...
BHEL summer training report on ROLE OF CNC MACHINE IN MANUFACTURING OF 500/60...BHEL summer training report on ROLE OF CNC MACHINE IN MANUFACTURING OF 500/60...
BHEL summer training report on ROLE OF CNC MACHINE IN MANUFACTURING OF 500/60...
 
Stator design
Stator designStator design
Stator design
 
ELB044 Lecture 18. Introduction to Induction Machines
ELB044 Lecture 18. Introduction to Induction MachinesELB044 Lecture 18. Introduction to Induction Machines
ELB044 Lecture 18. Introduction to Induction Machines
 
Ac motor winding
Ac motor windingAc motor winding
Ac motor winding
 
Manufacturing process of 500/600MW stator winding bar
Manufacturing process of 500/600MW stator winding barManufacturing process of 500/600MW stator winding bar
Manufacturing process of 500/600MW stator winding bar
 
Mechanical Vibrations all slides
Mechanical Vibrations all slidesMechanical Vibrations all slides
Mechanical Vibrations all slides
 
Build Features, Not Apps
Build Features, Not AppsBuild Features, Not Apps
Build Features, Not Apps
 

Similar to PPT ON CIM ,BHEL HARIDWAR

MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR
MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR
MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR Shubham Kulshreshtha
 
Manufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineManufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineVAIBHAV SINGH
 
Manfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHELManfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHELPrabhu Raj
 
Gurtej bhel electrical report-at-bhel-haridwar-1
Gurtej bhel electrical report-at-bhel-haridwar-1Gurtej bhel electrical report-at-bhel-haridwar-1
Gurtej bhel electrical report-at-bhel-haridwar-1Gurtej Rai
 
PROJECT ON STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
PROJECT ON  STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - CopyPROJECT ON  STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
PROJECT ON STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - CopyAmanraj Singh Padan
 
Welding of Joints.pdf
Welding of Joints.pdfWelding of Joints.pdf
Welding of Joints.pdfTVijayaGowri
 
GEMCO(general electric manufacturing company),chittagong,bd
GEMCO(general electric manufacturing company),chittagong,bdGEMCO(general electric manufacturing company),chittagong,bd
GEMCO(general electric manufacturing company),chittagong,bdTanvir Shihan
 
500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPT500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPTMahadev Kovalli
 
Circuit Breaker: Part 2
Circuit Breaker: Part 2Circuit Breaker: Part 2
Circuit Breaker: Part 2Dr. Rohit Babu
 
Industrial training ppt bhel bhopal
Industrial training ppt bhel bhopalIndustrial training ppt bhel bhopal
Industrial training ppt bhel bhopalPRAVEENKUMARSINGH87
 
Repairing of kiln shell crack
Repairing of kiln shell crackRepairing of kiln shell crack
Repairing of kiln shell crackmkpq pasha
 
Repairing of kiln shell crack
Repairing of kiln shell crackRepairing of kiln shell crack
Repairing of kiln shell crackmkpq pasha
 
BHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEM
BHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEMBHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEM
BHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEMyash Natani
 
Bus Ducts or Hollow conductors
Bus Ducts or Hollow conductorsBus Ducts or Hollow conductors
Bus Ducts or Hollow conductorsAjay Meena
 
Tube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptTube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptssuserea7ebc
 
Presentation-GEMCO
Presentation-GEMCOPresentation-GEMCO
Presentation-GEMCODipen Shome
 

Similar to PPT ON CIM ,BHEL HARIDWAR (20)

Harshitagarwal 111109034529-phpapp02
Harshitagarwal 111109034529-phpapp02Harshitagarwal 111109034529-phpapp02
Harshitagarwal 111109034529-phpapp02
 
MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR
MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR
MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR
 
Manufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineManufacturing of Large Electrical Machine
Manufacturing of Large Electrical Machine
 
Manfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHELManfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHEL
 
Gurtej bhel electrical report-at-bhel-haridwar-1
Gurtej bhel electrical report-at-bhel-haridwar-1Gurtej bhel electrical report-at-bhel-haridwar-1
Gurtej bhel electrical report-at-bhel-haridwar-1
 
REPORT (1)
REPORT (1)REPORT (1)
REPORT (1)
 
PROJECT ON STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
PROJECT ON  STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - CopyPROJECT ON  STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
PROJECT ON STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
 
Welding of Joints.pdf
Welding of Joints.pdfWelding of Joints.pdf
Welding of Joints.pdf
 
GEMCO(general electric manufacturing company),chittagong,bd
GEMCO(general electric manufacturing company),chittagong,bdGEMCO(general electric manufacturing company),chittagong,bd
GEMCO(general electric manufacturing company),chittagong,bd
 
500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPT500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPT
 
Shashi
ShashiShashi
Shashi
 
Circuit Breaker: Part 2
Circuit Breaker: Part 2Circuit Breaker: Part 2
Circuit Breaker: Part 2
 
TELK Industrial Visit Report
TELK Industrial Visit ReportTELK Industrial Visit Report
TELK Industrial Visit Report
 
Industrial training ppt bhel bhopal
Industrial training ppt bhel bhopalIndustrial training ppt bhel bhopal
Industrial training ppt bhel bhopal
 
Repairing of kiln shell crack
Repairing of kiln shell crackRepairing of kiln shell crack
Repairing of kiln shell crack
 
Repairing of kiln shell crack
Repairing of kiln shell crackRepairing of kiln shell crack
Repairing of kiln shell crack
 
BHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEM
BHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEMBHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEM
BHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEM
 
Bus Ducts or Hollow conductors
Bus Ducts or Hollow conductorsBus Ducts or Hollow conductors
Bus Ducts or Hollow conductors
 
Tube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptTube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.ppt
 
Presentation-GEMCO
Presentation-GEMCOPresentation-GEMCO
Presentation-GEMCO
 

Recently uploaded

2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.elesangwon
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Sumanth A
 
KCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosKCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosVictor Morales
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsResearcher Researcher
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Communityprachaibot
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptJohnWilliam111370
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
CS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfCS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfBalamuruganV28
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptxmohitesoham12
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSsandhya757531
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESkarthi keyan
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdfAkritiPradhan2
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Erbil Polytechnic University
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Romil Mishra
 

Recently uploaded (20)

2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
 
KCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosKCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitos
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending Actuators
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Community
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
CS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfCS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdf
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptx
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________
 

PPT ON CIM ,BHEL HARIDWAR

  • 1. MANUFACTURING PROCESS OF 660 MW TURBO GENERTOR STATOR WINDING BAR ABHISHEK SINGH 12ERDME004 AT BHEL HARIDWAR
  • 2. INTRODUCTION In 1956 India took a major step towards the establishment of its heavy engineering industry when BHEL, the first heavy electrical Manufacturing unit of the country was set up at Bhopal. BHEL's Heavy Electrical Equipment Plant (HEEP) was set up in technical collaboration with USSR, for the manufacturing of power plant equipment. In 1976, BHEL entered into a collaboration agreement with M/s Kraftwerk Union, AG of Germany for design, manufacturing, erection and commissioning of large size steam turbines. More than 40 percent of the country's electrical energy is generated from the power equipment supplied by BHEL, Haridwar.
  • 3. MANUFACTURING BLOCKS: . BLOCK I: ELECTRICAL MACHINE BLOCK, IS DESIGNED TO MANUFACTURING OF TURBOGENERATORS BLOCK II: FABRICATION BLOCK BLOCK III: TURBINE BLADE BLOCK BLOCK IV: COIL & INSULATION MANUFACTURING & APPARATUS & CONTROL GEAR MANUFACTURING BLOCK BLOCK V: FEEDER BLOCK AND KNOWN AS FABRICATION AND FORGE BLOCK BLOCK VI: STAMPING AND DIES MANUFACTURING BLOCK BLOCK VII: WOODWORKING BLOCK BLOCK VIII: HEAT EXCHANGER BLOCK, IS DESIGNED TO MANUFACTURE HEAT EXCHANGER UNIT FOR STEAM TURBINES.
  • 4. COIL & INSULATION MANUFACTURING SHOP (BLOCK-IV) Block-4 is designed to manufacture stator winding bars of Turbo & Hydro generator and coil like DC Armature coil ,main pole coil , equalizer coil etc. There are three BAYS in this block each bay manufactures stator bars and coils for different machines
  • 5. BAY-I: Bar winding shop: manufacturing of stator winding bars of generator BAY-II: Manufacturing of heavy duty generator stator bars with New CNC M/c BAY-III: Insulation detail shop: Manufacturing of hard insulation & machining of hares insulation part (Glass Textolite) such as packing, washer, insulation box, wedges etc Bar Shop: This shop is meant for manufacturing of stator winding coils of turbo-generator and hydro generator
  • 6. Layout of CIM, Block-IV
  • 7. It is quite difficult (rather impossible) to manufacture, handle and wind in the stator slot of generator of higher generation capacity because of its bigger size and heavy weight. That is why we make coil in two parts. One part its bottom part of coil called bottom or lower bar and other part of coil is called top bar or upper bar. Why do we call it bar?
  • 8. Manufacturing Process • For the manufacturing of stator bars insulated copper conductors are brought from Bangalore, it’s of two type’s i.e. solid copper conductor & hollow copper conductors which are used in water cooled stator layer glass insulation. • solid bar for 600/660/700 MW volume - 9.5X1.2 • Hollow copper for 600/660/700 Volume – 8.0x 4.6x1.3
  • 9. Cutting This process is done by automatic 3-444CNC machine. In this process the pre insulated copper conductor is cut into number of required length. Insulation is removed from both ends of the conductor cut.
  • 10. Transposition Transposition means changing/shifting of position of each conductor in active core (slot) part. After cutting the required number of conductors, the conductors are arranged on the comb in staggered manner and then bends are given to the conductors with the help of bending die at required distance. Then the conductor are taken out from the comb & die and placed with their ends in a line and transposition is carried out. Need of transposition. 1. To reduce eddy current losses. 2. Equalize the voltage generator. 3. To minimize skin effect of ac current
  • 11. Cross Over Insulation • The pre insulation of the copper conductor may get damaged due to mechanical bending in die during transposition, hence the insulating spacers are provided at the crossover portion of the conductors. A filler material (insulating putty or moulding micanite) is provided along the height of the bar to maintain the rectangular shape and to cover the difference of level of conductors.
  • 12. Stack Pressing • The core part of bar stack is pressed in under the pressure b/w 70kg to 80 kg and Temperature b/w 90 C to160 C for given period. Four bar is pressed in one time and six to eight plate are used for pressing .after that the consolidated stack is withdraw from the press. Inter Stand Short Test The consolidated stack is tested for the short between any two conductors in the bar, if found then it has to be rectified.This is done to ensure that no local current is flowing due to short circuit between conductors.(300 A/C supply)
  • 13. Forming • This process of forming is very important as in this process the bars are bending from both the ends of the bar i.e. at exciter side and turbine side at specific angles and shape as per design. This process is done manually. First the former is set according to the design making different angles at different positions. The straight bar stack is formed as per overhang profile (as per design), The overhang portion is consolidated after forming. . Pickling process After the forming and cutting process of the bar and due to the transportation of the bar, there accumulate very minute particles of dust on the ends of the bar. These particles may cause at the time of brazing and may create some air gaps. So, in order to remove these unwanted particles, basically the oil particles pickling process is performed.
  • 14. Contact Sleeve Mounting • After the pickling process is complete, contact sleeve and water box bottom parts are mounted on both the ends of the bar. it is a rectangular sleeve which is used to make contact between upper and lower bars . All the solid conductors are cut from the ends of the bar after the contact sleeve except the outer solid conductors. The water box is mounted in two halves; first the water box bottom part is mounted after the contact sleeve keeping some distance between them.
  • 15. • Brazing is basically the process of fixation of both the contact sleeve and water box. • Brazing is suitable for small parts , when high joint strength is required.In brazing alloy is mixed with water. Brazing
  • 16. • Nitrogen gas is the main constituent of the test. This test is similar to puncture test that is inflated tube is dipped in water for any leakage, the air bubbles gives us the exact position of the puncture. Nitrogen test
  • 17. Thermal Shock Test Thermal shock test is performed to check whether the bar can withstand extreme conditions i.e. when the generator is working or running at about 3000 Rpm. This is achieved by thermal shock test. Thermal shock test consist of series of hot water & cold water cycles alternatively. So firstly hot water at temperature of about 90ºC is passed through the bar and then cold water at about room temperature 27ºC approx. is flowed inside the bar alternatively. This process is repeated again and again.
  • 18. Helium Leakage Test • After thermal shock test bar is tested for any leakage with help of Helium gas. Helium test is the most important test of all, because helium test is performed to check any minute leakage within the bar and at the brazed portion. because helium is one of the lightest gases.
  • 19. Reforming • After all the previous processes which had undergone on the bar. That the shape of the bar is deformed from its original shape due to handling of the bar from one place to another for different processes. So to keep the shape of the bar as per design, the bar is checked if it is found distorted then it is reformed in the previous former machine by placing the bar on the former . Insulation • The stator bars are insulated with Micalastic (trade name) insulation. • Insulation is basically done to prevent any kind of short circuit between the bar and the stator core when the bar is assembled in the stator of the machine
  • 20. Impregnation and Baking • Micalastic System : In case of poor resin system the insulated bars are heated under vacuum and the impregnated (dipped) in heated resin so that all the air gaps are filled, layer by layer, with resin. • After impregnation the bars are pressed to bring them back to the original dimensions.
  • 21. HIGH VOLTAGE TEST •When the bar is dried it is wrapped with aluminum sheet to make outer surface of the bar conducting so that H.V. (High voltage test) can be performed. After this tests the coating of red gel is applied at both the ends of the bar. •In this test the bar which is already wrapped with aluminum is used. •High voltage is applied to the bar using auto-transformer and it is increased in steps according to the working voltage of the generator. If the insulation is weak the bar will puncture at the place of weaker insulation. •If any of the bar fails this test i.e. bar is punctured at any point then the bar is sent back for re-insulation and all the processes are repeated again
  • 22. Finishing • The baked and dimensionally correct bars are sanded-off to smoothen the edges and the surface is calibrated, if required, for the dimension. Dispatched for winding • The bars preserved with polythene sleeves to protect from dust, dirt, oil, rain etc are send to Block-I (Electric Machines Production Block - I, Turbo Generators and Hydro Generators) for winding