Measurement and Metrics for Test Managers

467

Published on

To be most effective, test managers must develop and use metrics to help direct the testing effort and make informed recommendations about the software’s release readiness and associated risks. …

To be most effective, test managers must develop and use metrics to help direct the testing effort and make informed recommendations about the software’s release readiness and associated risks. Because one important testing activity is to “measure” the quality of the software, test managers must measure the results of both the development and testing processes. Collecting, analyzing, and using metrics is complicated because many developers and testers are concerned that the metrics will be used against them. Join Rick Craig as he addresses common metrics—measures of product quality, defect removal efficiency, defect density, defect arrival rate, and testing status. Learn the guidelines for developing a test measurement program, rules of thumb for collecting data, and ways to avoid “metrics dysfunction.” Rick identifies several metrics paradigms and discusses the pros and cons of each. Delegates are urged to bring their metrics problems and issues for use as discussion points.

Published in: Technology
0 Comments
1 Like
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total Views
467
On Slideshare
0
From Embeds
0
Number of Embeds
2
Actions
Shares
0
Downloads
38
Comments
0
Likes
1
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1.             Presented by:  Rick  raig  Software  eering  Brought to you by:      340 Corporate Way, Suite   Orange Park, FL 32073  888‐2 MG  PM Tutorial 4/7/2014  1:00 PM          “Measurement and Metrics for Test Managers”      C Quality Engin                   300, 68‐8770 ∙ 904‐278‐0524 ∙ sqeinfo@sqe.com ∙ www.sqe.com 
  • 2.                        A consultant, lecturer, author, and test manager, Rick Craig has led numerous teams ny e has quent on. Rick Craig ity EngineeringSoftware Qual       of testers on both large and small projects. In his twenty-five years of consulting worldwide, Rick has advised and supported a diverse group of organizations on ma testing and test management issues. From large insurance providers and telecommunications companies to smaller software services companies, h mentored senior software managers and helped test teams improve their effectiveness. Rick is coauthor of Systematic Software Testing and is a fre speaker at testing conferences, including every STAR conference since its incepti
  • 3. © 2014 SQE Training V3.2 1 Introduction MEASUREMENT AND METRICS FOR TEST MANAGERS Administrivia Course timing Meals timing Electronic devices Facilities Smoking Breaks 4© 2014 SQE Training V3.2
  • 4. © 2014 SQE Training V3.2 2 Course Agenda 1. Introduction to Software Measurement 2. Metrics—Rules of Thumb 3. A Tester’s Dashboard 4. Estimation (Optional) 5© 2014 SQE Training V3.2 1 INTRODUCTION TO SOFTWARE MEASUREMENT
  • 5. © 2014 SQE Training V3.2 3 What is software measurement? “It’s easy to get numbers, what is y g , hard is to know they are right and  understand what they mean” — Bill Hetzel 7© 2014 SQE Training V3.2 What is software measurement? “ ifi d b i ”“Quantified observations” about any aspect of software (product, process, or project)  8© 2014 SQE Training V3.2
  • 6. © 2014 SQE Training V3.2 4 Lord Kelvin “To measure is to know” “If you cannot measure it, you  cannot improve it”  “Th d d h i“The more you understand what is  wrong with a figure, the more  valuable that figure becomes” 9© 2014 SQE Training V3.2 There Are Lots and Lots of Measures Primitive:  – Aspirins consumed this week – Number of staff assigned to project A P f i t ifi ti– Pages of requirements specifications – Hours worked to accomplish change request X – Number of operational failures in system Y this year – Lines of code in program Z Computed: Defects per 1000 lines of code in program A– Defects per 1000 lines of code in program A – Productivity in function points delivered by person B – Quality Score for project C – Average coffee consumption per line of code – Accuracy of hours worked per week is ± 20% 10© 2014 SQE Training V3.2
  • 7. © 2014 SQE Training V3.2 5 Common Metrics • Test defects • Defects after release O bl• Open problems • Open issues • Schedule performance • Process compliance (e.g., ISO) • Test results • Reliability • Time fixing problems • Defects from fixes • Lines of code • Plan and schedule changes 11© 2014 SQE Training V3.2 Uncommon Metrics • Code coverage C l it• Complexity • Cost of rework • Cost of quality Defect age 12© 2014 SQE Training V3.2
  • 8. © 2014 SQE Training V3.2 6 Basic Definitions The four Ms: • Measure Primitive (raw data) 13, 34, 17, 74 42,  34 56 77 94 34• Measure • Metric • Meter • Meta‐measure 34, 56, 77 94, 34,  45, 63 45, 67, 12,  31 61, 06, 91, 42 Computed (information) 13© 2014 SQE Training V3.2 What Makes a Good Measure? • Simple Obj i• Objective • Easily collected • Robust • Valid 14© 2014 SQE Training V3.2
  • 9. © 2014 SQE Training V3.2 7 What Can Measures Do for You? • Facilitate estimation • Identify risky areasy y • Measure testing status • Measure/predict product quality • Measure test effectiveness • Identify training opportunitiesIdentify training opportunities • Identify process improvement opportunities • Provide “meters” to flag actions 15© 2014 SQE Training V3.2 2 METRICS—RULES OF THUMB
  • 10. © 2014 SQE Training V3.2 8 Metrics--Rules of Thumb • The Human Element • The Basics • KISS • And a Myth or Two 17© 2014 SQE Training V3.2 The Human Element •Without buy‐in, metrics  may be falsified •Without buy‐in, metrics  may be ignored Buy‐in  is key 18© 2014 SQE Training V3.2
  • 11. © 2014 SQE Training V3.2 9 Class Discussion How do you obtain buy‐in? 19© 2014 SQE Training V3.2 Ways to Obtain Buy-in • Training • Metrics • Feedback loops • ReviewsReviews • Participation 20© 2014 SQE Training V3.2
  • 12. © 2014 SQE Training V3.2 10 The Human Element • Measure processes and products instead of  l if iblpeople if possible • Beware of the dark side of the Hawthorne  Effect 21© 2014 SQE Training V3.2 Two Sides of Measurement …the  information  …the information  will help me  may be used  against me. p understand what  is going on and do  a better job. 22© 2014 SQE Training V3.2
  • 13. © 2014 SQE Training V3.2 11 The Hawthorne Effect Measuring people improves their productivity 23© 2014 SQE Training V3.2 The Human Element Tailor metrics to the audience Users, managers, practitioners all have  different languages Set the appropriate level of detailpp p How you present the material matters 24© 2014 SQE Training V3.2
  • 14. © 2014 SQE Training V3.2 12 Who is your audience? Users Developers Testers 25© 2014 SQE Training V3.2 % of Red Cars Soars 26 26 0 26.1 25.5 25.4 25.4 25.5 25.6 25.7 25.8 25.9 26.0 2008 2009 2010 25.1 25.2 25.3 26© 2014 SQE Training V3.2
  • 15. © 2014 SQE Training V3.2 13 % of Red Cars Soars? 100 50 75 25.5 2625 4 2008 2009 2010 25 25.4 27© 2014 SQE Training V3.2 The Human Factor Training is required Metrics are not second nature Your metrics are affected by how they are collected Establish range of expected values Publish historical values 28© 2014 SQE Training V3.2
  • 16. © 2014 SQE Training V3.2 14 The Basics • Use a metric to validate a metric • Use meta‐measures • Use meters when possible • Consistency sometimes trumps accuracy • Subjective is good; objective is better 29© 2014 SQE Training V3.2 KISS ― Keep It Simple Sir • More is not always better • All metrics are not foreverAll metrics are not forever – Consider temporary metrics – Consider sampling • Automate collection when possible 30© 2014 SQE Training V3.2
  • 17. © 2014 SQE Training V3.2 15 3 ’A TESTER’S DASHBOARD A Dashboard 33© 2014 SQE Training V3.2
  • 18. © 2014 SQE Training V3.2 16 Establish a Dashboard • Easy to use/understand at a glance Quality of productQuality of product Status Test effectiveness Resources * Remember you need at least two metrics per “instrument” Issues 34© 2014 SQE Training V3.2 Measures of Quality • It is difficult to develop practical measures of  qualityquality • The cost to achieve various quality levels must be  taken into account • Many quality metrics are relatively subjective • Quality goals will be affected by the industry and  corporate culture 35© 2014 SQE Training V3.2
  • 19. © 2014 SQE Training V3.2 17 What Is Quality? •Meeting requirements (stated and/or implied)Quality 36© 2014 SQE Training V3.2 Sample Quality Factors and Criteria • Correctness • Reliability • Testability • Flexibility • Usability • Portability • Interoperability • Efficiency Correctability Correctness Correctness Correctness • Integrity • Maintainability • Revisability • Survivability Correctness Correctness Correctness Correctness 37© 2014 SQE Training V3.2
  • 20. © 2014 SQE Training V3.2 18 Defect Density/Clustering # of Defects per 1,000 Lines of Code Module Name D B A C E F 38© 2014 SQE Training V3.2 Defect Density Issues Coverage of tests Weighting of defects Weighting by relative risk What to use as the denominator 39© 2014 SQE Training V3.2
  • 21. © 2014 SQE Training V3.2 19 Effect of Complexity on Quality asebilityofPost-relea Defect Complexity Probab 40© 2014 SQE Training V3.2 Other Measures of Product Quality • Customer satisfaction • Repeat customers? • Referrals? • Calls to the help desk? • Timeliness? • Defect age? • Complexity? • Rework? • Reliability? 41© 2014 SQE Training V3.2
  • 22. © 2014 SQE Training V3.2 20 Quality of Product • Record any current measures of product  quality that you are using here. Give them a q y y g grade for effectiveness (A, B, C, etc.) • Any new metrics you would use? * Remember you need at least two metrics per instrument 42© 2014 SQE Training V3.2 Establish a Dashboard • Easy to use/understand at a glance: Quality of productQuality of product Status Test effectiveness Resources * Remember you need at least two metrics per instrument Issues 43© 2014 SQE Training V3.2
  • 23. © 2014 SQE Training V3.2 21 Status Reporting • The Master Test Plan should specify – What to report – How often – To whom 44© 2014 SQE Training V3.2 Common Test Status Metrics % of Test Cases Executed IIssues: • Weighting of TC by coverage metrics • Weighting of TC by risk • Weighting of TC by execution effort • Weighting of TC by time to executeWeighting of TC by time to execute What do you really want to know? 45© 2014 SQE Training V3.2
  • 24. © 2014 SQE Training V3.2 22 Sample Test Status Report (raw data) Project: Online-Trade Date: 4/23/2009 Feature Total # % # % Tested Tests CompleteCompleteSuccess Success Open Acct 46 46 100 41 89 Sell Order 36 25 69 25 69 Buy Order 19 17 89 12 63 ….. ….. ….. ….. Totals 395 320 81 311 79 46© 2014 SQE Training V3.2 Open and Closed Over Time Incoming Released 30 40 2 4 6 8 10 12 14 16 18 20 Weeks Defects Fixed 0 10 20 24 22 20 18 16 14 12 veDefects Detected 12 10 8 6 4 2 0 Days Cumulativ Open 0 10 20 30 40 47© 2014 SQE Training V3.2
  • 25. © 2014 SQE Training V3.2 23 When Is the Software “Good Enough”? • Test exit criteria met When to stop testing • Return On Investment (ROI) not sufficient • Defect arrival rate • Resources exhausted – Time – Moneyy • Profiles (based on failures encountered using profiles of real data)  • Project cancelled! 48© 2014 SQE Training V3.2 Software Psychology What is “good enough”? # of# of Bugs Time 49© 2014 SQE Training V3.2
  • 26. © 2014 SQE Training V3.2 24 Economics of Test and Failure Source: IBM Systems Sciences Institute 50© 2014 SQE Training V3.2 Stopping Criteria ― Revisited Abnormal • Resource exhaustion – Schedule Normal • Test set exit criteria • Remaining defects – Budget – System access – Patience • Project redirection e a g de ects estimation criteria – Defect history of past software – Defect history of current item – Software complexity – Combination of these • Diminishing return criteria – Cost to Detect Next Defect • Combined criteria “There is no single, valid, rational criterion for stopping. Furthermore, given any set of applicable criteria, how each is weighed depends very much on the product, the environment, the culture, and the attitude to risk.” — Boris Beizer 51© 2014 SQE Training V3.2
  • 27. © 2014 SQE Training V3.2 25 Test Summary Report • Report identifier • References – Test items (with revision #s) Adequacy assessment Evaluation of coverage Identify uncovered attributes Summary of activitiesTest items (with revision #s) – Environments – References • Variances (deviations) – From test plan or requirements – Reasons for deviations • Summary of incidents Summary of activities System/CPU usage Staff time Elapsed time Software evaluation Limitations Failure likelihood Approvals Summary of incidents – Resolved incidents – Defect patterns – Unresolved incidents 52© 2014 SQE Training V3.2 Status • Record any current test status measures that you  are using here. Give them a grade for effectiveness  (A B C etc )(A, B, C, etc.) • Any new metrics you would use? * Remember you need at least two metrics per instrument 53© 2014 SQE Training V3.2
  • 28. © 2014 SQE Training V3.2 26 Establish a Dashboard • Easy to use/understand at a glance: Quality of productQuality of product Status Test effectiveness Resources * Remember you need at least two metrics per instrument Issues 54© 2014 SQE Training V3.2 How Do You Measure Test Effectiveness? 55© 2014 SQE Training V3.2
  • 29. © 2014 SQE Training V3.2 27 A Common Answer – Coverage – Defect age (phase or product version)Defect age (phase or product version) – # of bugs – Defect density – Defect removal efficiency – Defect seeding – Mutation analysis – Customer complaints 56© 2014 SQE Training V3.2 Three Major Categories 57© 2014 SQE Training V3.2
  • 30. © 2014 SQE Training V3.2 28 Customer Satisfaction Measures Issues Who to ask “After the fact” Diffi l i iDifficulty in measuring Doesn’t differentiate between the  effectiveness of development and testing 58© 2014 SQE Training V3.2 Customer Satisfaction Measures • Subjective is good • Objective is betterObjective is better 59© 2014 SQE Training V3.2
  • 31. © 2014 SQE Training V3.2 29 Defect Measures • Why is it important to track defects? • What are some ways to analyze defects?• What are some ways to analyze defects? • DDP • Defect density • Defect age 60© 2014 SQE Training V3.2 Why is it important to track defects? • Identify process improvement • Identify training needsy g • Identify problematic (high‐risk) areas • Determine test status 61© 2014 SQE Training V3.2
  • 32. © 2014 SQE Training V3.2 30 Defect Analysis ― Example • Phase • Type• Type • Severity • Priority • Author A• Age • Module 62© 2014 SQE Training V3.2 Defect Detection Percentage (DDP) D f t Di d DDP = Defects Discovered x 100% Defects at Start 85% is the average DRE for US softwareg projects greater than 1,000 function points in size. — Capers Jones 63© 2014 SQE Training V3.2
  • 33. © 2014 SQE Training V3.2 31 Defect Detection Percentage (DDP) Issues Severity and distribution of defects How to know when all bugs are found “After the fact” What constitutes bug‐finding activities? Some bugs cannot be found in testing 64© 2014 SQE Training V3.2 Defect “Value” (Cost Avoidance) Requirements 1 When discovered Typical hours to rework/fix High level design 1 Detailed design 1 Code 1 Unit Test 3 – 5 Integration test 5 –10 System/acceptance test 10 – 30 Production 20 – 60+ 65© 2014 SQE Training V3.2
  • 34. © 2014 SQE Training V3.2 32 Defect Age (PhAge) Phase discovered Requirements High level design 0 Phase created 1 432 98765 0 321 87654 Detailed design Coding 0 321 87654 210 76543 10 65432 66© 2014 SQE Training V3.2 Defect Age IssuesIssues Difficult to do root cause Requires weighting of defectsq g g How to handle latent/masked defects 67© 2014 SQE Training V3.2
  • 35. © 2014 SQE Training V3.2 33 Coverage Measures Discussion Requirements vs. design vs. code coverage Completeness/accuracy of test basis Coverage of test set vs. coverage of testsg g executed (e.g., we don’t always run every test) Coverage vs. actual results (DDP) 68© 2014 SQE Training V3.2 Mapping Test Cases to Requirements Requirements spec. 3 5 1 3 2 Test plan T t C #33.5.1.3.2 ….. 3.5.1.4.7 ….. 3.6.4.2.1 Test Case #3 ….. Test Case #5 ….. Test Case #12 ….. 3.8.2.7.1 ….. Test Case #19 69© 2014 SQE Training V3.2
  • 36. © 2014 SQE Training V3.2 34 Requirements/Design Coverage Test Case Conceptual model of requirements/ design coverage: Test Case 1 2 3 Covered? Requirement A X X Y B N C X X Y Feature A X Y B X X YB X X Y Design A X X Y B X Y C N D X X Y 70© 2014 SQE Training V3.2 Requirements/Design Coverage Issues Only as good as test basis Relatively low coverage of code Code coverage achieved with requirements tests b k ( )Major bank (20 apps) 20% Major DBMS vendor 47% Major h/w s/w vendor 60% — Source:  Bender and Associates 71© 2014 SQE Training V3.2
  • 37. © 2014 SQE Training V3.2 35 Code Coverage Test run Conceptual model of code coverage Test run 1 2 3 Covered? Statement A X X X Y B X X Y C X Y D N E X YE X Y 60% 20% 60% 80% 72© 2014 SQE Training V3.2 Code Coverage Issues Requires a tool Doesn’t prove the code actually “works” correctly Did we test the “right code”? Statement vs. branch vs. path 73© 2014 SQE Training V3.2
  • 38. © 2014 SQE Training V3.2 36 Test Effectiveness • Record any current test effectiveness measures  that you are using here. Give them a grade for  ff ti (A B C t )effectiveness (A, B, C, etc.) • Any new metrics you would use? * Remember you need at least two metrics per instrument 74© 2014 SQE Training V3.2 Establish a Dashboard • Easy to use/understand at a glance: Quality of productQuality of product Status Test effectiveness Resources * Remember you need at least two metrics per instrument Issues 75© 2014 SQE Training V3.2
  • 39. © 2014 SQE Training V3.2 37 Resources • Resource estimates/consumption are necessary  in order to do test planning, estimation,  budgeting and staffingbudgeting, and staffing • You must consider the level of granularity in the  collection of these metrics based on the accuracy  of the required metrics and your ability to  validate them • Some people choose to exclude the resources  instrument from the dashboard because they feel  it is not a “day to day” metric 76© 2014 SQE Training V3.2 Resources Resource metrics are normally collected Resource metrics are normally collected  in terms of Actual/expected budget Actual/expected engineering hours Test environment utilization/availability Staffing levelsStaffing levels Contractor availability Other hardware/software resources 77© 2014 SQE Training V3.2
  • 40. © 2014 SQE Training V3.2 38 Resources • Record any current resource measures that  you are using here. Give them a grade for  ff ti (A B C t )effectiveness (A, B, C, etc.) • Any new metrics you would use? * Remember you need at least two metrics per instrument 78© 2014 SQE Training V3.2 Establish a Dashboard • Easy to use/understand at a glance: Quality of ProductQuality of Product Status Test Effectiveness Resources * Remember you need at least two metrics per instrument Issues 79© 2014 SQE Training V3.2
  • 41. © 2014 SQE Training V3.2 39 Issues • This is included to address any important  items not otherwise included on theitems not otherwise included on the  dashboard. These are normally subjective and  not necessarily conducive to systematic  analysis I ld i l t i i i t ll ti f• Issues could involve training, installation of  new hardware/software, politics—even the  weather 80© 2014 SQE Training V3.2 A Sample Tester’s Dashboard Status • % completion • Defect info Product Quality • Defect density • Performance, etc. Test Effectiveness • DDP • Coverage Resources E i i h• Engineering hours • Money Issues 81© 2014 SQE Training V3.2
  • 42. © 2014 SQE Training V3.2 40 Avoiding Dysfunction • Measure processes and products—not people! • Beware of the dark side of the Hawthorne EffectBeware of the dark side of the Hawthorne Effect • Remember that more is not always better • Avoid the exclusive use of top‐down metrics • Provide training—not all metrics are intuitive • Consider temporary metricsConsider temporary metrics 82© 2014 SQE Training V3.2 Avoiding Dysfunction • Define each metric, its use, who will see it, expected  ranges etcranges, etc. • Remember your audience and tailor to their needs • Always seek multiple interpretations • Ask your audience what their interpretation of a  metric is before you offer yoursmetric is before you offer yours • Sell, sell, sell, sell 83© 2014 SQE Training V3.2
  • 43. © 2014 SQE Training V3.2 41 One Truth and One Myth in Closing The Truth Gilb’s Law “Anything you need to quantify can be  measured in some way that is  superior to not measuring it at all” —Tom Gilb The Myth “Some metrics are always better than  no metrics …” 84© 2014 SQE Training V3.2 4 ESTIMATION (OPTIONAL)
  • 44. © 2014 SQE Training V3.2 42 Estimation Estimate: 1. A tentative evaluation or rough calculation  g 2. A preliminary calculation of the cost of a project   3. A judgment based upon one’s impressions; opinion —The American Heritage Dictionary It is very difficult to make a vigorous plausible and job‐It is very difficult to make a vigorous, plausible, and job risking estimate that is derived by no quantitative method,  supported by little data and certified chiefly by hunches of the  managers. — Fred Brooks 87© 2014 SQE Training V3.2 Test Estimation Estimation: the creation of an approximate  target for costs and completion dates   The best estimates Represent the collective wisdom of practitioners and  have their buy‐in g p Provide specific, detailed catalogs of the costs,  resources, tasks, and people involved Present, for each activity estimated, the most likely cost,  effort, and duration 88© 2014 SQE Training V3.2
  • 45. © 2014 SQE Training V3.2 43 Test Estimation (cont.) Factors that can influence cost, effort, and duration include: Required level of quality of the system Size of the system to be tested Historical data Process factors (process maturity, etc.)Process factors (process maturity, etc.) Material factors (tools, data, etc.) People factors (skills, experience, managers, etc.) 89© 2014 SQE Training V3.2 Test Estimation (cont.) • Delivery of estimates should include  j tifi tijustification • Negotiation and re‐work of estimates is  normal • Final estimates represent a balance of  organizational and project goals in the areasorganizational and project goals in the areas  of quality, schedule, budget, and features 90© 2014 SQE Training V3.2
  • 46. © 2014 SQE Training V3.2 44 How Good Is Our Industry (at Estimating)? • Tata: 62% of projects fail to meet schedule 49% have budget overruns • Moiokken and Jorgensen: 30-40% overruns 91© 2014 SQE Training V3.2 Class Discussion Why is estimating not done well? Y t fiYour top five reasons: 1) Too many variables____________________ 2) ____________________________________ 3) ____________________________________ 4) ____________________________________ 5) ____________________________________ 92© 2014 SQE Training V3.2
  • 47. © 2014 SQE Training V3.2 45 Why Estimates Are Inaccurate ― Part I • Lack of estimating experience • Lack of historical data on which to base estimates • Lack of systematic estimation process sound• Lack of systematic estimation process, sound  techniques, or models suited to the project • Failure to include essential activities and products  within the scope of the estimates • Unrealistic expectations or assumptions • Failure to recognize and address the uncertainty  inherent in project estimatesinherent in project estimates Practical Software Measurement Addison‐Wesley, 2001 93© 2014 SQE Training V3.2 Why Estimates Are Inaccurate ― Part II • Lack of education and training • Confusing the target with the estimate • Hope‐based planning • Inability to communicate and support  estimates • Incomplete, changing, and creeping  requirements • Quality surprises (test and re‐fix)• Quality surprises (test and re‐fix) —adapted from Linda M. Laird The Limitations of Estimation 94© 2014 SQE Training V3.2
  • 48. © 2014 SQE Training V3.2 46 Bohem’s Cone of Uncertainty 95© 2014 SQE Training V3.2 NHC Track Forecast Cone 96© 2014 SQE Training V3.2
  • 49. © 2014 SQE Training V3.2 47 “Testing” Track Forecast Cone (or why it is important to constantly re-estimate) Tasks T i m e 97© 2014 SQE Training V3.2 The Fantasy Factor Today 1st 3rd 2nd Weeks 0 1 2 3 4 5 6 7 8 9 What would have to happen to deliver this in four  weeks?weeks? What should the estimate have been? 98© 2014 SQE Training V3.2
  • 50. © 2014 SQE Training V3.2 48 Estimation 1, 2, 3, or 4 Variables + Many Modifiers:  Time If it’s not variable, then it’s fixed. Size Resources 99© 2014 SQE Training V3.2 Time vs. Resources = 100© 2014 SQE Training V3.2
  • 51. © 2014 SQE Training V3.2 49 Test Estimation Techniques ― Examples • Intuition and guess • Work‐breakdown‐structures • Three‐point estimates • Company standards and norms • % of project effort or staffing • Industry averages and predictive models (e.g., FP, TPA ) • Team estimation sessions d b d l h– Wideband Delphi – Story point  sizing – Poker estimation – T‐shirt sizing 101© 2014 SQE Training V3.2 Karl Wiegers’s Estimation Safety Tips • A goal is not an estimate • The estimate you produce should be unrelated  to what you think the requester wants to hear • The correct answer to any request for an  estimate is “Let me get back to you on that”estimate is “Let me get back to you on that” • Avoid giving single point estimates • Incorporate contingency buffers into estimates 102© 2014 SQE Training V3.2
  • 52. © 2014 SQE Training V3.2 50 Rick Craig’s Tips for Better Estimates • Do it! • Collect metrics • Remember the “fantasy” factor• Remember the  fantasy  factor • Don’t “pad” your estimates* • Don’t spend a ton of time • Estimates don’t have to be perfect – Estimates are just estimates – They will change/constantly as you re‐estimate – Remember planning risks and contingenciesp g g – Remember Brooke’s Law • If the date is fixed, estimate something else • Use tools • Use ranges of value instead of discrete numbers 103© 2014 SQE Training V3.2

×