PMP Exam Preparation Course: 06 Project Cost Management


Published on

Presentation was prepared based on PMBOK 4th Edition

Published in: Education, Business, Technology
  • Be the first to comment

No Downloads
Total Views
On Slideshare
From Embeds
Number of Embeds
Embeds 0
No embeds

No notes for slide

PMP Exam Preparation Course: 06 Project Cost Management

  1. 1. | contact@wizardea.comB. M. Shahrier Majumder, PMPPMP® Exam Preparation
  2. 2. Project Cost Management
  3. 3. | contact@wizardea.comLearning ObjectivesUpon completion of this topic you will learn about– The processes, activities and documentation items for Project CostManagement– Elements (and deliverables) for Project Cost Management– Tools and techniques of the key activities of the Project CostManagement3
  4. 4. | contact@wizardea.comCost ManagementProject Cost Management includes the processes involved in planning,estimating, budgeting and controlling costs so that the project can becompleted within the approved budget.4
  5. 5. | contact@wizardea.comKey Activities of Cost Management• Estimate Cost: The process of developing an approximation of themonetary resources needed to complete project activities.• Determine Budget: The process of aggregating the estimated costs ofindividual activities or work packages to establish an authorized costbaseline.• Control Cost: The process of monitoring the status of the project toupdate the project budget and managing changes to the cost baseline.5
  6. 6. | contact@wizardea.comEstimate Cost | Data Flow Diagram
  7. 7. | contact@wizardea.comEstimate CostInputs Tools & Techniques OutputsScope baselineProject scheduleHuman resource PlanRisk registerEnterprise environmentalfactorsOrganizational processassetsExpert judgmentAnalogous estimatingParametric estimatingBottom-up estimatingThree point estimatingReserve analysisCost of qualityProject managementestimating softwareVendor bid analysisActivity cost estimatesBasis of estimatesProject document updates
  8. 8. | contact@wizardea.comEstimate > Inputs Enterprise Environmental Factors Market place condition Commercial database Organizational Process Assets Cost estimating policies Cost estimating templates Historical information Project knowledge database Lesson learn database8
  9. 9. | contact@wizardea.comEstimate Cost > Tools and Techniques• Bottom-up estimating• Estimates made at the work-package of the WBS and rolled up• Very accurate• Needs sufficient information to make an accurate estimate• Vendor Bid Analysis• Analysis of what the project should cost, based on the responsive bidsfrom qualified vendors. Where project are awarded to a vendor undercompetitive processes , additional cost estimating work can berequired of the project team to examine the price of individualdeliverables and to deliver the cost that supports the final total projectcost.9
  10. 10. | contact@wizardea.comDetermine Budget | Data Flow Diagram
  11. 11. | contact@wizardea.comDetermine BudgetInputs Tools & Techniques OutputsActivity cost estimatesBasis of estimatesScope baselineProject scheduleResources calendarsContractOrganization processassetsCost aggregationReserve analysisExpert judgmentHistorical relationshipsFunding limit reconciliationCost performance baselineProject fundingrequirementsProject document updates
  12. 12. | contact@wizardea.comDetermine Budget > Tools and Techniques• Cost Aggregation12
  13. 13. | contact@wizardea.comDetermine Budget > Tools and Techniques• Funding Limit Reconciliation• The expenditure of funds should be reconciled with any fundinglimit of the commitment of funds for the project.• A variance between funding limits and the planed expenditureswill sometimes necessitate the rescheduling of work to level outthe rate of expenditures.13
  14. 14. | contact@wizardea.comDetermine Budget > Outputs• Cost Performance Baseline– A time-phased budget that is usedto measure and monitor costperformance on a project– The approved cost estimates– Displayed graphically ascumulative costs over time– Displayed as an S-Curve14• Funding Requirements– Total and periodic fundingrequirements, are derived fromthe cost baseline and canestablished to exceed, usually bya margin to allow for either earlyprogress or cost overrun.
  15. 15. | contact@wizardea.comControl Costs
  16. 16. | contact@wizardea.comControl CostsInputs Tools & Techniques OutputsProject management planProject fundingrequirementsWork performanceinformationOrganizational processassetsEared value managementForecastingTo complete performanceindexPerformance reviewsVariance analysisProject managementsoftwareWork performancemeasurementsBudget forecastsOrganizational processassets updatesChange requestsProject management planupdatesProject document updates
  17. 17. | contact@wizardea.comControl Cost > Tools and Techniques• Earned Value Management (EVM)• EVM in its various forms is a commonly used method ofperformance measurement. It integrates project scope, cost andschedule measures to help project management team assessan measure project performance and progress.• EVM develops and monitors three key dimensions of each workpackage and control account. These are Planned Value (PV),Earned Value (EV) and Actual Cost (AC).17
  18. 18. | contact@wizardea.comControl Cost > Tools and Techniques• Terms to be remember:18Abbr. Name FormulaBAC Budget at Completion How much did we budget for the TOTAL project effort?PV Planned Value What is the estimated value of the work planned to be done asof now?EV Earn Value What is the estimated value of the work actually accomplishedas of now?AC Actual Cost What is the actual cost incurred for the work accomplished?CV Cost Variance Currently project is over budgeted or under budgeted?SV Schedule Variance Currently project is ahead of schedule or behind of schedule?CPI Cost Performance Index How much worth of work we are getting out of every $1 spent.SPI Schedule Performance Index What is our progress at percent of the rate originally planned?EAC Estimate at Completion What do we currently expect the TOTAL project to cost?VAC Variance at Completion How much over or under budget do we expect to be at the endof the project?ETC Estimate to Complete From this point of now, how much more do we expect it to costto finish the project?
  19. 19. | contact@wizardea.comControl Cost > Tools and Techniques• Earned Value Analysis19Abbr. Name Formula Good BadEV Earn Value BAC x Percent Complete NA NAPV Planned Value BAC x Percent Duration NA NACV Cost Variance EV-AC +ve -veSV Schedule Variance EV-PV +ve -veCPI Cost Performance Index EV/AC >1 <1SPI Schedule Performance Index EV/PV >1 <1CV% Cost Variance Percentage CV/EV +ve -veSV% Schedule Variance Percentage SV/PV +ve -veEAC Estimate at Completion BAC/CPI <BAC >BACVAC Variance at Completion BAC-EAC +ve -veETC Estimate to Complete EAC-AC NA NA
  20. 20. | contact@wizardea.comControl Cost > Tools and Techniques• Exercise– Total Budget = $2975– % Duration complete: 60%– % Complete = 59%– Actual Cost = 1575– Find out the all values as per EVM formula table.20
  21. 21. | contact@wizardea.comProject Selection Method• Present Value• Net Present Value• IRR (Internal Rate of Return): The rate at which the project inflows(revenue) and outflows (cost) are equal.• Payback Period• Benefit Cost Ratio21
  22. 22. | contact@wizardea.comCost Management > Some Important Definition• Present Value: The value of future cash flows– Formula (PV = (FV/(1+r)n [ Here, PV = Present Value, FV =Future Value, r = Interest Rate, n = Number of time periods]• Net Present Value: The difference between the present value ofcash inflows and the present value of cash outflows.• IRR (Internal Rate of Return): The rate at which the project inflows(revenue) and outflows (cost) are equal.22
  23. 23. | contact@wizardea.comCost Management > Some Important Definition• Payback Period: The number of time periods it takes to recover yourinvestment in the project before you start accumulating profit.• Benefit Cost Ratio: Benefit cost ratio > 1 means the benefits aregrater than the costs.• Sunk Cost: Money already spent and permanently lost.23
  24. 24. | contact@wizardea.comQuestions24• []•
  1. A particular slide catching your eye?

    Clipping is a handy way to collect important slides you want to go back to later.