1. Department of Computer Science
Sir Syed University of Engineering & Technology, Karachi
Final Year Projects (FYP)
Project Timeline for BS (CS) – Batch 2009
Saturday
1. Submission of Project Registration Form 25/02/12
Saturday
2. Submission of Project Proposal
3/03/12
Saturday
3. Project Proposal Defense
10/03/12
Saturday
4. Submission of Requirements Analysis Documents
17/03/12
5. Presentation of Requirements Analysis (exact 7/04/12 --
schedule for each group will be announced later) 10/04/12
6. Monday
Submission of Design Documents
23/07/12
Monday
7. Poster Presentation
30/07/12
8. Project Progress Review and Peer Evaluation (exact 22/10/12 --
schedule for each group will be announced later) 24/10/12
9. Submission of Project Report (exact schedule for 1st Week of
each group will be announced later) January 2013
10. Project Presentation + Viva (exact schedule for each 2nd Week of
group will be announced later) January 2013
Naheed Khan
FYPC Coordinator
2. Department of Computer Science
Sir Syed University of Engineering & Technology, Karachi
Final Year Projects (FYP)
Assessment Policy for BS (CS) – Batch 2009
Evaluation Total
S.NO. PROJECT ACTIVITY Supervisor
Committee MARKS
Requirements Analysis Document +
1. 10 10 20
Presentation
2. Design Document 35 - 35
3. Poster Presentation - 35 35
4. Formal Technical Review 20 20 40
Final Project Report, Presentation,
5. - 70 70
Demo, Viva
Grand Total 65 135 200
Naheed Khan
FYPC Coordinator