SlideShare a Scribd company logo
1 of 19
EXPERIENCE FROM TCM
OLAV FALK-PEDERSEN
3/23/20
15
1
TCM GOALS
Be a key player in the
development of the emerging
market for CO2 capture
technology
Test, verify and
demonstrate CO2 capture
technologies owned and marketed
by vendors
Reduce the cost
and the
technical,
environmental
and financial
risks of
implementing
full scale CO2
capture
technology
Power plant
Amine plant
Chilled ammonia plant
Admin
complex
Substation
Utility systems
Area for future
technologies
Sea water inlet
CO2 vent
Catalytic
cracker
CONSTRUCTION
PARTNERS
AMINE PLANT
• Aker:
– Test/verification of 2 solvents.
– Technology commercial
available from Aker.
• MEA test
– First baseline MEA testing
using industrial CHP exhaust
gas.
– Emissions, energy
consumption, design and
process
optimization/limitations.
– Published at GHGT 12.
• Shell Cansolv:
– Verification of
solvent/technology.
– Ongoing.
MASS BALANCE - AMINE PLANT
• Before start-up, all measurements needed for safe
operation and plant balance were calibrated.
• Capture rate of CO2 initially ranged from 50-94 %,
depending on data source used for calculation.
• Extensive work has since been carried out to achieve a
higher mass balance accuracy.
– Mass balance accuracy now 3 – 4 %
MASS BALANCE EXAMPLE - CHP FLOW METER
Ultrasonic Meter: Overall uncertainties typically 1,0%
Pitot tube: Overall uncertainties typically 2,6%
AMINE PLANT
Collecting data from 4000 online measuring points
AMINE PLANT
• Testing the capture during dynamic transitions, replicating a
fluctuating grid power consumptions
• Supporting growth of renewables
• The graph below shows an example of tripping and starting the
amine plant.
AMINE PLANT
MANUAL SAMPLING
OPTIMIZATION OF PROCESS COMPONENTS
CAP PLANT
• Alstom:
– Test/verification of 2 exhaust gas sources.
– Technology commercial available from Alstom.
CAP PLANT
UNIVERSITY OF TEXAS AUSTIN AND TCM
• The Parties agree to explore opportunities of
collaboration and establish a frame of work in
certain areas:
– Developing a test program for use of the SDR rig at
TCM.
– Perform testing of MEA and one UT’s proprietary
amine.
– Analysis work and publication of test results.
REDUCTION
OF FINANCIAL
RISK
The tests have confirmed successful
operations of a scaled up plant
• CAP plant- a significant process development from a
precipitating system to a solution based technology
and further energy optimization and design
modification for preventing salt precipitation
• Amine plant- important input with respect to material
selection. Gasket material needs to be replaced in
certain areas. Material selection for other key
components verified
• Achieved knowledge from two different construction
methods (modular and on site construction)
• Constructed and verified the use of concrete absorbers
with polymer (PP) lining. Experienced and verified the
easiness of repairing leakages i.e. welding and change
parts of the PP lining
• The TCM simulation tool is to be verified by testing
with real exhaust in our industrial sized test units.
• Established a good embryo for a future industrial CO2
cluster of vendors, supply industry, academia
Power plant
Amine plant
Chilled ammonia plant
Utility systems
Catalytic
cracker
MIST
GAS CHARACTERISATION
EVALUATION OF CONCEPTS

More Related Content

What's hot

Skills development for the new Oil & Gas industry
Skills development for the new Oil & Gas industrySkills development for the new Oil & Gas industry
Skills development for the new Oil & Gas industryAdvisian
 
KEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXTKEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXTAled Long
 
Building Grid Resilience
Building Grid ResilienceBuilding Grid Resilience
Building Grid ResilienceAdvisian
 
Permian Artificial Lift & Production Optimization 2015
Permian Artificial Lift & Production Optimization 2015Permian Artificial Lift & Production Optimization 2015
Permian Artificial Lift & Production Optimization 2015marketinglbcg
 
Compare cryogenic process
Compare cryogenic processCompare cryogenic process
Compare cryogenic processsimachem
 
Intergrated Rice Plant Progress 2013
Intergrated Rice Plant Progress 2013 Intergrated Rice Plant Progress 2013
Intergrated Rice Plant Progress 2013 M Abid Latif
 
Revised: Presentation of my SCADA-Petroleum Engineering Suite
Revised:  Presentation of my SCADA-Petroleum Engineering SuiteRevised:  Presentation of my SCADA-Petroleum Engineering Suite
Revised: Presentation of my SCADA-Petroleum Engineering SuiteColin Jordan
 
Fjell Technology Oil & Gas - A passion for innovation!
Fjell Technology Oil & Gas - A passion for innovation!Fjell Technology Oil & Gas - A passion for innovation!
Fjell Technology Oil & Gas - A passion for innovation!Njaal R. Soleng
 
Europe User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluationEurope User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluationKBC (A Yokogawa Company)
 
Equipment sizing and costing using Petro-SIM
Equipment sizing and costing using Petro-SIMEquipment sizing and costing using Petro-SIM
Equipment sizing and costing using Petro-SIMKBC (A Yokogawa Company)
 
BeeExperienceandCommissioningPhilosophy
BeeExperienceandCommissioningPhilosophyBeeExperienceandCommissioningPhilosophy
BeeExperienceandCommissioningPhilosophyFrank Richards
 
Ground Source Heat Installations - Learning Experiences
Ground Source Heat Installations - Learning ExperiencesGround Source Heat Installations - Learning Experiences
Ground Source Heat Installations - Learning Experiencesphancock346
 
Thembi Kodisang Sibanda - What Is RECP
Thembi Kodisang Sibanda - What Is RECPThembi Kodisang Sibanda - What Is RECP
Thembi Kodisang Sibanda - What Is RECP7391456
 
Debottlenecking a bulk manufacturing plant
Debottlenecking a bulk manufacturing plantDebottlenecking a bulk manufacturing plant
Debottlenecking a bulk manufacturing plantGBX Summits
 
Estimating the cost of novel (pre-commercial) systems for CO2 capture - Ed Ru...
Estimating the cost of novel (pre-commercial) systems for CO2 capture - Ed Ru...Estimating the cost of novel (pre-commercial) systems for CO2 capture - Ed Ru...
Estimating the cost of novel (pre-commercial) systems for CO2 capture - Ed Ru...Global CCS Institute
 
Sam najmi resume 04-20-2016
Sam najmi resume 04-20-2016Sam najmi resume 04-20-2016
Sam najmi resume 04-20-2016Sam Najmi
 

What's hot (19)

Skills development for the new Oil & Gas industry
Skills development for the new Oil & Gas industrySkills development for the new Oil & Gas industry
Skills development for the new Oil & Gas industry
 
CV-ZTUFAIL2016
CV-ZTUFAIL2016CV-ZTUFAIL2016
CV-ZTUFAIL2016
 
KEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXTKEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXT
 
Building Grid Resilience
Building Grid ResilienceBuilding Grid Resilience
Building Grid Resilience
 
Permian Artificial Lift & Production Optimization 2015
Permian Artificial Lift & Production Optimization 2015Permian Artificial Lift & Production Optimization 2015
Permian Artificial Lift & Production Optimization 2015
 
Luke Marshall - One Number to Prioritise Work?
Luke Marshall - One Number to Prioritise Work?Luke Marshall - One Number to Prioritise Work?
Luke Marshall - One Number to Prioritise Work?
 
Compare cryogenic process
Compare cryogenic processCompare cryogenic process
Compare cryogenic process
 
Intergrated Rice Plant Progress 2013
Intergrated Rice Plant Progress 2013 Intergrated Rice Plant Progress 2013
Intergrated Rice Plant Progress 2013
 
Revised: Presentation of my SCADA-Petroleum Engineering Suite
Revised:  Presentation of my SCADA-Petroleum Engineering SuiteRevised:  Presentation of my SCADA-Petroleum Engineering Suite
Revised: Presentation of my SCADA-Petroleum Engineering Suite
 
Case Study - Ammonia Recovery
Case Study - Ammonia RecoveryCase Study - Ammonia Recovery
Case Study - Ammonia Recovery
 
Fjell Technology Oil & Gas - A passion for innovation!
Fjell Technology Oil & Gas - A passion for innovation!Fjell Technology Oil & Gas - A passion for innovation!
Fjell Technology Oil & Gas - A passion for innovation!
 
Europe User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluationEurope User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluation
 
Equipment sizing and costing using Petro-SIM
Equipment sizing and costing using Petro-SIMEquipment sizing and costing using Petro-SIM
Equipment sizing and costing using Petro-SIM
 
BeeExperienceandCommissioningPhilosophy
BeeExperienceandCommissioningPhilosophyBeeExperienceandCommissioningPhilosophy
BeeExperienceandCommissioningPhilosophy
 
Ground Source Heat Installations - Learning Experiences
Ground Source Heat Installations - Learning ExperiencesGround Source Heat Installations - Learning Experiences
Ground Source Heat Installations - Learning Experiences
 
Thembi Kodisang Sibanda - What Is RECP
Thembi Kodisang Sibanda - What Is RECPThembi Kodisang Sibanda - What Is RECP
Thembi Kodisang Sibanda - What Is RECP
 
Debottlenecking a bulk manufacturing plant
Debottlenecking a bulk manufacturing plantDebottlenecking a bulk manufacturing plant
Debottlenecking a bulk manufacturing plant
 
Estimating the cost of novel (pre-commercial) systems for CO2 capture - Ed Ru...
Estimating the cost of novel (pre-commercial) systems for CO2 capture - Ed Ru...Estimating the cost of novel (pre-commercial) systems for CO2 capture - Ed Ru...
Estimating the cost of novel (pre-commercial) systems for CO2 capture - Ed Ru...
 
Sam najmi resume 04-20-2016
Sam najmi resume 04-20-2016Sam najmi resume 04-20-2016
Sam najmi resume 04-20-2016
 

Similar to Experience from TCM, Olav Falk Pedersen (Gassnova) UK/Norway/Canada Meeting 18/19 March 2015

Apec workshop 2 presentation 8 3 vegar apec workshop 8 presentation v4 3.ppt...
Apec workshop 2 presentation 8 3 vegar apec workshop 8  presentation v4 3.ppt...Apec workshop 2 presentation 8 3 vegar apec workshop 8  presentation v4 3.ppt...
Apec workshop 2 presentation 8 3 vegar apec workshop 8 presentation v4 3.ppt...Global CCS Institute
 
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...irvan septyan mulyana
 
Webinar: Post-combusion carbon capture - Thermodynamic modelling
Webinar: Post-combusion carbon capture - Thermodynamic modellingWebinar: Post-combusion carbon capture - Thermodynamic modelling
Webinar: Post-combusion carbon capture - Thermodynamic modellingGlobal CCS Institute
 
Test centre mongstad presentation may 2013
Test centre mongstad presentation may 2013Test centre mongstad presentation may 2013
Test centre mongstad presentation may 2013Global CCS Institute
 
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...NazrulIslam657555
 
Project services offering (november 2016)
Project services offering (november 2016)Project services offering (november 2016)
Project services offering (november 2016)Luis Domínguez
 
Project services offering (november 2016)
Project services offering (november 2016)Project services offering (november 2016)
Project services offering (november 2016)Process Ecology Inc
 
Saeidi-Abbas-Resume April 2015-updated
Saeidi-Abbas-Resume April 2015-updatedSaeidi-Abbas-Resume April 2015-updated
Saeidi-Abbas-Resume April 2015-updatedAbbas Saeidi
 
Leon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon
 
Mark Crame Lead Instrument Engineer CV
Mark Crame Lead Instrument Engineer CVMark Crame Lead Instrument Engineer CV
Mark Crame Lead Instrument Engineer CVMark Crame
 
JNJ CV _OilAndGas rev02
JNJ CV _OilAndGas rev02JNJ CV _OilAndGas rev02
JNJ CV _OilAndGas rev02Jamal Jamil
 
jermaine_brown resume 2016 updated
jermaine_brown resume 2016 updatedjermaine_brown resume 2016 updated
jermaine_brown resume 2016 updatedJermaine Brown
 

Similar to Experience from TCM, Olav Falk Pedersen (Gassnova) UK/Norway/Canada Meeting 18/19 March 2015 (20)

Apec workshop 2 presentation 8 3 vegar apec workshop 8 presentation v4 3.ppt...
Apec workshop 2 presentation 8 3 vegar apec workshop 8  presentation v4 3.ppt...Apec workshop 2 presentation 8 3 vegar apec workshop 8  presentation v4 3.ppt...
Apec workshop 2 presentation 8 3 vegar apec workshop 8 presentation v4 3.ppt...
 
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
 
TCM presentation May 2013
TCM presentation May 2013TCM presentation May 2013
TCM presentation May 2013
 
Webinar: Post-combusion carbon capture - Thermodynamic modelling
Webinar: Post-combusion carbon capture - Thermodynamic modellingWebinar: Post-combusion carbon capture - Thermodynamic modelling
Webinar: Post-combusion carbon capture - Thermodynamic modelling
 
Test centre mongstad presentation may 2013
Test centre mongstad presentation may 2013Test centre mongstad presentation may 2013
Test centre mongstad presentation may 2013
 
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
 
LinkedIn
LinkedInLinkedIn
LinkedIn
 
richard resume word
richard resume wordrichard resume word
richard resume word
 
Project services offering (november 2016)
Project services offering (november 2016)Project services offering (november 2016)
Project services offering (november 2016)
 
Project services offering (november 2016)
Project services offering (november 2016)Project services offering (november 2016)
Project services offering (november 2016)
 
2016 Resume
2016  Resume2016  Resume
2016 Resume
 
Saeidi-Abbas-Resume April 2015-updated
Saeidi-Abbas-Resume April 2015-updatedSaeidi-Abbas-Resume April 2015-updated
Saeidi-Abbas-Resume April 2015-updated
 
Santhosh Resume updated
Santhosh Resume updatedSanthosh Resume updated
Santhosh Resume updated
 
Leon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016R
 
My Updated CV
My  Updated CVMy  Updated CV
My Updated CV
 
Mark Crame Lead Instrument Engineer CV
Mark Crame Lead Instrument Engineer CVMark Crame Lead Instrument Engineer CV
Mark Crame Lead Instrument Engineer CV
 
JNJ CV _OilAndGas rev02
JNJ CV _OilAndGas rev02JNJ CV _OilAndGas rev02
JNJ CV _OilAndGas rev02
 
Sr.Inst Tech
Sr.Inst TechSr.Inst Tech
Sr.Inst Tech
 
CV - M. Taj Arain
CV - M. Taj ArainCV - M. Taj Arain
CV - M. Taj Arain
 
jermaine_brown resume 2016 updated
jermaine_brown resume 2016 updatedjermaine_brown resume 2016 updated
jermaine_brown resume 2016 updated
 

More from UK Carbon Capture and Storage Research Centre

More from UK Carbon Capture and Storage Research Centre (20)

CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
 
Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...
Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...
Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...
 
Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...
Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...
Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...
 
Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...
Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...
Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...
 
20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...
20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...
20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...
 
Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...
Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...
Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...
 
Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...
Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...
Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...
 
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
 
Multiphase flow modelling of calcite dissolution patterns from core scale to ...
Multiphase flow modelling of calcite dissolution patterns from core scale to ...Multiphase flow modelling of calcite dissolution patterns from core scale to ...
Multiphase flow modelling of calcite dissolution patterns from core scale to ...
 
Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...
Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...
Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...
 
Challenges in the chemical industry, jay brookes (boc) industry ccs worksho...
Challenges in the chemical industry, jay brookes (boc)   industry ccs worksho...Challenges in the chemical industry, jay brookes (boc)   industry ccs worksho...
Challenges in the chemical industry, jay brookes (boc) industry ccs worksho...
 
Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...
Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...
Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...
 
Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...
Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...
Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...
 
Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...
Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...
Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...
 
Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...
Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...
Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...
 
Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...
Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...
Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...
 
Research Coordination Network on Carbon Capture, Utilization and Storage Fund...
Research Coordination Network on Carbon Capture, Utilization and Storage Fund...Research Coordination Network on Carbon Capture, Utilization and Storage Fund...
Research Coordination Network on Carbon Capture, Utilization and Storage Fund...
 
Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...
Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...
Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...
 
Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...
Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...
Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...
 
Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...
Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...
Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...
 

Recently uploaded

DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdfAkritiPradhan2
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSneha Padhiar
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书rnrncn29
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Romil Mishra
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfNainaShrivastava14
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming languageSmritiSharma901052
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfisabel213075
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptxmohitesoham12
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfDrew Moseley
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSsandhya757531
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsapna80328
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionSneha Padhiar
 
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmDeepika Walanjkar
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
KCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosKCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosVictor Morales
 

Recently uploaded (20)

DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming language
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdf
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptx
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdf
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveying
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based question
 
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
KCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosKCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitos
 

Experience from TCM, Olav Falk Pedersen (Gassnova) UK/Norway/Canada Meeting 18/19 March 2015

  • 1. EXPERIENCE FROM TCM OLAV FALK-PEDERSEN 3/23/20 15 1
  • 2. TCM GOALS Be a key player in the development of the emerging market for CO2 capture technology Test, verify and demonstrate CO2 capture technologies owned and marketed by vendors Reduce the cost and the technical, environmental and financial risks of implementing full scale CO2 capture technology
  • 3. Power plant Amine plant Chilled ammonia plant Admin complex Substation Utility systems Area for future technologies Sea water inlet CO2 vent Catalytic cracker
  • 6. AMINE PLANT • Aker: – Test/verification of 2 solvents. – Technology commercial available from Aker. • MEA test – First baseline MEA testing using industrial CHP exhaust gas. – Emissions, energy consumption, design and process optimization/limitations. – Published at GHGT 12. • Shell Cansolv: – Verification of solvent/technology. – Ongoing.
  • 7. MASS BALANCE - AMINE PLANT • Before start-up, all measurements needed for safe operation and plant balance were calibrated. • Capture rate of CO2 initially ranged from 50-94 %, depending on data source used for calculation. • Extensive work has since been carried out to achieve a higher mass balance accuracy. – Mass balance accuracy now 3 – 4 %
  • 8. MASS BALANCE EXAMPLE - CHP FLOW METER Ultrasonic Meter: Overall uncertainties typically 1,0% Pitot tube: Overall uncertainties typically 2,6%
  • 9. AMINE PLANT Collecting data from 4000 online measuring points
  • 10. AMINE PLANT • Testing the capture during dynamic transitions, replicating a fluctuating grid power consumptions • Supporting growth of renewables • The graph below shows an example of tripping and starting the amine plant.
  • 14. CAP PLANT • Alstom: – Test/verification of 2 exhaust gas sources. – Technology commercial available from Alstom.
  • 16. UNIVERSITY OF TEXAS AUSTIN AND TCM • The Parties agree to explore opportunities of collaboration and establish a frame of work in certain areas: – Developing a test program for use of the SDR rig at TCM. – Perform testing of MEA and one UT’s proprietary amine. – Analysis work and publication of test results.
  • 17. REDUCTION OF FINANCIAL RISK The tests have confirmed successful operations of a scaled up plant • CAP plant- a significant process development from a precipitating system to a solution based technology and further energy optimization and design modification for preventing salt precipitation • Amine plant- important input with respect to material selection. Gasket material needs to be replaced in certain areas. Material selection for other key components verified • Achieved knowledge from two different construction methods (modular and on site construction) • Constructed and verified the use of concrete absorbers with polymer (PP) lining. Experienced and verified the easiness of repairing leakages i.e. welding and change parts of the PP lining • The TCM simulation tool is to be verified by testing with real exhaust in our industrial sized test units. • Established a good embryo for a future industrial CO2 cluster of vendors, supply industry, academia
  • 18. Power plant Amine plant Chilled ammonia plant Utility systems Catalytic cracker