SlideShare a Scribd company logo
1 of 20
Diploma Project Management
       Captain Cook College
                Sharon Boyle
   Presentation –
   Revision of last week’s terms
   Cost management techniques – some detail as
    requested
   Time to catch up and finalise LMS
   Morning Tea
   Balance of cost unit
    ◦ SB Cost Unit started last week & finish tomorrow
   Everyone continues with Cost
    ◦ Today & Friday – completing cost Friday 23 August
1.   EVM an overview
2.   Basic Elements
3.   Cost Variances
4.   Schedule Variances
   tracking tools upon which to base forecasts
   Integrates scope, schedule & cost
   Answers many questions stakeholders need
   Performance can be shown as
    ◦ Past
    ◦ Current
    ◦ Predictive
   Promises to reduce over-runs
   financial analysis specialty from United States
    Government programs in the 1960s,
   Now significant branch of project
    management.
   In the late 1980s and early 1990s, EVM
    emerged as a project management
    methodology
   EVM has become an essential part of every
    project tracking.
   http://www.youtube.com/watch?v=7WsfuvHe
    gxE&feature=related
   Planned Value
    ◦ (PV) = PV or Budgeted cost of work scheduled BCWS
      = Hourly Rate * Total Hours Planned or Scheduled
   Actual Cost
    ◦ (AC) = hourly rate x total hours spent
   Earned Value
    ◦ (EV)= Baselined costs x % complete
   % Completed Planned
    ◦ % Completed planning =PV/BAC
   Cost Variance (CV) indicates how much over
    or under budget the project is.
   Why is under cost a problem?
   (CV) = Earned Value (EV) – Actual Cost (AC)

   Also
   CV = BCWP – ACWP
    ◦ Positive Cost Variance Indicates the project is under
      budget
    ◦ Negative Cost Variance Indicates the project is over
      budget
   Cost Variance % - how much over or under
    budget the project is in terms of percentage

   CV% = CV/EV
    ◦ Or
   CV% = CV/Budgeted Cost of Work
   CPI = EV/AC

   Shows how efficient we are
   Above 1 good efficiency
   Below 1 project not using resources
    efficiently
   TCPI = Total Budget – EV/Total Budget – AC

   Another measure of efficiency –
    ◦ The correct people do the correct things within a
      clear process
    ◦ Above 1 utilization must be stringent
    ◦ Below 1 lenient.
    Schedule Variance (SV) = Earned Value (EV) -
    Planned Value (PV)

   How much is yet to be completed as per
    schedule
   +ve Schedule variances = we are ahead of
    time
   -ve Schedule variance = we are behind
    schedule
   Then same % as for Costs
   Budget at Completion = total budget

   BAC = Baselined effort hours x hourly rate

   Estimate to complete – just what it says.
   Estimate hours required x hourly rate
   1. Assist with the
    development of the project
    budget
   2. Monitor project costs
   3. Contribute to cost
    finalisation process
   Determine
    ◦ estimated costs for tasks & activities and
    ◦ communicate these costs to others for inclusion in
      project budget
   Map costs against
    ◦ duration /effort &
    ◦ resources allocated, and
    ◦ communicate to project manager for inclusion
      project plan,
      budget
      expenditure flow
   Contribute to
    ◦ development of cost management strategies &
      processes,
    ◦ financial authorisation within delegated authority
   Monitor income and expenditure against
    ◦ agreed project plan
    ◦ budgets to facilitate cost management throughout
      the project life cycle
   Use established cost management methods,
    techniques & tools
   Implement & monitor
    ◦ agreed actions
    ◦ report progress
   Project records
    ◦   cost management lessons learned
    ◦   cost verification and validation documentation
    ◦   input to cost management plans
    ◦   invoice and payment records
    ◦   lists of potential costs
    ◦   project and/or organisation files and records
    ◦   reports to relevant stakeholders
   Provide assistance in the finalisation and transfer
    of financial assets, liabilities and records to the
    client or relevant operational support agency

   Provide assistance in the review of project
    outcomes by use of project records, to determine
    the effectiveness of initial and subsequent cost
    management strategies and processes

   Report cost management issues and responses to
    project/program manager for application in
    future projects
   Assessment Item 1
   Cost Estimating
   Use template for Fred’s shed budget
       Completed cost estimates

   Assessment Item 2
   Finalisation & handover report Documents
       Completed templates

More Related Content

What's hot

Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniquesWissem Amara
 
Cost unit 2012 part 2
Cost unit 2012   part 2Cost unit 2012   part 2
Cost unit 2012 part 2Skript
 
Cost unit 2013 part 1. 18 jan
Cost unit 2013 part 1. 18 janCost unit 2013 part 1. 18 jan
Cost unit 2013 part 1. 18 janSkript
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...Tipsographic . com
 
Cost management plan tyre recycling plant
Cost management plan  tyre recycling plantCost management plan  tyre recycling plant
Cost management plan tyre recycling plantabhishekthakur309
 
Project Management 5 Cost Management
Project Management 5 Cost ManagementProject Management 5 Cost Management
Project Management 5 Cost Managementgrmkslideshare
 
Quality unit 2012 part 1. day 1 - 31 jan
Quality unit 2012   part 1. day 1 - 31 janQuality unit 2012   part 1. day 1 - 31 jan
Quality unit 2012 part 1. day 1 - 31 janSkript
 
Cost unit 2013 part 1. 17 jan
Cost unit 2013 part 1. 17  janCost unit 2013 part 1. 17  jan
Cost unit 2013 part 1. 17 janSkript
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 
Summary of key project manager actions & results
Summary of key project manager actions & resultsSummary of key project manager actions & results
Summary of key project manager actions & resultsTut Andrei-Eugen
 

What's hot (19)

project monitoring and control
project monitoring and controlproject monitoring and control
project monitoring and control
 
Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniques
 
For expressways
For expresswaysFor expressways
For expressways
 
Cost unit 2012 part 2
Cost unit 2012   part 2Cost unit 2012   part 2
Cost unit 2012 part 2
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
Cost unit 2013 part 1. 18 jan
Cost unit 2013 part 1. 18 janCost unit 2013 part 1. 18 jan
Cost unit 2013 part 1. 18 jan
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
 
Cost management
Cost managementCost management
Cost management
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
Cost management plan tyre recycling plant
Cost management plan  tyre recycling plantCost management plan  tyre recycling plant
Cost management plan tyre recycling plant
 
Project Management 5 Cost Management
Project Management 5 Cost ManagementProject Management 5 Cost Management
Project Management 5 Cost Management
 
Quality unit 2012 part 1. day 1 - 31 jan
Quality unit 2012   part 1. day 1 - 31 janQuality unit 2012   part 1. day 1 - 31 jan
Quality unit 2012 part 1. day 1 - 31 jan
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Cost unit 2013 part 1. 17 jan
Cost unit 2013 part 1. 17  janCost unit 2013 part 1. 17  jan
Cost unit 2013 part 1. 17 jan
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Summary of key project manager actions & results
Summary of key project manager actions & resultsSummary of key project manager actions & results
Summary of key project manager actions & results
 

Viewers also liked

Cert iv time unit 2 assessments gantt charts 13 nov
Cert iv  time unit 2 assessments  gantt charts 13 novCert iv  time unit 2 assessments  gantt charts 13 nov
Cert iv time unit 2 assessments gantt charts 13 novSkript
 
Time unit 2012 nov 12 part 1
Time unit 2012 nov 12   part 1 Time unit 2012 nov 12   part 1
Time unit 2012 nov 12 part 1 Skript
 
Implementation
ImplementationImplementation
Implementationdbgray00
 
Cost management and performance evaluation in petroleum upstream industry part b
Cost management and performance evaluation in petroleum upstream industry part bCost management and performance evaluation in petroleum upstream industry part b
Cost management and performance evaluation in petroleum upstream industry part bHamdy Rashed
 
Scope part 2 day 1
Scope part 2 day 1 Scope part 2 day 1
Scope part 2 day 1 Skript
 
Monitoring Challenges - Monitorama 2016 - Monitoringless
Monitoring Challenges - Monitorama 2016 - MonitoringlessMonitoring Challenges - Monitorama 2016 - Monitoringless
Monitoring Challenges - Monitorama 2016 - MonitoringlessAdrian Cockcroft
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 
The Project Management Process - Week 11 Contemporary Issues
The Project Management Process - Week 11   Contemporary IssuesThe Project Management Process - Week 11   Contemporary Issues
The Project Management Process - Week 11 Contemporary IssuesCraig Brown
 
The Project Management Process - Week 7 Managing Teams
The Project Management Process - Week 7   Managing TeamsThe Project Management Process - Week 7   Managing Teams
The Project Management Process - Week 7 Managing TeamsCraig Brown
 
Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...
Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...
Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...ASPE, Inc.
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project managementBarun_agnihotri
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleAndrew Schwartz
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project ManagementRodolfo Siles
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Jeremy Jay Lim
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.Hagi Sahib
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPTbletindia
 

Viewers also liked (18)

Cert iv time unit 2 assessments gantt charts 13 nov
Cert iv  time unit 2 assessments  gantt charts 13 novCert iv  time unit 2 assessments  gantt charts 13 nov
Cert iv time unit 2 assessments gantt charts 13 nov
 
Time unit 2012 nov 12 part 1
Time unit 2012 nov 12   part 1 Time unit 2012 nov 12   part 1
Time unit 2012 nov 12 part 1
 
Implementation
ImplementationImplementation
Implementation
 
Cost management and performance evaluation in petroleum upstream industry part b
Cost management and performance evaluation in petroleum upstream industry part bCost management and performance evaluation in petroleum upstream industry part b
Cost management and performance evaluation in petroleum upstream industry part b
 
Scope part 2 day 1
Scope part 2 day 1 Scope part 2 day 1
Scope part 2 day 1
 
Monitoring Challenges - Monitorama 2016 - Monitoringless
Monitoring Challenges - Monitorama 2016 - MonitoringlessMonitoring Challenges - Monitorama 2016 - Monitoringless
Monitoring Challenges - Monitorama 2016 - Monitoringless
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
The Project Management Process - Week 11 Contemporary Issues
The Project Management Process - Week 11   Contemporary IssuesThe Project Management Process - Week 11   Contemporary Issues
The Project Management Process - Week 11 Contemporary Issues
 
The Project Management Process - Week 7 Managing Teams
The Project Management Process - Week 7   Managing TeamsThe Project Management Process - Week 7   Managing Teams
The Project Management Process - Week 7 Managing Teams
 
Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...
Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...
Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern Sample
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPT
 
Project management
Project managementProject management
Project management
 
Project management
Project managementProject management
Project management
 

Similar to Cert iv cost part 2

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementHayat Denzi
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systemsLibra chudry
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdfzohir khellouf
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptxYogesh Singh
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfHuyNguyen657394
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business planfarouq umar
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaJoshua Render
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxssusercf695b
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
Cost unit 2012
Cost unit 2012Cost unit 2012
Cost unit 2012Skript
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 

Similar to Cert iv cost part 2 (20)

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systems
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
UNIT-3.pptx
UNIT-3.pptxUNIT-3.pptx
UNIT-3.pptx
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
Cost unit 2012
Cost unit 2012Cost unit 2012
Cost unit 2012
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 

More from Skript

Quality unit 2012 part 1. day 1 - 31 jan
Quality unit 2012   part 1. day 1 - 31 janQuality unit 2012   part 1. day 1 - 31 jan
Quality unit 2012 part 1. day 1 - 31 janSkript
 
Hr unit 2012 part 1
Hr unit 2012 part 1 Hr unit 2012 part 1
Hr unit 2012 part 1 Skript
 
Time unit 2012 nov part 2
Time unit 2012 nov part 2 Time unit 2012 nov part 2
Time unit 2012 nov part 2 Skript
 
Hr unit 2
Hr unit 2Hr unit 2
Hr unit 2Skript
 
Time unit 2012 nov part 2.
Time unit 2012 nov part 2.Time unit 2012 nov part 2.
Time unit 2012 nov part 2.Skript
 
Quality unit 2012
Quality unit 2012 Quality unit 2012
Quality unit 2012 Skript
 
Table of contents_1_without_questions
Table of contents_1_without_questionsTable of contents_1_without_questions
Table of contents_1_without_questionsSkript
 
Templates without questions
Templates without questionsTemplates without questions
Templates without questionsSkript
 
Table of contents_3_without_questions
Table of contents_3_without_questionsTable of contents_3_without_questions
Table of contents_3_without_questionsSkript
 
Table of contents_2_without_questions
Table of contents_2_without_questionsTable of contents_2_without_questions
Table of contents_2_without_questionsSkript
 
Mail merge 2_without_questions
Mail merge 2_without_questionsMail merge 2_without_questions
Mail merge 2_without_questionsSkript
 
Mail merge 1_without_questions
Mail merge 1_without_questionsMail merge 1_without_questions
Mail merge 1_without_questionsSkript
 
Headers footers without_questions
Headers footers without_questionsHeaders footers without_questions
Headers footers without_questionsSkript
 
Headers footers document_selection_without_questions
Headers footers document_selection_without_questionsHeaders footers document_selection_without_questions
Headers footers document_selection_without_questionsSkript
 
Bullets numbering lists_without_questions
Bullets numbering lists_without_questionsBullets numbering lists_without_questions
Bullets numbering lists_without_questionsSkript
 
Backgrounds borders effects_without_questions
Backgrounds borders effects_without_questionsBackgrounds borders effects_without_questions
Backgrounds borders effects_without_questionsSkript
 
Bsbled401 a develop_teams_and_individuals_sah 2012
Bsbled401 a develop_teams_and_individuals_sah 2012Bsbled401 a develop_teams_and_individuals_sah 2012
Bsbled401 a develop_teams_and_individuals_sah 2012Skript
 
Cert iv time unit 1
Cert iv  time unit 1Cert iv  time unit 1
Cert iv time unit 1Skript
 
Cert iv time unit 1 lms
Cert iv  time unit 1 lmsCert iv  time unit 1 lms
Cert iv time unit 1 lmsSkript
 
Scope part 1 day 1
Scope part 1 day 1 Scope part 1 day 1
Scope part 1 day 1 Skript
 

More from Skript (20)

Quality unit 2012 part 1. day 1 - 31 jan
Quality unit 2012   part 1. day 1 - 31 janQuality unit 2012   part 1. day 1 - 31 jan
Quality unit 2012 part 1. day 1 - 31 jan
 
Hr unit 2012 part 1
Hr unit 2012 part 1 Hr unit 2012 part 1
Hr unit 2012 part 1
 
Time unit 2012 nov part 2
Time unit 2012 nov part 2 Time unit 2012 nov part 2
Time unit 2012 nov part 2
 
Hr unit 2
Hr unit 2Hr unit 2
Hr unit 2
 
Time unit 2012 nov part 2.
Time unit 2012 nov part 2.Time unit 2012 nov part 2.
Time unit 2012 nov part 2.
 
Quality unit 2012
Quality unit 2012 Quality unit 2012
Quality unit 2012
 
Table of contents_1_without_questions
Table of contents_1_without_questionsTable of contents_1_without_questions
Table of contents_1_without_questions
 
Templates without questions
Templates without questionsTemplates without questions
Templates without questions
 
Table of contents_3_without_questions
Table of contents_3_without_questionsTable of contents_3_without_questions
Table of contents_3_without_questions
 
Table of contents_2_without_questions
Table of contents_2_without_questionsTable of contents_2_without_questions
Table of contents_2_without_questions
 
Mail merge 2_without_questions
Mail merge 2_without_questionsMail merge 2_without_questions
Mail merge 2_without_questions
 
Mail merge 1_without_questions
Mail merge 1_without_questionsMail merge 1_without_questions
Mail merge 1_without_questions
 
Headers footers without_questions
Headers footers without_questionsHeaders footers without_questions
Headers footers without_questions
 
Headers footers document_selection_without_questions
Headers footers document_selection_without_questionsHeaders footers document_selection_without_questions
Headers footers document_selection_without_questions
 
Bullets numbering lists_without_questions
Bullets numbering lists_without_questionsBullets numbering lists_without_questions
Bullets numbering lists_without_questions
 
Backgrounds borders effects_without_questions
Backgrounds borders effects_without_questionsBackgrounds borders effects_without_questions
Backgrounds borders effects_without_questions
 
Bsbled401 a develop_teams_and_individuals_sah 2012
Bsbled401 a develop_teams_and_individuals_sah 2012Bsbled401 a develop_teams_and_individuals_sah 2012
Bsbled401 a develop_teams_and_individuals_sah 2012
 
Cert iv time unit 1
Cert iv  time unit 1Cert iv  time unit 1
Cert iv time unit 1
 
Cert iv time unit 1 lms
Cert iv  time unit 1 lmsCert iv  time unit 1 lms
Cert iv time unit 1 lms
 
Scope part 1 day 1
Scope part 1 day 1 Scope part 1 day 1
Scope part 1 day 1
 

Cert iv cost part 2

  • 1. Diploma Project Management Captain Cook College Sharon Boyle
  • 2. Presentation –  Revision of last week’s terms  Cost management techniques – some detail as requested  Time to catch up and finalise LMS  Morning Tea  Balance of cost unit ◦ SB Cost Unit started last week & finish tomorrow  Everyone continues with Cost ◦ Today & Friday – completing cost Friday 23 August
  • 3. 1. EVM an overview 2. Basic Elements 3. Cost Variances 4. Schedule Variances
  • 4. tracking tools upon which to base forecasts  Integrates scope, schedule & cost  Answers many questions stakeholders need  Performance can be shown as ◦ Past ◦ Current ◦ Predictive  Promises to reduce over-runs
  • 5. financial analysis specialty from United States Government programs in the 1960s,  Now significant branch of project management.  In the late 1980s and early 1990s, EVM emerged as a project management methodology  EVM has become an essential part of every project tracking.
  • 6. http://www.youtube.com/watch?v=7WsfuvHe gxE&feature=related
  • 7. Planned Value ◦ (PV) = PV or Budgeted cost of work scheduled BCWS = Hourly Rate * Total Hours Planned or Scheduled  Actual Cost ◦ (AC) = hourly rate x total hours spent  Earned Value ◦ (EV)= Baselined costs x % complete  % Completed Planned ◦ % Completed planning =PV/BAC
  • 8. Cost Variance (CV) indicates how much over or under budget the project is.  Why is under cost a problem?  (CV) = Earned Value (EV) – Actual Cost (AC)  Also  CV = BCWP – ACWP ◦ Positive Cost Variance Indicates the project is under budget ◦ Negative Cost Variance Indicates the project is over budget
  • 9. Cost Variance % - how much over or under budget the project is in terms of percentage  CV% = CV/EV ◦ Or  CV% = CV/Budgeted Cost of Work
  • 10. CPI = EV/AC  Shows how efficient we are  Above 1 good efficiency  Below 1 project not using resources efficiently
  • 11. TCPI = Total Budget – EV/Total Budget – AC  Another measure of efficiency – ◦ The correct people do the correct things within a clear process ◦ Above 1 utilization must be stringent ◦ Below 1 lenient.
  • 12. Schedule Variance (SV) = Earned Value (EV) - Planned Value (PV)  How much is yet to be completed as per schedule  +ve Schedule variances = we are ahead of time  -ve Schedule variance = we are behind schedule  Then same % as for Costs
  • 13. Budget at Completion = total budget  BAC = Baselined effort hours x hourly rate  Estimate to complete – just what it says.  Estimate hours required x hourly rate
  • 14.
  • 15. 1. Assist with the development of the project budget  2. Monitor project costs  3. Contribute to cost finalisation process
  • 16. Determine ◦ estimated costs for tasks & activities and ◦ communicate these costs to others for inclusion in project budget  Map costs against ◦ duration /effort & ◦ resources allocated, and ◦ communicate to project manager for inclusion  project plan,  budget  expenditure flow  Contribute to ◦ development of cost management strategies & processes, ◦ financial authorisation within delegated authority
  • 17. Monitor income and expenditure against ◦ agreed project plan ◦ budgets to facilitate cost management throughout the project life cycle  Use established cost management methods, techniques & tools  Implement & monitor ◦ agreed actions ◦ report progress
  • 18. Project records ◦ cost management lessons learned ◦ cost verification and validation documentation ◦ input to cost management plans ◦ invoice and payment records ◦ lists of potential costs ◦ project and/or organisation files and records ◦ reports to relevant stakeholders
  • 19. Provide assistance in the finalisation and transfer of financial assets, liabilities and records to the client or relevant operational support agency  Provide assistance in the review of project outcomes by use of project records, to determine the effectiveness of initial and subsequent cost management strategies and processes   Report cost management issues and responses to project/program manager for application in future projects
  • 20. Assessment Item 1  Cost Estimating  Use template for Fred’s shed budget Completed cost estimates  Assessment Item 2  Finalisation & handover report Documents Completed templates