Job Site Visit
Upcoming SlideShare
Loading in...5
×
 

Job Site Visit

on

  • 96 views

This is a memo of a job site visit that I did for my scheduling class.

This is a memo of a job site visit that I did for my scheduling class.

Statistics

Views

Total Views
96
Views on SlideShare
94
Embed Views
2

Actions

Likes
0
Downloads
0
Comments
0

1 Embed 2

http://www.linkedin.com 2

Accessibility

Upload Details

Uploaded via as Microsoft Word

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    Job Site Visit Job Site Visit Document Transcript

    • MEMORANDUM TO: JEFF SUCHY FROM: ZACH HIMLER LAB TIME: 8:00 A.M. SUBJECT: HOMEWORK #1 JOBSITE VISIT DATE: 11/5/2013 CBEC JOBSITE VISIT The Chemical and Biomolecular Engineering and Chemistry (CBEC) Building is a $126 million building that has 225,000 gross sq. ft. The construction site is between Woodruff and 19th Street on The Ohio State University campus. The groundbreaking ceremony took place on June 18, 2012. Gilbane Inc. is the head construction company. So far, the floors that have concrete placed are the ground floor, first floor, second floor, third floor, and they are working on the fourth floor now getting all the scaffolding and rebar in place. The structural dimensions, floor-to-floor height, and environmental stability are crucial in this project to support the research that is planned to occur within this building. The CBEC Building is going to be a “green” building by having a LEED Silver rating. It is expected to be finished by the end of 2014. There were several issues that I came up with for this project that took some thought and figuring before the project began. The first issue that came to mind was where large trucks and equipment could park on the site. Being right in the middle of one of the most crowded places on campus during the day, there isn’t much room to park equipment or materials. There are buildings on both sides of the site and roads on the other two sides. Not only are the buildings and roadways in the way, but Gilbane has to leave pathways for students to walk to their classes. This issue of having very little room to work with brings me to my next point.
    • With there being little room to work, there comes the problem of getting longer trucks to turn into the site. The roads are only so wide for the trucks to make their wide turns into the site.So the problem arises of trucks cannot get into the site to drop off materials. Therefore, needed materials are stuck outside of the site. The outside perimeter of the site is fenced off which helps keep trespassers like students out of the site. This is the third and probably most important issue that needed solved. In order to solve the issue of not having room to store material, if the material is brought in and immediately put up into the building, then it doesn’t have to be stored some place. Obviously this isn’t always possible, so maybe some of the materials can be stored in the actual building floors. A solution to not being able to have trucks pull into the site is to have the trucks come during the middle of the night and park in the street. This way they do not have to come into the site, and if they unload at night, then the trucks block a very minimal amount of traffic. The solution to help keep out trespassers is the fence that is around the site. The fence doesn’t keep everyone out, but it does at least slow them down. 2
    • As you can tell from this picture, the site goes right up to the sidewalk and almost to the street itself. This makes it tough to park equipment and pull into the site, so a way to fix it is to have trucks park on the streets in the middle of the night and unload material then. Also, here is the fence that helps keep out trespassers. 3