2. MILESTONE PROJECT (Status up to April 2015)
MILESTONE Target Unit #1 Target Unit #2 Status Remark
Site Development (Cut & Fill) May 2015 May 2015 Site Preparation
Commencement Of Date May 2015 May 2015 EPC Power Plant
First Piling July 2015 July 2015 EPC Power Plant
Boiler on Site Dec 2015 Januari 2016 EPC Power Plant
Boiler Steam Drum Lifting February 2016 April 2016 EPC Power Plant
Turbine Generator On site February 2016 April 2016 EPC Power Plant
Transmision Line & Substation ready
operation
September 2016 September 2016 Substation 150 KV &
Transmission (15km)
Back Feeding September 2016 September 2016 EPC Power Plant
Control Room Fully Operation October 2016 October 2016 EPC Power Plant
Demin Water Production October 2016 Nov 2016 EPC Power Plant
Hydrotest Boiler October 2016 Dec 2017 EPC Power Plant
Coal handling System Ready January 2016 February 2017 EPC Power Plant
First Firing Boiler Februari 2017 April 2017 EPC Power Plant
Steam Blow March 2017 May 2017 EPC Power Plant
First Synchrone
April 2017 June 2017 EPC Power Plant
RR
April 2017 June 2017 EPC Power Plant
PT
May 2017 July 2017 EPC Power Plant
COD
May 2017 July 2017 EPC Power Plant
4. 2015 2016 2017
Ma
y
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Ma
y
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Ma
y
Jun jUL
M0 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26
Schedule Equipment On Site
Boiler Steel Structure On site (Oct’15)
Boiler Unit 1 On site (Dec’15)
Boiler Unit 2 On site (Jan’16)
Turbine & Generator foundation bolts, plates,
Steel Structure unit 1 & 2 On site (Dec’15)
Turbine Generator unit 1 On Site (Feb’16)
Turbine Generator unit 2 On site (Apr’16)
Batch 1
Batch 2
Batch 3
Batch 4
Batch 6
Batch 5
On Site Batch 4 :
1. Coal crusher
2. Draft Fan(Induced draft fan,primary air
fan,secondary air fan)
3. Electrostatic precipitator
4. Coal feeder
5. Feed pump
6. High pressure heater
7. Deaerator
8. Transformers
9. Circulation-water pump
10. Condensate pump
11. Overhead crane Turbine house
On Site Batch 5 :
1. Coal handling system
2. Mechanical cooling tower
3. Coal Unloader
4. Seawater desalination Plant
5. Chemical water treatment system
6. Vacuum pump
7. Ash handling system
8. Slag removal system
9. HP feed-water/steam pipe
10. Hoisting Equipments
11. DC system
12. Electrical protection system
13. 6kV switch cabinet
14. 6kV switch cabinet delivery
15. PC&MCC cabinet
16. HP&LP electrical panel cabinets
17. Medium pressure and low pressure pipe (in
batches)
18. Valves (in batches)
19. Cable & Cable tray
On Site Batch 6 :
1. Air compressor
2. Turbine bypass
3. Rubber ball cleaning device
4. DCS system
5. HP fluidization fan
6. Heating Ventilation Air Conditioning
7. Continuous Emission Monitoring
System
8. Fuel oil pump house equipments 3.
Communication
9. Emergency diesel generator
10. Thermal control system
11. Plant & Demestic sewag treatment
device
12. Hydraulic fire system
Batch 7
On Site Batch 7
1. Fire alarm system
2. Chemical laboratory equipment
3. Thermal instrusments
4. Motorized valve of CW system
5. CONSTRUCTION ACTIVITIES
I. Current Month Activities
1. Pekerjaan EPC Project PLTU 2x25 MW
a. Soil Investigation (Soil test)
•CHEC telah Memulai Pekerjaan Soil Test pada tanggal 26 Februari 2015.
b. Pekerjaan Temporary Facility dan Batching Plant
•Persiapan Pengiriman dan Install
2. Pekerjaan EPC Project 150KV Substation and Transmission Line (15KM)
a.Land Acquisition (Pembebasan Lahan) :
Proses pembebasan lahan Transmisi Line (15KM) bekerja sama dengan PT PLN UIP XIII dan Pemda Mamuju,
target total penyelesaian pembebasan lahan pada bulan Juli 2015.
b. Target Ready to Supply : September 2016
Area Jumlah Rencana titik Soil Test Jumlah Aktual titik Soil Test Keterangan
BTG & Chimney 43 43 Done
BOP 24 11
Oil Tank 5 1
Coal Yard 28 23
Building 12 12 Done
Jetty 22 22 Done
Ash Yard 9 9 Done