P ark        R andy P ark        P rojec t Development Direc tor
Strategic Goals Preserve Infrastructure Optimize Mobility Improve Safety Strengthen the Economy
Program       200       180       160       140       120       100             May 11 J une   J uly 11 Aug 11   S ept   O...
Contractor Payments                                                                                          by Month$160,...
Economic Impact              Number of c ontrac tor and                c ons ultant c ompanies                           (...
HighlightedProjects
Washington Blvd                               OgdenLocation:   Washington Blvd. (U.S. 89),            26th St. to 40th St....
I-15, Weber to DavisLocations:   650 S. (S.R. 103) in Clearfield to I-84             in Riverdale; and Pages Ln. in       ...
7800 South and Bangerter                               Salt Lake County  Locations:   Bangerter Highway and 7800 South  Bu...
I-15 | 106th South                            Salt Lake CountyLocations:   I-15, 10600 S. to 600 N.Budget:      $2.8 milli...
Mountain View Corridor                  Right size project | Right time Location:   5400 South to Redwood Road            ...
Mountain View Corridor        April 2012
S.R. 92, Timpanogos           HighwayLocation:   SR-92, Lehi to HighlandBudget:     $112.7 millionCompletion: Summer
I-15 Core                        Utah CountyLocation:    I-15 from Lehi to Spanish ForkBudget:      $1.725 billionCompleti...
I-15 COREUniversity Parkway and Sandhill Roadfirst Continuous Flow Intersection in Utah County
U.S. 40 VernalLocation:     Vernal Main St.Budget:       $7.7 millionCompletion:   Fall 2012
U.S. 189, Wallsburg to      Heber CityLocation:   U.S. 189, Wallsburg to Heber CityBudget:     $8.35 millionCompletion: Th...
Restore S.R. 14                            Southern UtahLocation:   S.R. 14, Cedar City to Cedar Breaks            Nationa...
Restore S.R. 14    April 2012
I-15, Southern UtahLocation:   I-15, Summit to Paragonah in            Iron Co.; I-15, north of Toquerville            Was...
TIGsudot.utah.gov/trans parenc y
TIGs
Buy America Utah Department of Transportation ~ May 2012  Randy Park, Project Development Director
What Is Buy America?  Applies to all projects that include any  federal funds  Applies to iron & steel only  - Includes ...
Triggering Buy America?
Triggering Buy America?
Triggering Buy America?  Utilities located within the roadway
Why now?
Challenges    1. Compliance certification        2. Product availability    3. Increased project costs4. Utility organizat...
Solution Options1. Seek a FHWA waiver for foreign               products    2. Separate Utility contract  3. Investigating...
Buy AmericaUtah Department of Transportation ~ May 2012
May 16, 2012 Transportation Interim Committee Presentations
Upcoming SlideShare
Loading in …5
×

May 16, 2012 Transportation Interim Committee Presentations

237
-1

Published on

These presentations were given by Randy Park at the May 16, 2012 Transportation Interim Committee meeting.

Published in: Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
237
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
1
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

May 16, 2012 Transportation Interim Committee Presentations

  1. 1. P ark R andy P ark P rojec t Development Direc tor
  2. 2. Strategic Goals Preserve Infrastructure Optimize Mobility Improve Safety Strengthen the Economy
  3. 3. Program 200 180 160 140 120 100 May 11 J une J uly 11 Aug 11 S ept Oc t 11 Nov 11 Dec 11 J an 12 F eb 12 Mar 12 Apr 12 11 11Number of projects currently under construction: 199Total authorized amount under construction: $2,686,332,308Number of projects currently in design: 151
  4. 4. Contractor Payments by Month$160,000,000$140,000,000$120,000,000$100,000,000 $80,000,000 $60,000,000 40,000,000 $0 May 11 J une J uly Aug 11 S ept Oc t 11 Nov 11 Dec 11 J an 12 F eb 12 Mar 12 Apr 11 11 11 11
  5. 5. Economic Impact Number of c ontrac tor and c ons ultant c ompanies (P rimes and S ubs ) 686 P rivate s ec tor employees as s oc iated with c urrent c ons truc tion projec ts 14,699
  6. 6. HighlightedProjects
  7. 7. Washington Blvd OgdenLocation: Washington Blvd. (U.S. 89), 26th St. to 40th St.Budget: $1.8 millionCompletion: Fall 2012
  8. 8. I-15, Weber to DavisLocations: 650 S. (S.R. 103) in Clearfield to I-84 in Riverdale; and Pages Ln. in Centerville to 2600 S. in BountifulBudget: $10.8 millionCompletion: Fall 2012
  9. 9. 7800 South and Bangerter Salt Lake County Locations: Bangerter Highway and 7800 South Budget: $33.8 million Completion: Late Summer 2012
  10. 10. I-15 | 106th South Salt Lake CountyLocations: I-15, 10600 S. to 600 N.Budget: $2.8 millionCompletion: Summer 2012
  11. 11. Mountain View Corridor Right size project | Right time Location: 5400 South to Redwood Road at 16000 South Budget: $730 million Completion: December 2012
  12. 12. Mountain View Corridor April 2012
  13. 13. S.R. 92, Timpanogos HighwayLocation: SR-92, Lehi to HighlandBudget: $112.7 millionCompletion: Summer
  14. 14. I-15 Core Utah CountyLocation: I-15 from Lehi to Spanish ForkBudget: $1.725 billionCompletion: December 2012
  15. 15. I-15 COREUniversity Parkway and Sandhill Roadfirst Continuous Flow Intersection in Utah County
  16. 16. U.S. 40 VernalLocation: Vernal Main St.Budget: $7.7 millionCompletion: Fall 2012
  17. 17. U.S. 189, Wallsburg to Heber CityLocation: U.S. 189, Wallsburg to Heber CityBudget: $8.35 millionCompletion: Through December 2012
  18. 18. Restore S.R. 14 Southern UtahLocation: S.R. 14, Cedar City to Cedar Breaks National MonumentBudget: $7.47 millionCompletion: Through June 2012
  19. 19. Restore S.R. 14 April 2012
  20. 20. I-15, Southern UtahLocation: I-15, Summit to Paragonah in Iron Co.; I-15, north of Toquerville Washington Co.Budget: $10 millionCompletion: November 2012
  21. 21. TIGsudot.utah.gov/trans parenc y
  22. 22. TIGs
  23. 23. Buy America Utah Department of Transportation ~ May 2012 Randy Park, Project Development Director
  24. 24. What Is Buy America?  Applies to all projects that include any federal funds  Applies to iron & steel only - Includes imported steel melted in the U.S.  All manufacturing must take place domestically
  25. 25. Triggering Buy America?
  26. 26. Triggering Buy America?
  27. 27. Triggering Buy America?  Utilities located within the roadway
  28. 28. Why now?
  29. 29. Challenges 1. Compliance certification 2. Product availability 3. Increased project costs4. Utility organizations compliance
  30. 30. Solution Options1. Seek a FHWA waiver for foreign products 2. Separate Utility contract 3. Investigating other solutions
  31. 31. Buy AmericaUtah Department of Transportation ~ May 2012