Cert iv  cost part 2
Upcoming SlideShare
Loading in...5
×
 

Cert iv cost part 2

on

  • 607 views

 

Statistics

Views

Total Views
607
Views on SlideShare
603
Embed Views
4

Actions

Likes
0
Downloads
2
Comments
0

1 Embed 4

http://ccc-lms.com.au 4

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

Cert iv  cost part 2 Cert iv cost part 2 Presentation Transcript

  • Diploma Project Management Captain Cook College Sharon Boyle
  •  Presentation – Revision of last week’s terms Cost management techniques – some detail as requested Time to catch up and finalise LMS Morning Tea Balance of cost unit ◦ SB Cost Unit started last week & finish tomorrow Everyone continues with Cost ◦ Today & Friday – completing cost Friday 23 August
  • 1. EVM an overview2. Basic Elements3. Cost Variances4. Schedule Variances View slide
  •  tracking tools upon which to base forecasts Integrates scope, schedule & cost Answers many questions stakeholders need Performance can be shown as ◦ Past ◦ Current ◦ Predictive Promises to reduce over-runs View slide
  •  financial analysis specialty from United States Government programs in the 1960s, Now significant branch of project management. In the late 1980s and early 1990s, EVM emerged as a project management methodology EVM has become an essential part of every project tracking.
  •  http://www.youtube.com/watch?v=7WsfuvHe gxE&feature=related
  •  Planned Value ◦ (PV) = PV or Budgeted cost of work scheduled BCWS = Hourly Rate * Total Hours Planned or Scheduled Actual Cost ◦ (AC) = hourly rate x total hours spent Earned Value ◦ (EV)= Baselined costs x % complete % Completed Planned ◦ % Completed planning =PV/BAC
  •  Cost Variance (CV) indicates how much over or under budget the project is. Why is under cost a problem? (CV) = Earned Value (EV) – Actual Cost (AC) Also CV = BCWP – ACWP ◦ Positive Cost Variance Indicates the project is under budget ◦ Negative Cost Variance Indicates the project is over budget
  •  Cost Variance % - how much over or under budget the project is in terms of percentage CV% = CV/EV ◦ Or CV% = CV/Budgeted Cost of Work
  •  CPI = EV/AC Shows how efficient we are Above 1 good efficiency Below 1 project not using resources efficiently
  •  TCPI = Total Budget – EV/Total Budget – AC Another measure of efficiency – ◦ The correct people do the correct things within a clear process ◦ Above 1 utilization must be stringent ◦ Below 1 lenient.
  •  Schedule Variance (SV) = Earned Value (EV) - Planned Value (PV) How much is yet to be completed as per schedule +ve Schedule variances = we are ahead of time -ve Schedule variance = we are behind schedule Then same % as for Costs
  •  Budget at Completion = total budget BAC = Baselined effort hours x hourly rate Estimate to complete – just what it says. Estimate hours required x hourly rate
  •  1. Assist with the development of the project budget 2. Monitor project costs 3. Contribute to cost finalisation process
  •  Determine ◦ estimated costs for tasks & activities and ◦ communicate these costs to others for inclusion in project budget Map costs against ◦ duration /effort & ◦ resources allocated, and ◦ communicate to project manager for inclusion  project plan,  budget  expenditure flow Contribute to ◦ development of cost management strategies & processes, ◦ financial authorisation within delegated authority
  •  Monitor income and expenditure against ◦ agreed project plan ◦ budgets to facilitate cost management throughout the project life cycle Use established cost management methods, techniques & tools Implement & monitor ◦ agreed actions ◦ report progress
  •  Project records ◦ cost management lessons learned ◦ cost verification and validation documentation ◦ input to cost management plans ◦ invoice and payment records ◦ lists of potential costs ◦ project and/or organisation files and records ◦ reports to relevant stakeholders
  •  Provide assistance in the finalisation and transfer of financial assets, liabilities and records to the client or relevant operational support agency Provide assistance in the review of project outcomes by use of project records, to determine the effectiveness of initial and subsequent cost management strategies and processes Report cost management issues and responses to project/program manager for application in future projects
  •  Assessment Item 1 Cost Estimating Use template for Fred’s shed budget Completed cost estimates Assessment Item 2 Finalisation & handover report Documents Completed templates