Manchester Bridge
Final Recommendation Report
July 9, 2013
Project Location
Current Configuration
Project Need
Project Need
Project Need
US-40 Historic Bridge
Manchester Bridge
Optional Improvement
Optional Improvement
Project Scope
Project Goals
1. Impress our customers through innovative solutions that
conveniently and efficiently move drivers through...
Project Schedule
• MHTC Delegation of Authority - August 2012
• Industry Meeting - January 8, 2013
• Issue Request for Qua...
Four Short-Listed Teams
Evaluation Criteria
Area Available Points
Maintenance of Traffic 350 + 50
Durability 200
Optional Improvements 100
Environ...
Disadvantaged Business
Enterprise & Workforce Goals
• DBE Construction: 12%
• DBE Professional Services: 18%
DBE firms mus...
Technical Summary
• No complete closures of I-70
• No lane closures during peak periods
• New four-lane bridges on I-70
• ...
Score Summary
Area Clarkson
Emery
Sapp
Kiewit Walsh
Maintenance of Traffic (350 Points) 338 324 345 334
Maintenance of Tra...
Maintenance of Traffic
Clarkson Construction Company
Maintenance of Traffic
Clarkson Construction Company
Maintenance of Traffic
Clarkson Construction Company
Location Impact(s)
Point
Reduction
I-70 Weekday Night 2-Lane Closure
...
Durability
Clarkson Construction Company
• Brand new structures
• Multi-girder redundant system
• Minimal number of expans...
Optional Improvements –
Weave/Merge Area
Weave/Merge Area
Clarkson Construction Company
• Provide separate lanes for I-435 NB and I-435 SB
• Increase weave distanc...
Optional Improvements
I-70 Bridge over US-40
I-70 Bridge over US-40
Clarkson
• Eastbound: 8’ shoulder
• Westbound: 6’ shoulder
• Full depth & half-sole repairs to enti...
Completion Schedule
One year ahead of schedule
December 15, 2015
Project Cost
$63,757,689
Recommendation of
Best Value Proposer
Upcoming SlideShare
Loading in …5
×

Design-Build For I-70 Manchester Bridge to Deliver More for Travelers

2,182 views

Published on

I-70 travelers will be treated to a smooth journey both during and after construction to replace the Manchester Bridge, thanks to the innovative proposal MoDOT has selected for the design-build project.

The successful team, Clarkson/HNTB, will keep all mainline lanes of I-70 open during peak weekday periods to minimize any construction-related congestion during the two-year bridge replacement project. Once the $63,757,689 project is finished, two completely new I-70 bridges will span Manchester Trafficway, the Blue River and several railroad tracks with four lanes in both directions and retain full access between I-70 and Manchester.

http://www.modot.org/kansascity/major_projects/ManchesterBridgeatI-70.htm

Published in: Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
2,182
On SlideShare
0
From Embeds
0
Number of Embeds
1
Actions
Shares
0
Downloads
28
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide
  • Looking east
  • Design-Build For I-70 Manchester Bridge to Deliver More for Travelers

    1. 1. Manchester Bridge Final Recommendation Report July 9, 2013
    2. 2. Project Location
    3. 3. Current Configuration
    4. 4. Project Need
    5. 5. Project Need
    6. 6. Project Need
    7. 7. US-40 Historic Bridge Manchester Bridge Optional Improvement Optional Improvement Project Scope
    8. 8. Project Goals 1. Impress our customers through innovative solutions that conveniently and efficiently move drivers through the project during and after construction. 2. Construct durable structures that minimize future maintenance impacts. 3. Balance regional mobility with total project cost to achieve optimal value. ($75 Million Max) 4. Deliver the Project no later than December 15, 2016.
    9. 9. Project Schedule • MHTC Delegation of Authority - August 2012 • Industry Meeting - January 8, 2013 • Issue Request for Qualifications (RFQ) - January 8 • Short-listed - February 22 • Issued Request for Proposals (RFP) - March 4 • Proposals submitted – June 7 • Recommendation to MHTC – Today
    10. 10. Four Short-Listed Teams
    11. 11. Evaluation Criteria Area Available Points Maintenance of Traffic 350 + 50 Durability 200 Optional Improvements 100 Environmental 50 Completion Schedule 50 Cost 200 TOTAL 1000
    12. 12. Disadvantaged Business Enterprise & Workforce Goals • DBE Construction: 12% • DBE Professional Services: 18% DBE firms must be certified with the Missouri Regional Certification Committee (MRCC) • Workforce: 12.7% minority • Workforce: 6.9% women Workforce goals are per craft or trade.
    13. 13. Technical Summary • No complete closures of I-70 • No lane closures during peak periods • New four-lane bridges on I-70 • Improved overall safety • Committed to environmental stewardship • One year ahead of schedule
    14. 14. Score Summary Area Clarkson Emery Sapp Kiewit Walsh Maintenance of Traffic (350 Points) 338 324 345 334 Maintenance of Traffic (50 Points) 23 28 21 28 Durability (200 Points) 165 185 175 172 Optional Improvements (100 Points) 72 94 85 71 Environmental (50 Points) 38 43 44 38 Completion Schedule (50 Points) 24 27 40 26 Cost (200 Points) 200 128 117 97 Total (1000 Points) 860 829 827 766
    15. 15. Maintenance of Traffic Clarkson Construction Company
    16. 16. Maintenance of Traffic Clarkson Construction Company
    17. 17. Maintenance of Traffic Clarkson Construction Company Location Impact(s) Point Reduction I-70 Weekday Night 2-Lane Closure I-70 Weekday Night 1-Lane Closure I-70 Weekend 2-Lane Closure 8 (12 points) I-70 Weekend 1-Lane Closure Impress our customers through innovative solutions that conveniently and efficiently move drivers through the project during and after construction.
    18. 18. Durability Clarkson Construction Company • Brand new structures • Multi-girder redundant system • Minimal number of expansion joints • Easily inspected by snooper truck Construct durable structures that minimize future maintenance impacts.
    19. 19. Optional Improvements – Weave/Merge Area
    20. 20. Weave/Merge Area Clarkson Construction Company • Provide separate lanes for I-435 NB and I-435 SB • Increase weave distance by 300’ • Maximum of one lane change in tight weave section
    21. 21. Optional Improvements I-70 Bridge over US-40
    22. 22. I-70 Bridge over US-40 Clarkson • Eastbound: 8’ shoulder • Westbound: 6’ shoulder • Full depth & half-sole repairs to entire deck • Epoxy polymer overlay to entire deck • Estimated additional 10-25 year service life
    23. 23. Completion Schedule One year ahead of schedule December 15, 2015
    24. 24. Project Cost $63,757,689
    25. 25. Recommendation of Best Value Proposer

    ×