CH6:
Project Time Management
ABDULLAH ALKHADRAWY, PMP
Course Instructor:
 Abdullah Ahmed Al-Khadrawy.
 BSc. Civil Engineering 2006 (V.Good HD).
 Graduation Project (Project Management)
2006.(Excellent graded)
 Certified from Primavera Inc. ® : Advanced user for
Primavera P6 (2008).
 Certified from Primavera Inc. ® : Advanced user for
primavera Contract Manager 12 (2009).
 Attended courses (PMP, CCE, FIDIC, Project
Management, Arbitration for Engineering Contracts)
[2007-2013]
 Certified from PMI ® as PMP ® April2011
mahmed210@gmail.com
Schedule model
Representation of the plan for executing the project’s activities
including durations, dependencies, and other planning
information, used to produce project schedules along with
other scheduling artifacts.
Scheduling
6.1 Plan
Schedule
6.7 Control
Management Schedule
6.2 Define
Activities
6.3 Sequence
Activities
6.4 Estimate
Activity
Resources
6.5 Estimate
Activity
Durations
6.6 Develop
Schedule
manage the timely completion of the project
Initiating Planning Executing
Monitoring and
Controlling
Closing
6
Project Time
Management
6.1 Plan
Schedule
6.7 Control
Management Schedule
6.2 Define
Activities
6.3 Sequence
Activities
6.4 Estimate
Activity
Resources
6.5 Estimate
Activity
Durations
6.6 Develop
Schedule
manage the timely completion of the project
Initiating Planning Executing
Monitoring and
Controlling
Closing
Project Time
Management
6
6.1 Plan Schedule Management
.1 Project management plan
.2 Project charter
.3 Enterprise environmental factors
.4 Organizational process assets
.1 Expert judgment
.2 Analytical techniques
.3 Meetings
.1 Schedule management plan
establishing the policies, procedures, and documentation for planning,
developing, managing, executing, and controlling the project schedule
Planning
6.1PlanScheduleManagement:-
1. Project management plan
2. Project charter
3. Enterprise environmental factors
4. Organizational process assets
Inputs
6.1PlanScheduleManagement:- Inputs
3. Enterprise Environmental Factors
• Organizational culture and structure can all influence schedule
management;
• Resource availability and skills that may influence schedule planning;
• Project management software provides the scheduling tool and
alternative possibilities for managing the schedule;
• Published commercial information, such as resource productivity
information, is often available from commercial databases that track;
• Organizational work authorization systems.
6.1PlanScheduleManagement:- Inputs
4. Organizational process assets
• Monitoring and reporting tools to be used;
• Historical information;
• Schedule control tools;
• Existing formal and informal schedule control related policies, procedures, and
guidelines;
• Templates;
• Project closure guidelines;
• Change control procedures; and
• Risk control procedures including risk categories, probability definition and impact,
and probability and impact matrix.
6.1PlanScheduleManagement:- ToolsandTechniques:-
1. Expert judgment
2. Analytical techniques
3. Meetings
6.1PlanScheduleManagement:- ToolsandTechniques:-
2. Analytical techniques
• Scheduling methodology,
• Scheduling tools and techniques,
• Estimating approaches,
• Formats,
• Project management software.
• Ways to fast track or crash
6.1 Plan Schedule Management Outputs
1. Schedule Management Plan
• Project schedule model development. The scheduling methodology and the
scheduling tool
• Level of accuracy. The acceptable range used in determining realistic activity
duration.
• Units of measure. Each unit used in measurements is defined for each of the
resources.
• Organizational procedures links. The WBS (Section 5.4) provides the framework
for the schedule management plan.
• Project schedule model maintenance. The process used to update the status and
record progress of the project in the schedule model during the execution of the
project is defined.
• Control thresholds. Variance thresholds for monitoring schedule performance.
Thresholds are typically expressed as percentage deviations from the parameters
established in the baseline plan.
6.1 Plan Schedule Management Outputs
1. Schedule Management Plan
• Rules of performance measurement. Earned value management (EVM) rules or
other physical measurement rules of performance measurement are set. For
example, the schedule management plan may specify:
 Rules for establishing percent complete,
 Control accounts at which management of progress and schedule will be measured,
 Earned value measurement techniques (e.g., baselines, fixed-formula, percent complete, etc.)
• Schedule performance measurements such as schedule variance (SV) and schedule
performance index (SPI)
• Reporting formats. The formats and frequency for the various schedule reports are
defined.
• Process descriptions. Descriptions of each of the schedule management processes.
Project charter
provides the PM
with authority
Q: Which project management
process should a project manager
perform to get a formal authorization
for a project or a project phase?
A. Develop Project Management plan
B. Develop Project Charter
C. Perform Integrated Change Control
D. Direct and Manage Project Execution
B
6.2 Define Activities
.1 Schedule management plan
.2 Scope baseline
.3 Enterprise environmental factors
.4 Organizational process assets
.1 Decomposition
.2 Rolling wave planning
.3 Expert judgment
.1 Activity list
.2 Activity attributes
.3 Milestone list
identifying and documenting the specific actions to be performed to produce
the project deliverables
Planning
6.2DefineActivities
1. Schedule management plan
2. Scope baseline
3. Enterprise environmental factors
4. Organizational process assets
Inputs
6.2DefineActivities:- ToolsandTechniques:-
1. Decomposition
2. Rolling wave planning
3. Expert judgment
6.2DefineActivities:- ToolsandTechniques:-
2. Rolling wave planning
• an iterative planning technique in which the work to
be accomplished in the near term is planned in detail,
while the work in the future is planned at a higher level
• It is a form of progressive elaboration.
•. As more is known about the upcoming events in the
near term, work packages can be decomposed into
activities.
6.2 Define Activities Outputs
1. Activity list
2. Activity attributes
3. Milestone list
6.2 Define Activities Outputs
1. Activity list
Code Description UOM
GENERAL
110 Asset inspections
111 Routine inspections km
112 Additional inspections each
PAVEMENT MAINTENANCE
200 Routine Pavement
201 Pothole repair m
2
202 Edge repair m
203 Repair wearing surface m
2
204 Correct pavement shape m
2
209 Reinstatement of road openings m
2
210 Cracks and Joints
211 Crack sealing flexible pavement m
2
212 Crack sealing rigid pavement m
2
213 Cross-stitching cracks and joints each
214 Repair joints m
215 Repair spalls m
220 Unsealed Pavement
221 Formation grading km
222 Formation resheeting
A
km
223 Incorporate new base material
B
m
3
224 Formation earthworks m
3
225 Initial sealing of formation km
Activity
Group
Maintenance Activity
6.2 Define Activities Outputs
2. Activity attributes
 During the initial stages of the project, they include
• the activity identifier (ID), WBS ID, and activity label or name, and
 when completed, may include
• Activity codes, activity description, predecessor activities, successor activities, logical
relationships, leads and lags, resource requirements, imposed dates, constraints, and
assumptions, the person responsible for executing the work, geographic area, or place
,calendar the activity is assigned to, and activity type such as level of effort (often
abbreviated as LOE), discrete effort, and apportioned effort.
6.2 Define Activities Outputs
3. Milestone list
 Significant events.
 Almost represents start date or finish date, or a standalone event
 Maybe mandatory (contractual), or just guidance.
 Zero duration & no resources.
6.3 Sequence Activities
identifying and documenting relationships among the project activities
Planning
.1 Precedence diagramming method
(PDM)
.2 Dependency determination
.3 Leads and lags
.1 Schedule management plan
.2 Activity list
.3 Activity attributes
.4 Milestone list
.5 Project scope statement
.6 Enterprise environmental
factors
.7 Organizational process assets
.1 Project schedule network
diagrams
.2 Project documents updates
Logical Relationships
ActivityActivity
Start to Start (SS)
ActivityActivity
ActivityActivity ActivityActivity
ActivityActivity ActivityActivity
ActivityActivity ActivityActivity
Finish to Start (FS)
Finish to Finish (FF)
Start to Finish (SF)
Logical Relationships
Start FinishActivityActivity
At l e a st o n e p re d e ce s s o r
( FS - o r - S S )
At l e a st o n e s u c c e s s o r
( FS - o r - F F )
6.3SequenceActivities:-
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Milestone list
5. Project scope statement
6. Enterprise environmental factors
7. Organizational process assets
Inputs
6.3SequenceActivities:-
6. Enterprise environmental factors
• Government or industry standards,
•Project management information system (PMIS),
• Scheduling tool,
•Company work authorization systems.
Inputs
6.3SequenceActivities:-
7. Organizational process assets
• Project files from the corporate knowledge base used for scheduling
methodology,
• Existing formal and informal activity planning-related policies,
procedures, and guidelines, such as the scheduling methodology
• Templates
• Related activity attributes information in templates
Inputs
6.3SequenceActivities:- ToolsandTechniques:-
1. Precedence diagramming method (PDM)
2. Dependency determination
3. Leads and lags
LogicalRelationships
ActivityActivity
Start to Start (SS)
ActivityActivity
ActivityActivity ActivityActivity
ActivityActivity ActivityActivity
ActivityActivity ActivityActivity
Finish to Start (FS)
Finish to Finish (FF)
Start to Finish (SF)
6.3SequenceActivities:- Tools and Techniques:-
1. Precedence diagramming method (PDM)
6.3SequenceActivities:- Tools and Techniques:-
1. Precedence diagramming method (PDM)
6.3SequenceActivities:- ToolsandTechniques:-
2. Dependency determination
•Mandatory dependencies :- legally or contractually required or
inherent in the nature of the work (Hard Logic)
E.g. Construction (form work must be finished before
concreting).
•Discretionary dependencies (Soft Logic) :- also (preferred logic)
 You have the option to prefer to implement any of the two
activities before or concurrent the other one.
6.3SequenceActivities:- ToolsandTechniques:-
2. Dependency determination
•External dependencies:- relationship between project activities and
non-project activities OR dependencies are usually outside the
project team’s control
 e.g. Delivery of testing hardware for a software project.
•Internal dependencies :- precedence relationship between project
activities. & inside the project team’s control
6.3SequenceActivities:- ToolsandTechniques:-
3. Leads and lags
•Leads: amount of time, the successor can advance the predecessor .
e.g. Landscaping can be started, before the building construction totally
completes.
•Lags (Waiting Period) e.g. you can’t dismantle the form for a
concrete poured element, unless you wait for a main period.
6.3 Sequence Activities Outputs
1. Project schedule network diagrams
2. Project documents updates
6.3 Sequence Activities Outputs
2. Project documents updates
Project documents that may be updated include, but are not limited to:
Activity lists,
Activity attributes,
Milestone list, and
Risk register.
6.4 Estimate Activity Resources
estimating the type and quantities of material, human resources,
equipment, or supplies required to perform each activity
Planning
.1 Expert judgment
.2 Alternative analysis
.3 Published estimating data
.4 Bottom-up estimating
.5 Project management software
.1 Schedule management plan
.2 Activity list
.3 Activity attributes
.4 Resource calendars
.5 Risk register
.6 Activity cost estimates
.7 Enterprise environmental factors
.8 Organizational process assets
.1 Activity resource requirements
.2 Resource breakdown structure
.3 Project documents updates
6.4EstimateActivityResources:-
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Resource calendars
5. Risk register
6. Activity cost estimates
7. Enterprise environmental factors
8. Organizational process assets
Inputs
6.4EstimateActivityResources:-
4. Resource calendars
• identifies the working days and shifts on which each specific resource is
available.
Inputs
5. Risk register
• Risk events may impact resource selection and availability.
6.4EstimateActivityResources:- Inputs
7. Enterprise environmental factors
• E.g. resource location, availability, and skills.
8. Organizational process assets
• E.g. Policies and procedures regarding staffing,
•Policies and procedures relating to rental and purchase of
supplies and equipment, and
•Historical information regarding types of resources used for
similar work on previous projects.
6.4EstimateActivityResources:- Inputs
6.4EstimateActivityResources:- ToolsandTechniques:-
1. Expert judgment
2. Alternative analysis
3. Published estimating data
4. Bottom-up estimating
5. Project management software
6.4EstimateActivityResources:- ToolsandTechniques:-
1. Expert judgment
•Any group or person with specialized knowledge in resource planning
and estimating can provide such expertise
6.4EstimateActivityResources:- ToolsandTechniques:-
2. Alternative analysis
•Many schedule activities have alternative methods of accomplishment.
•Using various levels of resource capability or skills, different size
or type of machines, different tools (hand versus automated),
and make- rent-or-buy decisions regarding the resource
6.4EstimateActivityResources:- ToolsandTechniques:-
3. Published estimating data
• Updated production rates and unit costs of resources for an extensive
array of labor trades, material, and equipment for different countries and
geographical locations within countries.
6.4EstimateActivityResources:- ToolsandTechniques:-
4. Bottom-up estimating
•Estimating project duration, resources, or cost by aggregating the
estimates of the lower-level components of the WBS.
•When an activity cannot be estimated with a reasonable degree of
confidence, the work within the activity is decomposed into more detail.
•The resource needs are estimated. These estimates are then aggregated
into a total quantity for each of the activity’s resources.
6.4EstimateActivityResources:- ToolsandTechniques:-
5. Project management software
•E.g.
•Scheduling Software.
•ERP Software (Enterprise Resource Planning).
•Work Sheets.
6.4 Estimate Activity Resources Outputs
1. Activity resource requirements
2. Resource breakdown structure
3. Project documents updates
6.3 Sequence Activities Outputs
1. Activity resource requirements
* The types and quantities of resources required for each activity in a
work package.
* Aggregated to determine the estimated resources for each work
package and each work period.
6.3 Sequence Activities Outputs
2. Resource Breakdown Structure
* Hierarchical representation of resources by category and type
6.3 Sequence Activities Outputs
3. Project Documents Updates
e.g.
•Activity list,
•Activity attributes,
•Resource calendars.
6.5 Estimate Activity Durations
estimating the number of work periods needed to complete individual activities
with estimated resources
Planning
.1 Expert judgment
.2 Analogous estimating
.3 Parametric estimating
.4 Three-point estimating
.5 Group decision-making
techniques
.6 Reserve analysis
.1 Schedule management plan
.2 Activity list
.3 Activity attributes
.4 Activity resource requirements
.5 Resource calendars
.6 Project scope statement
.7 Risk register
.8 Resource breakdown structure
.9 Enterprise environmental factors
.10 Organizational process assets
.1 Activity duration estimates
.2 Project documents updates
6.5EstimateActivityDurations:-
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Activity resource requirements
5. Resource calendars
6. Project scope statement
7. Risk register
8. Resource breakdown structure
9. Enterprise environmental factors
10. Organizational process assets
Inputs
7. Enterprise environmental factors
• E.g. Duration estimating databases and other reference data,
•Productivity metrics,
•Published commercial information, and
•Location of team members.
8. Organizational process assets
• E.g. Historical duration information,
•Project calendars,
•Scheduling methodology, and
•Lessons learned.
6.5EstimateActivityDurations:- Inputs
6.5EstimateActivityDurations:- ToolsandTechniques:-
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Three-point estimating
5. Group decision-making techniques
6. Reserve analysis
6.5EstimateActivityDurations:-ToolsandTechniques:-
2- Analogous Estimating:
oUses historical information, expert judgment.
oThink “analogy” – something similar
oRelatively quick and low cost to produce
oUsed when:
o Only limited information available.
o Similar project information available
o Estimators have right experience.
ABDULLAH ALKHADRAWY, PMP
6.5EstimateActivityDurations:- Tools and Techniques:-
3- Parametric Estimating:
oUsed to predict total project costs or duration by using project's
characteristics in a mathematical model .
oFor example, if the assigned resource is capable of installing 25 meters
of cable per hour, the duration required to install 1,000 meters is 40
hours. (1,000 meters divided by 25 meters per hour).
ocan produce higher levels of accuracy depending upon the
sophistication and underlying data built into the model.
ABDULLAH ALKHADRAWY, PMP
6.5EstimateActivityDurations:- Tools and Techniques:-
4- Three Points Estimating: (Weighted average)
oTriangular Distribution = (O + M + P) / 3
oBeta Distribution = (O + 4M + P) / 6 (Refer to PERT analysis )
ABDULLAH ALKHADRAWY, PMP
6.5EstimateActivityDurations:- ToolsandTechniques:-
6. Reserve analysis
• Contingency reserves, sometimes referred to as time reserves or buffers,
into the project schedule to account for schedule uncertainty
Original Duration Buffer
6.5 Estimate Activity Durations Outputs
1. Activity duration estimates
2. Project documents updates
6.6 Develop Schedule
analyzing activity sequences, durations, resource requirements, and schedule
constraints to create the project schedule model
Planning
.1 Schedule network analysis
.2 Critical path method
.3 Critical chain method
.4 Resource optimization techniques
.5 Modeling techniques
.6 Leads and lags
.7 Schedule compression
.8 Scheduling tool
.1 Schedule management plan
.2 Activity list
.3 Activity attributes
.4 Project schedule network
diagrams
.5 Activity resource requirements
.6 Resource calendars
.7 Activity duration estimates
.8 Project scope statement
.9 Risk register
.10 Project staff assignments
.11 Resource breakdown structure
.12 Enterprise environmental
factors
.13 Organizational process assets
.1 Schedule baseline
.2 Project schedule
.3 Schedule data
.4 Project calendars
.5 Project management plan updates
.6 Project documents updates
6.6DevelopSchedule:-
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Project schedule network diagrams
5. Activity resource requirements
6. Resource calendars
7. Activity duration estimates
8. Project scope statement
9. Risk register
10. Project staff assignments
11. Resource breakdown structure
12. Enterprise environmental factors
13. Organizational process assets
Inputs
6.6DevelopSchedule:- ToolsandTechniques:-
1. Schedule network analysis
2. Critical path method
3. Critical chain method
4. Resource optimization techniques
5. Modeling techniques
6. Leads and lags
7. Schedule compression
8. Scheduling tool
6.6DevelopSchedule:- Tools and Techniques:-
1. Schedule network analysis
• Technique that generates the project schedule model.
• Various analytical techniques, such as critical path method, critical
chain method, what-if analysis, and resource optimization techniques to
calculate the early and late start and finish dates for the uncompleted
portions of project activities
6.6DevelopSchedule:- Tools and Techniques:-
2. Critical path method
• Method used to estimate the minimum project duration and determine
the amount of scheduling flexibility on the logical network paths within
the schedule model.
• Calculates the early start, early finish, late start, and late finish dates for
all activities
• Without regard for any resource limitations.
• Performing a forward and backward pass analysis through the
schedule network
6.6DevelopSchedule:- Tools and Techniques:-
2. Critical path method
• The critical path is the sequence of activities that represents the longest
path through a project.
• The critical path determines the shortest possible project duration.
• The resulting early and late start and finish dates are not necessarily the
project schedule, because the critical path method is used to calculate the
amount of scheduling flexibility on the logical network paths within the
schedule model.
© WILEY 2010
Some Network Definitions
• All activities on the critical path have zero slack (0 float)
• Slack defines how long non-critical activities can be delayed without
delaying the project
• Slack = the activity’s late finish minus its early finish (or its late start
minus its early start)
• Earliest Start (ES) = the earliest finish of the immediately preceding
activity
• Earliest Finish (EF) = is the ES plus the activity time
• Latest Start (LS) and Latest Finish (LF) = the latest an activity can start
(LS) or finish (LF) without delaying the project completion
6.6DevelopSchedule:- ToolsandTechniques:-
© WILEY 2010
6.6DevelopSchedule:- Tools and Techniques:-
-Example:
* Find the Critical Path for the next network
© WILEY 2010
NetworkDiagramthe-1Step
6.6DevelopSchedule:- ToolsandTechniques:-
© WILEY 2010
AddDeterministicTimeEstimatesandConnectedPaths-2Step
6.6DevelopSchedule:- ToolsandTechniques:-
© WILEY 2010
:CalculatetheProjectCompletionTimes)Con’t(2Step
The longest path (A B D E G I J K ) limits the
project’s duration (project cannot finish in less
time than its longest path)
ABDEGIJK is the project’s critical path
6.6DevelopSchedule:- ToolsandTechniques:-
6.6DevelopSchedule:- Tools and Techniques:-
3. Critical chain method (CCM)
• Schedule method that allows the project team to place buffers on any
project schedule path to account for limited resources and project
uncertainties.
• It is developed from the critical path method approach and considers
the effects of resource allocation, resource optimization, resource
leveling, and activity duration uncertainty on the critical path
determined using the critical path method.
• To do so, the critical chain method introduces the concept of buffers and
buffer management.
6.6DevelopSchedule:- Tools and Techniques:-
3. Critical chain method (CCM)
• The critical chain method uses activities with durations that do not
include safety margins, logical relationships, and resource availability
• The resource-constrained critical path is known as the critical chain.
• The critical chain method adds duration buffers that are non-work
schedule activities to manage uncertainty
• One buffer, placed at the end of the critical chain, is known as the
project buffer and protects the target finish date from slippage along the
critical chain.
6.6DevelopSchedule:- Tools and Techniques:-
3. Critical chain method (CCM)
• Once the buffer schedule activities are determined, the planned
activities are scheduled to their latest possible planned start and finish
dates.
• Consequently, instead of managing the total float of network paths, the
critical chain method focuses on managing the remaining buffer
durations against the remaining durations of chains of activities.
6.6DevelopSchedule:- Tools and Techniques:-
3. Critical chain method (CCM)
6.6DevelopSchedule:- Tools and Techniques:-
3. Critical chain method (CCM)
• Feeding buffers, placed at each point where a chain of dependent
activities that are not on the critical chain feeds into the critical chain.
• Feeding buffers thus protect the critical chain from slippage along the
feeding chains.
• Duration buffers non-work schedule activities be added to manage
uncertainty
• Project buffer One buffer, placed at the end of the critical chain
6.6DevelopSchedule:- Tools and Techniques:-
3. Critical chain method (CCM)
CPM CCM
Consideration for Duration & relation Consider resources conditions & the
uncertainity in addition
Resources Conditions Considers the optimumstatus Consider resource allocation, resource
optimization, resource leveling
Paths Concept Calculation Custumized by buffers
Criticality Criticalpath (zero float) Criticalchain (group of buffer assigned paths)
Calculation Forward path & backword path Depend on cpmcalculations plus buffers
Buffers Not custumized, just float calculation Calculated to cover resources conditions and
uncertainity
6.6DevelopSchedule:- Tools and Techniques:-
4. Resource optimization techniques
• Resource leveling. A technique in which start and finish dates are
adjusted based on resource constraints with the goal of balancing
demand for resources with the available supply.
6.6DevelopSchedule:- Tools and Techniques:-
4. Resource optimization techniques
• Resource leveling
6.6DevelopSchedule:- Tools and Techniques:-
4. Resource optimization techniques
• Resource Smoothing adjusts the activities of a schedule model such
that the requirements for resources on the project do not exceed certain
predefined resource limits
• In resource smoothing, , the project’s critical path is not changed and
the completion date may not be delayed, as opposed to resource leveling
• Activities may only be delayed within their free and total float. Thus
resource smoothing may not be able to optimize all resources.
6.6DevelopSchedule:- Tools and Techniques:-
5. Modeling techniques e.g.
• What-If Scenario Analysis process of evaluating scenarios in order to
predict their effect, positively or negatively, on project objectives
• The outcome of the what-if scenario analysis can be used to assess the
feasibility of the project schedule under adverse conditions, and in
preparing contingency and response plans to overcome or mitigate the
impact of unexpected situations.
6.6DevelopSchedule:- Tools and Techniques:-
5. Modeling techniques e.g.
• Simulation calculating multiple project durations with
different sets of activity assumptions.
• usually using probability distributions constructed from
the three-point estimates to account for uncertainty.
• The most common simulation technique is Monte Carlo,
• in which a distribution of possible activity durations is
defined for each activity and used to calculate a
distribution of possible outcomes for the total project.
6.6DevelopSchedule:- Tools and Techniques:-
7. Schedule Compression
• To shorten the schedule duration without reducing the project scope, in
order to meet schedule constraints, imposed dates, or other schedule
objectives. E.g.
• Crashing shorten the schedule duration for the least incremental cost by
adding resources.
• Fast tracking in which activities or phases normally done in sequence
are performed in parallel for at least a portion of their duration.
6.6DevelopSchedule:- Tools and Techniques:-
7. Schedule Compression
6.6DevelopSchedule:- Tools and Techniques:-
8. Scheduling Tool
• Automated scheduling tools contain the schedule model and expedite
the scheduling process by generating start and finish dates based on the
inputs of activities, network diagrams, resources and activity durations
using schedule network analysis.
• A scheduling tool can be used in conjunction with other project
management software applications as well as manual methods.
6.6 Develop Schedule Outputs
1. Schedule baseline
2. Project schedule
3. Schedule data
4. Project calendars
5. Project management plan updates
6. Project documents updates
6.6 Develop Schedule Outputs
1. Schedule baseline
• The approved version of a schedule model that can be changed only through
formal change control procedures and is used as a basis for comparison to actual
results.
• It is accepted and approved by the appropriate stakeholders as the schedule
baseline with baseline start dates and baseline finish dates.
• During monitoring and controlling, the approved baseline dates are compared to
the actual start and finish dates to determine whether variances have occurred.
• The schedule baseline is a component of the project management plan.
6.6 Develop Schedule Outputs
2. Project schedule (Presentation)
• The outputs from a schedule model are schedule presentations. The
project schedule is an output of a schedule model that presents linked
activities with planned dates, durations, milestones, and resources.
6.6 Develop Schedule Outputs
2. Project schedule (e.g.)
• Bar charts (Gantt charts)
6.6 Develop Schedule Outputs
2. Project schedule (e.g.)
• Milestone charts
6.6 Develop Schedule Outputs
2. Project schedule (e.g.)
• Project schedule network diagrams
6.6 Develop Schedule Outputs
3. Schedule data
• Includes at least the schedule milestones, schedule activities, activity attributes, and
documentation of all identified assumptions and constraints.
• Information frequently supplied as supporting detail includes, but is not limited to:
* Resource requirements by time period, often in the form of a resource
histogram;
* Alternative schedules, such as best-case or worst-case, not resource-leveled,
or resource-leveled, with or without imposed dates; and
* Scheduling of contingency reserves.
6.6 Develop Schedule Outputs
3. Project Documents Updates
* E.g.
• Activity resource requirements.
• Activity attributes.
• Calendars.
• Risk register.
6.7 Control Schedule
.1 Project management plan
.2 Project schedule
.3 Work performance data
.4 Project calendars
.5 Schedule data
.6 Organizational process assets
.1 Performance reviews
.2 Project management software
.3 Resource optimization
techniques
.4 Modeling techniques
.5 Leads and lags
.6 Schedule compression
.7 Scheduling tool
.1 Work performance information
.2 Schedule forecasts
.3 Change requests
.4 Project management plan
updates
.5 Project documents updates
.6 Organizational process assets
updates
monitoring the status of project activities to update project progress and
manage changes to the schedule baseline to achieve the plan.
Monitoring&controlling
6.7ControlSchedule
- As a component of the Perform Integrated Change Control process
concerned with:
• Determining the current status of the project schedule,
• Influencing the factors that create schedule changes,
• Determining if the project schedule has changed, and
• Managing the actual changes as they occur.
6.7ControlSchedule
- If any agile approach is utilized, control schedule is concerned with:
• Determining the current status of the project schedule by comparing the total
amount of work delivered and accepted against the estimates of work complete
for the elapsed time cycle,
• Conducting retrospective reviews (scheduled reviews to record lessons learne
for correcting processes and improving, if required,
• Reprioritizing the remaining work plan (backlog),
• Determining the rate at which the deliverables are produced, validated, and
accepted (velocity) in given time per iteration (agreed work cycle duration,
typically two weeks or one month),
• Determining that the project schedule has changed, and
• Managing the actual changes as they occur.
6.7ControlSchedule:-
1. Project management plan
2. Project schedule
3. Work performance data
4. Project calendars
5. Schedule data
6. Organizational process assets
Inputs
6.7ControlSchedule:-
6. Organizational process assets
E.g.
•Existing formal and informal schedule control-related policies,
procedures, and guidelines;
• Schedule control tools; and
• Monitoring and reporting methods to be used.
Inputs
6.7ControlSchedule:- Tools andTechniques:-
1. Performance reviews
2. Project management software
3. Resource optimization techniques
4. Modeling techniques
5. Leads and lags
6. Schedule compression
7. Scheduling tool
6.7ControlSchedule:- Tools andTechniques:-
1. Performance reviews
• Trend analysis
• Examines project performance over
time to determine whether
performance is improving or
deteriorating.
• Graphical analysis techniques are
valuable for understanding performance
to date and for comparison to future
performance goals in the form of
completion dates.
6.7ControlSchedule:- Tools andTechniques:-
1. Performance reviews
• Critical path method (CPM)
• Comparing the progress along the critical path can help determine
schedule status.
• The variance on the critical path will have a direct impact on the project end date.
• Critical chain method (CCM)
• Comparing the amount of buffer remaining to the amount of buffer
needed to protect the delivery date can help determine schedule status.
• The difference between the buffer needed and the buffer remaining can
determine whether corrective action is appropriate.
6.7ControlSchedule:- Tools andTechniques:-
1. Performance reviews
• Earned value management
• Schedule performance measurements such as schedule variance
(SV) and schedule performance index (SPI), are used to assess the
magnitude of variation to the original schedule baseline.
• For projects not using earned value management, similar variance
analysis can be performed by comparing planned activity start or
finish dates against actual start or finish dates to identify variances
between the schedule baseline and actual project performance
6.7 Control Schedule Outputs
1. Work performance information
2. Schedule forecasts
3. Change requests
4. Project management plan updates
5. Project documents updates
6. Organizational process assets updates
6.7 Control Schedule Outputs
1. Work performance information
* The calculated SV and SPI time performance
indicators for WBS components, in particular the
work packages and control accounts, are
documented and communicated to stakeholders.
6.7 Control Schedule Outputs
2. Schedule Forecasts
• Schedule forecasts are predictions of conditions and events in the project’s
future, & updated and reissued based on work performance information
provided as the project is executed.
6.7 Control Schedule Outputs
3. Change requests
• Modifications to the project scope or project schedule may result in change
requests to the schedule baseline, scope baseline, and/or other components of
the project management plan.
• Preventive actions may include recommended changes to eliminate or reduce
the probability of negative schedule variances..
6.7 Control Schedule Outputs
4. Project management plan updates
• include, but are not limited to:
•Schedule baseline. related to project scope changes, activity resources, or The
schedule baseline may be updated to reflect changes caused by schedule
compression techniques.
• Schedule management plan.
• Cost baseline. The cost baseline may be updated to reflect approved change
requests or changes caused by compression techniques.
6.7 Control Schedule Outputs
5. Project Documents Updates
• include, but are not limited to:
• Schedule Data.
• Project Schedule.
• Risk Register.
6.7 Control Schedule Outputs
6. Organizational Process Assets Updates
• include, but are not limited to:
• Causes of variances,
•Corrective action chosen and the reasons, and
•Other types of lessons learned from project schedule control
PMP PMBOK 5TH Ch 6 time management

More Related Content

What's hot

05 project scope management
05  project scope management05  project scope management
05 project scope managementAla Ibrahim
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1Anand Bobade
 
Project scope management
Project scope managementProject scope management
Project scope managementANOOP S NAIR
 
Project time management
Project time managementProject time management
Project time managementImran Jamil
 
Pmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalPmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalYudha Pratama, PMP
 
PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)Mohammad Mohammadi
 
project time management
 project time management project time management
project time managementHira Atiq
 
Project integration management
Project integration management Project integration management
Project integration management KU Leuven
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementHisham Ali,PMP
 
Episode 21 : Project Scope Management
Episode 21 :  Project Scope ManagementEpisode 21 :  Project Scope Management
Episode 21 : Project Scope ManagementSAJJAD KHUDHUR ABBAS
 
Ed4 P4 Project Integration Management
Ed4 P4 Project Integration ManagementEd4 P4 Project Integration Management
Ed4 P4 Project Integration Managementjonash99
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2Anand Bobade
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementMohamed Loey
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTSAJJAD KHUDHUR ABBAS
 
Knowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartKnowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartAnand Bobade
 

What's hot (20)

05 project scope management
05  project scope management05  project scope management
05 project scope management
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
Project scope management
Project scope managementProject scope management
Project scope management
 
Project time management
Project time managementProject time management
Project time management
 
Pmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalPmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management final
 
PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)
 
Scope management
Scope managementScope management
Scope management
 
project time management
 project time management project time management
project time management
 
Project integration management
Project integration management Project integration management
Project integration management
 
Project scope management 2
Project scope management 2Project scope management 2
Project scope management 2
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope Management
 
Episode 21 : Project Scope Management
Episode 21 :  Project Scope ManagementEpisode 21 :  Project Scope Management
Episode 21 : Project Scope Management
 
Ed4 P4 Project Integration Management
Ed4 P4 Project Integration ManagementEd4 P4 Project Integration Management
Ed4 P4 Project Integration Management
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENT
 
Knowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartKnowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes Chart
 

Viewers also liked

PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryPMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryYudha Pratama, PMP
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementAbdullah Ahmed, PMP, RMP
 
Project time management
Project time managementProject time management
Project time managementJivan Nepali
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Editionpankajsh10
 
Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6Nam Trung
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Managementtkrikau
 
Pmp slide share
Pmp slide sharePmp slide share
Pmp slide sharesaleem54
 
Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5pankajsh10
 
Project Procurement Management PMBOK 5
Project Procurement Management PMBOK 5Project Procurement Management PMBOK 5
Project Procurement Management PMBOK 5pankajsh10
 
Project Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th EditionProject Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th Editionpankajsh10
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5pankajsh10
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Managementpankajsh10
 
Project Risk Management - PMBOK5
Project Risk Management - PMBOK5Project Risk Management - PMBOK5
Project Risk Management - PMBOK5pankajsh10
 

Viewers also liked (20)

PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryPMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk Management
 
PMP_Project Human Resources Management
PMP_Project Human Resources ManagementPMP_Project Human Resources Management
PMP_Project Human Resources Management
 
Project time management
Project time managementProject time management
Project time management
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Edition
 
PMP Preparation - 06 Time Management
PMP Preparation - 06 Time ManagementPMP Preparation - 06 Time Management
PMP Preparation - 06 Time Management
 
Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
 
PMP_Economic Selection Criteria
PMP_Economic Selection CriteriaPMP_Economic Selection Criteria
PMP_Economic Selection Criteria
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
PMP_Project Procurement Management
PMP_Project Procurement ManagementPMP_Project Procurement Management
PMP_Project Procurement Management
 
Pmp slide share
Pmp slide sharePmp slide share
Pmp slide share
 
Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5
 
Project Procurement Management PMBOK 5
Project Procurement Management PMBOK 5Project Procurement Management PMBOK 5
Project Procurement Management PMBOK 5
 
Project Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th EditionProject Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th Edition
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
Project Risk Management - PMBOK5
Project Risk Management - PMBOK5Project Risk Management - PMBOK5
Project Risk Management - PMBOK5
 

Similar to PMP PMBOK 5TH Ch 6 time management

Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part twoHossam Maghrabi
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management areaZaur Ahmadov, PMP
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
3- Project Time Management.ppt
3- Project Time Management.ppt3- Project Time Management.ppt
3- Project Time Management.pptMohamadAGhareb
 
NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2Future Managers
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxMohanadRabea1
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptxTecnicoItca
 
Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Jeffrey Cheah
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMPSubodh Kumar
 
Pmbok 5th executing process group
Pmbok 5th executing process groupPmbok 5th executing process group
Pmbok 5th executing process groupHossam Maghrabi
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material Abdel Rahman okasha
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptxWajihAnsari7
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...Arlene Smith
 
Units 2-11 Project management.ppt By Tol
Units 2-11 Project management.ppt By TolUnits 2-11 Project management.ppt By Tol
Units 2-11 Project management.ppt By TolTolessaSolomon
 

Similar to PMP PMBOK 5TH Ch 6 time management (20)

Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part two
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
3- Project Time Management.ppt
3- Project Time Management.ppt3- Project Time Management.ppt
3- Project Time Management.ppt
 
NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
 
Ch 8(spi)cm mi-pp
Ch 8(spi)cm mi-ppCh 8(spi)cm mi-pp
Ch 8(spi)cm mi-pp
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
 
#Pmp in a3 edition_1
#Pmp in a3 edition_1#Pmp in a3 edition_1
#Pmp in a3 edition_1
 
Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
Pmbok 5th executing process group
Pmbok 5th executing process groupPmbok 5th executing process group
Pmbok 5th executing process group
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
 
Entra lecture6 PM1.pdf
Entra lecture6 PM1.pdfEntra lecture6 PM1.pdf
Entra lecture6 PM1.pdf
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...
 
Units 2-11 Project management.ppt By Tol
Units 2-11 Project management.ppt By TolUnits 2-11 Project management.ppt By Tol
Units 2-11 Project management.ppt By Tol
 

More from Abdullah Ahmed, PMP, RMP (16)

Sr. Planning Engineer/ Lead Planner resume
Sr. Planning Engineer/ Lead Planner resume Sr. Planning Engineer/ Lead Planner resume
Sr. Planning Engineer/ Lead Planner resume
 
Float paths
Float pathsFloat paths
Float paths
 
EDIT-ADD WBS FOR ORACLE PRIMAVERA P6® USING NOTEPAD`& MS EXCEL
EDIT-ADD WBS FOR ORACLE PRIMAVERA P6® USING NOTEPAD`& MS EXCELEDIT-ADD WBS FOR ORACLE PRIMAVERA P6® USING NOTEPAD`& MS EXCEL
EDIT-ADD WBS FOR ORACLE PRIMAVERA P6® USING NOTEPAD`& MS EXCEL
 
Strategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should knowStrategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should know
 
Organizational Risk Management
Organizational Risk Management Organizational Risk Management
Organizational Risk Management
 
Pm study project risk management test
Pm study project  risk management testPm study project  risk management test
Pm study project risk management test
 
Q+&+as+
Q+&+as+Q+&+as+
Q+&+as+
 
RMP risk management-final exam
RMP risk management-final examRMP risk management-final exam
RMP risk management-final exam
 
Self test engine PSP-PMI-SP
Self test engine PSP-PMI-SPSelf test engine PSP-PMI-SP
Self test engine PSP-PMI-SP
 
Pmi rmp
Pmi rmpPmi rmp
Pmi rmp
 
PMI-RMP a test mod 00
PMI-RMP a test  mod 00PMI-RMP a test  mod 00
PMI-RMP a test mod 00
 
ENGINEERING CONTRACTS العقود الهندسية
  ENGINEERING CONTRACTS العقود الهندسية  ENGINEERING CONTRACTS العقود الهندسية
ENGINEERING CONTRACTS العقود الهندسية
 
PMP PMBOK5 project management processes
PMP PMBOK5 project management processesPMP PMBOK5 project management processes
PMP PMBOK5 project management processes
 
PMP PMbok 5th CH1 - CH2
PMP PMbok 5th CH1 - CH2PMP PMbok 5th CH1 - CH2
PMP PMbok 5th CH1 - CH2
 
PMP PMBok 5th Project management processes
PMP PMBok 5th Project management processesPMP PMBok 5th Project management processes
PMP PMBok 5th Project management processes
 
Ch1 ch2
Ch1 ch2Ch1 ch2
Ch1 ch2
 

Recently uploaded

Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesDoe Paoro
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterJamesConcepcion7
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingrajputmeenakshi733
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...ssuserf63bd7
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in PhilippinesDavidSamuel525586
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckHajeJanKamps
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdfMintel Group
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfJamesConcepcion7
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerAggregage
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...Hector Del Castillo, CPM, CPMM
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
BAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptxBAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptxran17april2001
 

Recently uploaded (20)

Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic Experiences
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare Newsletter
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketing
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in Philippines
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deck
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdf
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon Harmer
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
BAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptxBAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptx
 

PMP PMBOK 5TH Ch 6 time management

  • 2. Course Instructor:  Abdullah Ahmed Al-Khadrawy.  BSc. Civil Engineering 2006 (V.Good HD).  Graduation Project (Project Management) 2006.(Excellent graded)  Certified from Primavera Inc. ® : Advanced user for Primavera P6 (2008).  Certified from Primavera Inc. ® : Advanced user for primavera Contract Manager 12 (2009).  Attended courses (PMP, CCE, FIDIC, Project Management, Arbitration for Engineering Contracts) [2007-2013]  Certified from PMI ® as PMP ® April2011 mahmed210@gmail.com
  • 3. Schedule model Representation of the plan for executing the project’s activities including durations, dependencies, and other planning information, used to produce project schedules along with other scheduling artifacts.
  • 5. 6.1 Plan Schedule 6.7 Control Management Schedule 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.6 Develop Schedule manage the timely completion of the project Initiating Planning Executing Monitoring and Controlling Closing 6 Project Time Management 6.1 Plan Schedule 6.7 Control Management Schedule 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.6 Develop Schedule manage the timely completion of the project Initiating Planning Executing Monitoring and Controlling Closing Project Time Management 6
  • 6. 6.1 Plan Schedule Management .1 Project management plan .2 Project charter .3 Enterprise environmental factors .4 Organizational process assets .1 Expert judgment .2 Analytical techniques .3 Meetings .1 Schedule management plan establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule Planning
  • 7. 6.1PlanScheduleManagement:- 1. Project management plan 2. Project charter 3. Enterprise environmental factors 4. Organizational process assets Inputs
  • 8. 6.1PlanScheduleManagement:- Inputs 3. Enterprise Environmental Factors • Organizational culture and structure can all influence schedule management; • Resource availability and skills that may influence schedule planning; • Project management software provides the scheduling tool and alternative possibilities for managing the schedule; • Published commercial information, such as resource productivity information, is often available from commercial databases that track; • Organizational work authorization systems.
  • 9. 6.1PlanScheduleManagement:- Inputs 4. Organizational process assets • Monitoring and reporting tools to be used; • Historical information; • Schedule control tools; • Existing formal and informal schedule control related policies, procedures, and guidelines; • Templates; • Project closure guidelines; • Change control procedures; and • Risk control procedures including risk categories, probability definition and impact, and probability and impact matrix.
  • 10. 6.1PlanScheduleManagement:- ToolsandTechniques:- 1. Expert judgment 2. Analytical techniques 3. Meetings
  • 11. 6.1PlanScheduleManagement:- ToolsandTechniques:- 2. Analytical techniques • Scheduling methodology, • Scheduling tools and techniques, • Estimating approaches, • Formats, • Project management software. • Ways to fast track or crash
  • 12. 6.1 Plan Schedule Management Outputs 1. Schedule Management Plan • Project schedule model development. The scheduling methodology and the scheduling tool • Level of accuracy. The acceptable range used in determining realistic activity duration. • Units of measure. Each unit used in measurements is defined for each of the resources. • Organizational procedures links. The WBS (Section 5.4) provides the framework for the schedule management plan. • Project schedule model maintenance. The process used to update the status and record progress of the project in the schedule model during the execution of the project is defined. • Control thresholds. Variance thresholds for monitoring schedule performance. Thresholds are typically expressed as percentage deviations from the parameters established in the baseline plan.
  • 13. 6.1 Plan Schedule Management Outputs 1. Schedule Management Plan • Rules of performance measurement. Earned value management (EVM) rules or other physical measurement rules of performance measurement are set. For example, the schedule management plan may specify:  Rules for establishing percent complete,  Control accounts at which management of progress and schedule will be measured,  Earned value measurement techniques (e.g., baselines, fixed-formula, percent complete, etc.) • Schedule performance measurements such as schedule variance (SV) and schedule performance index (SPI) • Reporting formats. The formats and frequency for the various schedule reports are defined. • Process descriptions. Descriptions of each of the schedule management processes.
  • 14. Project charter provides the PM with authority Q: Which project management process should a project manager perform to get a formal authorization for a project or a project phase? A. Develop Project Management plan B. Develop Project Charter C. Perform Integrated Change Control D. Direct and Manage Project Execution B
  • 15. 6.2 Define Activities .1 Schedule management plan .2 Scope baseline .3 Enterprise environmental factors .4 Organizational process assets .1 Decomposition .2 Rolling wave planning .3 Expert judgment .1 Activity list .2 Activity attributes .3 Milestone list identifying and documenting the specific actions to be performed to produce the project deliverables Planning
  • 16. 6.2DefineActivities 1. Schedule management plan 2. Scope baseline 3. Enterprise environmental factors 4. Organizational process assets Inputs
  • 17. 6.2DefineActivities:- ToolsandTechniques:- 1. Decomposition 2. Rolling wave planning 3. Expert judgment
  • 18. 6.2DefineActivities:- ToolsandTechniques:- 2. Rolling wave planning • an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level • It is a form of progressive elaboration. •. As more is known about the upcoming events in the near term, work packages can be decomposed into activities.
  • 19. 6.2 Define Activities Outputs 1. Activity list 2. Activity attributes 3. Milestone list
  • 20. 6.2 Define Activities Outputs 1. Activity list Code Description UOM GENERAL 110 Asset inspections 111 Routine inspections km 112 Additional inspections each PAVEMENT MAINTENANCE 200 Routine Pavement 201 Pothole repair m 2 202 Edge repair m 203 Repair wearing surface m 2 204 Correct pavement shape m 2 209 Reinstatement of road openings m 2 210 Cracks and Joints 211 Crack sealing flexible pavement m 2 212 Crack sealing rigid pavement m 2 213 Cross-stitching cracks and joints each 214 Repair joints m 215 Repair spalls m 220 Unsealed Pavement 221 Formation grading km 222 Formation resheeting A km 223 Incorporate new base material B m 3 224 Formation earthworks m 3 225 Initial sealing of formation km Activity Group Maintenance Activity
  • 21. 6.2 Define Activities Outputs 2. Activity attributes  During the initial stages of the project, they include • the activity identifier (ID), WBS ID, and activity label or name, and  when completed, may include • Activity codes, activity description, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions, the person responsible for executing the work, geographic area, or place ,calendar the activity is assigned to, and activity type such as level of effort (often abbreviated as LOE), discrete effort, and apportioned effort.
  • 22. 6.2 Define Activities Outputs 3. Milestone list  Significant events.  Almost represents start date or finish date, or a standalone event  Maybe mandatory (contractual), or just guidance.  Zero duration & no resources.
  • 23. 6.3 Sequence Activities identifying and documenting relationships among the project activities Planning .1 Precedence diagramming method (PDM) .2 Dependency determination .3 Leads and lags .1 Schedule management plan .2 Activity list .3 Activity attributes .4 Milestone list .5 Project scope statement .6 Enterprise environmental factors .7 Organizational process assets .1 Project schedule network diagrams .2 Project documents updates
  • 24. Logical Relationships ActivityActivity Start to Start (SS) ActivityActivity ActivityActivity ActivityActivity ActivityActivity ActivityActivity ActivityActivity ActivityActivity Finish to Start (FS) Finish to Finish (FF) Start to Finish (SF)
  • 25. Logical Relationships Start FinishActivityActivity At l e a st o n e p re d e ce s s o r ( FS - o r - S S ) At l e a st o n e s u c c e s s o r ( FS - o r - F F )
  • 26. 6.3SequenceActivities:- 1. Schedule management plan 2. Activity list 3. Activity attributes 4. Milestone list 5. Project scope statement 6. Enterprise environmental factors 7. Organizational process assets Inputs
  • 27. 6.3SequenceActivities:- 6. Enterprise environmental factors • Government or industry standards, •Project management information system (PMIS), • Scheduling tool, •Company work authorization systems. Inputs
  • 28. 6.3SequenceActivities:- 7. Organizational process assets • Project files from the corporate knowledge base used for scheduling methodology, • Existing formal and informal activity planning-related policies, procedures, and guidelines, such as the scheduling methodology • Templates • Related activity attributes information in templates Inputs
  • 29. 6.3SequenceActivities:- ToolsandTechniques:- 1. Precedence diagramming method (PDM) 2. Dependency determination 3. Leads and lags
  • 30. LogicalRelationships ActivityActivity Start to Start (SS) ActivityActivity ActivityActivity ActivityActivity ActivityActivity ActivityActivity ActivityActivity ActivityActivity Finish to Start (FS) Finish to Finish (FF) Start to Finish (SF) 6.3SequenceActivities:- Tools and Techniques:- 1. Precedence diagramming method (PDM)
  • 31. 6.3SequenceActivities:- Tools and Techniques:- 1. Precedence diagramming method (PDM)
  • 32. 6.3SequenceActivities:- ToolsandTechniques:- 2. Dependency determination •Mandatory dependencies :- legally or contractually required or inherent in the nature of the work (Hard Logic) E.g. Construction (form work must be finished before concreting). •Discretionary dependencies (Soft Logic) :- also (preferred logic)  You have the option to prefer to implement any of the two activities before or concurrent the other one.
  • 33. 6.3SequenceActivities:- ToolsandTechniques:- 2. Dependency determination •External dependencies:- relationship between project activities and non-project activities OR dependencies are usually outside the project team’s control  e.g. Delivery of testing hardware for a software project. •Internal dependencies :- precedence relationship between project activities. & inside the project team’s control
  • 34. 6.3SequenceActivities:- ToolsandTechniques:- 3. Leads and lags •Leads: amount of time, the successor can advance the predecessor . e.g. Landscaping can be started, before the building construction totally completes. •Lags (Waiting Period) e.g. you can’t dismantle the form for a concrete poured element, unless you wait for a main period.
  • 35. 6.3 Sequence Activities Outputs 1. Project schedule network diagrams 2. Project documents updates
  • 36. 6.3 Sequence Activities Outputs 2. Project documents updates Project documents that may be updated include, but are not limited to: Activity lists, Activity attributes, Milestone list, and Risk register.
  • 37. 6.4 Estimate Activity Resources estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity Planning .1 Expert judgment .2 Alternative analysis .3 Published estimating data .4 Bottom-up estimating .5 Project management software .1 Schedule management plan .2 Activity list .3 Activity attributes .4 Resource calendars .5 Risk register .6 Activity cost estimates .7 Enterprise environmental factors .8 Organizational process assets .1 Activity resource requirements .2 Resource breakdown structure .3 Project documents updates
  • 38. 6.4EstimateActivityResources:- 1. Schedule management plan 2. Activity list 3. Activity attributes 4. Resource calendars 5. Risk register 6. Activity cost estimates 7. Enterprise environmental factors 8. Organizational process assets Inputs
  • 39. 6.4EstimateActivityResources:- 4. Resource calendars • identifies the working days and shifts on which each specific resource is available. Inputs
  • 40. 5. Risk register • Risk events may impact resource selection and availability. 6.4EstimateActivityResources:- Inputs
  • 41. 7. Enterprise environmental factors • E.g. resource location, availability, and skills. 8. Organizational process assets • E.g. Policies and procedures regarding staffing, •Policies and procedures relating to rental and purchase of supplies and equipment, and •Historical information regarding types of resources used for similar work on previous projects. 6.4EstimateActivityResources:- Inputs
  • 42. 6.4EstimateActivityResources:- ToolsandTechniques:- 1. Expert judgment 2. Alternative analysis 3. Published estimating data 4. Bottom-up estimating 5. Project management software
  • 43. 6.4EstimateActivityResources:- ToolsandTechniques:- 1. Expert judgment •Any group or person with specialized knowledge in resource planning and estimating can provide such expertise
  • 44. 6.4EstimateActivityResources:- ToolsandTechniques:- 2. Alternative analysis •Many schedule activities have alternative methods of accomplishment. •Using various levels of resource capability or skills, different size or type of machines, different tools (hand versus automated), and make- rent-or-buy decisions regarding the resource
  • 45. 6.4EstimateActivityResources:- ToolsandTechniques:- 3. Published estimating data • Updated production rates and unit costs of resources for an extensive array of labor trades, material, and equipment for different countries and geographical locations within countries.
  • 46. 6.4EstimateActivityResources:- ToolsandTechniques:- 4. Bottom-up estimating •Estimating project duration, resources, or cost by aggregating the estimates of the lower-level components of the WBS. •When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail. •The resource needs are estimated. These estimates are then aggregated into a total quantity for each of the activity’s resources.
  • 47. 6.4EstimateActivityResources:- ToolsandTechniques:- 5. Project management software •E.g. •Scheduling Software. •ERP Software (Enterprise Resource Planning). •Work Sheets.
  • 48. 6.4 Estimate Activity Resources Outputs 1. Activity resource requirements 2. Resource breakdown structure 3. Project documents updates
  • 49. 6.3 Sequence Activities Outputs 1. Activity resource requirements * The types and quantities of resources required for each activity in a work package. * Aggregated to determine the estimated resources for each work package and each work period.
  • 50. 6.3 Sequence Activities Outputs 2. Resource Breakdown Structure * Hierarchical representation of resources by category and type
  • 51. 6.3 Sequence Activities Outputs 3. Project Documents Updates e.g. •Activity list, •Activity attributes, •Resource calendars.
  • 52. 6.5 Estimate Activity Durations estimating the number of work periods needed to complete individual activities with estimated resources Planning .1 Expert judgment .2 Analogous estimating .3 Parametric estimating .4 Three-point estimating .5 Group decision-making techniques .6 Reserve analysis .1 Schedule management plan .2 Activity list .3 Activity attributes .4 Activity resource requirements .5 Resource calendars .6 Project scope statement .7 Risk register .8 Resource breakdown structure .9 Enterprise environmental factors .10 Organizational process assets .1 Activity duration estimates .2 Project documents updates
  • 53. 6.5EstimateActivityDurations:- 1. Schedule management plan 2. Activity list 3. Activity attributes 4. Activity resource requirements 5. Resource calendars 6. Project scope statement 7. Risk register 8. Resource breakdown structure 9. Enterprise environmental factors 10. Organizational process assets Inputs
  • 54. 7. Enterprise environmental factors • E.g. Duration estimating databases and other reference data, •Productivity metrics, •Published commercial information, and •Location of team members. 8. Organizational process assets • E.g. Historical duration information, •Project calendars, •Scheduling methodology, and •Lessons learned. 6.5EstimateActivityDurations:- Inputs
  • 55. 6.5EstimateActivityDurations:- ToolsandTechniques:- 1. Expert judgment 2. Analogous estimating 3. Parametric estimating 4. Three-point estimating 5. Group decision-making techniques 6. Reserve analysis
  • 56. 6.5EstimateActivityDurations:-ToolsandTechniques:- 2- Analogous Estimating: oUses historical information, expert judgment. oThink “analogy” – something similar oRelatively quick and low cost to produce oUsed when: o Only limited information available. o Similar project information available o Estimators have right experience. ABDULLAH ALKHADRAWY, PMP
  • 57. 6.5EstimateActivityDurations:- Tools and Techniques:- 3- Parametric Estimating: oUsed to predict total project costs or duration by using project's characteristics in a mathematical model . oFor example, if the assigned resource is capable of installing 25 meters of cable per hour, the duration required to install 1,000 meters is 40 hours. (1,000 meters divided by 25 meters per hour). ocan produce higher levels of accuracy depending upon the sophistication and underlying data built into the model. ABDULLAH ALKHADRAWY, PMP
  • 58. 6.5EstimateActivityDurations:- Tools and Techniques:- 4- Three Points Estimating: (Weighted average) oTriangular Distribution = (O + M + P) / 3 oBeta Distribution = (O + 4M + P) / 6 (Refer to PERT analysis ) ABDULLAH ALKHADRAWY, PMP
  • 59. 6.5EstimateActivityDurations:- ToolsandTechniques:- 6. Reserve analysis • Contingency reserves, sometimes referred to as time reserves or buffers, into the project schedule to account for schedule uncertainty Original Duration Buffer
  • 60. 6.5 Estimate Activity Durations Outputs 1. Activity duration estimates 2. Project documents updates
  • 61. 6.6 Develop Schedule analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model Planning .1 Schedule network analysis .2 Critical path method .3 Critical chain method .4 Resource optimization techniques .5 Modeling techniques .6 Leads and lags .7 Schedule compression .8 Scheduling tool .1 Schedule management plan .2 Activity list .3 Activity attributes .4 Project schedule network diagrams .5 Activity resource requirements .6 Resource calendars .7 Activity duration estimates .8 Project scope statement .9 Risk register .10 Project staff assignments .11 Resource breakdown structure .12 Enterprise environmental factors .13 Organizational process assets .1 Schedule baseline .2 Project schedule .3 Schedule data .4 Project calendars .5 Project management plan updates .6 Project documents updates
  • 62. 6.6DevelopSchedule:- 1. Schedule management plan 2. Activity list 3. Activity attributes 4. Project schedule network diagrams 5. Activity resource requirements 6. Resource calendars 7. Activity duration estimates 8. Project scope statement 9. Risk register 10. Project staff assignments 11. Resource breakdown structure 12. Enterprise environmental factors 13. Organizational process assets Inputs
  • 63. 6.6DevelopSchedule:- ToolsandTechniques:- 1. Schedule network analysis 2. Critical path method 3. Critical chain method 4. Resource optimization techniques 5. Modeling techniques 6. Leads and lags 7. Schedule compression 8. Scheduling tool
  • 64. 6.6DevelopSchedule:- Tools and Techniques:- 1. Schedule network analysis • Technique that generates the project schedule model. • Various analytical techniques, such as critical path method, critical chain method, what-if analysis, and resource optimization techniques to calculate the early and late start and finish dates for the uncompleted portions of project activities
  • 65. 6.6DevelopSchedule:- Tools and Techniques:- 2. Critical path method • Method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model. • Calculates the early start, early finish, late start, and late finish dates for all activities • Without regard for any resource limitations. • Performing a forward and backward pass analysis through the schedule network
  • 66. 6.6DevelopSchedule:- Tools and Techniques:- 2. Critical path method • The critical path is the sequence of activities that represents the longest path through a project. • The critical path determines the shortest possible project duration. • The resulting early and late start and finish dates are not necessarily the project schedule, because the critical path method is used to calculate the amount of scheduling flexibility on the logical network paths within the schedule model.
  • 67. © WILEY 2010 Some Network Definitions • All activities on the critical path have zero slack (0 float) • Slack defines how long non-critical activities can be delayed without delaying the project • Slack = the activity’s late finish minus its early finish (or its late start minus its early start) • Earliest Start (ES) = the earliest finish of the immediately preceding activity • Earliest Finish (EF) = is the ES plus the activity time • Latest Start (LS) and Latest Finish (LF) = the latest an activity can start (LS) or finish (LF) without delaying the project completion 6.6DevelopSchedule:- ToolsandTechniques:-
  • 68. © WILEY 2010 6.6DevelopSchedule:- Tools and Techniques:- -Example: * Find the Critical Path for the next network
  • 71. © WILEY 2010 :CalculatetheProjectCompletionTimes)Con’t(2Step The longest path (A B D E G I J K ) limits the project’s duration (project cannot finish in less time than its longest path) ABDEGIJK is the project’s critical path 6.6DevelopSchedule:- ToolsandTechniques:-
  • 72. 6.6DevelopSchedule:- Tools and Techniques:- 3. Critical chain method (CCM) • Schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties. • It is developed from the critical path method approach and considers the effects of resource allocation, resource optimization, resource leveling, and activity duration uncertainty on the critical path determined using the critical path method. • To do so, the critical chain method introduces the concept of buffers and buffer management.
  • 73. 6.6DevelopSchedule:- Tools and Techniques:- 3. Critical chain method (CCM) • The critical chain method uses activities with durations that do not include safety margins, logical relationships, and resource availability • The resource-constrained critical path is known as the critical chain. • The critical chain method adds duration buffers that are non-work schedule activities to manage uncertainty • One buffer, placed at the end of the critical chain, is known as the project buffer and protects the target finish date from slippage along the critical chain.
  • 74. 6.6DevelopSchedule:- Tools and Techniques:- 3. Critical chain method (CCM) • Once the buffer schedule activities are determined, the planned activities are scheduled to their latest possible planned start and finish dates. • Consequently, instead of managing the total float of network paths, the critical chain method focuses on managing the remaining buffer durations against the remaining durations of chains of activities.
  • 75. 6.6DevelopSchedule:- Tools and Techniques:- 3. Critical chain method (CCM)
  • 76. 6.6DevelopSchedule:- Tools and Techniques:- 3. Critical chain method (CCM) • Feeding buffers, placed at each point where a chain of dependent activities that are not on the critical chain feeds into the critical chain. • Feeding buffers thus protect the critical chain from slippage along the feeding chains. • Duration buffers non-work schedule activities be added to manage uncertainty • Project buffer One buffer, placed at the end of the critical chain
  • 77. 6.6DevelopSchedule:- Tools and Techniques:- 3. Critical chain method (CCM) CPM CCM Consideration for Duration & relation Consider resources conditions & the uncertainity in addition Resources Conditions Considers the optimumstatus Consider resource allocation, resource optimization, resource leveling Paths Concept Calculation Custumized by buffers Criticality Criticalpath (zero float) Criticalchain (group of buffer assigned paths) Calculation Forward path & backword path Depend on cpmcalculations plus buffers Buffers Not custumized, just float calculation Calculated to cover resources conditions and uncertainity
  • 78. 6.6DevelopSchedule:- Tools and Techniques:- 4. Resource optimization techniques • Resource leveling. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
  • 79. 6.6DevelopSchedule:- Tools and Techniques:- 4. Resource optimization techniques • Resource leveling
  • 80. 6.6DevelopSchedule:- Tools and Techniques:- 4. Resource optimization techniques • Resource Smoothing adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits • In resource smoothing, , the project’s critical path is not changed and the completion date may not be delayed, as opposed to resource leveling • Activities may only be delayed within their free and total float. Thus resource smoothing may not be able to optimize all resources.
  • 81. 6.6DevelopSchedule:- Tools and Techniques:- 5. Modeling techniques e.g. • What-If Scenario Analysis process of evaluating scenarios in order to predict their effect, positively or negatively, on project objectives • The outcome of the what-if scenario analysis can be used to assess the feasibility of the project schedule under adverse conditions, and in preparing contingency and response plans to overcome or mitigate the impact of unexpected situations.
  • 82. 6.6DevelopSchedule:- Tools and Techniques:- 5. Modeling techniques e.g. • Simulation calculating multiple project durations with different sets of activity assumptions. • usually using probability distributions constructed from the three-point estimates to account for uncertainty. • The most common simulation technique is Monte Carlo, • in which a distribution of possible activity durations is defined for each activity and used to calculate a distribution of possible outcomes for the total project.
  • 83. 6.6DevelopSchedule:- Tools and Techniques:- 7. Schedule Compression • To shorten the schedule duration without reducing the project scope, in order to meet schedule constraints, imposed dates, or other schedule objectives. E.g. • Crashing shorten the schedule duration for the least incremental cost by adding resources. • Fast tracking in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
  • 84. 6.6DevelopSchedule:- Tools and Techniques:- 7. Schedule Compression
  • 85. 6.6DevelopSchedule:- Tools and Techniques:- 8. Scheduling Tool • Automated scheduling tools contain the schedule model and expedite the scheduling process by generating start and finish dates based on the inputs of activities, network diagrams, resources and activity durations using schedule network analysis. • A scheduling tool can be used in conjunction with other project management software applications as well as manual methods.
  • 86. 6.6 Develop Schedule Outputs 1. Schedule baseline 2. Project schedule 3. Schedule data 4. Project calendars 5. Project management plan updates 6. Project documents updates
  • 87. 6.6 Develop Schedule Outputs 1. Schedule baseline • The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results. • It is accepted and approved by the appropriate stakeholders as the schedule baseline with baseline start dates and baseline finish dates. • During monitoring and controlling, the approved baseline dates are compared to the actual start and finish dates to determine whether variances have occurred. • The schedule baseline is a component of the project management plan.
  • 88. 6.6 Develop Schedule Outputs 2. Project schedule (Presentation) • The outputs from a schedule model are schedule presentations. The project schedule is an output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.
  • 89. 6.6 Develop Schedule Outputs 2. Project schedule (e.g.) • Bar charts (Gantt charts)
  • 90. 6.6 Develop Schedule Outputs 2. Project schedule (e.g.) • Milestone charts
  • 91. 6.6 Develop Schedule Outputs 2. Project schedule (e.g.) • Project schedule network diagrams
  • 92. 6.6 Develop Schedule Outputs 3. Schedule data • Includes at least the schedule milestones, schedule activities, activity attributes, and documentation of all identified assumptions and constraints. • Information frequently supplied as supporting detail includes, but is not limited to: * Resource requirements by time period, often in the form of a resource histogram; * Alternative schedules, such as best-case or worst-case, not resource-leveled, or resource-leveled, with or without imposed dates; and * Scheduling of contingency reserves.
  • 93. 6.6 Develop Schedule Outputs 3. Project Documents Updates * E.g. • Activity resource requirements. • Activity attributes. • Calendars. • Risk register.
  • 94. 6.7 Control Schedule .1 Project management plan .2 Project schedule .3 Work performance data .4 Project calendars .5 Schedule data .6 Organizational process assets .1 Performance reviews .2 Project management software .3 Resource optimization techniques .4 Modeling techniques .5 Leads and lags .6 Schedule compression .7 Scheduling tool .1 Work performance information .2 Schedule forecasts .3 Change requests .4 Project management plan updates .5 Project documents updates .6 Organizational process assets updates monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. Monitoring&controlling
  • 95. 6.7ControlSchedule - As a component of the Perform Integrated Change Control process concerned with: • Determining the current status of the project schedule, • Influencing the factors that create schedule changes, • Determining if the project schedule has changed, and • Managing the actual changes as they occur.
  • 96. 6.7ControlSchedule - If any agile approach is utilized, control schedule is concerned with: • Determining the current status of the project schedule by comparing the total amount of work delivered and accepted against the estimates of work complete for the elapsed time cycle, • Conducting retrospective reviews (scheduled reviews to record lessons learne for correcting processes and improving, if required, • Reprioritizing the remaining work plan (backlog), • Determining the rate at which the deliverables are produced, validated, and accepted (velocity) in given time per iteration (agreed work cycle duration, typically two weeks or one month), • Determining that the project schedule has changed, and • Managing the actual changes as they occur.
  • 97. 6.7ControlSchedule:- 1. Project management plan 2. Project schedule 3. Work performance data 4. Project calendars 5. Schedule data 6. Organizational process assets Inputs
  • 98. 6.7ControlSchedule:- 6. Organizational process assets E.g. •Existing formal and informal schedule control-related policies, procedures, and guidelines; • Schedule control tools; and • Monitoring and reporting methods to be used. Inputs
  • 99. 6.7ControlSchedule:- Tools andTechniques:- 1. Performance reviews 2. Project management software 3. Resource optimization techniques 4. Modeling techniques 5. Leads and lags 6. Schedule compression 7. Scheduling tool
  • 100. 6.7ControlSchedule:- Tools andTechniques:- 1. Performance reviews • Trend analysis • Examines project performance over time to determine whether performance is improving or deteriorating. • Graphical analysis techniques are valuable for understanding performance to date and for comparison to future performance goals in the form of completion dates.
  • 101. 6.7ControlSchedule:- Tools andTechniques:- 1. Performance reviews • Critical path method (CPM) • Comparing the progress along the critical path can help determine schedule status. • The variance on the critical path will have a direct impact on the project end date. • Critical chain method (CCM) • Comparing the amount of buffer remaining to the amount of buffer needed to protect the delivery date can help determine schedule status. • The difference between the buffer needed and the buffer remaining can determine whether corrective action is appropriate.
  • 102. 6.7ControlSchedule:- Tools andTechniques:- 1. Performance reviews • Earned value management • Schedule performance measurements such as schedule variance (SV) and schedule performance index (SPI), are used to assess the magnitude of variation to the original schedule baseline. • For projects not using earned value management, similar variance analysis can be performed by comparing planned activity start or finish dates against actual start or finish dates to identify variances between the schedule baseline and actual project performance
  • 103. 6.7 Control Schedule Outputs 1. Work performance information 2. Schedule forecasts 3. Change requests 4. Project management plan updates 5. Project documents updates 6. Organizational process assets updates
  • 104. 6.7 Control Schedule Outputs 1. Work performance information * The calculated SV and SPI time performance indicators for WBS components, in particular the work packages and control accounts, are documented and communicated to stakeholders.
  • 105. 6.7 Control Schedule Outputs 2. Schedule Forecasts • Schedule forecasts are predictions of conditions and events in the project’s future, & updated and reissued based on work performance information provided as the project is executed.
  • 106. 6.7 Control Schedule Outputs 3. Change requests • Modifications to the project scope or project schedule may result in change requests to the schedule baseline, scope baseline, and/or other components of the project management plan. • Preventive actions may include recommended changes to eliminate or reduce the probability of negative schedule variances..
  • 107. 6.7 Control Schedule Outputs 4. Project management plan updates • include, but are not limited to: •Schedule baseline. related to project scope changes, activity resources, or The schedule baseline may be updated to reflect changes caused by schedule compression techniques. • Schedule management plan. • Cost baseline. The cost baseline may be updated to reflect approved change requests or changes caused by compression techniques.
  • 108. 6.7 Control Schedule Outputs 5. Project Documents Updates • include, but are not limited to: • Schedule Data. • Project Schedule. • Risk Register.
  • 109. 6.7 Control Schedule Outputs 6. Organizational Process Assets Updates • include, but are not limited to: • Causes of variances, •Corrective action chosen and the reasons, and •Other types of lessons learned from project schedule control