• Share
  • Email
  • Embed
  • Like
  • Save
  • Private Content
Ifla October 2009
 

Ifla October 2009

on

  • 294 views

 

Statistics

Views

Total Views
294
Views on SlideShare
294
Embed Views
0

Actions

Likes
0
Downloads
2
Comments
0

0 Embeds 0

No embeds

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    Ifla October 2009 Ifla October 2009 Presentation Transcript

    • NLS Flood February 2009 Rab Jackson Preservation and Conservation Manager National Library of Scotland
    • NLS Flood
      • Thursday 26 February at 6:30pm a flooding incident occurred
      • Fault with sprinkler pipe in Reprographics room on Level 12
      • Water from sprinkler flowing out of 4” pipe at 3000 litres per minute
      • 6 to 8 minutes to isolate water with approximately 25,000 litres of water infiltrating floors
      • Emergency Evacuation Plan was instigated
      • Disaster Recovery Plan instigated to include protection of collections and removal of flood water from building
    • Damage to Collections
      • Some 4000 books affected by the flood
      • Thousands of manuscript items were laid out to dry
      • Overview of air drying material in reading room
      • 516 Items required conservation treatment
      • Boxing of collections protected items from flood
    • Drying methods
      • Interleaving
      • Air drying
      • Wind Tunnels
      • Material with coated paper were bagged and frozen
    • Damage to Building
      • Some 25,000 litres of water cascaded through the building
      • Water entered from level 12 and cascaded to level 2 ground floor
    • Residual Moisture Investigation
      • Consultant engaged to establish damage
      • Moisture mapping of affected areas took place
      • Residual moisture measured
      • Mycoflora and environmental monitoring
      • Contact samples of moulds
    • Residual Moisture Investigation
      • There was water damage from level 12 through to ground floor
      • Floor coverings were lifted to determine residual moisture at surface and 40mm depth
      • Moisture levels high
    • Residual Moisture Investigation
      • High moisture levels could lead to potential problems of infestation by microorganisms to books
    • Recommendations
      • Dry out masonry to acceptable levels
      • Use oil filled radiators and oscillating fans to introduce gentle heating and ventilation
    • Recommendations
      • Closely monitor flood damaged areas for mould infestation
      • Closely monitor environmental conditions
      • Install Air movers on all floors
    • Discovery of Toxic Mould
      • Toxic mould (Stachybotrys chartarum)
      • Confined to level 8 strongroom area
      • Infected area was sealed
      • Boxed material was vacuumed and moved to a holding area
      • PPE was worn at all times
    • Discovery of Toxic Mould
      • Dr Singh recommended a specialist company expert in toxic mould removal to remediate the area
    • Action taken
      • Company established plan to remove the mould and reinstate the affected area
    • Risk assessment
      • Toxic mould presented an obvious health risk which could only get greater if not treated
      • Danger of infecting the collections
      • Danger of infecting the building
    • Action taken
      • Fire retardant polythene enclosure constructed to encompass the areas of contamination
      • Shelving was removed before cleaning and reinstatement
      • Smoke extraction fans provided adequate negative pressure to suppress spores
    • Action taken
      • Operatives were required to wear specialist respiratory protective equipment providing organic and dust protection
      • Affected areas were treated with ‘Jati’ mould remover
      • Further one metre of flooring was removed to ensure mould had not spread
    • Action taken
      • All contaminated flooring and walls were removed and sprayed with the mould remover before being double bagged
      • The waste was carefully removed at set times to reduce the contact with staff and keeping to routes avoiding contact with collection material
    • Action taken
      • Once all mould contamination had been removed the area was then subject to two atmospheric decontaminations using the mould remover through an atomising device
      • This was to ensure that any airborne spores were removed
      • Finally the area was then cleared of plant and materials and subject to a final clean
    • What Cost?
      • Equipment - £67K
      • Stock - £10K
      • Conservation staff time – 800 hours
      • Flooring - £12K
      • Rebuilding of walls - £6K
      • Service delivery – Backlogs
      • Reputation - ???
    • What Cost?
      • John Murray Archive Exhibition – closed for 6 months
      • JMA Remedial works - £25K
      • Specialists consultants - £108K
      • Legal costs - £10K
      • Overtime claimed - £6K
      • Final outturn – estimate…….
      • £250K excluding staff time!
    • Lessons Confirmed
      • Mss and rare books staff to assist – keeping items in order
      • More extension cables and power points required at our drying facility
      • Project Managers and contract staff – be firm with requirements when building work is taking place
    • Lessons confirmed
      • More staff training – setting up tables
      • Medical conditions of volunteer staff should be known
      • Items in disaster store rooms need to be logically listed with the list visible for all to see when entering the room
    • Lessons Confirmed
      • Boxing of collections proved invaluable
      • Facility to cover book shelves quickly in the event of an incident
    • Lessons Confirmed
      • Protect collections in advance of building works
      • Staff and Fire Brigade tours of building
      • Not too many volunteers on site
    • Lessons Confirmed
      • Regular checks of disaster response supplies
      • Annual training on use of disaster response equipment
      • Take locks off sprinkler zones
    • Offers of assistance
      • The National Archives of Scotland – took up the offer of two NAS conservators to assist with the aftermath of the flood
      • National Museum of Scotland
      • The British Library