How do you get accurate  visibility        on a multi-team project?
Success of an Agile project depends on the
Success of an Agile project depends on theCooperation       and    Coordination          of multiple teams
As such, visibility of the progressof each team and the program as a whole
As such, visibility of the progressof each team and the program as a whole              is critical
Rollups are not the answer
Rollups are not the answer        Why?
Rollups hide valuable informationThe problem with                   about individual team and program progress    Rollups ...
They inaccurately forecastThe problem with   when the program may be complete    Rollups     #2
They set incorrect   expectationsThe problem with    Rollups     #3
For   example...
The problem with           Team   Chicago    Rollups Example                   Team   Bangalore
The problem with          Team Chicago    Rollups Example           Common Goal                       Team Bangalore
The problem with                     Team Chicago   5 stories    Rollups Example           Common Goal 40     stories     ...
Progress of Team ChicagoThe problem with    Rollups Example
Progress of Team Chicago                   5 stories doneThe problem with    Rollups Example
Progress of Team Chicago                   5 stories done on Jan 1stThe problem with    Rollups Example
Progress of Team Chicago                   5 stories done on Jan 1stThe problem with   All work complete    Rollups Example
Progress of Team BangaloreThe problem with    Rollups Example
Progress of Team Bangalore                   10 stories doneThe problem with    Rollups Example
Progress of Team Bangalore                   10 stories done on Jan 5thThe problem with    Rollups Example
Progress of Team Bangalore                   10 stories done on Jan 5thThe problem with   Forecasted end date Jan 21st    ...
Rollups of both teamsThe problem with    Rollups  Example
Rollups of both teams                   Incorrect forecasted end date of Jan 15thThe problem with    Rollups  Example
Rollups of both teams                   Incorrect forecasted end date of Jan 15thThe problem with   when it should be Jan ...
Rollups of both teams                   Incorrect forecasted end date of Jan 15thThe problem with   when it should be Jan ...
What do we recommend for bettervisibility of your program’s progress?
Correlate progress of program objectives with project progressFor better program   visibility
Correlate progress of program objectives with project progress                     Track the progress of each project with...
Correlate progress of program objectives with project progress                     Track the progress of each project with...
Correlate progress of program objectives with project progress                     Track the progress of each project with...
What helps you getvisibility of your program?
Agile workers talk often and welcome change. Mingle creates a shared space tomake quick decisions and track details, even ...
Upcoming SlideShare
Loading in...5
×

How do you get accurate visibility on a multi-team project?

1,581

Published on

Published in: Technology
0 Comments
2 Likes
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total Views
1,581
On Slideshare
0
From Embeds
0
Number of Embeds
8
Actions
Shares
0
Downloads
25
Comments
0
Likes
2
Embeds 0
No embeds

No notes for slide

How do you get accurate visibility on a multi-team project?

  1. 1. How do you get accurate visibility on a multi-team project?
  2. 2. Success of an Agile project depends on the
  3. 3. Success of an Agile project depends on theCooperation and Coordination of multiple teams
  4. 4. As such, visibility of the progressof each team and the program as a whole
  5. 5. As such, visibility of the progressof each team and the program as a whole is critical
  6. 6. Rollups are not the answer
  7. 7. Rollups are not the answer Why?
  8. 8. Rollups hide valuable informationThe problem with about individual team and program progress Rollups #1
  9. 9. They inaccurately forecastThe problem with when the program may be complete Rollups #2
  10. 10. They set incorrect expectationsThe problem with Rollups #3
  11. 11. For example...
  12. 12. The problem with Team Chicago Rollups Example Team Bangalore
  13. 13. The problem with Team Chicago Rollups Example Common Goal Team Bangalore
  14. 14. The problem with Team Chicago 5 stories Rollups Example Common Goal 40 stories Team Bangalore 35 stories
  15. 15. Progress of Team ChicagoThe problem with Rollups Example
  16. 16. Progress of Team Chicago 5 stories doneThe problem with Rollups Example
  17. 17. Progress of Team Chicago 5 stories done on Jan 1stThe problem with Rollups Example
  18. 18. Progress of Team Chicago 5 stories done on Jan 1stThe problem with All work complete Rollups Example
  19. 19. Progress of Team BangaloreThe problem with Rollups Example
  20. 20. Progress of Team Bangalore 10 stories doneThe problem with Rollups Example
  21. 21. Progress of Team Bangalore 10 stories done on Jan 5thThe problem with Rollups Example
  22. 22. Progress of Team Bangalore 10 stories done on Jan 5thThe problem with Forecasted end date Jan 21st Rollups Example
  23. 23. Rollups of both teamsThe problem with Rollups Example
  24. 24. Rollups of both teams Incorrect forecasted end date of Jan 15thThe problem with Rollups Example
  25. 25. Rollups of both teams Incorrect forecasted end date of Jan 15thThe problem with when it should be Jan 21st Rollups Example
  26. 26. Rollups of both teams Incorrect forecasted end date of Jan 15thThe problem with when it should be Jan 21st Rollups with no visibility of individual team progress Example
  27. 27. What do we recommend for bettervisibility of your program’s progress?
  28. 28. Correlate progress of program objectives with project progressFor better program visibility
  29. 29. Correlate progress of program objectives with project progress Track the progress of each project without masking informationFor better program visibility
  30. 30. Correlate progress of program objectives with project progress Track the progress of each project without masking information Get alerts when attention is needed to project schedulesFor better program visibility
  31. 31. Correlate progress of program objectives with project progress Track the progress of each project without masking information Get alerts when attention is needed to project schedulesFor better program Forecast the effects of scope changes on project timelines visibility
  32. 32. What helps you getvisibility of your program?
  33. 33. Agile workers talk often and welcome change. Mingle creates a shared space tomake quick decisions and track details, even when the team can’t be together. See how Mingle can help you effectively track the progress of your project or program
  1. A particular slide catching your eye?

    Clipping is a handy way to collect important slides you want to go back to later.

×