2. BASIC INFORMATION
• NAME :- ADANI POWER
•
• ADDRESS:- MIDC ,TIRODA.(80 KM FROM NAGPUR)
• ONE OF THE FIRST 660 MW POWER PLANT IN MAHARASHTRA
• ALL EQUIPMENT ARE CHINA MADE
• 4 Million tonnes of coal per year .
• Total 1750 hectares (including 1600 hectares of Forest Land) is used.
• PHONE NO:- MR GHIKE((9764600071)
MR GOKHLE(9823093546)
• NAME OF DEPT. HEAD:- HR- MR SANJAY ARGADE
LANDMR JAYANT GHIKE
CIVIL/OPERATIONS MR BHARDWAJ
SECURITY KERNEL ROY
7. RAW MATERIAL AND PRODUCTION
PROCESS:-
• WATER RESERVOIR
• COAL
• PETROL/ DIESEL
• THE PROCESS OF THERMAL POWER PLANT IS
USED FOR ELECRICITY PRODUCTION.
8. IMPROVEMENT AREA:-
• A> WASTE MATERIAL (ASH)
UTILIZATION.
• B> COAL AVAILABILITY IS LIMITED.
• C> POWER CANT BE STORED