A Report on HAZOP Analysis
CONTENTS
1. Introduction
2. HAZOP Preparation
 Selection of HAZOP study team members
 Information required for HAZOP study
 Other responsibilities
3. HAZOP Terminology
 System
 Design Intent
 HAZOP Guide words
 Safeguards & Recommendations
 HAZOP Study Record & Risk Assessment
4. HAZOP Meeting Procedure
5. HAZOP Following Up actions
6. HAZOP Closure
7. Documentation
1. Introduction
Increasing demand by governments and public bodies for improved safety in addition
to a strong awareness within the industry that safe operation can also be highly efficient
and profitable, support the need for plant safety and effective safety management.
Advances in technology and trends to highly complex and integrated plant designs have
sensitized people for systematic and sustainable methods to identify hazards of which the
HAZOP study is generally recognized as the foremost solution being able to cover standard
and also new complex technology.
A Hazard and Operability (HAZOP) study is a structured and systematic examination of
a planned or existing process or operation in order to identify and evaluate problems that
may represent a risk to personnel or equipment, or prevent efficient operation. A HAZOP is
a qualitative technique based on "guide words" and is carried out by a multi-disciplinary
team (the HAZOP Team) during one or more meetings.
A HAZOP is a design verification process. It should not be used as a design development
process. The HAZOP should be performed at the stage in the design process when all
preliminary engineering is complete and the basic design has been fixed. This includes
complete process design, process flow diagrams, P&ID’s, plant and equipment layout,
operating philosophy, control and instrumentation philosophy, utilities requirements,
specification and selection of major equipment items, protection systems, start up and
shutdown systems.
2. HAZOP Preparation
It is the responsibility of the Responsible Officer to initiate the HAZOP study where the
project or modification meets the criteria.
 Selection of HAZOP study team members:
The Responsible Officer will first appoint an independent HAZOP Leader to act as
the Chairperson for the HAZOP meetings. The HAZOP Leader must be trained in HAZOP
methodology and have successfully completed a suitably recognised HAZOP Leader
Course, or equivalent experience, as approved by the Manager - Project Engineering.
The HAZOP Leader should be independent, i.e. with no responsibility for the process or
operations in the area where the process being reviewed is located.
HAZOP studies will be conducted using a team approach, with a minimum of four
members. The Responsible Officer together with the HAZOP Leader will select the
HAZOP team members to achieve the spread of knowledge and skills required for the
particular project, and may include:
1. Representative of the customer
2. A person with Process knowledge
3. A person with Safety & Environmental knowledge
4. A person with operating and/or maintenance experience in comparable
environment.
5. A person with Engineering/Design knowledge
 Information required for HAZOP study
The following information should be assembled by the Responsible Officer and the
HAZOP Leader before the HAZOP study team commences work.
Essential Items:
1. Functionally complete P & ID for the process
2. System design philosophy and process description
Desirable Items:
1. Plot plans or layouts
2. Process flow diagrams
3. Piping class specifications
4. Equipment data sheets and purchase specifications
5. Vessel inventories
6. Relief valve specifications
7. Start up and emergency shut-down procedures
8. Emergency depressurizing system functions
9. Electrical area classification
10. Standards used
11. Procedures - operating and maintenance as applicable
 Other responsibilities
The Responsible Officer is responsible for the following HAZOP study arrangements:
1. Organizing meeting dates, venue and notices to the attendees
2. Layout of venue and supply of stationery and other resources for the meeting
3. Provision of information required for the HAZOP study
4. Close out meeting date, venue and notice to the attendees.
3. HAZOP Terminology
 SYSTEM
A System is a specific location or logical part of the process or operation in which
possible deviations from the design intent are to be evaluated. Examples might be a heat
exchanger, vessel, pump, compressor and interconnecting pipeline or group of lines.
Systems should be progressively identified on the P&ID as the HAZOP study proceeds.
 DESIGN INTENT
The design intent is a description of how the process is expected to behave at the
system being studied. This is qualitatively described as an activity eg feed, reaction,
transfer, heating, and quantitatively in process parameters such as pressure, temperature,
flow rate.
 HAZOP GUIDE WORDS
All possible deviations in process parameters in a reactor or a pipeline are
considered to determine their causes and consequences. If a hazard is identified, first the
existing protective measures are analyzed with respect to the intensity of the hazard. If the
protective measures are not adequate, recommendations are given to mitigate the hazard.
HAZOP study involves a set of standardized GUIDEWORDS, which are required to initiate
analysis.
Examples of process parameters include the following:
Each guide word is combined with relevant process parameters and applied at each point
(study node, process section, or operating step) in the process that is being examined.
The following Table showed examples of creating deviation using guide words and
process parameters:
 Safeguards
Safeguards are facilities, processes or procedures that help to reduce the likelihood
or frequency of the deviation, or to mitigate its consequences.
Examples of safeguards include the following.
1. Procedures to define what actions to take in the event of a deviation.
2. Increased frequency of inspection, servicing or calibration of critical items.
3. Facilities that draw attention to the deviation (eg indicators and alarms to inform
operators so that they can make the process safe).
4. Facilities that automatically compensate for the deviation (eg an automatic control.
5. System, usually an integrated part of the process control).
6. Facilities that prevent the deviation from occurring (eg excess flow valve).
7. Facilities that prevent further escalation of the deviation (eg by total trip of the
activity or process by a safety interlock, control system, or emergency shutdown
(ESD) system).
8. Facilities that relieve the process from a hazardous deviation (eg pressure safety
valve (PSV) and vent systems)
As each cause and consequence scenario is identified, planned safeguards should be
reviewed to determine if they are adequate to either prevent the deviation or to protect the
System if the deviation occurs. Any decision on the adequacy of the safeguards should take
into consideration the magnitude of the potential consequences and the likelihood of the
event occurring with all the planned safeguards in place. This is reflected in the risk
assessment as below. Each scenario will usually have more than a single layer of protection.
For high risk deviations, it is useful to review each of the layers of protection before
determining the adequacy of the safeguards.
 Recommendations
If the HAZOP Team recommends that additional safeguards or changes to the design
should be made to ensure the safety of the system, these recommendations must be
recorded on the HAZOP Record for further action after the HAZOP study. The name of the
person who will be responsible for the further actions should be recorded on the form next
to the assigned action.
 HAZOP study record
HAZOP Study Record form is used to create a historic record of the HAZOP Study.
Details of discussions, decisions taken, risk assessments made and further actions
recommended during evaluation of each of the HAZOP Study Cards will be progressively
recorded by the HAZOP Secretary on the HAZOP Study Record form.
 Risk Assessment
Risk assessments should be carried out to quantify the risks associated with
deviations and their potential consequences, and to assist in determining the adequacy of
planned safeguards and the possible need for further action. An initial informal risk
assessment should be carried out on each cause - consequence scenario based on the
inherent risk in the unprotected state.
The Risk Matrix included in the below table should be used as a guide. The risk
should then be re-assessed taking into consideration the planned safeguards and risk
reduction measures. For less important risks, the need for further action can be based on
the experience and judgment of the HAZOP Study Team.
Once the reasonable consequence and likelihood of each potential unwanted event
is determined, the risk can be ranked using the “Risk Assessment Matrix” below and
recorded on the HAZOP Study Record sheet.
For high risk scenarios, several layers of protection will usually be necessary to
reduce the risk to an acceptable level. If the HAZOP team agrees that, so long as the planned
safeguards are in place, the risk of an unwanted event occurring is reduced to an acceptable
level, then no further action is required.
For extreme risk scenarios, the adequacy of safeguards and the need for further
action should be quantitatively assessed using higher level risk assessment techniques
such as Layer of Protection Analysis (LOPA), or Safety Integrity Level (SIL) analysis. The
risk assessment process and outcome should be recorded on the HAZOP Study Record form
against each item.
4. HAZOP Meeting Procedure
At the HAZOP meeting, the HAZOP Leader will act as Chairperson to lead the team
through each of the following steps.
a) Introduce the project:
 Ensure all team members are familiar with the HAZOP process
 Define the project for the team
 Review the proposed process or modification using the Process and
Instrumentation Diagram (P&ID) and describe its operation
 On the P&ID, divide the process to be studied into logical Systems.
b) Carry out HAZOP Study:
 Select a particular System for detailed review and describe the design intent for that
System. Work through the guide words on the HAZOP Study Cards, following the
HAZOP Process Flow Chart.
 For each guide word, establish if the deviation from normal conditions suggested by
the guide word could occur. If the deviation could occur, identify the possible causes
of the deviation.
 Determine the possible consequences or problems if the deviation occurred.
 Carry out an initial assessment of the risk associated with the identified
consequences Review any proposed safeguards to prevent or mitigate the
consequences.
 Evaluate if the proposed safeguards adequately reduce the risk to an acceptable
level and if not, suggest further actions having regard to the consequences and the
safeguards already proposed.
 Repeat procedure from [step (a)] above for the next System. Progressively complete
HAZOP Study Record form including recording of further actions.
Modifications must be assessed for impact during a variety of plant conditions (ie.
startup, running, plant upset, and plant shutdown). This aspect will be formally
documented where appropriate throughout the HAZOP, and must also feature as a specific
element considered within the agreement and sign-off of the final records of the HAZOP.
5. HAZOP Following Up actions
The Responsible Officer shall ensure that all actions arising from the HAZOP are
properly managed and are completed prior to commencing the modification or
HAZOP PROCESS FLOW CHART
commissioning the modified plant as determined during the HAZOP. The items recorded on
the HAZOP Study Record form SF1309 as requiring action shall be numbered and a
required date of completion established. This information shall be entered into the
“Recommendations” column on the HAZOP Study Record.
6. HAZOP Closure
When all follow-up actions are complete, the Responsible Officer shall note on the
HAZOP Study Record of Discussions (SF 1909) that all items have been completed and
make reference to the Inspection Reference Number in Cintellate. To assist in later
verification, a copy of the complete Cintellate record should be printed out after all actions
have been completed and attached to the HAZOP Study Record in the Project file.
Close out meeting:
The Responsible Officer will arrange a close out meeting to record completion of
outstanding issues.
Once all parties are satisfied that all issues arising from the study have been
adequately addressed and are reflected in the project design documentation, form HAZOP
Study Record of Discussions form shall be completed and signed off by the Responsible
Officer and the Customer Representative.
No commissioning activities associated with the modification or the new plant
covered by the HAZOP shall commence until form HAZOP Study Record of Discussions
(SF1909) has been signed off.
7. Documentation
The following HAZOP study information and documents are required for the files:
a) HAZOP Study Record which includes:
 Project title
 Project number (that is, work order number for the parent project)
 Project scope
 Study date
 Participant names, job titles, organisation, brief profile
b) Signed off HAZOP Study Record of Discussions
c) The original copy of all P&IDs used in the study (with lines clearly identified)
d) Variations in guide words used.
e) Signed off Action Summary sheet
f) Signed off HAZOP Action sheets
The study Responsible Officer is responsible for the preparation and collation of the
output documentation from the HAZOP study, and for forwarding it to all attendees,
including the Chairperson who should sign off the HAZOP Study Record before filing by the
Responsible Officer.
The Responsible Officer ensures an electronic copy the documentation listed above
is filed in the Domino. Doc System in accordance with Management of Risk Assessment
Records. A hard copy of all this documentation will also be filed in the Project File by the
Project Officer.

More Related Content

What's hot

Hazop Hazard and Operability Study
Hazop Hazard and Operability StudyHazop Hazard and Operability Study
Hazop Hazard and Operability StudyAnand kumar
 
Process Hazard Analysis
Process Hazard AnalysisProcess Hazard Analysis
Process Hazard AnalysisNGE
 
Quantative-Risk assessment-Hazop-Study
Quantative-Risk assessment-Hazop-StudyQuantative-Risk assessment-Hazop-Study
Quantative-Risk assessment-Hazop-StudyMassimo Talia
 
Hazop study on sewage treatment plant at educational institution
Hazop study on sewage treatment plant at educational institutionHazop study on sewage treatment plant at educational institution
Hazop study on sewage treatment plant at educational institutioneSAT Publishing House
 
Hazop group 7
Hazop   group 7Hazop   group 7
Hazop group 7Xin Yi
 
HAZOP AND OPERABILITY STUDY
HAZOP AND OPERABILITY STUDY HAZOP AND OPERABILITY STUDY
HAZOP AND OPERABILITY STUDY damomech92
 
SPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT SlidesSPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT Slidesidell bryan
 
Hazop training - Hazard training
Hazop training - Hazard training Hazop training - Hazard training
Hazop training - Hazard training Easwaran Kanason
 
Hazop suplimentry study
Hazop suplimentry studyHazop suplimentry study
Hazop suplimentry studyAneel Ahmad
 
LOPA | Layer Of Protection Analysis | Gaurav Singh Rajput
LOPA | Layer Of Protection Analysis | Gaurav Singh RajputLOPA | Layer Of Protection Analysis | Gaurav Singh Rajput
LOPA | Layer Of Protection Analysis | Gaurav Singh RajputGaurav Singh Rajput
 
Work Permit System
Work Permit SystemWork Permit System
Work Permit SystemGagan Tanwar
 
HZOP-HAZID Presentation by Tony
HZOP-HAZID Presentation by TonyHZOP-HAZID Presentation by Tony
HZOP-HAZID Presentation by TonyAnthony Izegaegbe
 
HAZARD & OPERABILITY STUDY (HAZOP) & MATERIAL SAFETY DATA SHEET (MSDS)
HAZARD & OPERABILITY STUDY (HAZOP) & MATERIAL SAFETY DATA SHEET (MSDS)HAZARD & OPERABILITY STUDY (HAZOP) & MATERIAL SAFETY DATA SHEET (MSDS)
HAZARD & OPERABILITY STUDY (HAZOP) & MATERIAL SAFETY DATA SHEET (MSDS)Angel Darío González-Delgado
 

What's hot (20)

Hazop Hazard and Operability Study
Hazop Hazard and Operability StudyHazop Hazard and Operability Study
Hazop Hazard and Operability Study
 
Process Hazard Analysis
Process Hazard AnalysisProcess Hazard Analysis
Process Hazard Analysis
 
Quantative-Risk assessment-Hazop-Study
Quantative-Risk assessment-Hazop-StudyQuantative-Risk assessment-Hazop-Study
Quantative-Risk assessment-Hazop-Study
 
Hazop study on sewage treatment plant at educational institution
Hazop study on sewage treatment plant at educational institutionHazop study on sewage treatment plant at educational institution
Hazop study on sewage treatment plant at educational institution
 
Hazop & hazan
Hazop & hazanHazop & hazan
Hazop & hazan
 
Hazop ppt
Hazop pptHazop ppt
Hazop ppt
 
14 Tips for Process Safety Management
14 Tips for Process Safety Management14 Tips for Process Safety Management
14 Tips for Process Safety Management
 
Hazop group 7
Hazop   group 7Hazop   group 7
Hazop group 7
 
HAZOP AND OPERABILITY STUDY
HAZOP AND OPERABILITY STUDY HAZOP AND OPERABILITY STUDY
HAZOP AND OPERABILITY STUDY
 
SPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT SlidesSPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT Slides
 
Hazop training - Hazard training
Hazop training - Hazard training Hazop training - Hazard training
Hazop training - Hazard training
 
Hazop suplimentry study
Hazop suplimentry studyHazop suplimentry study
Hazop suplimentry study
 
LOPA | Layer Of Protection Analysis | Gaurav Singh Rajput
LOPA | Layer Of Protection Analysis | Gaurav Singh RajputLOPA | Layer Of Protection Analysis | Gaurav Singh Rajput
LOPA | Layer Of Protection Analysis | Gaurav Singh Rajput
 
Work Permit System
Work Permit SystemWork Permit System
Work Permit System
 
HZOP-HAZID Presentation by Tony
HZOP-HAZID Presentation by TonyHZOP-HAZID Presentation by Tony
HZOP-HAZID Presentation by Tony
 
management of change
management of changemanagement of change
management of change
 
Hazid & hazops
Hazid & hazopsHazid & hazops
Hazid & hazops
 
Process safety managment
Process safety managmentProcess safety managment
Process safety managment
 
HAZARD & OPERABILITY STUDY (HAZOP) & MATERIAL SAFETY DATA SHEET (MSDS)
HAZARD & OPERABILITY STUDY (HAZOP) & MATERIAL SAFETY DATA SHEET (MSDS)HAZARD & OPERABILITY STUDY (HAZOP) & MATERIAL SAFETY DATA SHEET (MSDS)
HAZARD & OPERABILITY STUDY (HAZOP) & MATERIAL SAFETY DATA SHEET (MSDS)
 
Introduction to oil & gas health safety environment
Introduction to oil & gas health safety environmentIntroduction to oil & gas health safety environment
Introduction to oil & gas health safety environment
 

Viewers also liked

HAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDY
HAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDYHAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDY
HAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDYOsho Shemil Baba
 
Department Of Chemical
Department Of ChemicalDepartment Of Chemical
Department Of ChemicalSamuel Essien
 
HAZOP – Guide Words
HAZOP – Guide WordsHAZOP – Guide Words
HAZOP – Guide WordsKevyn Lockyer
 
RITUXIMAB PLANT DESIGN
RITUXIMAB PLANT DESIGNRITUXIMAB PLANT DESIGN
RITUXIMAB PLANT DESIGNAnil Vibhute
 
BE Chemical Engineering Design Project Production Of Propylene Oxide
BE Chemical Engineering Design Project   Production Of Propylene OxideBE Chemical Engineering Design Project   Production Of Propylene Oxide
BE Chemical Engineering Design Project Production Of Propylene Oxidepatrickconneran
 
The Effectiveness of the Hazard and Operability Study Methodology in Process ...
The Effectiveness of the Hazard and Operability Study Methodology in Process ...The Effectiveness of the Hazard and Operability Study Methodology in Process ...
The Effectiveness of the Hazard and Operability Study Methodology in Process ...PECB
 
A report on accident scenarios in process plants & how hazop can take lead ro...
A report on accident scenarios in process plants & how hazop can take lead ro...A report on accident scenarios in process plants & how hazop can take lead ro...
A report on accident scenarios in process plants & how hazop can take lead ro...Ravi chandra kancherla
 

Viewers also liked (15)

Hazop steps
Hazop stepsHazop steps
Hazop steps
 
HAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDY
HAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDYHAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDY
HAZOP - AN INTEGRATED SAFETY ASSESSMENT STUDY
 
HAZOP Basics
HAZOP BasicsHAZOP Basics
HAZOP Basics
 
FYDP Sem 2
FYDP Sem 2FYDP Sem 2
FYDP Sem 2
 
What is a HAZOP?
What is a HAZOP?What is a HAZOP?
What is a HAZOP?
 
Department Of Chemical
Department Of ChemicalDepartment Of Chemical
Department Of Chemical
 
HAZOP – Guide Words
HAZOP – Guide WordsHAZOP – Guide Words
HAZOP – Guide Words
 
Hazop
HazopHazop
Hazop
 
RITUXIMAB PLANT DESIGN
RITUXIMAB PLANT DESIGNRITUXIMAB PLANT DESIGN
RITUXIMAB PLANT DESIGN
 
BE Chemical Engineering Design Project Production Of Propylene Oxide
BE Chemical Engineering Design Project   Production Of Propylene OxideBE Chemical Engineering Design Project   Production Of Propylene Oxide
BE Chemical Engineering Design Project Production Of Propylene Oxide
 
The Effectiveness of the Hazard and Operability Study Methodology in Process ...
The Effectiveness of the Hazard and Operability Study Methodology in Process ...The Effectiveness of the Hazard and Operability Study Methodology in Process ...
The Effectiveness of the Hazard and Operability Study Methodology in Process ...
 
SLIDE FYDP2
SLIDE FYDP2SLIDE FYDP2
SLIDE FYDP2
 
Report
ReportReport
Report
 
A report on accident scenarios in process plants & how hazop can take lead ro...
A report on accident scenarios in process plants & how hazop can take lead ro...A report on accident scenarios in process plants & how hazop can take lead ro...
A report on accident scenarios in process plants & how hazop can take lead ro...
 
Safety Audit: An Overview
Safety Audit: An OverviewSafety Audit: An Overview
Safety Audit: An Overview
 

Similar to Hazop analysis complete report

HAZOP (Hazard & Operability) Study.pdf
HAZOP (Hazard & Operability) Study.pdfHAZOP (Hazard & Operability) Study.pdf
HAZOP (Hazard & Operability) Study.pdfiFluidsEngineering1
 
HAZOP_Training_Guide.pdf
HAZOP_Training_Guide.pdfHAZOP_Training_Guide.pdf
HAZOP_Training_Guide.pdfFarahbennour
 
Hazop leaders manual final
Hazop leaders manual finalHazop leaders manual final
Hazop leaders manual finalumar farooq
 
HAZOP ppt for chambal urea -1.pptx
HAZOP ppt for chambal urea -1.pptxHAZOP ppt for chambal urea -1.pptx
HAZOP ppt for chambal urea -1.pptxvidhyasagarverma
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Gaurav Singh Rajput
 
Risk Analysis and.pdf
Risk Analysis and.pdfRisk Analysis and.pdf
Risk Analysis and.pdfCesarPuma10
 
22801434-HAZOP-Training.pdf
22801434-HAZOP-Training.pdf22801434-HAZOP-Training.pdf
22801434-HAZOP-Training.pdfssuser6c7f421
 
industrial safety and hazar
industrial safety and hazarindustrial safety and hazar
industrial safety and hazarmannukumar24
 
HAZOP Module.pptx
HAZOP Module.pptxHAZOP Module.pptx
HAZOP Module.pptxakaash13
 
Hazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluidsHazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluidsJohn Kingsley
 
hazard identification methods in risk analysis
hazard identification methods in risk analysishazard identification methods in risk analysis
hazard identification methods in risk analysisssusera08fc81
 
09.1 hazop studytrainingcourse
09.1 hazop studytrainingcourse09.1 hazop studytrainingcourse
09.1 hazop studytrainingcoursejoepaulnelson
 
Understanding HAZOP: Implementation, Advantages, and Limitations in the Oil a...
Understanding HAZOP: Implementation, Advantages, and Limitations in the Oil a...Understanding HAZOP: Implementation, Advantages, and Limitations in the Oil a...
Understanding HAZOP: Implementation, Advantages, and Limitations in the Oil a...soginsider
 

Similar to Hazop analysis complete report (20)

HAZOP (Hazard & Operability) Study.pdf
HAZOP (Hazard & Operability) Study.pdfHAZOP (Hazard & Operability) Study.pdf
HAZOP (Hazard & Operability) Study.pdf
 
HAZOP_Training_Guide.pdf
HAZOP_Training_Guide.pdfHAZOP_Training_Guide.pdf
HAZOP_Training_Guide.pdf
 
What is HAZOP?
What is HAZOP?What is HAZOP?
What is HAZOP?
 
HAZOP and QRA.pptx
HAZOP and QRA.pptxHAZOP and QRA.pptx
HAZOP and QRA.pptx
 
Hazop leaders manual final
Hazop leaders manual finalHazop leaders manual final
Hazop leaders manual final
 
HAZOP ppt for chambal urea -1.pptx
HAZOP ppt for chambal urea -1.pptxHAZOP ppt for chambal urea -1.pptx
HAZOP ppt for chambal urea -1.pptx
 
Hazop_study_introduction
Hazop_study_introductionHazop_study_introduction
Hazop_study_introduction
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
 
Risk Analysis and.pdf
Risk Analysis and.pdfRisk Analysis and.pdf
Risk Analysis and.pdf
 
hazopanalysis-.pdf
hazopanalysis-.pdfhazopanalysis-.pdf
hazopanalysis-.pdf
 
22801434-HAZOP-Training.pdf
22801434-HAZOP-Training.pdf22801434-HAZOP-Training.pdf
22801434-HAZOP-Training.pdf
 
Hazard analysis
Hazard analysisHazard analysis
Hazard analysis
 
industrial safety and hazar
industrial safety and hazarindustrial safety and hazar
industrial safety and hazar
 
HAZOP Module.pptx
HAZOP Module.pptxHAZOP Module.pptx
HAZOP Module.pptx
 
Hazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluidsHazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluids
 
hazard identification methods in risk analysis
hazard identification methods in risk analysishazard identification methods in risk analysis
hazard identification methods in risk analysis
 
09.1 hazop studytrainingcourse
09.1 hazop studytrainingcourse09.1 hazop studytrainingcourse
09.1 hazop studytrainingcourse
 
Understanding HAZOP: Implementation, Advantages, and Limitations in the Oil a...
Understanding HAZOP: Implementation, Advantages, and Limitations in the Oil a...Understanding HAZOP: Implementation, Advantages, and Limitations in the Oil a...
Understanding HAZOP: Implementation, Advantages, and Limitations in the Oil a...
 
Understanding HAZOP_Rev.0.pdf
Understanding HAZOP_Rev.0.pdfUnderstanding HAZOP_Rev.0.pdf
Understanding HAZOP_Rev.0.pdf
 
2.pptx
2.pptx2.pptx
2.pptx
 

Recently uploaded

Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdfHafizMudaserAhmad
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentBharaniDharan195623
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectErbil Polytechnic University
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectssuserb6619e
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 

Recently uploaded (20)

Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managament
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction Project
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 

Hazop analysis complete report

  • 1. A Report on HAZOP Analysis
  • 2. CONTENTS 1. Introduction 2. HAZOP Preparation  Selection of HAZOP study team members  Information required for HAZOP study  Other responsibilities 3. HAZOP Terminology  System  Design Intent  HAZOP Guide words  Safeguards & Recommendations  HAZOP Study Record & Risk Assessment 4. HAZOP Meeting Procedure 5. HAZOP Following Up actions 6. HAZOP Closure 7. Documentation
  • 3. 1. Introduction Increasing demand by governments and public bodies for improved safety in addition to a strong awareness within the industry that safe operation can also be highly efficient and profitable, support the need for plant safety and effective safety management. Advances in technology and trends to highly complex and integrated plant designs have sensitized people for systematic and sustainable methods to identify hazards of which the HAZOP study is generally recognized as the foremost solution being able to cover standard and also new complex technology. A Hazard and Operability (HAZOP) study is a structured and systematic examination of a planned or existing process or operation in order to identify and evaluate problems that may represent a risk to personnel or equipment, or prevent efficient operation. A HAZOP is a qualitative technique based on "guide words" and is carried out by a multi-disciplinary team (the HAZOP Team) during one or more meetings. A HAZOP is a design verification process. It should not be used as a design development process. The HAZOP should be performed at the stage in the design process when all preliminary engineering is complete and the basic design has been fixed. This includes complete process design, process flow diagrams, P&ID’s, plant and equipment layout, operating philosophy, control and instrumentation philosophy, utilities requirements, specification and selection of major equipment items, protection systems, start up and shutdown systems. 2. HAZOP Preparation It is the responsibility of the Responsible Officer to initiate the HAZOP study where the project or modification meets the criteria.  Selection of HAZOP study team members: The Responsible Officer will first appoint an independent HAZOP Leader to act as the Chairperson for the HAZOP meetings. The HAZOP Leader must be trained in HAZOP methodology and have successfully completed a suitably recognised HAZOP Leader Course, or equivalent experience, as approved by the Manager - Project Engineering. The HAZOP Leader should be independent, i.e. with no responsibility for the process or operations in the area where the process being reviewed is located.
  • 4. HAZOP studies will be conducted using a team approach, with a minimum of four members. The Responsible Officer together with the HAZOP Leader will select the HAZOP team members to achieve the spread of knowledge and skills required for the particular project, and may include: 1. Representative of the customer 2. A person with Process knowledge 3. A person with Safety & Environmental knowledge 4. A person with operating and/or maintenance experience in comparable environment. 5. A person with Engineering/Design knowledge
  • 5.  Information required for HAZOP study The following information should be assembled by the Responsible Officer and the HAZOP Leader before the HAZOP study team commences work. Essential Items: 1. Functionally complete P & ID for the process 2. System design philosophy and process description Desirable Items: 1. Plot plans or layouts 2. Process flow diagrams 3. Piping class specifications 4. Equipment data sheets and purchase specifications 5. Vessel inventories 6. Relief valve specifications 7. Start up and emergency shut-down procedures 8. Emergency depressurizing system functions 9. Electrical area classification 10. Standards used 11. Procedures - operating and maintenance as applicable  Other responsibilities The Responsible Officer is responsible for the following HAZOP study arrangements: 1. Organizing meeting dates, venue and notices to the attendees 2. Layout of venue and supply of stationery and other resources for the meeting 3. Provision of information required for the HAZOP study 4. Close out meeting date, venue and notice to the attendees.
  • 6. 3. HAZOP Terminology  SYSTEM A System is a specific location or logical part of the process or operation in which possible deviations from the design intent are to be evaluated. Examples might be a heat
  • 7. exchanger, vessel, pump, compressor and interconnecting pipeline or group of lines. Systems should be progressively identified on the P&ID as the HAZOP study proceeds.  DESIGN INTENT The design intent is a description of how the process is expected to behave at the system being studied. This is qualitatively described as an activity eg feed, reaction, transfer, heating, and quantitatively in process parameters such as pressure, temperature, flow rate.  HAZOP GUIDE WORDS All possible deviations in process parameters in a reactor or a pipeline are considered to determine their causes and consequences. If a hazard is identified, first the existing protective measures are analyzed with respect to the intensity of the hazard. If the protective measures are not adequate, recommendations are given to mitigate the hazard. HAZOP study involves a set of standardized GUIDEWORDS, which are required to initiate
  • 8. analysis. Examples of process parameters include the following: Each guide word is combined with relevant process parameters and applied at each point (study node, process section, or operating step) in the process that is being examined.
  • 9. The following Table showed examples of creating deviation using guide words and process parameters:  Safeguards Safeguards are facilities, processes or procedures that help to reduce the likelihood or frequency of the deviation, or to mitigate its consequences. Examples of safeguards include the following. 1. Procedures to define what actions to take in the event of a deviation. 2. Increased frequency of inspection, servicing or calibration of critical items. 3. Facilities that draw attention to the deviation (eg indicators and alarms to inform operators so that they can make the process safe). 4. Facilities that automatically compensate for the deviation (eg an automatic control. 5. System, usually an integrated part of the process control). 6. Facilities that prevent the deviation from occurring (eg excess flow valve). 7. Facilities that prevent further escalation of the deviation (eg by total trip of the activity or process by a safety interlock, control system, or emergency shutdown (ESD) system). 8. Facilities that relieve the process from a hazardous deviation (eg pressure safety valve (PSV) and vent systems) As each cause and consequence scenario is identified, planned safeguards should be reviewed to determine if they are adequate to either prevent the deviation or to protect the System if the deviation occurs. Any decision on the adequacy of the safeguards should take into consideration the magnitude of the potential consequences and the likelihood of the event occurring with all the planned safeguards in place. This is reflected in the risk assessment as below. Each scenario will usually have more than a single layer of protection. For high risk deviations, it is useful to review each of the layers of protection before determining the adequacy of the safeguards.
  • 10.  Recommendations If the HAZOP Team recommends that additional safeguards or changes to the design should be made to ensure the safety of the system, these recommendations must be recorded on the HAZOP Record for further action after the HAZOP study. The name of the person who will be responsible for the further actions should be recorded on the form next to the assigned action.  HAZOP study record HAZOP Study Record form is used to create a historic record of the HAZOP Study. Details of discussions, decisions taken, risk assessments made and further actions recommended during evaluation of each of the HAZOP Study Cards will be progressively recorded by the HAZOP Secretary on the HAZOP Study Record form.  Risk Assessment Risk assessments should be carried out to quantify the risks associated with deviations and their potential consequences, and to assist in determining the adequacy of planned safeguards and the possible need for further action. An initial informal risk assessment should be carried out on each cause - consequence scenario based on the inherent risk in the unprotected state. The Risk Matrix included in the below table should be used as a guide. The risk should then be re-assessed taking into consideration the planned safeguards and risk reduction measures. For less important risks, the need for further action can be based on the experience and judgment of the HAZOP Study Team.
  • 11. Once the reasonable consequence and likelihood of each potential unwanted event is determined, the risk can be ranked using the “Risk Assessment Matrix” below and recorded on the HAZOP Study Record sheet. For high risk scenarios, several layers of protection will usually be necessary to reduce the risk to an acceptable level. If the HAZOP team agrees that, so long as the planned
  • 12. safeguards are in place, the risk of an unwanted event occurring is reduced to an acceptable level, then no further action is required. For extreme risk scenarios, the adequacy of safeguards and the need for further action should be quantitatively assessed using higher level risk assessment techniques such as Layer of Protection Analysis (LOPA), or Safety Integrity Level (SIL) analysis. The risk assessment process and outcome should be recorded on the HAZOP Study Record form against each item. 4. HAZOP Meeting Procedure At the HAZOP meeting, the HAZOP Leader will act as Chairperson to lead the team through each of the following steps. a) Introduce the project:  Ensure all team members are familiar with the HAZOP process  Define the project for the team  Review the proposed process or modification using the Process and Instrumentation Diagram (P&ID) and describe its operation  On the P&ID, divide the process to be studied into logical Systems. b) Carry out HAZOP Study:  Select a particular System for detailed review and describe the design intent for that System. Work through the guide words on the HAZOP Study Cards, following the HAZOP Process Flow Chart.  For each guide word, establish if the deviation from normal conditions suggested by the guide word could occur. If the deviation could occur, identify the possible causes of the deviation.  Determine the possible consequences or problems if the deviation occurred.  Carry out an initial assessment of the risk associated with the identified consequences Review any proposed safeguards to prevent or mitigate the consequences.  Evaluate if the proposed safeguards adequately reduce the risk to an acceptable level and if not, suggest further actions having regard to the consequences and the safeguards already proposed.  Repeat procedure from [step (a)] above for the next System. Progressively complete HAZOP Study Record form including recording of further actions.
  • 13. Modifications must be assessed for impact during a variety of plant conditions (ie. startup, running, plant upset, and plant shutdown). This aspect will be formally documented where appropriate throughout the HAZOP, and must also feature as a specific element considered within the agreement and sign-off of the final records of the HAZOP. 5. HAZOP Following Up actions The Responsible Officer shall ensure that all actions arising from the HAZOP are properly managed and are completed prior to commencing the modification or HAZOP PROCESS FLOW CHART
  • 14. commissioning the modified plant as determined during the HAZOP. The items recorded on the HAZOP Study Record form SF1309 as requiring action shall be numbered and a required date of completion established. This information shall be entered into the “Recommendations” column on the HAZOP Study Record. 6. HAZOP Closure When all follow-up actions are complete, the Responsible Officer shall note on the HAZOP Study Record of Discussions (SF 1909) that all items have been completed and make reference to the Inspection Reference Number in Cintellate. To assist in later verification, a copy of the complete Cintellate record should be printed out after all actions have been completed and attached to the HAZOP Study Record in the Project file. Close out meeting: The Responsible Officer will arrange a close out meeting to record completion of outstanding issues. Once all parties are satisfied that all issues arising from the study have been adequately addressed and are reflected in the project design documentation, form HAZOP Study Record of Discussions form shall be completed and signed off by the Responsible Officer and the Customer Representative. No commissioning activities associated with the modification or the new plant covered by the HAZOP shall commence until form HAZOP Study Record of Discussions (SF1909) has been signed off. 7. Documentation The following HAZOP study information and documents are required for the files: a) HAZOP Study Record which includes:  Project title  Project number (that is, work order number for the parent project)  Project scope  Study date  Participant names, job titles, organisation, brief profile b) Signed off HAZOP Study Record of Discussions c) The original copy of all P&IDs used in the study (with lines clearly identified) d) Variations in guide words used.
  • 15. e) Signed off Action Summary sheet f) Signed off HAZOP Action sheets The study Responsible Officer is responsible for the preparation and collation of the output documentation from the HAZOP study, and for forwarding it to all attendees, including the Chairperson who should sign off the HAZOP Study Record before filing by the Responsible Officer. The Responsible Officer ensures an electronic copy the documentation listed above is filed in the Domino. Doc System in accordance with Management of Risk Assessment Records. A hard copy of all this documentation will also be filed in the Project File by the Project Officer.