WELCOME
Presentation
on

FLYOVER PILING

Prepared by:

Course Teacher:
Md. Arman Chowdhury
Wahid Hasan

(GROUP-5)
12.01.03.008; 12...
What is Pile?
• It is a long slender foundation
member made either of
timber,structural steel or
concrete to transfer the ...
Why do we use Pile?

Weak Soil

Deep Foundation

Structure

PILE

Bed Rock
Advantage of Piling
• To take the structure deep into the ground and
hence preventing over turning.
• To provide a strong ...
Types of pile
Depending on their function:
• Bearing piles
• Friction piles
• Sheet piles
• Anchor piles
• Batter piles
• ...
Casting of a Flyover Pile
(cast in situ)
(Location- Mouchak Mogbazar Flyover)
•At first, the
locations of piles are
fixed by theodolite
surveying.
1. Excavation Started

2. If utility pipes are found during
excavation, then the location
point of pile is changed

3. No ...
Hydraulic Rig machine

Cutting Bucket
•After excavating 6m
temporary steel case is
placed and then bentonite
is used.
• Excavation continues
according to design using
rotary rig machine
•Using hose pipe to
remove Bentonite
mixed water after
excavation process is
completed
Making of Steel Case
•Process of making the
vertical reinforcements in
circular arrangement
•Circular rings
are used to
make stirrups
and to
maintain
perfect
circular
arrangement
Stirrups
Completion of steel case
Thread Coupler

•It is used to join the inner
rebars
After applying pressure

Punching machine

Plane coupler

(N.B: These two couplers are used for the very first time in our...
Circular
CC block

weiring
welding
•Placing of steel case
Placing of trimmy pipe

Started casting
•After completion of casting
Top head of the pile is removed

Removed pile heads
Load test of pile :

•Load test is done by using hydraulic jack

Load test continued
(each block weighs 1 ton)
One layer BFS to level the surface of the pile cap
Casting on the BFS

After Casting on the BFS
Placing of reinforcement after initial casting of pile cap
Chair
Completion of placing reinforcement of pile cap
Completion of casting of pile cap
Observations:
• The water that they used to admix the bentonite was recycled
for next use also.
•They maintained the weiri...
THANK YOU… 
Do you have any Questions?
Upcoming SlideShare
Loading in...5
×

Piling of a flyover (AUST 2.2 A)

920

Published on

some information about piling and process of piling of a flyover.

Published in: Design
0 Comments
2 Likes
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total Views
920
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
83
Comments
0
Likes
2
Embeds 0
No embeds

No notes for slide

Piling of a flyover (AUST 2.2 A)

  1. 1. WELCOME
  2. 2. Presentation on FLYOVER PILING Prepared by: Course Teacher: Md. Arman Chowdhury Wahid Hasan (GROUP-5) 12.01.03.008; 12.01.03.016; 12.01.03.019; 12.01.03.025; 12.01.03.026; 12.01.03.032; 12.01.03.035; 12.01.03.038; 08.02.03.020;
  3. 3. What is Pile? • It is a long slender foundation member made either of timber,structural steel or concrete to transfer the load of the structure in deep foundation. Fig- Pile
  4. 4. Why do we use Pile? Weak Soil Deep Foundation Structure PILE Bed Rock
  5. 5. Advantage of Piling • To take the structure deep into the ground and hence preventing over turning. • To provide a strong bedrock soil (i.e. higher bearing capacity) for the structure and transfer the total load of the structure. • To distribute the weight of the structure over a large area. • To prevent unequal settlement.
  6. 6. Types of pile Depending on their function: • Bearing piles • Friction piles • Sheet piles • Anchor piles • Batter piles • Fender piles • Compaction piles Depending on their materials: • Timber piles • Concrete piles • Composite piles • Steel piles
  7. 7. Casting of a Flyover Pile (cast in situ) (Location- Mouchak Mogbazar Flyover)
  8. 8. •At first, the locations of piles are fixed by theodolite surveying.
  9. 9. 1. Excavation Started 2. If utility pipes are found during excavation, then the location point of pile is changed 3. No utility within 2 meter
  10. 10. Hydraulic Rig machine Cutting Bucket
  11. 11. •After excavating 6m temporary steel case is placed and then bentonite is used.
  12. 12. • Excavation continues according to design using rotary rig machine
  13. 13. •Using hose pipe to remove Bentonite mixed water after excavation process is completed
  14. 14. Making of Steel Case •Process of making the vertical reinforcements in circular arrangement
  15. 15. •Circular rings are used to make stirrups and to maintain perfect circular arrangement Stirrups
  16. 16. Completion of steel case
  17. 17. Thread Coupler •It is used to join the inner rebars
  18. 18. After applying pressure Punching machine Plane coupler (N.B: These two couplers are used for the very first time in our country)
  19. 19. Circular CC block weiring welding
  20. 20. •Placing of steel case
  21. 21. Placing of trimmy pipe Started casting
  22. 22. •After completion of casting
  23. 23. Top head of the pile is removed Removed pile heads
  24. 24. Load test of pile : •Load test is done by using hydraulic jack Load test continued (each block weighs 1 ton)
  25. 25. One layer BFS to level the surface of the pile cap
  26. 26. Casting on the BFS After Casting on the BFS
  27. 27. Placing of reinforcement after initial casting of pile cap
  28. 28. Chair
  29. 29. Completion of placing reinforcement of pile cap
  30. 30. Completion of casting of pile cap
  31. 31. Observations: • The water that they used to admix the bentonite was recycled for next use also. •They maintained the weiring and welding properly to make steel case strong enough to carry the load. •When they broke the pile head, it should be above 6” from the ground surface. But in some cases accidently, they couldn’t manage to do so. Therefore, they placed an extra layer of CC of 6” which shouldn’t be as it couldn’t take the load properly.
  32. 32. THANK YOU… 
  33. 33. Do you have any Questions?
  1. A particular slide catching your eye?

    Clipping is a handy way to collect important slides you want to go back to later.

×