SlideShare a Scribd company logo
1 of 4
Download to read offline
Economy Parking                                                                         By Alan H. Simon, P.E.




Simon Design Engineering




                           Bridging underground utilities and reducing future maintenance
                                  needs are just two of the benefits steel provided.




  F
         For years, there were discussions of replacing Eero Saarin-      ing structure needed to reflect and compliment the aesthetic
         en’s aging Trans World Airlines Terminal at New York’s John      nature of the surrounding area, including the new T5 expan-
         F. Kennedy International Airport. In 2007, those discussions     sion and monorail system. Although the existing site utilities
         became a reality when JetBlue Airways chose JFK as its hub.      were indicated in the bridging documents, it also was noted
         To support JetBlue’s new Terminal 5, (T5), expansion proxi-      that the number, location, and types of utilities had not been
         mate parking for 1,500 vehicles was required. The so-called      fully verified. This apparently innocuous note would later
         Yellow Garage had to be built in a limited timeframe that        prove to impact the project in a significant way.
         corresponded with the opening of T5. The Port Authority of          The Wellesley, Mass.-based structural engineering firm Simon
         New York and New Jersey (PANYNJ), in conjunction with            Design Engineering, LLC, and The Berlin Steel Construction
         JetBlue Airways, compiled preliminary bridging documents         Company, Inc., Kensington, Conn., were approached as a team
         and issued a Request for Proposals that was made available to    by Peter Scalamandre & Sons, Inc., a local New York contrac-
         a select group of general contractors.                           tor with significant Port Authority experience. Although the
             The bridging documents established preferred points          preliminary bridging documents were based on a fully precast
         of egress and desired car counts, and the general footprint      concrete solution, they allowed for alternative structural systems.
         parameters based on a six-story, precast structure. Pedes-       Scalamandre, the general contractor and lead on the design-build
         trian egress included elevator cores, enclosed stairwells, and   team, believed that a steel solution would greatly benefit the Port
         connections to the existing AirTrain monorail system. A key      Authority and JetBlue based on comparing the available solutions.
         criterion indicated in the documents was that the new park-      Simon Design revised the precast structural system, footprint, and


       MODERN STEEL CONSTRUCTION november 2010
Simon Design Engineering


    As part of constructing the new Terminal 5 at New York’s John            The design-build team’s decision to use steel framing with long-
➤
                                                                         ➤




    F. Kennedy International Airport, the Port Authority of New York         span precast spandrels resulted in an open parking structure and
    and New Jersey added a steel-framed new six-story parking                reduced both the initial cost and maintenance requirements.
    structure for 1,500 cars.




column grid with the assistance of Berlin Steel and Scalamandre in       ered by barge to the construction site. The double tees were fur-
response to the RFP and bridging documents.                              nished by Bayshore Concrete Products Corp. of Virginia, which
    The design-build team’s structural steel beam and column             also recently had provided the AirTrain monorail system’s seg-
solution with a precast concrete decking system was ultimately           mental, precast concrete elements to the Port Authority at JFK.
the preferred design solution, making the Yellow Garage the first        The ability to use 15-ft double tees and other long-span pre-
PANYNJ design-build garage project using this approach. The
final design incorporated precast spandrels, steel railings, and steel
mesh, reflecting the surrounding structures while meeting the
building code requirements as an open parking structure, which               Alan H. Simon, P.E., is presi-
had several benefits. As an open parking structure the use of struc-         dent of Simon Design Engi-
tural steel, devoid of supplemental fireproofing, allowed for open           neering, LLC. Highly regarded
stairwells as a means of egress. It also permitted the use of exposed        for his perceptive and innova-
fire suppression standpipes and eliminated the need for sprinklers           tive approach, he has dedicated
(no sprinklering). In addition, the Port Authority realized the ben-         his career to the advancement
efits of steel construction, including the initial economical costs          of structured parking to benefit
and the minimal maintenance requirements, among others.                      every client, each community,
    The final design approach used 15-ft-wide precast concrete               and the environment.
double tee floor slabs, manufactured off site, that were deliv-


                                                                                              november 2010 MODERN STEEL CONSTRUCTION
{
manufactured structural elements, which           cept called for the use of hot-dipped gal-
are traditionally considered too large to         vanized steel, which is economical and has
be transported on roadways, provided the          demonstrated longevity and significant
Port Authority and JetBlue with a host            durability with little to no maintenance
of inherent benefits. Using steel framing         required in the first 50 years of a structure’s
and wider floor units allowed for longer          life. However, the Port Authority’s own
spans, large parking bays and stalls, fewer       design standards for steel required a three-
columns and visual obstructions (ideal            coat paint system to provide a less indus-
for patron safety and utility conflicts).         trial finish and appearance. As a result, all
It also considerably reduced the number           steel beams and columns were blast cleaned
of deep foundations and foundation ele-           to an SP6 standard, and a stringent qual-
ments, overall construction time, and the         ity assurance program was implemented to
amount of joint sealants and waterproof-          ensure the surface preparation and coating
ing elements required.                            applications were done in the factory with
    The team’s original steel coating con-        the requisite quality.



    Using steel framing and the ability to deliver the precast double tees by barge enabled the
➤




    use of 15-ft-wide panels and other long-span structural elements, resulting in larger parking
    bays as well as fewer columns and visual obstructions.




                                                                                                    Simon Design Engineering




 MODERN STEEL CONSTRUCTION november 2010
{                                                                                                                              }
      Toward Parking Automation
          With the advancements in materials handling and robotics
      made in recent years, providing each client with a customized,
      optimal solution to meet individual parking needs is no longer
      restricted to traditional solutions. Solutions to parking have
      advanced significantly over the decades, and that advancement
      is gaining momentum.
          Automated parking, often referred to as robotic parking, is
      here and carries with it a myriad of benefits. For example, with
      the absence of floors, an automated facility may be implemented
      under zoning code rules to avoid Floor Area Ratio (FAR) controls,
      which limit the size of buildings, even for above-grade facilities.
          Structural steel is the logical choice for automated parking
      structures. Structural members are small and compact, which
      increases the speed of construction, supports the elimination
      of concrete floors, and potentially eliminates the need for fire
      ratings. Automated parking is also environmentally friendly.
      The facilities provide small building and construction site foot-
      prints, fewer structural and foundation elements, negligible
      carbon footprints, low head heights that greatly reduce overall
      building heights, and the ability to use a variety of “green”
      façade options such as solar panels. All those benefits and
      every patron could have a wait time of just 60 seconds to
      retrieve his or her car. To learn more about automated parking,
      visit www.sde-us.com/docs/autoparking.htm.
                                                                                                   photos by Simon Design Engineering



Foundational Issues                                                     utility bridging, and allowed the box beams to be used as integral
    Speed of delivery was paramount. A full geotechnical explo-         elements in the structure’s steel moment frames, with large forces
ration and test pit program was set in motion immediately upon          transferred to the foundations. After the steel box beams were
contract initiation to support the fast-track construction of founda-   in place, they were color coded for future reference and safety,
tions, prior to design of the steel superstructure. The Port Author-    and ultimately concrete encased and backfilled. Pile caps were
ity originally had planned to relocate the existing on-site utilities   also used to bridge the primary utility feeders that lead directly
prior to commencing construction of the new steel and precast six-      to JFK and were redesigned as the utility feeder locations were
level parking structure; however, due to schedule constraints, the      uncovered during construction.
relocation of the utilities was released to the design-build team.
    Once construction began, it became apparent that the existing       Access Relocation
utilities could not be relocated in a timely manner and that the            Another noteworthy modification during construction was
project delivery schedule would be compromised. Even with con-          the decision by the owner and architect to relocate the primary
siderable preconstruction design coordination and efforts, many         pedestrian core from the outside perimeter of the structure, to
conflicts with existing underground utilities still needed mitiga-      the center of the interior. To accommodate this change numerous
tion. Ultimately, more than 50% of the original foundation plan         columns were retrofitted with cover plates or swapped out, more
design had to be modified or redesigned during construction.            than half of the foundations were redesigned, and transfer girders
    In real time, Simon Design worked with both the design              were added—all without consequence to the project’s fabrication
and construction teams to enable the pile-driving and over-             and construction schedule.
all construction operations to keep moving as the foundation                Although there were several hurdles throughout the Yellow
structural redesign was being done. By using BIM technology             Garage project, the revisions of the structural system saved 20%
in conjunction with the steel and precast manufacturers, Simon          of the overall project cost and reduced the construction schedule
Design was able to quickly and accurately lay out and design            by a year. The garage was completed in time for the opening of
the project’s foundations and superstructure in response to the         the T5 terminal. 
daily discoveries of additional existing utilities, with a resolu-      Architect, Civil and MEP Engineer
tion turnaround of 24 hours or less. The BIM model also aided           STV Inc., New York (AISC Member)
in the integration of the steel and precast systems, which greatly
                                                                        Structural Engineer
reduced the number of architectural component conflicts.
                                                                        Simon Design Engineering LLC, Wellesley, Mass. (AISC
    Existing electrical utility conflicts were bridged with shallow,
                                                                        Member)
heavy steel box beams, weighing up to a ton per ft, allowing the
utilities to remain in place and functioning throughout construc-       Steel Fabricator and Erector
tion. Structural steel’s inherent ability to provide a high degree of   The Berlin Steel Construction Company, Inc., Kensington,
torsional resistance made steel box beams the ideal solution for        Conn. (AISC Member)

                                                                                           november 2010 MODERN STEEL CONSTRUCTION

More Related Content

What's hot

IRJET-Pre-Engineered Building Design of an Industrial Warehouse
IRJET-Pre-Engineered Building Design of an Industrial WarehouseIRJET-Pre-Engineered Building Design of an Industrial Warehouse
IRJET-Pre-Engineered Building Design of an Industrial WarehouseIRJET Journal
 
Pre engineered metal buildings - the latest trend in building construction
Pre   engineered metal buildings - the latest trend in building constructionPre   engineered metal buildings - the latest trend in building construction
Pre engineered metal buildings - the latest trend in building constructionhlksd
 
IRJET- Comparison of Structural Elements of a Pre-Engineered Building in Two ...
IRJET- Comparison of Structural Elements of a Pre-Engineered Building in Two ...IRJET- Comparison of Structural Elements of a Pre-Engineered Building in Two ...
IRJET- Comparison of Structural Elements of a Pre-Engineered Building in Two ...IRJET Journal
 
Delta Steel Structures PEB Products and Accessories
Delta Steel Structures PEB Products and AccessoriesDelta Steel Structures PEB Products and Accessories
Delta Steel Structures PEB Products and AccessoriesDelta Steel Structures Pvt Ltd
 
Peb structures (1)
Peb structures (1)Peb structures (1)
Peb structures (1)hlksd
 
BM Assignment 1A
BM Assignment 1A BM Assignment 1A
BM Assignment 1A Sharon Chow
 
Civil pre engennerd structure
Civil pre engennerd structureCivil pre engennerd structure
Civil pre engennerd structureArpan Dixit
 
ABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeJill Reeves
 
Kbe parking structures
Kbe parking structuresKbe parking structures
Kbe parking structurescharkins
 
Pre Engineered buildings
Pre Engineered buildingsPre Engineered buildings
Pre Engineered buildingsYamini K
 
Advance section properties_for_students
Advance section properties_for_studentsAdvance section properties_for_students
Advance section properties_for_studentsChhay Teng
 
Low Density Cellular Concrete
Low Density Cellular ConcreteLow Density Cellular Concrete
Low Density Cellular ConcreteJill Reeves
 

What's hot (19)

IRJET-Pre-Engineered Building Design of an Industrial Warehouse
IRJET-Pre-Engineered Building Design of an Industrial WarehouseIRJET-Pre-Engineered Building Design of an Industrial Warehouse
IRJET-Pre-Engineered Building Design of an Industrial Warehouse
 
Pre engineered metal buildings - the latest trend in building construction
Pre   engineered metal buildings - the latest trend in building constructionPre   engineered metal buildings - the latest trend in building construction
Pre engineered metal buildings - the latest trend in building construction
 
IRJET- Comparison of Structural Elements of a Pre-Engineered Building in Two ...
IRJET- Comparison of Structural Elements of a Pre-Engineered Building in Two ...IRJET- Comparison of Structural Elements of a Pre-Engineered Building in Two ...
IRJET- Comparison of Structural Elements of a Pre-Engineered Building in Two ...
 
Pre Engineered Steel Buildings
Pre Engineered Steel BuildingsPre Engineered Steel Buildings
Pre Engineered Steel Buildings
 
Delta Steel Structures PEB Products and Accessories
Delta Steel Structures PEB Products and AccessoriesDelta Steel Structures PEB Products and Accessories
Delta Steel Structures PEB Products and Accessories
 
BPA Commercial
BPA CommercialBPA Commercial
BPA Commercial
 
Peb structures (1)
Peb structures (1)Peb structures (1)
Peb structures (1)
 
BM Assignment 1A
BM Assignment 1A BM Assignment 1A
BM Assignment 1A
 
Phillips Howard
Phillips HowardPhillips Howard
Phillips Howard
 
Civil pre engennerd structure
Civil pre engennerd structureCivil pre engennerd structure
Civil pre engennerd structure
 
Pre engineered building
Pre engineered buildingPre engineered building
Pre engineered building
 
ABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel Bridge
 
Peb
PebPeb
Peb
 
Kbe parking structures
Kbe parking structuresKbe parking structures
Kbe parking structures
 
Peb ss
Peb ssPeb ss
Peb ss
 
Pre Engineered buildings
Pre Engineered buildingsPre Engineered buildings
Pre Engineered buildings
 
Advance section properties_for_students
Advance section properties_for_studentsAdvance section properties_for_students
Advance section properties_for_students
 
Mpil pre engineered-building
Mpil pre engineered-buildingMpil pre engineered-building
Mpil pre engineered-building
 
Low Density Cellular Concrete
Low Density Cellular ConcreteLow Density Cellular Concrete
Low Density Cellular Concrete
 

Viewers also liked

Outspoken Communication
Outspoken CommunicationOutspoken Communication
Outspoken Communicationsecretariaatdebiz
 
Luums lighting 2013 biz oosterhout wsite 1
Luums lighting 2013 biz oosterhout wsite 1Luums lighting 2013 biz oosterhout wsite 1
Luums lighting 2013 biz oosterhout wsite 1secretariaatdebiz
 
Rijksdienst voor Ondernemend Nederland
Rijksdienst voor Ondernemend NederlandRijksdienst voor Ondernemend Nederland
Rijksdienst voor Ondernemend Nederlandsecretariaatdebiz
 
130418 internet en exporteer meer v2
130418 internet en exporteer meer v2130418 internet en exporteer meer v2
130418 internet en exporteer meer v2secretariaatdebiz
 
Ag nl presentatie - zakendoen met marokko
Ag nl   presentatie - zakendoen met marokkoAg nl   presentatie - zakendoen met marokko
Ag nl presentatie - zakendoen met marokkosecretariaatdebiz
 
Social media
Social mediaSocial media
Social mediashan678
 
130221 presentation de biz
130221 presentation de biz130221 presentation de biz
130221 presentation de bizsecretariaatdebiz
 
SIMON DESIGN ENGINEERING
SIMON DESIGN ENGINEERINGSIMON DESIGN ENGINEERING
SIMON DESIGN ENGINEERINGWilliam Wieners
 
Bmg presentatie de biz 18.06.2015
Bmg presentatie de biz 18.06.2015Bmg presentatie de biz 18.06.2015
Bmg presentatie de biz 18.06.2015secretariaatdebiz
 
Brigham green underground parking
Brigham green underground parkingBrigham green underground parking
Brigham green underground parkingWilliam Wieners
 
The History of HYBRID PARKING GARAGES
The History of HYBRID PARKING GARAGESThe History of HYBRID PARKING GARAGES
The History of HYBRID PARKING GARAGESWilliam Wieners
 

Viewers also liked (16)

2013 mazars
2013   mazars2013   mazars
2013 mazars
 
Outspoken Communication
Outspoken CommunicationOutspoken Communication
Outspoken Communication
 
Luums lighting 2013 biz oosterhout wsite 1
Luums lighting 2013 biz oosterhout wsite 1Luums lighting 2013 biz oosterhout wsite 1
Luums lighting 2013 biz oosterhout wsite 1
 
Rijksdienst voor Ondernemend Nederland
Rijksdienst voor Ondernemend NederlandRijksdienst voor Ondernemend Nederland
Rijksdienst voor Ondernemend Nederland
 
130418 internet en exporteer meer v2
130418 internet en exporteer meer v2130418 internet en exporteer meer v2
130418 internet en exporteer meer v2
 
Ag nl presentatie - zakendoen met marokko
Ag nl   presentatie - zakendoen met marokkoAg nl   presentatie - zakendoen met marokko
Ag nl presentatie - zakendoen met marokko
 
Get Your Tag
Get Your TagGet Your Tag
Get Your Tag
 
Social media
Social mediaSocial media
Social media
 
130221 presentation de biz
130221 presentation de biz130221 presentation de biz
130221 presentation de biz
 
Get Your Tag
Get Your TagGet Your Tag
Get Your Tag
 
Presentatie biz-v2 0
Presentatie biz-v2 0Presentatie biz-v2 0
Presentatie biz-v2 0
 
SIMON DESIGN ENGINEERING
SIMON DESIGN ENGINEERINGSIMON DESIGN ENGINEERING
SIMON DESIGN ENGINEERING
 
Bmg presentatie de biz 18.06.2015
Bmg presentatie de biz 18.06.2015Bmg presentatie de biz 18.06.2015
Bmg presentatie de biz 18.06.2015
 
Brigham green underground parking
Brigham green underground parkingBrigham green underground parking
Brigham green underground parking
 
The History of HYBRID PARKING GARAGES
The History of HYBRID PARKING GARAGESThe History of HYBRID PARKING GARAGES
The History of HYBRID PARKING GARAGES
 
Presentatie colombia
Presentatie colombiaPresentatie colombia
Presentatie colombia
 

Similar to Economy Parking at JFK Jet Blue Airways

White paper - Encapsulated Post Tensioned Concrete
White paper -  Encapsulated Post Tensioned ConcreteWhite paper -  Encapsulated Post Tensioned Concrete
White paper - Encapsulated Post Tensioned ConcreteAMSYSCO Inc.
 
Projects MeerkatII Copy
Projects MeerkatII CopyProjects MeerkatII Copy
Projects MeerkatII CopyDalubuhle Yengwa
 
Low cost houisng and alternate building materials
Low cost houisng and alternate building materialsLow cost houisng and alternate building materials
Low cost houisng and alternate building materialsNaresh Yadav
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Ramin Vaghei
 
City of orlando db colonial ped overpass technical
City of orlando db colonial ped overpass   technicalCity of orlando db colonial ped overpass   technical
City of orlando db colonial ped overpass technicalBrendan O'Connor
 
Structural E.I.T. Armen Miskarov
Structural E.I.T. Armen MiskarovStructural E.I.T. Armen Miskarov
Structural E.I.T. Armen MiskarovArmen Miskarov
 
fastrack technologies in bridges ppt
fastrack technologies in bridges pptfastrack technologies in bridges ppt
fastrack technologies in bridges pptSrinivasulu Srinu
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
Research Paper on Analysis and Design of Steel Truss by using Angle and Tube ...
Research Paper on Analysis and Design of Steel Truss by using Angle and Tube ...Research Paper on Analysis and Design of Steel Truss by using Angle and Tube ...
Research Paper on Analysis and Design of Steel Truss by using Angle and Tube ...IRJET Journal
 
Company Overview
Company OverviewCompany Overview
Company Overviewaitllc
 
Ilias Michalis PMV Workshop Dubai 2014
Ilias Michalis PMV Workshop Dubai 2014Ilias Michalis PMV Workshop Dubai 2014
Ilias Michalis PMV Workshop Dubai 2014ILIAS MICHALIS
 
Parking shade Project Brochure Final
Parking shade Project Brochure FinalParking shade Project Brochure Final
Parking shade Project Brochure FinalMohammed Ahmed
 
Senior Capstone Presentation
Senior Capstone PresentationSenior Capstone Presentation
Senior Capstone Presentationarsimmons
 
Jonathan Rose CV
Jonathan Rose CV Jonathan Rose CV
Jonathan Rose CV Jonny Rose
 
Comparative Study of Pre-Engineered Building and Conventional Steel Structures
Comparative Study of Pre-Engineered Building and Conventional Steel StructuresComparative Study of Pre-Engineered Building and Conventional Steel Structures
Comparative Study of Pre-Engineered Building and Conventional Steel StructuresIRJET Journal
 
Final Chassis Report 2010
Final Chassis Report 2010Final Chassis Report 2010
Final Chassis Report 2010Thomas Ayres
 
Civil Project structural engineering.pptx
Civil Project structural engineering.pptxCivil Project structural engineering.pptx
Civil Project structural engineering.pptxssuserbdc52c
 
CV_AKSHAY RAJPUT
CV_AKSHAY RAJPUTCV_AKSHAY RAJPUT
CV_AKSHAY RAJPUTAkshay Rajput
 
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...IRJET Journal
 

Similar to Economy Parking at JFK Jet Blue Airways (20)

White paper - Encapsulated Post Tensioned Concrete
White paper -  Encapsulated Post Tensioned ConcreteWhite paper -  Encapsulated Post Tensioned Concrete
White paper - Encapsulated Post Tensioned Concrete
 
Projects MeerkatII Copy
Projects MeerkatII CopyProjects MeerkatII Copy
Projects MeerkatII Copy
 
Low cost houisng and alternate building materials
Low cost houisng and alternate building materialsLow cost houisng and alternate building materials
Low cost houisng and alternate building materials
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...
 
City of orlando db colonial ped overpass technical
City of orlando db colonial ped overpass   technicalCity of orlando db colonial ped overpass   technical
City of orlando db colonial ped overpass technical
 
Structural E.I.T. Armen Miskarov
Structural E.I.T. Armen MiskarovStructural E.I.T. Armen Miskarov
Structural E.I.T. Armen Miskarov
 
fastrack technologies in bridges ppt
fastrack technologies in bridges pptfastrack technologies in bridges ppt
fastrack technologies in bridges ppt
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Research Paper on Analysis and Design of Steel Truss by using Angle and Tube ...
Research Paper on Analysis and Design of Steel Truss by using Angle and Tube ...Research Paper on Analysis and Design of Steel Truss by using Angle and Tube ...
Research Paper on Analysis and Design of Steel Truss by using Angle and Tube ...
 
Company Overview
Company OverviewCompany Overview
Company Overview
 
Ilias Michalis PMV Workshop Dubai 2014
Ilias Michalis PMV Workshop Dubai 2014Ilias Michalis PMV Workshop Dubai 2014
Ilias Michalis PMV Workshop Dubai 2014
 
Parking shade Project Brochure Final
Parking shade Project Brochure FinalParking shade Project Brochure Final
Parking shade Project Brochure Final
 
Senior Capstone Presentation
Senior Capstone PresentationSenior Capstone Presentation
Senior Capstone Presentation
 
Jonathan Rose CV
Jonathan Rose CV Jonathan Rose CV
Jonathan Rose CV
 
Comparative Study of Pre-Engineered Building and Conventional Steel Structures
Comparative Study of Pre-Engineered Building and Conventional Steel StructuresComparative Study of Pre-Engineered Building and Conventional Steel Structures
Comparative Study of Pre-Engineered Building and Conventional Steel Structures
 
Final Chassis Report 2010
Final Chassis Report 2010Final Chassis Report 2010
Final Chassis Report 2010
 
Company profile
Company profileCompany profile
Company profile
 
Civil Project structural engineering.pptx
Civil Project structural engineering.pptxCivil Project structural engineering.pptx
Civil Project structural engineering.pptx
 
CV_AKSHAY RAJPUT
CV_AKSHAY RAJPUTCV_AKSHAY RAJPUT
CV_AKSHAY RAJPUT
 
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...
 

Recently uploaded

Dynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management SoftwareDynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management SoftwareDynamic Netsoft
 
Prestige Somerville Whitefield Bangalore E- Brochure.pdf
Prestige Somerville Whitefield Bangalore E- Brochure.pdfPrestige Somerville Whitefield Bangalore E- Brochure.pdf
Prestige Somerville Whitefield Bangalore E- Brochure.pdffaheemali990101
 
Ebullient Investments Limited specializes in Building contractor
Ebullient Investments Limited specializes in Building contractorEbullient Investments Limited specializes in Building contractor
Ebullient Investments Limited specializes in Building contractorEbullient Investments Limited
 
What Is Biophilic Design .pdf
What Is Biophilic Design            .pdfWhat Is Biophilic Design            .pdf
What Is Biophilic Design .pdfyamunaNMH
 
Provident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdf
Provident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdfProvident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdf
Provident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdffaheemali990101
 
What-are-the-latest-modular-wardrobe-designs.pdf
What-are-the-latest-modular-wardrobe-designs.pdfWhat-are-the-latest-modular-wardrobe-designs.pdf
What-are-the-latest-modular-wardrobe-designs.pdfKams Designer Zone
 
Shapoorji Pallonji Vanaha GolfLand 2 | A Space For You To Find Your Space
Shapoorji Pallonji Vanaha GolfLand 2 | A Space For You To Find Your SpaceShapoorji Pallonji Vanaha GolfLand 2 | A Space For You To Find Your Space
Shapoorji Pallonji Vanaha GolfLand 2 | A Space For You To Find Your Spaceaidasheikh47
 
_Navigating Inflation's Influence on Commercial Real Estate (CRE) Investing I...
_Navigating Inflation's Influence on Commercial Real Estate (CRE) Investing I..._Navigating Inflation's Influence on Commercial Real Estate (CRE) Investing I...
_Navigating Inflation's Influence on Commercial Real Estate (CRE) Investing I...SyndicationPro, LLC
 
A Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdfA Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdfTim Wilmath
 
How to Navigate the Eviction Process in Pennsylvania: A Landlord's Guide
How to Navigate the Eviction Process in Pennsylvania: A Landlord's GuideHow to Navigate the Eviction Process in Pennsylvania: A Landlord's Guide
How to Navigate the Eviction Process in Pennsylvania: A Landlord's GuideezLandlordForms
 
The Role of Mortgage Brokers in Retirement Housing: Key Considerations
The Role of Mortgage Brokers in Retirement Housing: Key ConsiderationsThe Role of Mortgage Brokers in Retirement Housing: Key Considerations
The Role of Mortgage Brokers in Retirement Housing: Key Considerationssunlite Mortgage
 
MADHUGIRI FARM LAND BROCHURES (11)_compressed (1).pdf
MADHUGIRI FARM LAND BROCHURES (11)_compressed (1).pdfMADHUGIRI FARM LAND BROCHURES (11)_compressed (1).pdf
MADHUGIRI FARM LAND BROCHURES (11)_compressed (1).pdfknoxdigital1
 
Managed Farmland Brochures to get more in
Managed Farmland Brochures to get more inManaged Farmland Brochures to get more in
Managed Farmland Brochures to get more inknoxdigital1
 
Ajmera Prive at Juhu, Mumbai E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai  E-Brochure.pdfAjmera Prive at Juhu, Mumbai  E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai E-Brochure.pdfManishSaxena95
 
SVN Live 4.22.24 Weekly Property Broadcast
SVN Live 4.22.24 Weekly Property BroadcastSVN Live 4.22.24 Weekly Property Broadcast
SVN Live 4.22.24 Weekly Property BroadcastSVN International Corp.
 
Experion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdfExperion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdfkratirudram
 
DLF Plots Sriperumbudur in Chennai E Brochure Pdf
DLF Plots Sriperumbudur in Chennai E Brochure PdfDLF Plots Sriperumbudur in Chennai E Brochure Pdf
DLF Plots Sriperumbudur in Chennai E Brochure Pdfashiyadav24
 
Anandtara Iris Residences Mundhwa Pune Brochure.pdf
Anandtara Iris Residences Mundhwa Pune Brochure.pdfAnandtara Iris Residences Mundhwa Pune Brochure.pdf
Anandtara Iris Residences Mundhwa Pune Brochure.pdfabbu831446
 

Recently uploaded (20)

Dynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management SoftwareDynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management Software
 
Prestige Somerville Whitefield Bangalore E- Brochure.pdf
Prestige Somerville Whitefield Bangalore E- Brochure.pdfPrestige Somerville Whitefield Bangalore E- Brochure.pdf
Prestige Somerville Whitefield Bangalore E- Brochure.pdf
 
Call Girls in Mahavir Nagar whatsaap call US +919953056974
Call Girls in Mahavir Nagar  whatsaap call US  +919953056974Call Girls in Mahavir Nagar  whatsaap call US  +919953056974
Call Girls in Mahavir Nagar whatsaap call US +919953056974
 
Ebullient Investments Limited specializes in Building contractor
Ebullient Investments Limited specializes in Building contractorEbullient Investments Limited specializes in Building contractor
Ebullient Investments Limited specializes in Building contractor
 
Hot call girls in Moti Bagh🔝 9953056974 🔝 escort Service
Hot call girls in Moti Bagh🔝 9953056974 🔝 escort ServiceHot call girls in Moti Bagh🔝 9953056974 🔝 escort Service
Hot call girls in Moti Bagh🔝 9953056974 🔝 escort Service
 
What Is Biophilic Design .pdf
What Is Biophilic Design            .pdfWhat Is Biophilic Design            .pdf
What Is Biophilic Design .pdf
 
Provident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdf
Provident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdfProvident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdf
Provident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdf
 
What-are-the-latest-modular-wardrobe-designs.pdf
What-are-the-latest-modular-wardrobe-designs.pdfWhat-are-the-latest-modular-wardrobe-designs.pdf
What-are-the-latest-modular-wardrobe-designs.pdf
 
Shapoorji Pallonji Vanaha GolfLand 2 | A Space For You To Find Your Space
Shapoorji Pallonji Vanaha GolfLand 2 | A Space For You To Find Your SpaceShapoorji Pallonji Vanaha GolfLand 2 | A Space For You To Find Your Space
Shapoorji Pallonji Vanaha GolfLand 2 | A Space For You To Find Your Space
 
_Navigating Inflation's Influence on Commercial Real Estate (CRE) Investing I...
_Navigating Inflation's Influence on Commercial Real Estate (CRE) Investing I..._Navigating Inflation's Influence on Commercial Real Estate (CRE) Investing I...
_Navigating Inflation's Influence on Commercial Real Estate (CRE) Investing I...
 
A Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdfA Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdf
 
How to Navigate the Eviction Process in Pennsylvania: A Landlord's Guide
How to Navigate the Eviction Process in Pennsylvania: A Landlord's GuideHow to Navigate the Eviction Process in Pennsylvania: A Landlord's Guide
How to Navigate the Eviction Process in Pennsylvania: A Landlord's Guide
 
The Role of Mortgage Brokers in Retirement Housing: Key Considerations
The Role of Mortgage Brokers in Retirement Housing: Key ConsiderationsThe Role of Mortgage Brokers in Retirement Housing: Key Considerations
The Role of Mortgage Brokers in Retirement Housing: Key Considerations
 
MADHUGIRI FARM LAND BROCHURES (11)_compressed (1).pdf
MADHUGIRI FARM LAND BROCHURES (11)_compressed (1).pdfMADHUGIRI FARM LAND BROCHURES (11)_compressed (1).pdf
MADHUGIRI FARM LAND BROCHURES (11)_compressed (1).pdf
 
Managed Farmland Brochures to get more in
Managed Farmland Brochures to get more inManaged Farmland Brochures to get more in
Managed Farmland Brochures to get more in
 
Ajmera Prive at Juhu, Mumbai E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai  E-Brochure.pdfAjmera Prive at Juhu, Mumbai  E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai E-Brochure.pdf
 
SVN Live 4.22.24 Weekly Property Broadcast
SVN Live 4.22.24 Weekly Property BroadcastSVN Live 4.22.24 Weekly Property Broadcast
SVN Live 4.22.24 Weekly Property Broadcast
 
Experion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdfExperion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdf
 
DLF Plots Sriperumbudur in Chennai E Brochure Pdf
DLF Plots Sriperumbudur in Chennai E Brochure PdfDLF Plots Sriperumbudur in Chennai E Brochure Pdf
DLF Plots Sriperumbudur in Chennai E Brochure Pdf
 
Anandtara Iris Residences Mundhwa Pune Brochure.pdf
Anandtara Iris Residences Mundhwa Pune Brochure.pdfAnandtara Iris Residences Mundhwa Pune Brochure.pdf
Anandtara Iris Residences Mundhwa Pune Brochure.pdf
 

Economy Parking at JFK Jet Blue Airways

  • 1. Economy Parking By Alan H. Simon, P.E. Simon Design Engineering Bridging underground utilities and reducing future maintenance needs are just two of the benefits steel provided. F For years, there were discussions of replacing Eero Saarin- ing structure needed to reflect and compliment the aesthetic en’s aging Trans World Airlines Terminal at New York’s John nature of the surrounding area, including the new T5 expan- F. Kennedy International Airport. In 2007, those discussions sion and monorail system. Although the existing site utilities became a reality when JetBlue Airways chose JFK as its hub. were indicated in the bridging documents, it also was noted To support JetBlue’s new Terminal 5, (T5), expansion proxi- that the number, location, and types of utilities had not been mate parking for 1,500 vehicles was required. The so-called fully verified. This apparently innocuous note would later Yellow Garage had to be built in a limited timeframe that prove to impact the project in a significant way. corresponded with the opening of T5. The Port Authority of The Wellesley, Mass.-based structural engineering firm Simon New York and New Jersey (PANYNJ), in conjunction with Design Engineering, LLC, and The Berlin Steel Construction JetBlue Airways, compiled preliminary bridging documents Company, Inc., Kensington, Conn., were approached as a team and issued a Request for Proposals that was made available to by Peter Scalamandre & Sons, Inc., a local New York contrac- a select group of general contractors. tor with significant Port Authority experience. Although the The bridging documents established preferred points preliminary bridging documents were based on a fully precast of egress and desired car counts, and the general footprint concrete solution, they allowed for alternative structural systems. parameters based on a six-story, precast structure. Pedes- Scalamandre, the general contractor and lead on the design-build trian egress included elevator cores, enclosed stairwells, and team, believed that a steel solution would greatly benefit the Port connections to the existing AirTrain monorail system. A key Authority and JetBlue based on comparing the available solutions. criterion indicated in the documents was that the new park- Simon Design revised the precast structural system, footprint, and MODERN STEEL CONSTRUCTION november 2010
  • 2. Simon Design Engineering As part of constructing the new Terminal 5 at New York’s John The design-build team’s decision to use steel framing with long- ➤ ➤ F. Kennedy International Airport, the Port Authority of New York span precast spandrels resulted in an open parking structure and and New Jersey added a steel-framed new six-story parking reduced both the initial cost and maintenance requirements. structure for 1,500 cars. column grid with the assistance of Berlin Steel and Scalamandre in ered by barge to the construction site. The double tees were fur- response to the RFP and bridging documents. nished by Bayshore Concrete Products Corp. of Virginia, which The design-build team’s structural steel beam and column also recently had provided the AirTrain monorail system’s seg- solution with a precast concrete decking system was ultimately mental, precast concrete elements to the Port Authority at JFK. the preferred design solution, making the Yellow Garage the first The ability to use 15-ft double tees and other long-span pre- PANYNJ design-build garage project using this approach. The final design incorporated precast spandrels, steel railings, and steel mesh, reflecting the surrounding structures while meeting the building code requirements as an open parking structure, which Alan H. Simon, P.E., is presi- had several benefits. As an open parking structure the use of struc- dent of Simon Design Engi- tural steel, devoid of supplemental fireproofing, allowed for open neering, LLC. Highly regarded stairwells as a means of egress. It also permitted the use of exposed for his perceptive and innova- fire suppression standpipes and eliminated the need for sprinklers tive approach, he has dedicated (no sprinklering). In addition, the Port Authority realized the ben- his career to the advancement efits of steel construction, including the initial economical costs of structured parking to benefit and the minimal maintenance requirements, among others. every client, each community, The final design approach used 15-ft-wide precast concrete and the environment. double tee floor slabs, manufactured off site, that were deliv- november 2010 MODERN STEEL CONSTRUCTION
  • 3. { manufactured structural elements, which cept called for the use of hot-dipped gal- are traditionally considered too large to vanized steel, which is economical and has be transported on roadways, provided the demonstrated longevity and significant Port Authority and JetBlue with a host durability with little to no maintenance of inherent benefits. Using steel framing required in the first 50 years of a structure’s and wider floor units allowed for longer life. However, the Port Authority’s own spans, large parking bays and stalls, fewer design standards for steel required a three- columns and visual obstructions (ideal coat paint system to provide a less indus- for patron safety and utility conflicts). trial finish and appearance. As a result, all It also considerably reduced the number steel beams and columns were blast cleaned of deep foundations and foundation ele- to an SP6 standard, and a stringent qual- ments, overall construction time, and the ity assurance program was implemented to amount of joint sealants and waterproof- ensure the surface preparation and coating ing elements required. applications were done in the factory with The team’s original steel coating con- the requisite quality. Using steel framing and the ability to deliver the precast double tees by barge enabled the ➤ use of 15-ft-wide panels and other long-span structural elements, resulting in larger parking bays as well as fewer columns and visual obstructions. Simon Design Engineering MODERN STEEL CONSTRUCTION november 2010
  • 4. { } Toward Parking Automation With the advancements in materials handling and robotics made in recent years, providing each client with a customized, optimal solution to meet individual parking needs is no longer restricted to traditional solutions. Solutions to parking have advanced significantly over the decades, and that advancement is gaining momentum. Automated parking, often referred to as robotic parking, is here and carries with it a myriad of benefits. For example, with the absence of floors, an automated facility may be implemented under zoning code rules to avoid Floor Area Ratio (FAR) controls, which limit the size of buildings, even for above-grade facilities. Structural steel is the logical choice for automated parking structures. Structural members are small and compact, which increases the speed of construction, supports the elimination of concrete floors, and potentially eliminates the need for fire ratings. Automated parking is also environmentally friendly. The facilities provide small building and construction site foot- prints, fewer structural and foundation elements, negligible carbon footprints, low head heights that greatly reduce overall building heights, and the ability to use a variety of “green” façade options such as solar panels. All those benefits and every patron could have a wait time of just 60 seconds to retrieve his or her car. To learn more about automated parking, visit www.sde-us.com/docs/autoparking.htm. photos by Simon Design Engineering Foundational Issues utility bridging, and allowed the box beams to be used as integral Speed of delivery was paramount. A full geotechnical explo- elements in the structure’s steel moment frames, with large forces ration and test pit program was set in motion immediately upon transferred to the foundations. After the steel box beams were contract initiation to support the fast-track construction of founda- in place, they were color coded for future reference and safety, tions, prior to design of the steel superstructure. The Port Author- and ultimately concrete encased and backfilled. Pile caps were ity originally had planned to relocate the existing on-site utilities also used to bridge the primary utility feeders that lead directly prior to commencing construction of the new steel and precast six- to JFK and were redesigned as the utility feeder locations were level parking structure; however, due to schedule constraints, the uncovered during construction. relocation of the utilities was released to the design-build team. Once construction began, it became apparent that the existing Access Relocation utilities could not be relocated in a timely manner and that the Another noteworthy modification during construction was project delivery schedule would be compromised. Even with con- the decision by the owner and architect to relocate the primary siderable preconstruction design coordination and efforts, many pedestrian core from the outside perimeter of the structure, to conflicts with existing underground utilities still needed mitiga- the center of the interior. To accommodate this change numerous tion. Ultimately, more than 50% of the original foundation plan columns were retrofitted with cover plates or swapped out, more design had to be modified or redesigned during construction. than half of the foundations were redesigned, and transfer girders In real time, Simon Design worked with both the design were added—all without consequence to the project’s fabrication and construction teams to enable the pile-driving and over- and construction schedule. all construction operations to keep moving as the foundation Although there were several hurdles throughout the Yellow structural redesign was being done. By using BIM technology Garage project, the revisions of the structural system saved 20% in conjunction with the steel and precast manufacturers, Simon of the overall project cost and reduced the construction schedule Design was able to quickly and accurately lay out and design by a year. The garage was completed in time for the opening of the project’s foundations and superstructure in response to the the T5 terminal. daily discoveries of additional existing utilities, with a resolu- Architect, Civil and MEP Engineer tion turnaround of 24 hours or less. The BIM model also aided STV Inc., New York (AISC Member) in the integration of the steel and precast systems, which greatly Structural Engineer reduced the number of architectural component conflicts. Simon Design Engineering LLC, Wellesley, Mass. (AISC Existing electrical utility conflicts were bridged with shallow, Member) heavy steel box beams, weighing up to a ton per ft, allowing the utilities to remain in place and functioning throughout construc- Steel Fabricator and Erector tion. Structural steel’s inherent ability to provide a high degree of The Berlin Steel Construction Company, Inc., Kensington, torsional resistance made steel box beams the ideal solution for Conn. (AISC Member) november 2010 MODERN STEEL CONSTRUCTION