Your SlideShare is downloading. ×
Work breakdown Structure
Upcoming SlideShare
Loading in...5
×

Thanks for flagging this SlideShare!

Oops! An error has occurred.

×
Saving this for later? Get the SlideShare app to save on your phone or tablet. Read anywhere, anytime – even offline.
Text the download link to your phone
Standard text messaging rates apply

Work breakdown Structure

300
views

Published on

Published in: Technology, Business

0 Comments
1 Like
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total Views
300
On Slideshare
0
From Embeds
0
Number of Embeds
1
Actions
Shares
0
Downloads
27
Comments
0
Likes
1
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. Work Breakdown Structure Subtitle
  • 2. WBS Characteristics: ▪ The Work Breakdown Structure is a hierarchy which specifies the list of tasks involved in a project – down to the finest detail. ▪ The WBS splits the task list up into major ‘packages’ ▪ On the following slide, is the WBS for the project to outsource these Learning Materials.
  • 3. Packages: ▪ The split of the task list into different packages should be logical, and also compatible with regards to cost control and reporting. ▪ For each Package, it should be possible to test whether the entire package is completed or not. ▪ You will see 5 different packages in the previous example.
  • 4. Lowest Level: ▪ The lowest level of each activity on a WBS should be an individual task ▪ This task should be possible to complete by an individual, or team, within a reasonable defined period of time. ▪ For example, delegating the task of drawing up action lists could be completed by an individual within a defined period of time, such as one afternoon.
  • 5. Limitations to the WBS: ▪ No consideration for the order in which tasks should be carried out, and whether a task is dependant on another. ▪ No representation of how long each task might take. ▪ Does not show you who, or what resources are involved in each task.
  • 6. Alternatives to WBS: 1. Product Breakdown Structure 2. Cost Breakdown Structure – Completed AFTER the Work Breakdown Structure and Product Breakdown Structure
  • 7. Product Breakdown Structure: • This is a tool for dealing with complex products, such as the motorcycle in the opposite example. • The PBS provides a means for identifying all the components that make up a particular product. • It is worth noting the Project Management methodology PRINCE uses the PBS as an alternative to the WBS.
  • 8. Cost Breakdown Structure: • The CBS can only be completed after the WBS and PBS (if any). This is because, for example, the costs of labour should be possible to cross reference with the WBS. • This is a tool for identifying each cost category associated with a project
  • 9. Sources and Further Reading: ▪ Field, M. and Keller, M. (1998), Croatia: Thomson Learning – Chapter 2.1 ▪ Servello, M. and Evans, M. W. (2002) Work Breakdown Structure. Encyclopedia of Software Engineering.