2010-RTA Corona Transit Center Update

2,265 views
2,037 views

Published on

Corona California Tranist Center Construction Update. January 2010

Published in: News & Politics
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
2,265
On SlideShare
0
From Embeds
0
Number of Embeds
13
Actions
Shares
0
Downloads
1
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

2010-RTA Corona Transit Center Update

  1. 1. Corona Transit Center Project Update Riverside Transit Agency Board of Directors January 28, 2010
  2. 2. <ul><ul><li>2.1 acres </li></ul></ul><ul><ul><li>8 bus bays </li></ul></ul><ul><ul><li>26 parking stalls </li></ul></ul><ul><ul><li>Covered pedestrian plaza </li></ul></ul><ul><ul><li>Elevator/bridge connection to Metrolink </li></ul></ul>
  3. 3. Pedestrian Bridge
  4. 7. Corona Transit Center <ul><ul><li>Groundbreaking November 20, 2009 </li></ul></ul><ul><ul><li>Construction began on November 23, 2009 </li></ul></ul><ul><ul><li>To date 2,500 man-hours on the project </li></ul></ul><ul><ul><li>Communication with the City and the Railroad is good </li></ul></ul><ul><ul><li>Completion in August 2010 </li></ul></ul>
  5. 8. Construction Site <ul><ul><li>Debris removal </li></ul></ul><ul><ul><ul><li>1,500 feet of fence </li></ul></ul></ul><ul><ul><ul><li>300 feet of a rail spur </li></ul></ul></ul><ul><ul><ul><li>Approximately 2 acres of buried asphalt </li></ul></ul></ul><ul><ul><ul><li>One 1,300 sq-foot loading dock </li></ul></ul></ul><ul><ul><li>Grading </li></ul></ul><ul><ul><ul><li>Required to raise the site 4-6 feet </li></ul></ul></ul><ul><ul><ul><li>Imported 11,500 cubic yards of soil, 895 truckloads of dirt </li></ul></ul></ul>
  6. 11. North Retaining Wall <ul><ul><li>210 cubic yards of concrete in wall </li></ul></ul><ul><ul><li>238 cubic yards of concrete in footing </li></ul></ul><ul><ul><li>9’ tall, 708’ long, 1’ thick </li></ul></ul>
  7. 14. Note the change in elevation
  8. 15. Cast in place wall (CIP) Saves time & money and is just as strong
  9. 23. Rain <ul><li>To date there have been 12 rain days </li></ul><ul><li>1 million gallons of runoff went through the site without catastrophic results </li></ul>
  10. 24. Next Steps <ul><ul><li>Tower foundations </li></ul></ul><ul><ul><li>South retaining wall construction </li></ul></ul><ul><ul><li>Solar panels for powering center </li></ul></ul>

×