SlideShare a Scribd company logo
1 of 29
Download to read offline
North Carolina Military Business Center

   2012 FEDCON SUMMIT
        Post Award Issues:
          Change Orders


            11 October 2012

                 Paulanne Page
        Military Construction Specialist
Agenda

• Contract Change Order Clauses
• Types of Changes Orders
• Change Order Administration Needs
• Brief Info on Claims
• Questions
Change Order Clauses
FAR 52.243 -The “Changes Clause”
• Enables the government to make changes to the contract during
    performance:
• (a) The Contracting Officer may at any time, by written order, and without
    notice, make changes within the general scope of the contract in any one
    or more of the following:
• (1) Drawings, designs, or specifications
• (2) Method of shipment or packing
• (3) Place of delivery
Virtually every contract contains provisions that address what can be
changed, how it can be changed, and the required process for the changes.
Change Order Clauses
FAR 52.243 - The “Changes Clauses”
• The Construction Contract Changes Clause at FAR 52.243-4 applies only to
   construction contracts and states that only costs incurred within 20 days
   from the time that the contractor gives notice are recoverable.
• The Notification of Changes Clause at FAR 52.243-7 requires that the
   contracting officer be notified of a constructive change promptly, usually
   within 30 days.
Change Order Administration

• Impact to Schedules
• Contract Administrative Deliverables
  – Reports (Progress, Quality, Testing)
  – Forms
• Change Order Billing Deliverables
  – Schedule of Pricing/Values
  – Invoices
  – Certified Payroll (Davis Bacon and Service Act)
Changes to the Contract
Types of Contract Changes:

• Written Changes
     - Client Request

• Constructive Changes
     - Identified Statement of Work change in
    relationship to contract document requirements.
Written Change Orders
Determine If the Work Is Properly Ordered under the
Contract or If the Work Is a Change.
• Determine whether the work is within the scope of the contract.
       • “Within the scope” determined by:
            – Nature of the work
            – Cost of the work
            – Degree of work disruption
       • If not, then the work is a change, and you must put the
         Contracting Officer on notice that you consider it to be a
         change and intend to seek an equitable adjustment
Written Change Orders
Confirm the Order Is in WRITING


  • Change orders from the Government must be in writing to
    be effective.
  • If the Government does not put the order in writing, YOU
    should send a confirming letter.
Written Change Orders
Clarify Any Ambiguities & Confirm Any Missing Details.

• Contractors have a duty to inquire - contractors do not get the
  “benefit of the doubt”.
• Make sure any clarifications are put in writing - if Government does
  not put it in writing, send a confirming letter.
• Do not sign off on the change or submit a price until all issues are
  resolved - if you do, you’ve waived any arguments you might have.
• Additional reason for clarifying order – can’t correctly price work
  without full understanding of the requirements.
Written Change Orders
Entitled to Recover As a Result of the Change.
• The amount of the adjustment is almost always the cost impact to
  the contractor.
• Contractor has the burden of proving the cost impact.
       - Estimates – must be supported by detailed, substantiating data;
         vague estimates without any factual support are not sufficient.
       - Actual cost data (if work already performed).
• Allowable overhead and reasonable profit can also be recovered.
       • Many construction contracts include contractual limitations
         on the overhead and profit that can be recovered on an
         equitable adjustment.
Written Change Orders
Consider Your Subcontractors

• If a change affects a subcontractor, you are expected to negotiate
  an equitable adjustment with your sub and include that amount in
  your proposal for an equitable adjustment to the Government.
        Note: be sure your subcontract allows you to make a
        deduction in your subcontractor’s price if a Government
        change results in a reduction of the subcontractor’s work!
Written Change Orders
Submit a Request for Equitable Adjustment
    • Right to adjustment must be asserted within 30 days of the
      contractor’s receipt of the change order – this does not
      necessarily require the submission of a fully-documented and
      finalized request during this time period.
    • Although the 30-day notice requirement is often not strictly
      enforced, it is always better to submit timely notice, even if it
      is relatively vague and supplemented later.
    • All claims must be submitted before final payment is made or
      they are waived.
Written Change Orders
Submit a Request for Equitable Adjustment
    • Right to adjustment must be asserted within 30 days of the
      contractor’s receipt of the request for change – this does not
      necessarily require the submission of a fully-documented and
      finalized request during this time period.
    • Although the 30-day notice requirement is often not strictly
      enforced, it is always better to submit timely notice, even if it
      is relatively vague and supplemented later.
    • All claims must be submitted before final payment is made or
      they are waived.
Constructive Change Orders
Constructive Changes

•   Definition: when the contract work is changed, but the
    procedures of the Changes clause have not been followed.

•   Typically, you think it is a change, but the Government does
    not.
Constructive Change Orders
Constructive Changes (Examples)

  • Disagreements between Government and contractor
    over interpretations of contract requirements.
  • Acceleration.
  • Defective specifications.
  • Failure of Government to cooperate during performance
     –   Overzealous inspections
     –   Failure to provide assistance when requested
Constructive Change Orders
Constructive Changes

•   Same authority issues as written change orders
        - Only the CO can direct a contractor to do work and bind the
        Government to pay for it.
         - Inspectors, Quality Assurance do not have authority to direct a
        contractor to do additional work.
    Make sure your employees are aware of this, since they will be the ones getting
    directives from the Government on the job.
Constructive Change Orders
Constructive Changes

•   Instruct employees to inform Project Manager of all work
    requests by Government.
•   Bring all directives to the attention of the CO. In writing.
•   Where a constructive change results from an oral order, ask
    the CO to put it in writing for you
Constructive Change Orders
Constructive Changes

•   If the CO does notput it in writing, The contractor is required
    to confirm the order in writing to the CO.
    –   Describe the work that has been requested, who made
        request and when it was requested.
    –   State that you consider the work to be a constructive change
        to the contract .
    –   State that you will perform the work but that you reserve the
        right to seek an equitable adjustment to the contract.
Constructive Change Orders
Constructive Changes

•   The 30-day notice requirement that applies to written
    change orders applies to claims for constructive changes as
    well, so DO NOT WAIT to raise these issues.

•   For construction contracts, only costs incurred no more
    than 20 days prior to notice to the Government can be
    recovered (Excludes constructive changes based on
    defective specifications).
The Claims Process
Elements of a Formal Claim

A claim must contain: (1) a written demand (2) seeking as a
matter of right (3) the payment of money in a sum certain
       • “Sum certain” – “more than $50,000;” “about $50,000”
         are NOT claims for a sum certain
       • The amount claimed can be supplemented or
         additional claims can be submitted later
The Claims Process
Elements of a Formal Claim

Must contain sufficient detail to allow the CO to give meaningful
consideration.

Must provide adequate supporting documentation.

Must request a Contracting Officer decision.

“Let’s meet to discuss” is not a request for a CO decision and thus is not a claim.
The Claims Process
Elements of a Formal Claim
Must be submitted to the CO.

If claim is for over $100k, must be “certified”.
   •    “I certify that the claim is made in good faith, that the supporting data are
        accurate and complete to the best of my knowledge and belief, that the
        amount requested accurately reflects the contract adjustment for which
        the contractor believes the government is liable, and that I am duly
        authorized to certify the claim on behalf of the contractor”.


Must be submitted within 6 years of accrual of claim and before
final payment under contract.
The Claims Process
The Contracting Officer’s Final Decision

• Claims under $100k: within 60 days of receipt of claim, CO
  must issue final decision.
• Claims over $100k: within 60 days of receipt of claim, CO
  must: (1) issue final decision or (2) notify the contractor
  when a decision will be issued.
      • The time for issuing a decision must be a date certain.
      • The time must be “reasonable” – depends on the
        complexity of the claim.
The Claims Process
The Contracting Officer’s Final Decision
• If the CO does not timely issue a final decision, the contractor
  can treat the failure to issue a decision as a “deemed denial”
  and appeal.
       • If claim is less than $100k, you can treat lack of a final
          decision as a “deemed denial” after the 60 days are up.
       • If claim is more than $100k, you must wait a
          “reasonable” time for the CO to issue the decision
          (unless the CO gives no date certain for a decision)
• The final decision must be in writing and must state the
  reasons for the decision.
The Claims Process
Litigating Claims
• After an adverse CO final decision, the decision can be
  appealed to:
      • Agency Board of Contract Appeals
           – Armed Services Board of Contract Appeals or Civilian Board of
             Contract Appeals.
           – Must bring suit within 90 days of date of receipt of final
             decision.
           – Written notice of appeal delivered to the Board and the CO.
       • OR Court of Federal Claims (must pick one or the other)
           – Must bring suit within 1 year of date of receipt of final
             decision.
The Claims Process
Litigating Claims
• Agency Board of Contract Appeals
       • Expedited procedures for claims less than $50k (decision within 120
         days); accelerated procedures for claims less than $100k (decision within
         180 days)
       • Discovery and trial-type hearings
       • Trial held at location convenient to the parties
• Court of Federal Claims
       • Much more formal procedures and thus generally more expensive
       • Sometimes not as much deference given to the agencies
• There are differences in the decisions from the two forums –
  this could be the determining factor
The Claims Process
What About Subcontractors?

• Subcontractors are not in “privity” with the Government and
  therefore cannot pursue claims on their own
• Most subcontractor claims must be “sponsored” by the prime
  contractor
      • The prime can bring a claim on the sub’s behalf; or
      • The prime can permit the sub to bring a claim in the prime’s name
      * Note it is a good idea to address how subcontractor claims will be
        handled in your subcontract agreement and (if you are the sub)
        obligate the prime to sponsor your claims
The Claims Process
What About Subcontractors?
• A prime can sponsor a sub’s claim only if: (1) the prime has
  reimbursed the sub for the sub’s damages, or (2) the prime
  remains liable for such damages in the future
       • If a subcontract contains a strong limitation of liability
         clause such that the prime is not liable for the damages
         at issue, the sub’s claim cannot be brought
       • BUT, a subcontract can provide that the prime’s liability
         to the sub is conditioned on the prime’s recovery from
         the Government
Questions



                   ?
Questions, Comments and Amusing Ponderences

More Related Content

What's hot

Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in MalaysiaDayat Mohamad
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Bhalindra Bath - projects & M&A law
 
Price variation in works contracts
Price variation in works contractsPrice variation in works contracts
Price variation in works contractsDr K M SONI
 
Contract Conditions
Contract ConditionsContract Conditions
Contract ConditionsDr K M SONI
 
Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types Unanet
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...Zainab Zainordin
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKegler Brown Hill + Ritter
 
Construction - Accounting and Tax Aspects
Construction - Accounting and Tax AspectsConstruction - Accounting and Tax Aspects
Construction - Accounting and Tax Aspectssandesh mundra
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdfSaqib Imran
 
Basics of construction accouting
Basics of construction accoutingBasics of construction accouting
Basics of construction accoutinglgcdcpas
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Melvin Lim
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZmianmohsinmumtazshb
 

What's hot (20)

Unit-1_Contracts
Unit-1_ContractsUnit-1_Contracts
Unit-1_Contracts
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Construction contracts
Construction contractsConstruction contracts
Construction contracts
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
IAS 11 Construction Contracts
IAS 11 Construction ContractsIAS 11 Construction Contracts
IAS 11 Construction Contracts
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
Price variation in works contracts
Price variation in works contractsPrice variation in works contracts
Price variation in works contracts
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...
 
Gcc vs scc
Gcc vs sccGcc vs scc
Gcc vs scc
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
 
Construction - Accounting and Tax Aspects
Construction - Accounting and Tax AspectsConstruction - Accounting and Tax Aspects
Construction - Accounting and Tax Aspects
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
Basics of construction accouting
Basics of construction accoutingBasics of construction accouting
Basics of construction accouting
 
Contract management sys
Contract management sysContract management sys
Contract management sys
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
 

Similar to Post Award Requirements and Issues Change Orders 2012 fedcon

Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...
Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...
Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...Kegler Brown Hill + Ritter
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractSHKLaw
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesSamantha Ip
 
Cmwg contract breaches presentation
Cmwg contract breaches presentationCmwg contract breaches presentation
Cmwg contract breaches presentationBrandon Williams
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair IssuesTRIslides
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...
Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...
Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...McKonly & Asbury, LLP
 
Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference CBIZ, Inc.
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom LineCallPM
 
Supply Chain (Good)
Supply Chain (Good)Supply Chain (Good)
Supply Chain (Good)hayatscm
 
Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...
Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...
Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...Joshua C. Quinter
 
ICI Project 2 - Building and process & sample document
ICI Project 2 - Building and process & sample documentICI Project 2 - Building and process & sample document
ICI Project 2 - Building and process & sample documentHaziq1511
 
FASB Proposals Affecting Government Contractors
FASB Proposals Affecting Government ContractorsFASB Proposals Affecting Government Contractors
FASB Proposals Affecting Government ContractorsDecosimoCPAs
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysNC Military Business Center
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxAditya Mane
 
The Construction Lien Amendment Act - Very Briefly
The Construction Lien Amendment Act - Very BrieflyThe Construction Lien Amendment Act - Very Briefly
The Construction Lien Amendment Act - Very BrieflyIlia Valitsky
 
Accounts Payable & Contracts Payable
Accounts Payable & Contracts Payable Accounts Payable & Contracts Payable
Accounts Payable & Contracts Payable Rea & Associates
 

Similar to Post Award Requirements and Issues Change Orders 2012 fedcon (20)

Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...
Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...
Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the Contract
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case Studies
 
Cmwg contract breaches presentation
Cmwg contract breaches presentationCmwg contract breaches presentation
Cmwg contract breaches presentation
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
Tuning Up Your Offer Letter
Tuning Up Your Offer LetterTuning Up Your Offer Letter
Tuning Up Your Offer Letter
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...
Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...
Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...
 
Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom Line
 
Supply Chain (Good)
Supply Chain (Good)Supply Chain (Good)
Supply Chain (Good)
 
Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...
Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...
Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
ICI Project 2 - Building and process & sample document
ICI Project 2 - Building and process & sample documentICI Project 2 - Building and process & sample document
ICI Project 2 - Building and process & sample document
 
FASB Proposals Affecting Government Contractors
FASB Proposals Affecting Government ContractorsFASB Proposals Affecting Government Contractors
FASB Proposals Affecting Government Contractors
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/Delays
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
 
The Construction Lien Amendment Act - Very Briefly
The Construction Lien Amendment Act - Very BrieflyThe Construction Lien Amendment Act - Very Briefly
The Construction Lien Amendment Act - Very Briefly
 
Accounts Payable & Contracts Payable
Accounts Payable & Contracts Payable Accounts Payable & Contracts Payable
Accounts Payable & Contracts Payable
 

More from NC Military Business Center

Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14NC Military Business Center
 
FEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction ProjectsFEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction ProjectsNC Military Business Center
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysNC Military Business Center
 
FEDCON Summit: Department of Transportation Construction Opportunities
FEDCON Summit:  Department of Transportation Construction OpportunitiesFEDCON Summit:  Department of Transportation Construction Opportunities
FEDCON Summit: Department of Transportation Construction OpportunitiesNC Military Business Center
 
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal ContractsFEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal ContractsNC Military Business Center
 
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...NC Military Business Center
 
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry ExperienceFEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry ExperienceNC Military Business Center
 
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...NC Military Business Center
 
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry PanelFEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry PanelNC Military Business Center
 
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced AnalyticsHuman/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced AnalyticsNC Military Business Center
 

More from NC Military Business Center (20)

Camp Lejeune Small Business Outreach Event
Camp Lejeune Small Business Outreach EventCamp Lejeune Small Business Outreach Event
Camp Lejeune Small Business Outreach Event
 
MCAS Cherry Point Small Business Outreach Event
MCAS Cherry Point Small Business Outreach EventMCAS Cherry Point Small Business Outreach Event
MCAS Cherry Point Small Business Outreach Event
 
Spawar slides
Spawar slidesSpawar slides
Spawar slides
 
Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14
 
FEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction ProjectsFEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction Projects
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/Delays
 
FEDCON Summit: Department of Transportation Construction Opportunities
FEDCON Summit:  Department of Transportation Construction OpportunitiesFEDCON Summit:  Department of Transportation Construction Opportunities
FEDCON Summit: Department of Transportation Construction Opportunities
 
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal ContractsFEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
 
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
 
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry ExperienceFEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
 
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
 
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry PanelFEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
 
FEDCON Summit: Marine Corps Installations East
FEDCON Summit: Marine Corps Installations EastFEDCON Summit: Marine Corps Installations East
FEDCON Summit: Marine Corps Installations East
 
FEDCON Summit: NCMBC Tools for Contractors
FEDCON Summit: NCMBC Tools for ContractorsFEDCON Summit: NCMBC Tools for Contractors
FEDCON Summit: NCMBC Tools for Contractors
 
FEDCON Summit: Public Private Ventures
FEDCON Summit: Public Private VenturesFEDCON Summit: Public Private Ventures
FEDCON Summit: Public Private Ventures
 
FEDCON Summit: Teaming Arrangements
FEDCON Summit: Teaming ArrangementsFEDCON Summit: Teaming Arrangements
FEDCON Summit: Teaming Arrangements
 
FEDCON Summit: Veterans Affairs
FEDCON Summit: Veterans AffairsFEDCON Summit: Veterans Affairs
FEDCON Summit: Veterans Affairs
 
Medical Technologies
Medical TechnologiesMedical Technologies
Medical Technologies
 
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced AnalyticsHuman/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
 
Ground Vehicle and Robotics
Ground Vehicle and RoboticsGround Vehicle and Robotics
Ground Vehicle and Robotics
 

Post Award Requirements and Issues Change Orders 2012 fedcon

  • 1. North Carolina Military Business Center 2012 FEDCON SUMMIT Post Award Issues: Change Orders 11 October 2012 Paulanne Page Military Construction Specialist
  • 2. Agenda • Contract Change Order Clauses • Types of Changes Orders • Change Order Administration Needs • Brief Info on Claims • Questions
  • 3. Change Order Clauses FAR 52.243 -The “Changes Clause” • Enables the government to make changes to the contract during performance: • (a) The Contracting Officer may at any time, by written order, and without notice, make changes within the general scope of the contract in any one or more of the following: • (1) Drawings, designs, or specifications • (2) Method of shipment or packing • (3) Place of delivery Virtually every contract contains provisions that address what can be changed, how it can be changed, and the required process for the changes.
  • 4. Change Order Clauses FAR 52.243 - The “Changes Clauses” • The Construction Contract Changes Clause at FAR 52.243-4 applies only to construction contracts and states that only costs incurred within 20 days from the time that the contractor gives notice are recoverable. • The Notification of Changes Clause at FAR 52.243-7 requires that the contracting officer be notified of a constructive change promptly, usually within 30 days.
  • 5. Change Order Administration • Impact to Schedules • Contract Administrative Deliverables – Reports (Progress, Quality, Testing) – Forms • Change Order Billing Deliverables – Schedule of Pricing/Values – Invoices – Certified Payroll (Davis Bacon and Service Act)
  • 6. Changes to the Contract Types of Contract Changes: • Written Changes - Client Request • Constructive Changes - Identified Statement of Work change in relationship to contract document requirements.
  • 7. Written Change Orders Determine If the Work Is Properly Ordered under the Contract or If the Work Is a Change. • Determine whether the work is within the scope of the contract. • “Within the scope” determined by: – Nature of the work – Cost of the work – Degree of work disruption • If not, then the work is a change, and you must put the Contracting Officer on notice that you consider it to be a change and intend to seek an equitable adjustment
  • 8. Written Change Orders Confirm the Order Is in WRITING • Change orders from the Government must be in writing to be effective. • If the Government does not put the order in writing, YOU should send a confirming letter.
  • 9. Written Change Orders Clarify Any Ambiguities & Confirm Any Missing Details. • Contractors have a duty to inquire - contractors do not get the “benefit of the doubt”. • Make sure any clarifications are put in writing - if Government does not put it in writing, send a confirming letter. • Do not sign off on the change or submit a price until all issues are resolved - if you do, you’ve waived any arguments you might have. • Additional reason for clarifying order – can’t correctly price work without full understanding of the requirements.
  • 10. Written Change Orders Entitled to Recover As a Result of the Change. • The amount of the adjustment is almost always the cost impact to the contractor. • Contractor has the burden of proving the cost impact. - Estimates – must be supported by detailed, substantiating data; vague estimates without any factual support are not sufficient. - Actual cost data (if work already performed). • Allowable overhead and reasonable profit can also be recovered. • Many construction contracts include contractual limitations on the overhead and profit that can be recovered on an equitable adjustment.
  • 11. Written Change Orders Consider Your Subcontractors • If a change affects a subcontractor, you are expected to negotiate an equitable adjustment with your sub and include that amount in your proposal for an equitable adjustment to the Government. Note: be sure your subcontract allows you to make a deduction in your subcontractor’s price if a Government change results in a reduction of the subcontractor’s work!
  • 12. Written Change Orders Submit a Request for Equitable Adjustment • Right to adjustment must be asserted within 30 days of the contractor’s receipt of the change order – this does not necessarily require the submission of a fully-documented and finalized request during this time period. • Although the 30-day notice requirement is often not strictly enforced, it is always better to submit timely notice, even if it is relatively vague and supplemented later. • All claims must be submitted before final payment is made or they are waived.
  • 13. Written Change Orders Submit a Request for Equitable Adjustment • Right to adjustment must be asserted within 30 days of the contractor’s receipt of the request for change – this does not necessarily require the submission of a fully-documented and finalized request during this time period. • Although the 30-day notice requirement is often not strictly enforced, it is always better to submit timely notice, even if it is relatively vague and supplemented later. • All claims must be submitted before final payment is made or they are waived.
  • 14. Constructive Change Orders Constructive Changes • Definition: when the contract work is changed, but the procedures of the Changes clause have not been followed. • Typically, you think it is a change, but the Government does not.
  • 15. Constructive Change Orders Constructive Changes (Examples) • Disagreements between Government and contractor over interpretations of contract requirements. • Acceleration. • Defective specifications. • Failure of Government to cooperate during performance – Overzealous inspections – Failure to provide assistance when requested
  • 16. Constructive Change Orders Constructive Changes • Same authority issues as written change orders - Only the CO can direct a contractor to do work and bind the Government to pay for it. - Inspectors, Quality Assurance do not have authority to direct a contractor to do additional work. Make sure your employees are aware of this, since they will be the ones getting directives from the Government on the job.
  • 17. Constructive Change Orders Constructive Changes • Instruct employees to inform Project Manager of all work requests by Government. • Bring all directives to the attention of the CO. In writing. • Where a constructive change results from an oral order, ask the CO to put it in writing for you
  • 18. Constructive Change Orders Constructive Changes • If the CO does notput it in writing, The contractor is required to confirm the order in writing to the CO. – Describe the work that has been requested, who made request and when it was requested. – State that you consider the work to be a constructive change to the contract . – State that you will perform the work but that you reserve the right to seek an equitable adjustment to the contract.
  • 19. Constructive Change Orders Constructive Changes • The 30-day notice requirement that applies to written change orders applies to claims for constructive changes as well, so DO NOT WAIT to raise these issues. • For construction contracts, only costs incurred no more than 20 days prior to notice to the Government can be recovered (Excludes constructive changes based on defective specifications).
  • 20. The Claims Process Elements of a Formal Claim A claim must contain: (1) a written demand (2) seeking as a matter of right (3) the payment of money in a sum certain • “Sum certain” – “more than $50,000;” “about $50,000” are NOT claims for a sum certain • The amount claimed can be supplemented or additional claims can be submitted later
  • 21. The Claims Process Elements of a Formal Claim Must contain sufficient detail to allow the CO to give meaningful consideration. Must provide adequate supporting documentation. Must request a Contracting Officer decision. “Let’s meet to discuss” is not a request for a CO decision and thus is not a claim.
  • 22. The Claims Process Elements of a Formal Claim Must be submitted to the CO. If claim is for over $100k, must be “certified”. • “I certify that the claim is made in good faith, that the supporting data are accurate and complete to the best of my knowledge and belief, that the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable, and that I am duly authorized to certify the claim on behalf of the contractor”. Must be submitted within 6 years of accrual of claim and before final payment under contract.
  • 23. The Claims Process The Contracting Officer’s Final Decision • Claims under $100k: within 60 days of receipt of claim, CO must issue final decision. • Claims over $100k: within 60 days of receipt of claim, CO must: (1) issue final decision or (2) notify the contractor when a decision will be issued. • The time for issuing a decision must be a date certain. • The time must be “reasonable” – depends on the complexity of the claim.
  • 24. The Claims Process The Contracting Officer’s Final Decision • If the CO does not timely issue a final decision, the contractor can treat the failure to issue a decision as a “deemed denial” and appeal. • If claim is less than $100k, you can treat lack of a final decision as a “deemed denial” after the 60 days are up. • If claim is more than $100k, you must wait a “reasonable” time for the CO to issue the decision (unless the CO gives no date certain for a decision) • The final decision must be in writing and must state the reasons for the decision.
  • 25. The Claims Process Litigating Claims • After an adverse CO final decision, the decision can be appealed to: • Agency Board of Contract Appeals – Armed Services Board of Contract Appeals or Civilian Board of Contract Appeals. – Must bring suit within 90 days of date of receipt of final decision. – Written notice of appeal delivered to the Board and the CO. • OR Court of Federal Claims (must pick one or the other) – Must bring suit within 1 year of date of receipt of final decision.
  • 26. The Claims Process Litigating Claims • Agency Board of Contract Appeals • Expedited procedures for claims less than $50k (decision within 120 days); accelerated procedures for claims less than $100k (decision within 180 days) • Discovery and trial-type hearings • Trial held at location convenient to the parties • Court of Federal Claims • Much more formal procedures and thus generally more expensive • Sometimes not as much deference given to the agencies • There are differences in the decisions from the two forums – this could be the determining factor
  • 27. The Claims Process What About Subcontractors? • Subcontractors are not in “privity” with the Government and therefore cannot pursue claims on their own • Most subcontractor claims must be “sponsored” by the prime contractor • The prime can bring a claim on the sub’s behalf; or • The prime can permit the sub to bring a claim in the prime’s name * Note it is a good idea to address how subcontractor claims will be handled in your subcontract agreement and (if you are the sub) obligate the prime to sponsor your claims
  • 28. The Claims Process What About Subcontractors? • A prime can sponsor a sub’s claim only if: (1) the prime has reimbursed the sub for the sub’s damages, or (2) the prime remains liable for such damages in the future • If a subcontract contains a strong limitation of liability clause such that the prime is not liable for the damages at issue, the sub’s claim cannot be brought • BUT, a subcontract can provide that the prime’s liability to the sub is conditioned on the prime’s recovery from the Government
  • 29. Questions ? Questions, Comments and Amusing Ponderences