A project done by a group of classmates enrolled into the UC Berkeley Project Management Certification Program. This was for the Intro class by Mr. Joseph Mudd and submitted by our group of five

A project done by a group of classmates enrolled into the UC Berkeley Project Management Certification Program. This was for the Intro class by Mr. Joseph Mudd and submitted by our group of five

More in: Business , Technology
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Be the first to comment
    Be the first to like this
No Downloads

Views

Total Views
385
On Slideshare
0
From Embeds
0
Number of Embeds
1

Actions

Shares
Downloads
0
Comments
0
Likes
0

Embeds 0

No embeds

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
    No notes for slide
  • Jenny
  • Jenny
  • Jenny
  • Jenny
  • Jenny
  • Jenny
  • thomas
  • Thomas
  • Thomas
  • Thomas
  • Neha
  • Neha
  • Neha or Jenny?
  • Maria
  • Maria
  • Maria

Transcript

  • 1. World Movers Consultancy “ Moving into the future” Jenny, Maria, Neha and Thomas Project Management Introduction, 11/01/2008
  • 2. Project Objective
    • Move laboratory and office supplies and equipment from Building 1 (B1),1 st floor, to Building 2 (B2), 4 th floor. The project start on 10/15/2008. The actual relocation takes place Saturday the 10/22/2008 so that offices and laboratories are ready to occupy by 9 am 10/23/2008. The project is completed by 10/24/2008. The total relocation budget is 0.3 m $ US.
  • 3. Scope
    • Relocation of laboratory and office supplies and equipment from Building 1 (B1), 1st floor, to Building 2 (B2), 2nd floor
    • The project is initiated 10/15/2008. The move takes place on 10/22/2008. The project is completed by 10/24/2008.
    • Offices and laboratories should be ready to occupy by 9 am 10/23/2008.
    • The budget is 0.3 m $US
    • The move involves 5 laboratories and 10 offices, staffed by 50 people
    • The distance between building 1 and 2 is 1 mile
    • Items subject to relocation will be packed in B1, transported and unpacked in B2.
    • The equipment and supplies will be transported by trailers between building 1 and 2
    • Separate contractors will be employed for transport of animals, hazardous materials, chemicals, and frozen biologicals, cleaning of B2 pre-move and B1 post-move and for establishing adequate insurance coverage
  • 4. Scope cont’d…
    • Inclusions
      • Cleaning and decontamination of B1 and B2
      • Packing materials will be provided
      • Communication with staff for pre-move and post-move instructions
      • Relocation of laboratory supplies including animals, chemicals, biological materials and refrigerated items, large equipment, office supplies, furniture and electronic equipment
      • Insurance for any damage inflicted as a result of the relocation
      • Items already in storage in B2 will be distributed on the floor the day of the move
    • Exclusions
      • Personal items will not be moved
      • Assembly/reassembly of complicated technical equipment
    • Assumptions
      • B2 is designed to accommodate the relocated items
      • The facility (B2 floor 2) is functional and ready for move-in (lights, electricity, cable, phone lines in place. Vents, electric plugs, alarms where needed etc.)
      • The customer carries necessary licenses
      • Contingency plans not required for risks with low probability of occurring (earthquake, bad weather, traffic related problems)
  • 5. Risks
    • Damages (Equipment, Facility etc.)
    • Personal injuries during move
    • Chemical Spill
    • Power Outages
    • Earthquake
    • Traffic accident during transport
    5,6 Probability Low High Medium Impact Low High Medium PI Matrix 1 2, 3, 4
  • 6. Risks and Contingency Plans
    • Damages (Equipment etc.)
      • Comprehensive Insurance
    • Personal injuries during move
      • Emergency response team on site
      • Back-up personnel on call
    • Chemical Spill
      • Emergency response team on alert
    • Power Outages
      • Back-up generator
  • 7.  
  • 8. Organizational Diagram World Movers Consultants Company X Department of molecular biology Insurance Company Moving Firm Other Subcontractors - Packing materials - Trucks - Refrigerated transport - Movers
    • Animal Transport Service - Decontamination Service - Chemical Transport Experts - Emergency Response Teams
    - Insurance coverage for Relocated of items/Personal injuries/Damages to facilities - Staff of 50 - 5 Labs - 10 Offices PMs
  • 9. Critical Issues
    • Movers and trucks need to arrive on time
      • Hired local people and contractors
      • Plan to finish move in less than 8h to have a ”time buffer” for unexpected events
    • Minimize dislocated items
      • Design labeling system
      • Designated area for “orphan” boxes
    • Accepting vendor deliveries at new site
      • Ensure vendors are notified of new location
      • Put up signs at old facility
  • 10.  
  • 11. Project Phases and WBS PRE MOVE Visit B1 Determine total small items that need to be packed Determine number of items that need disassembly Visit B2 Acquire copy of the floor plan/furniture orientation Review final space plans Make move plan Established move plan draft Communicate Present plan to management Refine plan Obtain plan approval Present plan to ALL Agreed on final move plan Organize sub-contractors Insurance brokers Decontaminators Moving firm Refrigerated transporter Chemicals transport expert Animal transport handlers Planning finished MOVE Decontaminate B2 Prepare items Establish communication between sites Label/Coding of B2 site Give move manual to movers/packers Dismantle Pack Label/code of packed items Transport items Load truck Drive over Unload truck Install Items Unpack Re-assemble Moving finished POST MOVE Decontaminate B1 Assess damaged items B2 ready to occupy
  • 12. 2 Project Schedule Pre Move (days) 1/3 2 4.7 2.2 3 Post Move (days) Move (hours) 1/2 1 1/3 1/3 Established Move Plan Draft Agreed on Final Move Plan Planning Finished 2 Moving Finished B2 ready to occupy Visit B1 Visit B2 Make Move Plan Communicate Organize Sub-Contractors Prepare Items Decontaminate B2 Transport Items Install Items Decontaminate B1 Assess Damaged Items
  • 13. Critical Path Lead=90 Lead=30 Lead=5 Lead=30 Lead=30 Lead=60 All dependencies (  ) are F-S Network Logic Diagram (Move Phase) Durations in minutes
  • 14.  
  • 15. Resource Estimate PHASE PRE MOVE MOVE POST MOVE Day 1 2 and 3 4 5 Task Visit B1 Visit B2 Make Move Plan Communicate Organize Sub-contractors Prepare Items Transport Items Install Items Decon B2 Decon B1 Assess Damaged Items WMC Team Jenny 3 0 3 16 0 0 0 0 2 2 2 Maria 3 0 3 0 16 2 2 2 0 0 0 Neha 0 3 3 16 0 2 2 2 0 0 0 Thomas 0 3 3 0 16 2 2 2 0 0 0 Person assigned Sub-contractors                       Maria Office/Instrument Movers 0 0 0 0 1 5 2 3 0 0 0 Neha Chemicals transport expert 0 0 0 0 1 5 2 3 0 0 0 Neha Refrigerated transporter 0 0 0 0 1 5 2 3 0 0 0 Thomas Animal transport handlers 0 0 0 0 1 5 2 3 0 0 0 Jenny Decontamination Service 0 0 0 0 1 0 0 0 2 4 0 Jenny Insurance brokers 0 0 0 0 2 0 0 0 0 0 8   Sub Total per Day 6 6 12 32 39 26 14 18 4 6 10   FTE 0.8 0.8 1.5 4 4.875 3.25 1.75 2.25 0.5 0.75 1.25 Total Resource Hours 173
  • 16. Summary Cost Estimate Phase Cost Pre Move 40,000.00 Move 225,000.00 Post Move 20,000.00 Contingency (5%) 15,000.00 TOTAL 300,000.00
  • 17. Detailed Cost Estimate for Move Materials Cost Communication items 2,750.00 Stationery 2,000.00 Packing materials 4,000.00 Sub-contractors   Moving firm 75,000.00 Animal transport handlers 35,000.00 Chemicals transport expert 35,000.00 Refrigerated transporter 40,000.00 B2 decontaminators 20,000.00 Contingency   5% of total 11,250.00 TOTAL 225,000.00
  • 18.