Bts offline commissioning alcatel lucent

  1. 1. BTS Offline Commissioning Procedure (Alcatel-Lucent) : BY : S.Qaisar Shah BS Telecom,CCNA,CWNA.1st Step : Open Alcatel Lucent Software.
  2. 2. 2nd Step : Write UserName And PasswordUsername : commtePaswd : bts2site
  3. 3. 3rd Step : Go to Interface Setting
  4. 4. 4th Step : Go to Configuration Click On BTS Software Download
  5. 5. 5th Step : Select Master File And OCPF File and click OK.
  6. 6. 6th Step : No Go to Configuration Click On BTS Commissioning.
  7. 7. 7th Step : Click On Start Commissioning.
  8. 8. 8th Step : Go to Edit Q1 Address Type Q1.Address With 1 in start.
  9. 9. 9th Step : Go to Twin-TRA Setting Mark All Dual TRE.
  10. 10. 10th Step : Go to Modify Sector Mapping Do the same as in Pic below.11th Step : Go to Hardware Check And Close.
  11. 11. 12th Step : Go to Fan Test Mark All High and click Start.
  12. 12. 13th Step : Now Click On End Commissioning.

×