PRESENTATION
ON SUGAR COGEN
R.K.KAUL
Chief Energy Business
Saraya Industries Limited
New Delhi
rkkaul99@rediffmail.com ,rkkaul99@gmail.com
(M) 9810345642,
PUBLIC
PRIVATE
PARTNERSHIP
SUGAR COGENERATION ON BOOT BASIS
ISSUES , TECHNICAL & FINANCIAL ANALYSIS
``ONLINE ``
CONTENTS
 ENERGY RESOURCES & SCENE IN INDIA
 COGEN / TRI GEN BASIC DEFINITION / RANKINE CYCLE
 PPP MODEL GIVE AND TAKE
 BOOT MODEL –PUBLIC PRIVATE PARTNERSHIP
 BASIS OF PROJECTS EVALUATIONS- THE MILLS
 SUGAR BASE DATA – OPERATIONS-----REAL TIME ANALYSIS
 TECHNOLOGY / HEAT MASS BALANCE / POWER BALANCE/STEAM BALANCE
 REVENUES / COSTS / PBDIT / RETURNS/CASH FLOWS
 SUMMARY / WAY FORWARD
ENERGY RESOURCES
 BAGASSE
 OTHER BIOMASS
 RICE STRAW
 WHEAT STRAW
 MUSTARD HUSK
 SUBABOOL
 CANE TRASH
 WOOD CHIPS
 COCONUT SHELL
 COAL INDIAN
 COAL IMPORTED
IN SUGAR INDUSTRY
TOTAL RELIANCE ON
SUGAR OPERATIONS
NOT POSSIBLE
NATIONAL ENERGY DATA
POWER GENERATION RESOURCES-
MW
102,452.75
36,863.00
4,560.00
15521
THERMAL
HYDRO
NUCLEAR
RES
POWER GENERATION RESOURCES-
MW
93114
36158
4120
12194
THERMAL
HYDRO
NUCLEAR
RES
31-Mar-15
178341 69.75%
154170 60.30%
22971 10.89%
1200 0.57%
40867 19.37%
4780 2.27%
31692 15.02%
255680
NATIONAL ENERGY DATA
CONT…..
STATUS
 ENERGY NEED STANDS AT 2.75-3.00 LAC MW- NEXT 2-4 YRS
 SUPPLY STANDS AT 1.5 LAC MW
 GROWTH RATE >7.0 to 8.0 %
 DEMAND SUPPLY GAP WILL CONTINUE / INCREASE
 PRESSURE ON SAVING ENVIRONMENT
 SIZE OF BUSINESS BIG
 BUSINESSES KEEN TO HAVE A CUT OF THE BIG PIE
 RENEWABLE POWER – THRUST WORLD OVER
 HAVES & HAVE NOTS - GOVT/COOP/ PVT SEC
 OVERALL ENVIRONMENT CONDUCIVE
 PVT . SECTOR READY TO INVEST
BOOT IS
AN
OPTION
SUGAR
COGEN
HAS
POTENTIAL
SUGAR COGEN STATUS
 Total Sugar Mills 526 (OP) / 695(INST)
 Total TCD 2.5 Mn TCD
 Cogeneration potential – 8000 to 10000 MW
 Present Power Export - 3500 MW
 BALANCE POTENTIAL – 3000 TO 4000 MW
 INVESTMENT OPPORTUNITY- 15000 CR
RS
PP MODEL BASICS…….
 BOOT – BUILD OWN OPERATE
TRANSFER
 ITS GIVE AND TAKE MODEL
 CPMPLETE TRANSPARENCY
 ADMINISTRATIVE / TECHNICAL HELP
 ACCURATE MEASUREMENTS
 TIMELY DOCUMENTATION
COGEN / TRIGEN DEFINED
 Cogen is Simultaneous generation and use of electricity and heat
 Tri Generation is simultaneous generation and use of electricity , heat ,
and cooling
 Both far superior in efficiency as compared to independent generation
 Should be used where all forms of energy are required
 ITS LIKE CO-EDUCATION –SAME TEACHER
( ENERGY)
PPP - BOOT ISSUES
 POLITICAL WILL
 ADMINISTRATIVE / BEUROCRATIC WILL
 LOCAL MILL BOARD WILL
 INVESTORS WILL
 PROJECT DEVELOPERS WILL
 PROJECT VIABILITY- FUEL / PRICING
PPP- BOOT MODEL:
 Operates its own sugar plant
as usual
 Invites Project developer to
setup cogen project
 Give designated land-lease
free of cost
 Gives Free water
 Gives Free Bagasse
 All legal
 Commits to set up cogen
 Does technical & legal deligence
 Brings all capital at its own cost
and risk
 Gives power & steam free for mill
operations
 Provide capital for mill
modernisation/capacity
enhancement
 Gets all legal clearances
The Mill The Project developer
PPP- BOOT MODEL:…cont..
 Allows Connectivity to system
 Agree on mill modernisation-work as
well as costs
 Terms if steam/power norms not
followed
 Pass Board resolutions as per need
 Agree on concessation period,
revenue sharing/royalty on cane
crush
 Complete project development
including design, order, erection
and commissioning
 Procures balance of fuel
 Share revenue as per agreement
 Operate plants to optimum
capacity
 Hands over the plant to mill at
ZERO COST after concessation
period
The Mill The Project developer
BOOT ISSUES CONT……
 GUARANTEE FOR BAGASSE AVAILABILITY-MINIMUM QUANTITY
 MINIMUM DAYS OF SEASON OPERATION
 EXCESS POWER / STEAM DRAWN BY SUGAR PLANT
 REVENUE SHARING v/S CANE CRUSH ROYALTY
 PRICE FOR EXTRA STEAM / POWER- PSEB /EXCHANGE RATES
 FUNDING FROM SDF – GOVT. HELP/ POLICY CHANGE
 SENSITISING BANKING FOR THESE PROJECTS-DEDICATED FUNDS
 MORTGAGING OF ALLOTED MILL LAND
 BOOT PERIOD – 15/20/25/40 YEARS
 MORATORUIM FOR RETURNS TO SUGAR 2-3 YEARS
 ENHANCED RATE OF POWER TO GRID – some development -CE
 TIME FOR IMPLEMENTATION
 INTEGRATION OF SUGAR / COGEN/ CAPACITY ENHANVEMENT –
 PAYMENT GUARANTEE BY GRID
BASIS OF EVALUATION
 MILL PERFORMANCE OVER LAST 6-8 YEARS
 ACTUAL CANE CRUSH AND BAGASSE AVAILABILITY
 NO OF DAYS OF OPERATION IN A YEAR - SEASON & OFF SEASON
 PRESENT / FUTURE STEAM & POWER CONSUMPTION
 COGEN & MODERNISATION COST
 COST OF MONEY, RETURNS TO SUGAR PLANT
 SELLING POWER COST & CDM / REC BENEFITS
 TECHNOLOGY / PLANT PARAMETERS / INTEGRATION
 POWER OFFTAKE / CONNECTIVITY/DISTANCE TO GRID SUB STATION
 STANDARDISATION OF PLANT CONFIGURATION
 MILL MODERNISATION POTENTIAL
 PROJECT DEVELOPERS INVESTMENT PHILOSOPY
 INVESTORS RISKS INVOLVED
YEARLY CANE CRUSHED
3.34
3.73
3.41
3.16
1.944
1.22 1.234
2.182
2.4
1.80
2.00
2.80
5.1
4.4 4.3 4.4
3.27
2.48
2.83
3.417 3.52
2.80
3.50 3.50
2.56
2.732
3.118
2.7
1.66 1.64
1.858
2.6 2.7
2.50
2.80 2.80
0
1
2
3
4
5
6
99-00 00-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11
MORINDA
NAWASHAHR
GURDASPUR
AJNALA
BATALA
PROJECTED
AREA UNDER CULTIVATION - HECTARES
10885
11679
13446
11584
8280
4689
5122
6860
8152
6000
7500
8000
13718 13596
14084
13373
10615
5960
7022
8089
9549
12000
13000 13000
8364
9825
10902.4 10948
8084.4
5912.4
7520
8172
10231
11000
12000
11500
0
2000
4000
6000
8000
10000
12000
14000
16000
99-00 00-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11
MORINDA
NAWASHAHR
GURDASPUR
AJNALA
BATALA
PROJECTE
D
ANNUAL BAGASSE GENERATION
86840
96980
88660
82160
50544
31720 32515.9
57124.76
65016
50400
56000
78400
153000
131010 128400 131070
99179.1
68026.4
82098.3
101245.71 102291.2
81200
101500 101500
0
20000
40000
60000
80000
100000
120000
140000
160000
180000
99-00 00-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11
MORINDA
NAWASHAHR
GURDASPUR
AJNALA
BATALA
PROJECTE
D
DAYS OPERATION
130
150
132 127
79
52
68
88
107
80
120 120
192
165 166 169
128
98
110
145
154
122
155 155
128
137
161
146
91 91
100
138
152
120
150 150
0
50
100
150
200
250
99-00 00-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11
MORINDA
NAWASHAHR
GURDASPUR
AJNALA
BATALA
PROJECTE
D
ANALYSIS…..
5
5
2
4
3
5
4
5
3
3
3
0
1
2
3
4
5
TOTAL CULTIVATABLE AREA
CONSISTENANCY OF CANE
CRUSH
BAGASSE GENERATION
CANE YIELD
AGE OF PLANT
PLANT AVAILABILITYINFRASTRUCTURE
CAPACITY COMFORT
TECHNICAL BACKUP AT
SITE
SPACE AVAILABILITY
FARMER CONTROL
Series1
GURDASPUR SCORE
0
2
4
6
8
10
1
2
3
4
5
6
7
8
9
10
11
12
13
14
GURDASPUR SCORE
MORINDA SCORE
7.5
6.5
7
7.5
7
7.5
7
8
6
7
6
10
0
2
4
6
8
10
1
2
3
4
5
6
7
8
9
10
11
12
13
14
MORINDA SCORE
7.08
8.32 8.45
7.38 7.19
6.50
8.50
MORINDA NAWANSHAHRGURDASPUR AJNALA BATALA
S1
MILLS COMPARITIVE RATING
Series1
NAWANSHAHR SCORE
0
2
4
6
8
10
1
2
3
4
5
6
7
8
9
10
11
12
13
14
NAWANSHAHR SCORE
AJNALA SCORE
7
6
7
7
8.5
7.5
8.58
8
9
5
0
2
4
6
8
10
1
2
3
4
5
6
7
8
9
10
11
12
13
14
AJNALA SCORE
BATALA SCORE
0
2
4
6
8
10
1
2
3
4
5
6
78
9
10
11
12
13
BATALA SCORE
DECISION MAKING
PROCESS
Prefeasibility / DPR/Financial Closure
Pre Feasibility AnalysisPre Feasibility Analysis
•Establish Mill capacities/operating parametersEstablish Mill capacities/operating parameters
•Establish Fuel availability-season & Off seasonEstablish Fuel availability-season & Off season
•Establishing Capacity viabilityEstablishing Capacity viability
•Technology choicesTechnology choices
•Basic Flow ChartBasic Flow Chart
•Fuel flexibility and mixFuel flexibility and mix
•Water quality and availabilityWater quality and availability
•Ash handling and DisposalAsh handling and Disposal
•Environmental concernsEnvironmental concerns
•Capital cost estimatesCapital cost estimates
•Cash Flow requirementsCash Flow requirements
•Financial analysis-Loan repayments,IRR,DSCR,Taxes,BalanceFinancial analysis-Loan repayments,IRR,DSCR,Taxes,Balance
sheet,P&l statements etcsheet,P&l statements etc
•Sensitivity analysiscSensitivity analysisc
Detailed Project ReportDetailed Project Report
Power Purchase AgreementPower Purchase Agreement
Information MemorandumInformation Memorandum
Debt Syndication/Financial Closure/Cash FlowsDebt Syndication/Financial Closure/Cash Flows
REAL TIME INTEGRATED ANALYSIS
 Sugar Operations data
 Heat & Mass Balance Diagram
 Power & Steam Balance- Exports
 Capital Cost Estimation
 Revenue Generation & Sharing mechanism
 Expenses
 Depriciation calculation, Taxation,Loan
repayments
 IRR & DSCR Calculations
 Balance Sheet,Cash Flows
 Break Even point
 Sensitivity Analysis
 Project Summary ……………
ON LINE ANALYSIS
 SUGAR OPERATION PARAMETERS
 COGEN CAPACITIES / PARAMETERS
 HEAT & MASS BALANCE
 PROJECT COSTS
 FINANCIAL ANALYSIS
………..FOLLOWS
BASIC SUGAR PLANT DATA
BASIC RANKINE CYCLE
 There are four processes in the Rankine
cycle, each changing the state of the
working fluid. These states are identified
by number in the diagram to the right.
 Process 1-2: The working fluid is pumped
from low to high pressure, as the fluid is
a liquid at this stage the pump requires
little input energy.
 Process 2-3: The high pressure liquid
enters a boiler where it is heated at
constant pressure by an external heat
source to become a dry saturated
vapor.
 Process 3-4:
The dry saturated vapor expands through a turbine, generating power. This decreases the te
 Process 4-1: The wet vapor then enters
a condenser where it is cooled at a
constant pressure and temperature to
become a saturated liquid. The pressure
and temperature of the condenser is
fixed by the temperature of the cooling
coils as the fluid is undergoing a phase-
change.
COGEN HEAT MASS BALANCE- OFF SEASON
BALANCE OF POWER
Balance Of Bagasse
Balance Of Steam
PROJECTED CAPITAL COST
KEY PROJECT PARAMETERS….cont
PROJECT REVENUES / CASH FLOWS
PROJECT RETURNS
IDC
ADVANTAGES TO SUGAR PLANT
1. The Cooperative Mill gets complete power plant at ZERO cost
2. Mill gets modernized in terms of power & Steam consumption
3. Plant gets reliable power steam –Improved quality and better
efficiency
4. Improvement in crushing capacity –improved revenues
5. Additional revenue by way of sharing/Royalty on cane crush
6. Improved Pollution Control with ESP
7. Employment to Local people
8. Better returns to cooperative members
9. Other biomasses used- revenue to farmers
10. Environment protection – as crop residue may not be burnt
SUMMARY WAY FORWARD
 NEED FOR MORE CLEAN POWER IN THE COUNTRY
 RENEWABLE ENERGY FOCUS
 POLITICAL/ADMINISTRATIVE /LOCAL ``WILL`` REQD
 BOOT A WIN WIN PROPOSITION IF IMPLEMENTED
PROPERLY ..TRANSPARENCY …UNDERSTANDING
 BOOT PROCESS TO BE STANDARDISED
 FEASIBILITY ANALYSIS UTMOST IMPORTANT
 ALL ISSUES PRE DOCUMENTED & AGREED
 GO FOR IT WITHOUT LOOSING TIME
GO FOR IT WITHOUT LOOSING TIME
THANK YOU

More Related Content

What's hot

Hydrogen Production
Hydrogen ProductionHydrogen Production
Hydrogen Productionchrisd
 
Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)sometech
 
Gas turbine power plants
Gas turbine power plantsGas turbine power plants
Gas turbine power plantsNishkam Dhiman
 
A report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical onlyA report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical onlyShobhan Biswas
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
report on thermal power plant
report on thermal power plantreport on thermal power plant
report on thermal power plantsagar20jain
 
Steam Power Plant and Rankine Cycles
Steam Power Plant and Rankine CyclesSteam Power Plant and Rankine Cycles
Steam Power Plant and Rankine CyclesRidwanul Hoque
 
Conventional energy sources
Conventional energy sourcesConventional energy sources
Conventional energy sourcesRADO7900
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportUtkarsh Chaubey
 
POLLUTION CONTROL METHODS IN THERMAL POWER PLANTS
POLLUTION CONTROL METHODS IN THERMAL POWER PLANTSPOLLUTION CONTROL METHODS IN THERMAL POWER PLANTS
POLLUTION CONTROL METHODS IN THERMAL POWER PLANTSNaveen Cena
 
Thermal Power Plant training Report
Thermal Power Plant training ReportThermal Power Plant training Report
Thermal Power Plant training ReportShani Kumar Singh
 
power point presentation over thermal power plant
power point presentation over thermal power plantpower point presentation over thermal power plant
power point presentation over thermal power plantAnis Haider
 
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Aniket Raj
 
NTPC MECANICAL SUMMER REPORT
NTPC MECANICAL  SUMMER REPORTNTPC MECANICAL  SUMMER REPORT
NTPC MECANICAL SUMMER REPORTAnkur Pal
 

What's hot (20)

Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Hydrogen Production
Hydrogen ProductionHydrogen Production
Hydrogen Production
 
Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)
 
Gas turbine power plants
Gas turbine power plantsGas turbine power plants
Gas turbine power plants
 
Thermal Power Plant
Thermal Power PlantThermal Power Plant
Thermal Power Plant
 
Gas Turbine Power Plant
Gas Turbine Power PlantGas Turbine Power Plant
Gas Turbine Power Plant
 
Coal Power Plant
Coal Power PlantCoal Power Plant
Coal Power Plant
 
A report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical onlyA report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical only
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
report on thermal power plant
report on thermal power plantreport on thermal power plant
report on thermal power plant
 
Steam Power Plant and Rankine Cycles
Steam Power Plant and Rankine CyclesSteam Power Plant and Rankine Cycles
Steam Power Plant and Rankine Cycles
 
Conventional energy sources
Conventional energy sourcesConventional energy sources
Conventional energy sources
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
 
POLLUTION CONTROL METHODS IN THERMAL POWER PLANTS
POLLUTION CONTROL METHODS IN THERMAL POWER PLANTSPOLLUTION CONTROL METHODS IN THERMAL POWER PLANTS
POLLUTION CONTROL METHODS IN THERMAL POWER PLANTS
 
Thermal Power Plant training Report
Thermal Power Plant training ReportThermal Power Plant training Report
Thermal Power Plant training Report
 
power point presentation over thermal power plant
power point presentation over thermal power plantpower point presentation over thermal power plant
power point presentation over thermal power plant
 
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
 
NTPC MECANICAL SUMMER REPORT
NTPC MECANICAL  SUMMER REPORTNTPC MECANICAL  SUMMER REPORT
NTPC MECANICAL SUMMER REPORT
 
Heat Pump
Heat PumpHeat Pump
Heat Pump
 
Steam power plants
Steam power plantsSteam power plants
Steam power plants
 

Viewers also liked

Sugar cane - an energy crop
Sugar cane - an energy cropSugar cane - an energy crop
Sugar cane - an energy cropRajendran K
 
INDUSTRAIL WASTE WATER FOR SUGAR CANE INDUSTRY
INDUSTRAIL WASTE WATER FOR SUGAR CANE INDUSTRYINDUSTRAIL WASTE WATER FOR SUGAR CANE INDUSTRY
INDUSTRAIL WASTE WATER FOR SUGAR CANE INDUSTRYSampath Kumar
 
Sugarcane industry waste utilization
Sugarcane industry waste utilizationSugarcane industry waste utilization
Sugarcane industry waste utilizationTamanna Agarwal
 
OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR
OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR
OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR eecfncci
 
Trends and opportunities in sugar cogeneration
Trends and opportunities in sugar cogenerationTrends and opportunities in sugar cogeneration
Trends and opportunities in sugar cogenerationManoj Kumar
 
Energy conversion practical
Energy conversion practicalEnergy conversion practical
Energy conversion practicalJosiahSpears
 
Cogeneration: An Electrical Perspective
Cogeneration: An Electrical PerspectiveCogeneration: An Electrical Perspective
Cogeneration: An Electrical Perspectivemichaeljmack
 
CHP / Cogeneration As An Alternative Energy Resource
CHP / Cogeneration As An Alternative Energy ResourceCHP / Cogeneration As An Alternative Energy Resource
CHP / Cogeneration As An Alternative Energy ResourceJohn Thornton
 
Combined Heat and Power Generation - Commercial Energy Efficiency with Cogene...
Combined Heat and Power Generation - Commercial Energy Efficiency with Cogene...Combined Heat and Power Generation - Commercial Energy Efficiency with Cogene...
Combined Heat and Power Generation - Commercial Energy Efficiency with Cogene...The Brewer-Garrett Company
 
Cogeneracion
CogeneracionCogeneracion
CogeneracionGilmer RA
 
The Combined Heat & Power (CHP) story - Baltics
The Combined Heat & Power (CHP) story - BalticsThe Combined Heat & Power (CHP) story - Baltics
The Combined Heat & Power (CHP) story - BalticsFortum Heat Lietuva
 
Combined Cycle Power Plant
Combined Cycle Power PlantCombined Cycle Power Plant
Combined Cycle Power Plantmustafa hussain
 
Combined Heat and Power Generation
Combined Heat and Power GenerationCombined Heat and Power Generation
Combined Heat and Power GenerationHossein Lorvand
 
Combined Heat & Power, Energy Efficiency & Renewable Energy
Combined Heat & Power, Energy Efficiency & Renewable EnergyCombined Heat & Power, Energy Efficiency & Renewable Energy
Combined Heat & Power, Energy Efficiency & Renewable EnergyAlliance To Save Energy
 
Combined heat power plant (chp)
Combined heat power plant (chp)Combined heat power plant (chp)
Combined heat power plant (chp)numanahmed88
 

Viewers also liked (20)

Sugar cane - an energy crop
Sugar cane - an energy cropSugar cane - an energy crop
Sugar cane - an energy crop
 
Cogeneration Concept
Cogeneration ConceptCogeneration Concept
Cogeneration Concept
 
Cogeneration Of Power
Cogeneration Of PowerCogeneration Of Power
Cogeneration Of Power
 
INDUSTRAIL WASTE WATER FOR SUGAR CANE INDUSTRY
INDUSTRAIL WASTE WATER FOR SUGAR CANE INDUSTRYINDUSTRAIL WASTE WATER FOR SUGAR CANE INDUSTRY
INDUSTRAIL WASTE WATER FOR SUGAR CANE INDUSTRY
 
Sugarcane industry waste utilization
Sugarcane industry waste utilizationSugarcane industry waste utilization
Sugarcane industry waste utilization
 
OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR
OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR
OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR
 
Trends and opportunities in sugar cogeneration
Trends and opportunities in sugar cogenerationTrends and opportunities in sugar cogeneration
Trends and opportunities in sugar cogeneration
 
Energy conversion practical
Energy conversion practicalEnergy conversion practical
Energy conversion practical
 
Cogeneration: An Electrical Perspective
Cogeneration: An Electrical PerspectiveCogeneration: An Electrical Perspective
Cogeneration: An Electrical Perspective
 
CHP / Cogeneration As An Alternative Energy Resource
CHP / Cogeneration As An Alternative Energy ResourceCHP / Cogeneration As An Alternative Energy Resource
CHP / Cogeneration As An Alternative Energy Resource
 
Combined Heat and Power Generation - Commercial Energy Efficiency with Cogene...
Combined Heat and Power Generation - Commercial Energy Efficiency with Cogene...Combined Heat and Power Generation - Commercial Energy Efficiency with Cogene...
Combined Heat and Power Generation - Commercial Energy Efficiency with Cogene...
 
Sgi suggar & alcohool
Sgi  suggar & alcohoolSgi  suggar & alcohool
Sgi suggar & alcohool
 
Cogeneracion
CogeneracionCogeneracion
Cogeneracion
 
Cogeneration
CogenerationCogeneration
Cogeneration
 
Chp 2007
Chp 2007Chp 2007
Chp 2007
 
The Combined Heat & Power (CHP) story - Baltics
The Combined Heat & Power (CHP) story - BalticsThe Combined Heat & Power (CHP) story - Baltics
The Combined Heat & Power (CHP) story - Baltics
 
Combined Cycle Power Plant
Combined Cycle Power PlantCombined Cycle Power Plant
Combined Cycle Power Plant
 
Combined Heat and Power Generation
Combined Heat and Power GenerationCombined Heat and Power Generation
Combined Heat and Power Generation
 
Combined Heat & Power, Energy Efficiency & Renewable Energy
Combined Heat & Power, Energy Efficiency & Renewable EnergyCombined Heat & Power, Energy Efficiency & Renewable Energy
Combined Heat & Power, Energy Efficiency & Renewable Energy
 
Combined heat power plant (chp)
Combined heat power plant (chp)Combined heat power plant (chp)
Combined heat power plant (chp)
 

Similar to Sugar Cogen Presentation on PPP Model Financial Analysis

Biomass power plant
Biomass power plant Biomass power plant
Biomass power plant Santosh Kumar
 
IRJET- Modeling of Small Scale Solar Power Plant for Electricity and Cooling ...
IRJET- Modeling of Small Scale Solar Power Plant for Electricity and Cooling ...IRJET- Modeling of Small Scale Solar Power Plant for Electricity and Cooling ...
IRJET- Modeling of Small Scale Solar Power Plant for Electricity and Cooling ...IRJET Journal
 
NTPC Barh ppt by Shivank
NTPC Barh ppt by ShivankNTPC Barh ppt by Shivank
NTPC Barh ppt by Shivankshivank Kumar
 
IRJET - IC Engine Waste Heat Recovery Systems
IRJET -  	  IC Engine Waste Heat Recovery SystemsIRJET -  	  IC Engine Waste Heat Recovery Systems
IRJET - IC Engine Waste Heat Recovery SystemsIRJET Journal
 
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...NazrulIslam657555
 
Approach and future work on the formation of concept of smart grid allan p...
Approach and future work on the formation of concept of smart grid    allan p...Approach and future work on the formation of concept of smart grid    allan p...
Approach and future work on the formation of concept of smart grid allan p...Albert Yefimov
 
IRJET- IC Engine Waste Heat Recovery Systems
IRJET- IC Engine Waste Heat Recovery SystemsIRJET- IC Engine Waste Heat Recovery Systems
IRJET- IC Engine Waste Heat Recovery SystemsIRJET Journal
 
Benefits of Modular Gasification (Waste to Energy)
Benefits of Modular Gasification (Waste to Energy)Benefits of Modular Gasification (Waste to Energy)
Benefits of Modular Gasification (Waste to Energy)Erik Lindquist, P.Eng.
 
RASCO MEP Company Profile.pdf
RASCO MEP Company Profile.pdfRASCO MEP Company Profile.pdf
RASCO MEP Company Profile.pdfFathy19
 
A Review on Waste Heat from Sugar Indusrty to Drive Vapour Absorption AC’s
A Review on Waste Heat from Sugar Indusrty to Drive Vapour Absorption AC’sA Review on Waste Heat from Sugar Indusrty to Drive Vapour Absorption AC’s
A Review on Waste Heat from Sugar Indusrty to Drive Vapour Absorption AC’sIRJET Journal
 
Nikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil Singh
 
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptAPP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptsomnathmahapatra6
 
Rajghat power house ppt
Rajghat power house pptRajghat power house ppt
Rajghat power house pptEr Sagar
 
Lanco training
Lanco trainingLanco training
Lanco trainingKSOM
 
THE ECONOMICS OF RE-FRACTURING FOR MATURING WELLS
THE ECONOMICS OF RE-FRACTURING FOR MATURING WELLSTHE ECONOMICS OF RE-FRACTURING FOR MATURING WELLS
THE ECONOMICS OF RE-FRACTURING FOR MATURING WELLSiQHub
 
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONNRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONElliott Molnar
 

Similar to Sugar Cogen Presentation on PPP Model Financial Analysis (20)

CESC-TGS REPORT
CESC-TGS REPORTCESC-TGS REPORT
CESC-TGS REPORT
 
CESC PROJECT
CESC PROJECTCESC PROJECT
CESC PROJECT
 
Biomass power plant
Biomass power plant Biomass power plant
Biomass power plant
 
energy audit
energy auditenergy audit
energy audit
 
IRJET- Modeling of Small Scale Solar Power Plant for Electricity and Cooling ...
IRJET- Modeling of Small Scale Solar Power Plant for Electricity and Cooling ...IRJET- Modeling of Small Scale Solar Power Plant for Electricity and Cooling ...
IRJET- Modeling of Small Scale Solar Power Plant for Electricity and Cooling ...
 
NTPC Barh ppt by Shivank
NTPC Barh ppt by ShivankNTPC Barh ppt by Shivank
NTPC Barh ppt by Shivank
 
IRJET - IC Engine Waste Heat Recovery Systems
IRJET -  	  IC Engine Waste Heat Recovery SystemsIRJET -  	  IC Engine Waste Heat Recovery Systems
IRJET - IC Engine Waste Heat Recovery Systems
 
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
 
Approach and future work on the formation of concept of smart grid allan p...
Approach and future work on the formation of concept of smart grid    allan p...Approach and future work on the formation of concept of smart grid    allan p...
Approach and future work on the formation of concept of smart grid allan p...
 
IRJET- IC Engine Waste Heat Recovery Systems
IRJET- IC Engine Waste Heat Recovery SystemsIRJET- IC Engine Waste Heat Recovery Systems
IRJET- IC Engine Waste Heat Recovery Systems
 
Benefits of Modular Gasification (Waste to Energy)
Benefits of Modular Gasification (Waste to Energy)Benefits of Modular Gasification (Waste to Energy)
Benefits of Modular Gasification (Waste to Energy)
 
RASCO MEP Company Profile.pdf
RASCO MEP Company Profile.pdfRASCO MEP Company Profile.pdf
RASCO MEP Company Profile.pdf
 
A Review on Waste Heat from Sugar Indusrty to Drive Vapour Absorption AC’s
A Review on Waste Heat from Sugar Indusrty to Drive Vapour Absorption AC’sA Review on Waste Heat from Sugar Indusrty to Drive Vapour Absorption AC’s
A Review on Waste Heat from Sugar Indusrty to Drive Vapour Absorption AC’s
 
Nikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTI
 
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptAPP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
 
Rajghat power house ppt
Rajghat power house pptRajghat power house ppt
Rajghat power house ppt
 
Lanco training
Lanco trainingLanco training
Lanco training
 
THE ECONOMICS OF RE-FRACTURING FOR MATURING WELLS
THE ECONOMICS OF RE-FRACTURING FOR MATURING WELLSTHE ECONOMICS OF RE-FRACTURING FOR MATURING WELLS
THE ECONOMICS OF RE-FRACTURING FOR MATURING WELLS
 
Summer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power PlantSummer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power Plant
 
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONNRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
 

Sugar Cogen Presentation on PPP Model Financial Analysis

  • 1. PRESENTATION ON SUGAR COGEN R.K.KAUL Chief Energy Business Saraya Industries Limited New Delhi rkkaul99@rediffmail.com ,rkkaul99@gmail.com (M) 9810345642, PUBLIC PRIVATE PARTNERSHIP SUGAR COGENERATION ON BOOT BASIS ISSUES , TECHNICAL & FINANCIAL ANALYSIS ``ONLINE ``
  • 2. CONTENTS  ENERGY RESOURCES & SCENE IN INDIA  COGEN / TRI GEN BASIC DEFINITION / RANKINE CYCLE  PPP MODEL GIVE AND TAKE  BOOT MODEL –PUBLIC PRIVATE PARTNERSHIP  BASIS OF PROJECTS EVALUATIONS- THE MILLS  SUGAR BASE DATA – OPERATIONS-----REAL TIME ANALYSIS  TECHNOLOGY / HEAT MASS BALANCE / POWER BALANCE/STEAM BALANCE  REVENUES / COSTS / PBDIT / RETURNS/CASH FLOWS  SUMMARY / WAY FORWARD
  • 3. ENERGY RESOURCES  BAGASSE  OTHER BIOMASS  RICE STRAW  WHEAT STRAW  MUSTARD HUSK  SUBABOOL  CANE TRASH  WOOD CHIPS  COCONUT SHELL  COAL INDIAN  COAL IMPORTED IN SUGAR INDUSTRY TOTAL RELIANCE ON SUGAR OPERATIONS NOT POSSIBLE
  • 4. NATIONAL ENERGY DATA POWER GENERATION RESOURCES- MW 102,452.75 36,863.00 4,560.00 15521 THERMAL HYDRO NUCLEAR RES POWER GENERATION RESOURCES- MW 93114 36158 4120 12194 THERMAL HYDRO NUCLEAR RES 31-Mar-15 178341 69.75% 154170 60.30% 22971 10.89% 1200 0.57% 40867 19.37% 4780 2.27% 31692 15.02% 255680
  • 6. STATUS  ENERGY NEED STANDS AT 2.75-3.00 LAC MW- NEXT 2-4 YRS  SUPPLY STANDS AT 1.5 LAC MW  GROWTH RATE >7.0 to 8.0 %  DEMAND SUPPLY GAP WILL CONTINUE / INCREASE  PRESSURE ON SAVING ENVIRONMENT  SIZE OF BUSINESS BIG  BUSINESSES KEEN TO HAVE A CUT OF THE BIG PIE  RENEWABLE POWER – THRUST WORLD OVER  HAVES & HAVE NOTS - GOVT/COOP/ PVT SEC  OVERALL ENVIRONMENT CONDUCIVE  PVT . SECTOR READY TO INVEST BOOT IS AN OPTION SUGAR COGEN HAS POTENTIAL
  • 7. SUGAR COGEN STATUS  Total Sugar Mills 526 (OP) / 695(INST)  Total TCD 2.5 Mn TCD  Cogeneration potential – 8000 to 10000 MW  Present Power Export - 3500 MW  BALANCE POTENTIAL – 3000 TO 4000 MW  INVESTMENT OPPORTUNITY- 15000 CR RS
  • 8. PP MODEL BASICS…….  BOOT – BUILD OWN OPERATE TRANSFER  ITS GIVE AND TAKE MODEL  CPMPLETE TRANSPARENCY  ADMINISTRATIVE / TECHNICAL HELP  ACCURATE MEASUREMENTS  TIMELY DOCUMENTATION
  • 9. COGEN / TRIGEN DEFINED  Cogen is Simultaneous generation and use of electricity and heat  Tri Generation is simultaneous generation and use of electricity , heat , and cooling  Both far superior in efficiency as compared to independent generation  Should be used where all forms of energy are required  ITS LIKE CO-EDUCATION –SAME TEACHER ( ENERGY)
  • 10. PPP - BOOT ISSUES  POLITICAL WILL  ADMINISTRATIVE / BEUROCRATIC WILL  LOCAL MILL BOARD WILL  INVESTORS WILL  PROJECT DEVELOPERS WILL  PROJECT VIABILITY- FUEL / PRICING
  • 11. PPP- BOOT MODEL:  Operates its own sugar plant as usual  Invites Project developer to setup cogen project  Give designated land-lease free of cost  Gives Free water  Gives Free Bagasse  All legal  Commits to set up cogen  Does technical & legal deligence  Brings all capital at its own cost and risk  Gives power & steam free for mill operations  Provide capital for mill modernisation/capacity enhancement  Gets all legal clearances The Mill The Project developer
  • 12. PPP- BOOT MODEL:…cont..  Allows Connectivity to system  Agree on mill modernisation-work as well as costs  Terms if steam/power norms not followed  Pass Board resolutions as per need  Agree on concessation period, revenue sharing/royalty on cane crush  Complete project development including design, order, erection and commissioning  Procures balance of fuel  Share revenue as per agreement  Operate plants to optimum capacity  Hands over the plant to mill at ZERO COST after concessation period The Mill The Project developer
  • 13. BOOT ISSUES CONT……  GUARANTEE FOR BAGASSE AVAILABILITY-MINIMUM QUANTITY  MINIMUM DAYS OF SEASON OPERATION  EXCESS POWER / STEAM DRAWN BY SUGAR PLANT  REVENUE SHARING v/S CANE CRUSH ROYALTY  PRICE FOR EXTRA STEAM / POWER- PSEB /EXCHANGE RATES  FUNDING FROM SDF – GOVT. HELP/ POLICY CHANGE  SENSITISING BANKING FOR THESE PROJECTS-DEDICATED FUNDS  MORTGAGING OF ALLOTED MILL LAND  BOOT PERIOD – 15/20/25/40 YEARS  MORATORUIM FOR RETURNS TO SUGAR 2-3 YEARS  ENHANCED RATE OF POWER TO GRID – some development -CE  TIME FOR IMPLEMENTATION  INTEGRATION OF SUGAR / COGEN/ CAPACITY ENHANVEMENT –  PAYMENT GUARANTEE BY GRID
  • 14. BASIS OF EVALUATION  MILL PERFORMANCE OVER LAST 6-8 YEARS  ACTUAL CANE CRUSH AND BAGASSE AVAILABILITY  NO OF DAYS OF OPERATION IN A YEAR - SEASON & OFF SEASON  PRESENT / FUTURE STEAM & POWER CONSUMPTION  COGEN & MODERNISATION COST  COST OF MONEY, RETURNS TO SUGAR PLANT  SELLING POWER COST & CDM / REC BENEFITS  TECHNOLOGY / PLANT PARAMETERS / INTEGRATION  POWER OFFTAKE / CONNECTIVITY/DISTANCE TO GRID SUB STATION  STANDARDISATION OF PLANT CONFIGURATION  MILL MODERNISATION POTENTIAL  PROJECT DEVELOPERS INVESTMENT PHILOSOPY  INVESTORS RISKS INVOLVED
  • 15. YEARLY CANE CRUSHED 3.34 3.73 3.41 3.16 1.944 1.22 1.234 2.182 2.4 1.80 2.00 2.80 5.1 4.4 4.3 4.4 3.27 2.48 2.83 3.417 3.52 2.80 3.50 3.50 2.56 2.732 3.118 2.7 1.66 1.64 1.858 2.6 2.7 2.50 2.80 2.80 0 1 2 3 4 5 6 99-00 00-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 MORINDA NAWASHAHR GURDASPUR AJNALA BATALA PROJECTED AREA UNDER CULTIVATION - HECTARES 10885 11679 13446 11584 8280 4689 5122 6860 8152 6000 7500 8000 13718 13596 14084 13373 10615 5960 7022 8089 9549 12000 13000 13000 8364 9825 10902.4 10948 8084.4 5912.4 7520 8172 10231 11000 12000 11500 0 2000 4000 6000 8000 10000 12000 14000 16000 99-00 00-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 MORINDA NAWASHAHR GURDASPUR AJNALA BATALA PROJECTE D
  • 16. ANNUAL BAGASSE GENERATION 86840 96980 88660 82160 50544 31720 32515.9 57124.76 65016 50400 56000 78400 153000 131010 128400 131070 99179.1 68026.4 82098.3 101245.71 102291.2 81200 101500 101500 0 20000 40000 60000 80000 100000 120000 140000 160000 180000 99-00 00-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 MORINDA NAWASHAHR GURDASPUR AJNALA BATALA PROJECTE D DAYS OPERATION 130 150 132 127 79 52 68 88 107 80 120 120 192 165 166 169 128 98 110 145 154 122 155 155 128 137 161 146 91 91 100 138 152 120 150 150 0 50 100 150 200 250 99-00 00-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 MORINDA NAWASHAHR GURDASPUR AJNALA BATALA PROJECTE D
  • 17. ANALYSIS….. 5 5 2 4 3 5 4 5 3 3 3 0 1 2 3 4 5 TOTAL CULTIVATABLE AREA CONSISTENANCY OF CANE CRUSH BAGASSE GENERATION CANE YIELD AGE OF PLANT PLANT AVAILABILITYINFRASTRUCTURE CAPACITY COMFORT TECHNICAL BACKUP AT SITE SPACE AVAILABILITY FARMER CONTROL Series1 GURDASPUR SCORE 0 2 4 6 8 10 1 2 3 4 5 6 7 8 9 10 11 12 13 14 GURDASPUR SCORE MORINDA SCORE 7.5 6.5 7 7.5 7 7.5 7 8 6 7 6 10 0 2 4 6 8 10 1 2 3 4 5 6 7 8 9 10 11 12 13 14 MORINDA SCORE 7.08 8.32 8.45 7.38 7.19 6.50 8.50 MORINDA NAWANSHAHRGURDASPUR AJNALA BATALA S1 MILLS COMPARITIVE RATING Series1
  • 18. NAWANSHAHR SCORE 0 2 4 6 8 10 1 2 3 4 5 6 7 8 9 10 11 12 13 14 NAWANSHAHR SCORE AJNALA SCORE 7 6 7 7 8.5 7.5 8.58 8 9 5 0 2 4 6 8 10 1 2 3 4 5 6 7 8 9 10 11 12 13 14 AJNALA SCORE BATALA SCORE 0 2 4 6 8 10 1 2 3 4 5 6 78 9 10 11 12 13 BATALA SCORE DECISION MAKING PROCESS
  • 19. Prefeasibility / DPR/Financial Closure Pre Feasibility AnalysisPre Feasibility Analysis •Establish Mill capacities/operating parametersEstablish Mill capacities/operating parameters •Establish Fuel availability-season & Off seasonEstablish Fuel availability-season & Off season •Establishing Capacity viabilityEstablishing Capacity viability •Technology choicesTechnology choices •Basic Flow ChartBasic Flow Chart •Fuel flexibility and mixFuel flexibility and mix •Water quality and availabilityWater quality and availability •Ash handling and DisposalAsh handling and Disposal •Environmental concernsEnvironmental concerns •Capital cost estimatesCapital cost estimates •Cash Flow requirementsCash Flow requirements •Financial analysis-Loan repayments,IRR,DSCR,Taxes,BalanceFinancial analysis-Loan repayments,IRR,DSCR,Taxes,Balance sheet,P&l statements etcsheet,P&l statements etc •Sensitivity analysiscSensitivity analysisc Detailed Project ReportDetailed Project Report Power Purchase AgreementPower Purchase Agreement Information MemorandumInformation Memorandum Debt Syndication/Financial Closure/Cash FlowsDebt Syndication/Financial Closure/Cash Flows
  • 20. REAL TIME INTEGRATED ANALYSIS  Sugar Operations data  Heat & Mass Balance Diagram  Power & Steam Balance- Exports  Capital Cost Estimation  Revenue Generation & Sharing mechanism  Expenses  Depriciation calculation, Taxation,Loan repayments  IRR & DSCR Calculations  Balance Sheet,Cash Flows  Break Even point  Sensitivity Analysis  Project Summary ……………
  • 21. ON LINE ANALYSIS  SUGAR OPERATION PARAMETERS  COGEN CAPACITIES / PARAMETERS  HEAT & MASS BALANCE  PROJECT COSTS  FINANCIAL ANALYSIS ………..FOLLOWS
  • 23. BASIC RANKINE CYCLE  There are four processes in the Rankine cycle, each changing the state of the working fluid. These states are identified by number in the diagram to the right.  Process 1-2: The working fluid is pumped from low to high pressure, as the fluid is a liquid at this stage the pump requires little input energy.  Process 2-3: The high pressure liquid enters a boiler where it is heated at constant pressure by an external heat source to become a dry saturated vapor.  Process 3-4: The dry saturated vapor expands through a turbine, generating power. This decreases the te  Process 4-1: The wet vapor then enters a condenser where it is cooled at a constant pressure and temperature to become a saturated liquid. The pressure and temperature of the condenser is fixed by the temperature of the cooling coils as the fluid is undergoing a phase- change.
  • 24.
  • 25. COGEN HEAT MASS BALANCE- OFF SEASON
  • 31. PROJECT REVENUES / CASH FLOWS
  • 32.
  • 34. IDC
  • 35. ADVANTAGES TO SUGAR PLANT 1. The Cooperative Mill gets complete power plant at ZERO cost 2. Mill gets modernized in terms of power & Steam consumption 3. Plant gets reliable power steam –Improved quality and better efficiency 4. Improvement in crushing capacity –improved revenues 5. Additional revenue by way of sharing/Royalty on cane crush 6. Improved Pollution Control with ESP 7. Employment to Local people 8. Better returns to cooperative members 9. Other biomasses used- revenue to farmers 10. Environment protection – as crop residue may not be burnt
  • 36. SUMMARY WAY FORWARD  NEED FOR MORE CLEAN POWER IN THE COUNTRY  RENEWABLE ENERGY FOCUS  POLITICAL/ADMINISTRATIVE /LOCAL ``WILL`` REQD  BOOT A WIN WIN PROPOSITION IF IMPLEMENTED PROPERLY ..TRANSPARENCY …UNDERSTANDING  BOOT PROCESS TO BE STANDARDISED  FEASIBILITY ANALYSIS UTMOST IMPORTANT  ALL ISSUES PRE DOCUMENTED & AGREED  GO FOR IT WITHOUT LOOSING TIME
  • 37. GO FOR IT WITHOUT LOOSING TIME THANK YOU