2009 Summer Capital Projects

213
views

Published on

Published in: Education

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
213
On Slideshare
0
From Embeds
0
Number of Embeds
2
Actions
Shares
0
Downloads
0
Comments
0
Likes
0
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. Summer 2009 Capital Projects Elementary Debt Exclusion Work Summer 2009 Presentation for Town Meeting April 2010
  • 2. Capital Projects Summer 2009
    • Elementary Debt Exclusion
        • Hardy
        • Hunnewell
        • Schofield
        • Fiske
        • Upham
  • 3.
    • Time Frame for summer work
      • Last day of school for teachers was Thursday, June 24, 2009. Work began immediately after that.
      • The 42 work days between June 30 and August 27 described the time frame for all the moving and work.
  • 4.
    • Summer 2008
        • Roof replacement
        • Master Clock and Bell System
  • 5.
    • Summer 2008
        • Roof replacement
        • Master Clock and Bell System
    • Summer 2009
        • Flooring abatement and replacement in selected rooms
        • Gymnasium ceiling abatement / plaster / paint
        • Boiler replacement (in process)
  • 6. Old flooring was abated down to a wood subfloor.
  • 7. Old flooring was abated down to a wood subfloor. A new wood subfloor was installed in preparation for the new tile.
  • 8. Joints were patched
  • 9. Joints were patched and new tile installed.
  • 10.
    • Classroom and entry way tile
  • 11. Ceiling tiles were removed. A new ceiling with new lights and new acoustical panels were installed.
  • 12. Ceiling tiles were removed. A new ceiling with new lights and new acoustical panels were installed.
  • 13. New boiler installation
  • 14. The DPW completed work on a redesigned Hardy Road with increased parent drop off and pick up area.
  • 15.
    • Summer 2008
        • Master Clock and Bell System
        • Exterior lights and interior carpet
  • 16.
    • Summer 2008
        • Master Clock and Bell System
        • Exterior lights and interior carpet
    • Summer 2009
        • Flooring abatement and replacement
        • New air exchange units in gymnasium ceiling
        • Roof replacement
  • 17. New flooring was installed in 5 elementary schools.
  • 18. New flooring was installed in 5 elementary schools.
  • 19. Point distressed masonry
  • 20. Point distressed masonry Replace wood gutters
  • 21. Point distressed masonry Replace wood gutters New roof on the flat section
  • 22.
    • Summer 2008
        • Roof replacement
        • Master Clock and Bell System
  • 23.
    • Summer 2008
        • Roof replacement
        • Master Clock and Bell System
    • Summer 2009 - Phase I (required packing and moving of all rooms in the work area)
        • Ceiling abatement and replacement
          • New fire protection
          • New lighting
        • Flooring abatement and replacement
        • Enlarge two student bathrooms on cafeteria level
        • Gymnasium ceiling abatement / plaster / paint
        • Boiler replacement (in process)
  • 24.
    • Summer 2008
        • Roof replacement
        • Master Clock and Bell System
    • Summer 2009 - Phase I
        • Ceiling abatement and replacement
          • New fire protection
          • New lighting
        • Flooring abatement and replacement
        • Enlarge two student bathrooms on cafeteria level
        • Gymnasium ceiling abatement / plaster / paint
        • Boiler replacement (in process)
    • Summer 2010 - Phase II
        • Window replacements for both wings
        • Continued floor and ceiling abatement and replacement
  • 25. An area of old ceiling previously abated as a result of water damage The old ceiling was removed in preparation for the installation of fire protection (sprinkler system), new lights and a new suspended ceiling.
  • 26. New smoke and acoustical stops were installed above the new suspended ceiling in walls separating classrooms.
  • 27. New ceiling tile and new lighting
  • 28. New ceiling tile and new lighting brightened the hallways.
  • 29. Floor preparation and new tile in the cafeteria
  • 30. New tile in the cafeteria
  • 31. New tile in the cafeteria
  • 32.
    • Two student bathrooms on the cafeteria level were renovated
    • and are now ADA compliant.
  • 33. Old carpet flooring New tile flooring
  • 34. In the process of replacing the gym ceiling the gym floor was damaged.
  • 35. The floor was sanded, lines repainted and new coats of sealant applied.
  • 36. Excavation and extensive new piping was required to add the new sprinkler system.
  • 37. Fiske’s old boilers removed and ready for disposal.
  • 38. New boilers ready for installation.
  • 39.
    • Summer 2008
        • Master Clock and Bell System
        • New roof with improved roof drainage
  • 40.
    • Summer 2008
        • Master Clock and Bell System
        • New roof with improved roof drainage
    • Summer 2009
        • Flooring abatement and replacement in front hallway and
        • entryway
        • Boiler replacement (in process)
  • 41. Schofield’s entrance hallway rug was replaced with tile.
  • 42. Entrance to the Schofield boiler room
  • 43. Entrance to the Schofield boiler room
  • 44. Entrance to the Schofield boiler room
  • 45. New Boilers
  • 46.
    • Summer 2008
        • Master Clock and Bell System
  • 47.
    • Summer 2008
        • Master Clock and Bell System
    • Summer 2009 (required packing and moving of classrooms to complete the work)
        • New Roof
        • Flooring abatement and replacement
        • Gymnasium ceiling abatement / plaster / paint
        • Boiler replacement (in process)
  • 48. Roofing work was completed more quickly than last summer.
  • 49. Roofing work was completed more quickly than last summer.
  • 50.  
  • 51. On site demolition of the old boiler was required in preparation for installation of the new heating system.
  • 52. On site demolition of the old boiler was required in preparation for installation of the new heating system.
  • 53. Gym ceilings at Upham, Hardy and Fiske were abated and replaced this summer .
  • 54. Gym ceilings at Upham, Hardy and Fiske were abated and replaced this summer.
  • 55. Gym ceilings at Upham, Hardy and Fiske were abated and replaced this summer.
  • 56. New classroom tile
  • 57. New classroom tile New stair and landing tread
  • 58. New classroom tile New stair and landing tread New hallway tile