McKenney’s installed a wide variety of mechanical systems and controls at a North Carolina university’s new state-of-the-art football stadium. For more information visit http://www.mckenneys.com.

McKenney’s installed a wide variety of mechanical systems and controls at a North Carolina university’s new state-of-the-art football stadium. For more information visit http://www.mckenneys.com.

More in: Business
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Be the first to comment
    Be the first to like this
No Downloads

Views

Total Views
216
On Slideshare
215
From Embeds
1
Number of Embeds
1

Actions

Shares
Downloads
2
Comments
0
Likes
0

Embeds 1

https://twitter.com 1

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
    No notes for slide

Transcript

  • 1. Project Name University Football Stadium Project Location Charlotte, North Carolina Project Team Owner: University General Contractor: Rodgers PCL Russell Architect: Jenkins•Peer Engineer: United Engineering Group Specializations Building Information Modeling LEED Certification Pipe Shop Prefab Sheet Metal Shop Prefab Markets Public Assembly & Places of Worship Education
  • 2. McKenney’s installed a wide variety of mechanical systems and controls at a North Carolina university’s new state-of-the-art football stadium.
  • 3. The Challenge McKenney’s and joint venture partner Superior Mechanical Systems managed a complex systems installation for eight concession buildings as well as a ticket office, field house, commissary and press box. The concession buildings were constructed with block concrete masonry walls and the plenum space above the ceilings of the field house and press box were extremely congested. There was also no on-site storage. The Solution To maintain the schedule, the McKenney’s team brought all the materials to its warehouse to sort and deliver to the site as needed. A full-time person monitored concession building wall construction to help place wall blockouts as needed. Building Information Modeling was used to ensure accurate installation in the field house and press box. The content of this document is not intended as an endorsement.
  • 4. The Results Delivery of materials went smoothly and accurate modeling insured the project was delivered on time and met the budget goals.