City hall seismic upgrade
Upcoming SlideShare
Loading in...5
×
 

City hall seismic upgrade

on

  • 225 views

The building, which was originally designed to be a two-level parking structure, was deemed seismically unstable back in 2009. A study revealed that the building could not survive an earthquake of ...

The building, which was originally designed to be a two-level parking structure, was deemed seismically unstable back in 2009. A study revealed that the building could not survive an earthquake of even small size, and that is when the city made the decision to overhaul the building.

Statistics

Views

Total Views
225
Views on SlideShare
225
Embed Views
0

Actions

Likes
0
Downloads
1
Comments
0

0 Embeds 0

No embeds

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

City hall seismic upgrade City hall seismic upgrade Presentation Transcript

  • City of Coos BayCity Hall Seismic Upgrade Randy Dixon, Project Manager
  • Project Summary Coos Bay City Hall Police Station Seismic Renovation project was funded by Oregon Emergency Management and City of Coos Bay. The total budget for the project was; 2.5 million the upgrades include; Parking Deck Shear Walls, Structure Pinning, Interior Structure Walls secured to Truss Supports, Wall Anchor System, Electrical, HVAC, Plumbing and Landscaping. The project was completed on schedule and within budget. Included in the renovation were Energy Trust of Oregon incentives.Copyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic Project• Oregon Emergency Management (OEM) Grant $1.5 Million• City of Coos Bay Match: $1 Million• PE Budget: $350,000• Construction Budget $2.2 Million• Project Completed Under BudgetCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.
  • City Hall Seismic ProjectCopyright 2008 PresentationFx.com | Redistribution Prohibited | Image © 2008 Thomas Brian | This text section may bedeleted for presentation.