Feb 11 2014 public meeting

190 views
121 views

Published on

February 11, 2014 public meeting presentation for three proposed stormwater facility management projects off of Cabin Branch of Great Seneca Creek. (pdf file)

Published in: Design
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
190
On SlideShare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
2
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Feb 11 2014 public meeting

  1. 1. Cabin Branch  Stormwater Management Stormwater Management Retrofit Projects  Quail Valley Pond #1 Quail Valley Pond #2  il ll d Strawberry Knoll Facility Concept Design Presentation February 11, 2014 F b 11 2014
  2. 2. T d ’ A d Today’s Agenda  Sources of Water on Earth  Montgomery County background  Wh t i    W t h d & R What is a Watershed & Runoff? ff?  Intro to Stormwater   What the County is Doing to Protect Our Streams  Goals of the Project  Proposed Pond Retrofit  p  Questions/Comments 2
  3. 3. Sources of Water  About 97% is salt water  About 2% is frozen  Only 1% is available for drinking water   Across the country, most potable water is from groundwater  In Maryland, most is from surface water  Potential for greater impacts from runoff in Maryland g p y 3
  4. 4. Montgomery County, MD  500 sq. miles  970,000 people  Second only to Baltimore City within  Maryland in average people per  square mile  184 languages spoken  About 12% impervious surface overall p  About the size of Washington DC  Over 1,500 miles of streams  Two major river basins:   P Potomac  Patuxent  Eight local watersheds District of Columbia Impervious: Not allowing water to  I i  N t  ll i   t  t   soak through the ground.  4
  5. 5. What is a Watershed?  A watershed is an area  from which the water  above and below ground  drains to the same place.  Different scales of  watersheds:  Chesapeake Bay  Eight local watersheds  Neighborhood (to a storm  drain) 5
  6. 6. What is Runoff? h ff? Water that does not soak into the ground becomes  surface runoff.  This runoff flows over hard surfaces like  rooftops, driveways and parking lots collecting potential  contaminants and flows: • Directly into streams • Into storm drain pipes, eventually leading to  streams • Into stormwater management facilities, then  streams Two Major Issues: Volume/Timing of Runoff V l /Ti i   f R ff Water Quality 6
  7. 7. What is the County doing to protect our Streams?  Must meet regulatory requirements  Federal Clean Water Act permit program  MS4 = Municipal Separate  Storm Sewer System M S S S S  Applies to all large and medium Maryland jurisdictions  County programs  Restore our streams and watersheds Add runoff management  Meet water quality protection goals  Reduce pollutants getting into our streams  Educate and engage all stakeholders  Individual actions make a difference  Focus on watersheds showing greatest impacts  7
  8. 8. MS4 P i Wh i i ? MS4 Permit: What is it?   Montgomery County is responsible for: • What goes into our storm drain pipes  • What comes out of them • What flows into the streams   Requires additional stormwater management for 20  percent of untreated impervious surfaces (4,292 acres =  ( 6.7 square miles).  That’s about three times the size of  Takoma Park. 8
  9. 9. O ll G l f h P j Overall Goals of the Project  Provide water quality treatment and downstream channel      9 protection to meet MS4 program requirements.  Improve ecological value of existing stormwater  management facilities.  management facilities   Improve existing landscaping and plant diversity of  existing facilities.  Upgrade existing facilities to comply with safety and  U d   i ti  f iliti  t   l   ith  f t   d  design standards.  Utilize existing open space to provide stormwater  management.  t 
  10. 10. P j t L ti Project Location Cabin Branch 10
  11. 11. Q Quail Valley Pond # 1 y SWM Retrofit  Project Overview P j tO i 11
  12. 12. D i A Drainage Area  9.24 acre drainage  area to pond  51% impervious  L d  Land cover includes   i l d   roadway, sidewalks,  manicured  lawns/landscaping.  a s/ a dscap g. 12
  13. 13. Existing Conditions  Constructed in the early 1980s  Fully developed drainage area  Does not provide water quality functions  High groundwater exists in bottom of facility   Does not meet current safety and design standards  (materials and conveyance)   Sinkholes have recently developed in embankment  Maintenance access is inadequate  Minor sediment deposition from upstream erosion 13
  14. 14. E i ti Q il V ll P d # 1 Existing Quail Valley Pond # 1 View of facility from Centerway Rd 14 Existing substandard riser.  Bottom of facility showing base flow Sinkhole resulting from riser  degradation. 
  15. 15. Retrofit Design Details  Grade bottom of pond and eastern bank   Grade bottom of pond and eastern bank.   Create a 3.5’ deep wet pool.  Remove and replace existing riser and outflow pipe.  Reconstruct portion of existing embankment.  p g  Remove small diameter trees within limits of work.  P id   Provide access path for maintenance.   th f   i t  Re‐vegetate pond and plant additional trees.  15
  16. 16. P d P d R t fit Proposed Pond Retrofit Plan View 16
  17. 17. Proposed Pond Retrofit Profile 17
  18. 18. Qua a ey o d Quail Valley Pond # 2 SWM Retrofit  Project Overview P j O i 18
  19. 19. D i A Drainage Area  48.9 acre drainage  area to pond  24% impervious 19
  20. 20. Existing Conditions  Constructed in the early 1980s  Fully developed drainage area y p g  Dry detention pond constructed in a stream valley  Very few ecological or water quality benefits  Good condition, but riser is nearing end of service life  Maintenance access is inadequate  Minor sediment deposition from upstream erosion  Degradation and incision of downstream channel  20
  21. 21. E i ti Q il V ll P d # 2 Existing Quail Valley Pond # 2 21
  22. 22. Retrofit Design Details  Enlarge the storage volume to treat 50% of the  Water Quality Volume (WQv)  Add a sand berm to increase infiltration  Grade an additional storage basin in existing open  space adjacent to stream banks  Safely pass larger storms, including the 100‐year  Safely pass larger storms, including the 100 year  storm 22
  23. 23. Retrofit Design Details  Install a forebay at the top of the pond to improve  maintenance  Remove existing risers and replace with cobble riffle  structures  Restore downstream channel using step pools  Revegetate pond with native plants 23
  24. 24. P d P d R t fit Proposed Pond Retrofit 24
  25. 25. Proposed Pond Retrofit Profile of Proposed Retrofit p Cross‐Section of Proposed Retrofit 25
  26. 26. Stormwater Pond Retrofit Stormwater Pond Retrofit During Construction g 26
  27. 27. Stormwater Pond Retrofit Stormwater Pond Retrofit Within 1 Year After Construction 27
  28. 28. Stormwater Pond Retrofit Stormwater Pond Retrofit Within 5 Years After Construction 28
  29. 29. Strawberry Knoll Strawberry Knoll Underground SWM Facility Project Overview  29
  30. 30. D i A Drainage Area  20.5 acre drainage 20.5  acre drainage  area to facility  37% impervious L d Land cover includes  i l d roadway, sidewalks,  manicured lawns,  ope space, a d open space, and  landscaping.  30
  31. 31. Existing Site Conditions  Parcel is owned by the Flower Hill Central Corporation  p p p y  Parcel provides open space for Flower Hill Community  Two stormdrain systems connect under open space  Flow in existing stormdrain is not treated for Water Quality or Flow in existing stormdrain is not treated for Water Quality or  Channel Protection   Space is available on site to provide an SWM facility  Site is accessible from Strawberry Knoll Road 31
  32. 32. E i ti O S Existing Open Space Location of Proposed SWM Facility. 32 Open space south of proposed facility.  Location of proposed construction and  maintenance access.  Existing inlet which SWM system will  connect to.
  33. 33. SWM Design Details   Underground gravity driven treatment system Underground gravity driven treatment system.  Three components: pretreatment, storage, and  treatment. treatment  Pretreatment simplifies and reduces the need for  maintenance. maintenance  Storage System stores stormwater until filtered.  Filter replaces natural functions depleted with development Filter replaces natural functions depleted with development.  Provide stable vegetated access path for future  maintenance. maintenance 33
  34. 34. P d SWM D i Proposed SWM Design Plan View 34
  35. 35. Proposed SWM Design  Profile 35
  36. 36. Grass Pavers UrbanGreen Grass Paver Detail 36
  37. 37. Stormwater Treatment Vortechs Pretreatment System Stormfilter System
  38. 38. Underground SWM Facility Underground SWM Facility During Construction g Storage system being installed 38 Watertight joint being sealed
  39. 39. Q il V ll P d # 1 C t ti A Quail Valley Pond # 1 Construction Access      39 ……‡••ˆ ‘ ‡– ƒ› ‘ƒ† ” ‡”™ ” ” ‘˜ƒŽƒ† ‰” ‰ ‡‡ ‡ ƒ†‹ ” ’” ‡…–‘ ™ Š‡” ‡‡ ‘– ‹ ‡ ‡‡†‡† —Ž ’ ƒ…‡† ‘ ’ƒ– ƒ …Š ’Ž ’ Š † ” ‘˜‡† ƒˆ ‡”…‘•– ‹ ‡ – ”—…–‘ ……‡••™ ‹Ž„‡ •– Žœ‡† – Ž ƒ„‹‹ ‘ ’” ‡˜‡–•‡†‹ ‡–– ƒ•’‘”–  ” – ‡– ƒ› ‘ƒ† ‘ ‡”™
  40. 40. Q il V ll P d # 2 C t ti A Quail Valley Pond # 2 Construction Access  Access from Centerway Road   Cl   id h  ill lik l   Clear width will likely  require tree removal and  grading  Tree protection where  needed  Mulch placed on path  and removed after  construction  i   40
  41. 41. St b K ll Construction Access Strawberry Knoll C t ti A  Access from Strawberry Knoll  Road   Access will be stabilized to  ll b bl d prevent sediment transport to  Strawberry Knoll Road Strawberry Knoll Road  Curb ramp and grass pavers will  be provided at final stages of  construction.  41 Location of proposed construction and  Location of proposed construction and maintenance access.
  42. 42. Construction Access (Example) During Construction After Construction
  43. 43. Reforestation  43 Attractive native  trees and shrubs  will be planted  within the project  area
  44. 44. Schedule   Public meeting to discuss 30% designs 2/11/2014  60% design – Summer  2014  90% design  Winter 2014 90% design –  Permits issued – Spring 2015 C Construction – S t ti   Summer 2015   44