SlideShare a Scribd company logo
1 of 12
PROJECT PROGRESS
MAMUJU COAL FIRED STEAM POWER PLANT
2x25 MW
MILESTONE PROJECT (Status up to April 2015)
MILESTONE Target Unit #1 Target Unit #2 Status Remark
Site Development (Cut & Fill) May 2015 May 2015 Site Preparation
Commencement Of Date May 2015 May 2015 EPC Power Plant
First Piling July 2015 July 2015 EPC Power Plant
Boiler on Site Dec 2015 Januari 2016 EPC Power Plant
Boiler Steam Drum Lifting February 2016 April 2016 EPC Power Plant
Turbine Generator On site February 2016 April 2016 EPC Power Plant
Transmision Line & Substation ready
operation
September 2016 September 2016 Substation 150 KV &
Transmission (15km)
Back Feeding September 2016 September 2016 EPC Power Plant
Control Room Fully Operation October 2016 October 2016 EPC Power Plant
Demin Water Production October 2016 Nov 2016 EPC Power Plant
Hydrotest Boiler October 2016 Dec 2017 EPC Power Plant
Coal handling System Ready January 2016 February 2017 EPC Power Plant
First Firing Boiler Februari 2017 April 2017 EPC Power Plant
Steam Blow March 2017 May 2017 EPC Power Plant
First Synchrone
April 2017 June 2017 EPC Power Plant
RR
April 2017 June 2017 EPC Power Plant
PT
May 2017 July 2017 EPC Power Plant
COD
May 2017 July 2017 EPC Power Plant
ENGINEERING ACTIVITIES
Status 29 April 2015 (Before Consinyering Meting)
Status 11 Mei 2015 (after Consinyering Meeting)
2015 2016 2017
Ma
y
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Ma
y
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Ma
y
Jun jUL
M0 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26
Schedule Equipment On Site
Boiler Steel Structure On site (Oct’15)
Boiler Unit 1 On site (Dec’15)
Boiler Unit 2 On site (Jan’16)
Turbine & Generator foundation bolts, plates,
Steel Structure unit 1 & 2 On site (Dec’15)
Turbine Generator unit 1 On Site (Feb’16)
Turbine Generator unit 2 On site (Apr’16)
Batch 1
Batch 2
Batch 3
Batch 4
Batch 6
Batch 5
On Site Batch 4 :
1. Coal crusher
2. Draft Fan(Induced draft fan,primary air
fan,secondary air fan)
3. Electrostatic precipitator
4. Coal feeder
5. Feed pump
6. High pressure heater
7. Deaerator
8. Transformers
9. Circulation-water pump
10. Condensate pump
11. Overhead crane Turbine house
On Site Batch 5 :
1. Coal handling system
2. Mechanical cooling tower
3. Coal Unloader
4. Seawater desalination Plant
5. Chemical water treatment system
6. Vacuum pump
7. Ash handling system
8. Slag removal system
9. HP feed-water/steam pipe
10. Hoisting Equipments
11. DC system
12. Electrical protection system
13. 6kV switch cabinet
14. 6kV switch cabinet delivery
15. PC&MCC cabinet
16. HP&LP electrical panel cabinets
17. Medium pressure and low pressure pipe (in
batches)
18. Valves (in batches)
19. Cable & Cable tray
On Site Batch 6 :
1. Air compressor
2. Turbine bypass
3. Rubber ball cleaning device
4. DCS system
5. HP fluidization fan
6. Heating Ventilation Air Conditioning
7. Continuous Emission Monitoring
System
8. Fuel oil pump house equipments 3.
Communication
9. Emergency diesel generator
10. Thermal control system
11. Plant & Demestic sewag treatment
device
12. Hydraulic fire system
Batch 7
On Site Batch 7
1. Fire alarm system
2. Chemical laboratory equipment
3. Thermal instrusments
4. Motorized valve of CW system
CONSTRUCTION ACTIVITIES
I. Current Month Activities
1. Pekerjaan EPC Project PLTU 2x25 MW
a. Soil Investigation (Soil test)
•CHEC telah Memulai Pekerjaan Soil Test pada tanggal 26 Februari 2015.
b. Pekerjaan Temporary Facility dan Batching Plant
•Persiapan Pengiriman dan Install
2. Pekerjaan EPC Project 150KV Substation and Transmission Line (15KM)
a.Land Acquisition (Pembebasan Lahan) :
Proses pembebasan lahan Transmisi Line (15KM) bekerja sama dengan PT PLN UIP XIII dan Pemda Mamuju,
target total penyelesaian pembebasan lahan pada bulan Juli 2015.
b. Target Ready to Supply : September 2016
Area Jumlah Rencana titik Soil Test Jumlah Aktual titik Soil Test Keterangan
BTG & Chimney 43 43 Done
BOP 24 11
Oil Tank 5 1
Coal Yard 28 23
Building 12 12 Done
Jetty 22 22 Done
Ash Yard 9 9 Done
PHOTOS PROJECT
PHOTOS PROJECT
PHOTOS PROJECT
PHOTOS PROJECT
PHOTOS PROJECT
PHOTOS PROJECT
PHOTOS PROJECT

More Related Content

What's hot

Fuel Test Facility 2005[1]
Fuel Test Facility 2005[1]Fuel Test Facility 2005[1]
Fuel Test Facility 2005[1]MichaelVentre
 
Gas turbine advisors review of a 9 e.03 ccgt power plant
Gas turbine advisors review of a 9 e.03 ccgt power plant Gas turbine advisors review of a 9 e.03 ccgt power plant
Gas turbine advisors review of a 9 e.03 ccgt power plant Gasturbineconsultants
 
Lakeshore Center Heat Pump Study
Lakeshore Center Heat Pump Study Lakeshore Center Heat Pump Study
Lakeshore Center Heat Pump Study Daanish Tyrewala
 
Tkaczmarzyk git rebase_over_3_commits_ago
Tkaczmarzyk git rebase_over_3_commits_agoTkaczmarzyk git rebase_over_3_commits_ago
Tkaczmarzyk git rebase_over_3_commits_agoTomasz Kaczmarzyk
 
Bicycle sharing demand analysis using R
Bicycle sharing demand analysis using RBicycle sharing demand analysis using R
Bicycle sharing demand analysis using REvelyn Zoubi
 
Parametric Optimization of Solar Parabolic Collectors Using AHP-TOPSIS
Parametric Optimization of Solar Parabolic Collectors Using AHP-TOPSISParametric Optimization of Solar Parabolic Collectors Using AHP-TOPSIS
Parametric Optimization of Solar Parabolic Collectors Using AHP-TOPSISIRJET Journal
 
ongc project ppt
ongc project pptongc project ppt
ongc project pptAditya Oak
 
2nd law of thermodynamics
 2nd law of thermodynamics 2nd law of thermodynamics
2nd law of thermodynamicsGM Red
 
Me6301 engineering thermodynamics uq - nov dec 2014
Me6301 engineering thermodynamics   uq - nov dec 2014Me6301 engineering thermodynamics   uq - nov dec 2014
Me6301 engineering thermodynamics uq - nov dec 2014BIBIN CHIDAMBARANATHAN
 
Cogeneration project opportunity
Cogeneration project opportunityCogeneration project opportunity
Cogeneration project opportunityKittipass Wasinarom
 
Success Story (1) World Largest Urea and NH3 plant
Success Story (1) World Largest Urea and NH3 plantSuccess Story (1) World Largest Urea and NH3 plant
Success Story (1) World Largest Urea and NH3 plantSang Wai
 
Engineering Thermodynamics-second law of thermodynamics
Engineering Thermodynamics-second law of thermodynamics Engineering Thermodynamics-second law of thermodynamics
Engineering Thermodynamics-second law of thermodynamics Mani Vannan M
 
Toledo lo nuevo en Gxserver
Toledo lo nuevo en GxserverToledo lo nuevo en Gxserver
Toledo lo nuevo en GxserverGeneXus
 
Met council Environmental Services - overview of wastewater treatment
Met council Environmental Services - overview of wastewater treatment Met council Environmental Services - overview of wastewater treatment
Met council Environmental Services - overview of wastewater treatment Amanda Bilek
 

What's hot (19)

Sunoryx sizing tool
Sunoryx sizing toolSunoryx sizing tool
Sunoryx sizing tool
 
Fuel Test Facility 2005[1]
Fuel Test Facility 2005[1]Fuel Test Facility 2005[1]
Fuel Test Facility 2005[1]
 
Gas turbine advisors review of a 9 e.03 ccgt power plant
Gas turbine advisors review of a 9 e.03 ccgt power plant Gas turbine advisors review of a 9 e.03 ccgt power plant
Gas turbine advisors review of a 9 e.03 ccgt power plant
 
Lakeshore Center Heat Pump Study
Lakeshore Center Heat Pump Study Lakeshore Center Heat Pump Study
Lakeshore Center Heat Pump Study
 
Tkaczmarzyk git rebase_over_3_commits_ago
Tkaczmarzyk git rebase_over_3_commits_agoTkaczmarzyk git rebase_over_3_commits_ago
Tkaczmarzyk git rebase_over_3_commits_ago
 
Heat engine
Heat engineHeat engine
Heat engine
 
Bicycle sharing demand analysis using R
Bicycle sharing demand analysis using RBicycle sharing demand analysis using R
Bicycle sharing demand analysis using R
 
Parametric Optimization of Solar Parabolic Collectors Using AHP-TOPSIS
Parametric Optimization of Solar Parabolic Collectors Using AHP-TOPSISParametric Optimization of Solar Parabolic Collectors Using AHP-TOPSIS
Parametric Optimization of Solar Parabolic Collectors Using AHP-TOPSIS
 
ongc project ppt
ongc project pptongc project ppt
ongc project ppt
 
2nd law of thermodynamics
 2nd law of thermodynamics 2nd law of thermodynamics
2nd law of thermodynamics
 
Me6301 engineering thermodynamics uq - nov dec 2014
Me6301 engineering thermodynamics   uq - nov dec 2014Me6301 engineering thermodynamics   uq - nov dec 2014
Me6301 engineering thermodynamics uq - nov dec 2014
 
Cogeneration project opportunity
Cogeneration project opportunityCogeneration project opportunity
Cogeneration project opportunity
 
Success Story (1) World Largest Urea and NH3 plant
Success Story (1) World Largest Urea and NH3 plantSuccess Story (1) World Largest Urea and NH3 plant
Success Story (1) World Largest Urea and NH3 plant
 
Engineering Thermodynamics-second law of thermodynamics
Engineering Thermodynamics-second law of thermodynamics Engineering Thermodynamics-second law of thermodynamics
Engineering Thermodynamics-second law of thermodynamics
 
Chapter 4 second law
Chapter 4  second lawChapter 4  second law
Chapter 4 second law
 
LINK
LINKLINK
LINK
 
Toledo lo nuevo en Gxserver
Toledo lo nuevo en GxserverToledo lo nuevo en Gxserver
Toledo lo nuevo en Gxserver
 
Met council Environmental Services - overview of wastewater treatment
Met council Environmental Services - overview of wastewater treatment Met council Environmental Services - overview of wastewater treatment
Met council Environmental Services - overview of wastewater treatment
 
Big Data: WEATHER DATA ANALYSIS
Big Data: WEATHER DATA ANALYSISBig Data: WEATHER DATA ANALYSIS
Big Data: WEATHER DATA ANALYSIS
 

Viewers also liked

Viewers also liked (7)

Boiler PLTU
Boiler PLTUBoiler PLTU
Boiler PLTU
 
PLTU CTI BINTAN
PLTU CTI BINTANPLTU CTI BINTAN
PLTU CTI BINTAN
 
ppt Turbin Uap
ppt Turbin Uapppt Turbin Uap
ppt Turbin Uap
 
Pembangkit Listrik Tenaga Uap (PLTU)
Pembangkit Listrik Tenaga Uap (PLTU)Pembangkit Listrik Tenaga Uap (PLTU)
Pembangkit Listrik Tenaga Uap (PLTU)
 
Turbin uap
Turbin uapTurbin uap
Turbin uap
 
06 procedure of start up boiler ok
06 procedure of start up boiler ok06 procedure of start up boiler ok
06 procedure of start up boiler ok
 
Pembangkit listrik tenaga uap
Pembangkit listrik tenaga uapPembangkit listrik tenaga uap
Pembangkit listrik tenaga uap
 

Similar to Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia

PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...Mumin HACIMUSALAR
 
Generation of electricity_from_coal_&_dts
Generation of electricity_from_coal_&_dtsGeneration of electricity_from_coal_&_dts
Generation of electricity_from_coal_&_dtsKamal Kaushik
 
Themal power plant NTPC
Themal power plant NTPCThemal power plant NTPC
Themal power plant NTPCRahul Kurapati
 
Indian scenario of super critical power plants issues and challenges by ntpc...
Indian scenario of super critical power plants  issues and challenges by ntpc...Indian scenario of super critical power plants  issues and challenges by ntpc...
Indian scenario of super critical power plants issues and challenges by ntpc...Ajay Singhal
 
50 Mwe Concentrated Solar Power Plant (1)
50 Mwe Concentrated Solar Power Plant (1)50 Mwe Concentrated Solar Power Plant (1)
50 Mwe Concentrated Solar Power Plant (1)VICTOR MANICKAM
 
Modification of Coal Handling System in Boiler Power Plant
Modification of Coal Handling System in Boiler Power PlantModification of Coal Handling System in Boiler Power Plant
Modification of Coal Handling System in Boiler Power Plantpaperpublications3
 
Vivek ntpc final report
Vivek ntpc final reportVivek ntpc final report
Vivek ntpc final reportVivekSingh1739
 
Study of corrosion and erosion in boilers
Study of corrosion and erosion in boilersStudy of corrosion and erosion in boilers
Study of corrosion and erosion in boilersSajeed Mahaboob
 
Super thermal power plant,suratgarh
Super thermal power plant,suratgarhSuper thermal power plant,suratgarh
Super thermal power plant,suratgarhRajesh Nayak
 
Ntpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharmaNtpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharmaPrakash Sharma
 
InternshipReport.pdf fffffffffffffffffffff
InternshipReport.pdf fffffffffffffffffffffInternshipReport.pdf fffffffffffffffffffff
InternshipReport.pdf fffffffffffffffffffffthewebseries17th
 
DVC MTPS INSTRUMENTATION PROJECT REPORT
DVC MTPS INSTRUMENTATION PROJECT REPORTDVC MTPS INSTRUMENTATION PROJECT REPORT
DVC MTPS INSTRUMENTATION PROJECT REPORTUpamanyu Ray
 
thermal power plant - GNDTP Bathinda
thermal power plant - GNDTP Bathindathermal power plant - GNDTP Bathinda
thermal power plant - GNDTP BathindaSatyam Oswal
 
A seminar report on stps by ashok khoja
A seminar report on stps by ashok khojaA seminar report on stps by ashok khoja
A seminar report on stps by ashok khojaASHOK KHOJA
 
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Crosstown TO
 

Similar to Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia (20)

PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
 
Generation of electricity_from_coal_&_dts
Generation of electricity_from_coal_&_dtsGeneration of electricity_from_coal_&_dts
Generation of electricity_from_coal_&_dts
 
Themal power plant NTPC
Themal power plant NTPCThemal power plant NTPC
Themal power plant NTPC
 
AML-8
AML-8AML-8
AML-8
 
Indian scenario of super critical power plants issues and challenges by ntpc...
Indian scenario of super critical power plants  issues and challenges by ntpc...Indian scenario of super critical power plants  issues and challenges by ntpc...
Indian scenario of super critical power plants issues and challenges by ntpc...
 
50 Mwe Concentrated Solar Power Plant (1)
50 Mwe Concentrated Solar Power Plant (1)50 Mwe Concentrated Solar Power Plant (1)
50 Mwe Concentrated Solar Power Plant (1)
 
Modification of Coal Handling System in Boiler Power Plant
Modification of Coal Handling System in Boiler Power PlantModification of Coal Handling System in Boiler Power Plant
Modification of Coal Handling System in Boiler Power Plant
 
Vivek ntpc final report
Vivek ntpc final reportVivek ntpc final report
Vivek ntpc final report
 
Study of corrosion and erosion in boilers
Study of corrosion and erosion in boilersStudy of corrosion and erosion in boilers
Study of corrosion and erosion in boilers
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
PTPS
PTPSPTPS
PTPS
 
Super thermal power plant,suratgarh
Super thermal power plant,suratgarhSuper thermal power plant,suratgarh
Super thermal power plant,suratgarh
 
Ntpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharmaNtpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharma
 
InternshipReport.pdf fffffffffffffffffffff
InternshipReport.pdf fffffffffffffffffffffInternshipReport.pdf fffffffffffffffffffff
InternshipReport.pdf fffffffffffffffffffff
 
NTPC
NTPCNTPC
NTPC
 
DVC MTPS INSTRUMENTATION PROJECT REPORT
DVC MTPS INSTRUMENTATION PROJECT REPORTDVC MTPS INSTRUMENTATION PROJECT REPORT
DVC MTPS INSTRUMENTATION PROJECT REPORT
 
project -2
project -2project -2
project -2
 
thermal power plant - GNDTP Bathinda
thermal power plant - GNDTP Bathindathermal power plant - GNDTP Bathinda
thermal power plant - GNDTP Bathinda
 
A seminar report on stps by ashok khoja
A seminar report on stps by ashok khojaA seminar report on stps by ashok khoja
A seminar report on stps by ashok khoja
 
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018
 

Data Project PLTU 2x25 MW Mamuju -West Sulawesi - Indonesia

  • 1. PROJECT PROGRESS MAMUJU COAL FIRED STEAM POWER PLANT 2x25 MW
  • 2. MILESTONE PROJECT (Status up to April 2015) MILESTONE Target Unit #1 Target Unit #2 Status Remark Site Development (Cut & Fill) May 2015 May 2015 Site Preparation Commencement Of Date May 2015 May 2015 EPC Power Plant First Piling July 2015 July 2015 EPC Power Plant Boiler on Site Dec 2015 Januari 2016 EPC Power Plant Boiler Steam Drum Lifting February 2016 April 2016 EPC Power Plant Turbine Generator On site February 2016 April 2016 EPC Power Plant Transmision Line & Substation ready operation September 2016 September 2016 Substation 150 KV & Transmission (15km) Back Feeding September 2016 September 2016 EPC Power Plant Control Room Fully Operation October 2016 October 2016 EPC Power Plant Demin Water Production October 2016 Nov 2016 EPC Power Plant Hydrotest Boiler October 2016 Dec 2017 EPC Power Plant Coal handling System Ready January 2016 February 2017 EPC Power Plant First Firing Boiler Februari 2017 April 2017 EPC Power Plant Steam Blow March 2017 May 2017 EPC Power Plant First Synchrone April 2017 June 2017 EPC Power Plant RR April 2017 June 2017 EPC Power Plant PT May 2017 July 2017 EPC Power Plant COD May 2017 July 2017 EPC Power Plant
  • 3. ENGINEERING ACTIVITIES Status 29 April 2015 (Before Consinyering Meting) Status 11 Mei 2015 (after Consinyering Meeting)
  • 4. 2015 2016 2017 Ma y Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Ma y Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Ma y Jun jUL M0 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 Schedule Equipment On Site Boiler Steel Structure On site (Oct’15) Boiler Unit 1 On site (Dec’15) Boiler Unit 2 On site (Jan’16) Turbine & Generator foundation bolts, plates, Steel Structure unit 1 & 2 On site (Dec’15) Turbine Generator unit 1 On Site (Feb’16) Turbine Generator unit 2 On site (Apr’16) Batch 1 Batch 2 Batch 3 Batch 4 Batch 6 Batch 5 On Site Batch 4 : 1. Coal crusher 2. Draft Fan(Induced draft fan,primary air fan,secondary air fan) 3. Electrostatic precipitator 4. Coal feeder 5. Feed pump 6. High pressure heater 7. Deaerator 8. Transformers 9. Circulation-water pump 10. Condensate pump 11. Overhead crane Turbine house On Site Batch 5 : 1. Coal handling system 2. Mechanical cooling tower 3. Coal Unloader 4. Seawater desalination Plant 5. Chemical water treatment system 6. Vacuum pump 7. Ash handling system 8. Slag removal system 9. HP feed-water/steam pipe 10. Hoisting Equipments 11. DC system 12. Electrical protection system 13. 6kV switch cabinet 14. 6kV switch cabinet delivery 15. PC&MCC cabinet 16. HP&LP electrical panel cabinets 17. Medium pressure and low pressure pipe (in batches) 18. Valves (in batches) 19. Cable & Cable tray On Site Batch 6 : 1. Air compressor 2. Turbine bypass 3. Rubber ball cleaning device 4. DCS system 5. HP fluidization fan 6. Heating Ventilation Air Conditioning 7. Continuous Emission Monitoring System 8. Fuel oil pump house equipments 3. Communication 9. Emergency diesel generator 10. Thermal control system 11. Plant & Demestic sewag treatment device 12. Hydraulic fire system Batch 7 On Site Batch 7 1. Fire alarm system 2. Chemical laboratory equipment 3. Thermal instrusments 4. Motorized valve of CW system
  • 5. CONSTRUCTION ACTIVITIES I. Current Month Activities 1. Pekerjaan EPC Project PLTU 2x25 MW a. Soil Investigation (Soil test) •CHEC telah Memulai Pekerjaan Soil Test pada tanggal 26 Februari 2015. b. Pekerjaan Temporary Facility dan Batching Plant •Persiapan Pengiriman dan Install 2. Pekerjaan EPC Project 150KV Substation and Transmission Line (15KM) a.Land Acquisition (Pembebasan Lahan) : Proses pembebasan lahan Transmisi Line (15KM) bekerja sama dengan PT PLN UIP XIII dan Pemda Mamuju, target total penyelesaian pembebasan lahan pada bulan Juli 2015. b. Target Ready to Supply : September 2016 Area Jumlah Rencana titik Soil Test Jumlah Aktual titik Soil Test Keterangan BTG & Chimney 43 43 Done BOP 24 11 Oil Tank 5 1 Coal Yard 28 23 Building 12 12 Done Jetty 22 22 Done Ash Yard 9 9 Done