City of Lebanon, NH
CSO Contract 11
Community Conversation
March 23, 2015
Sacred Heart Church
Agenda
• Introductions
• Conversation Goals
• CSO Overview
• General Project Overview
• Small Group Sessions
• Q&A
Conversation Goals
• Collect information from residents
Sewer backups
Localized flooding (street, yard, basements)
Sidewalk locations (current vs. desired)
Pavement widths
Parking needs (existing vs. desired)
Curbing (vertical vs. sloped)
Tree/planting/landscaping concerns
Curb cuts (existing vs. desired)
CSO Terminology
CSO = Combined Sewer Overflow
CB = Catch Basin
CD = Consent Decree
Combined Sewer = pipe w/ storm and sanitary flow
Purpose of sewer separation project is to provide
separate sanitary pipe and separate storm drain
pipe.
CSO Program Overview
• September 1998 – Draft CSO Master Plan
• 2000 – Administrative Order from EPA
• December 2005 – CSO Engineering Study
• April 2009 – CD Issued
Nov 2018 – Complete Contract 11 Sewer Separation
Dec 2020 – Eliminate All CSOs
CSO Contract 11 Area (feet)
• Mechanic Street (2,000)
• Mascoma Street (840)
• High Street (600)
• Worthen Street (500)
• Cameron Avenue (500)
• Mason Street (520)
• West Street (1,070)
• Child Street (590)
• Granite Street (1,015)
• Young Street (1,300)
• Guyer Street (1,160)
• Bliss Street (370)
• Light Street (600)
• Bank Street Extension (1,000)
• Cooper Street (250)
• Bank Street Near Bank Street Extension (200)
• Bank Street Near East Park Street (250)
March 23, 2015 Meeting Area
• Mason Street (520)
• West Street (1,070)
• Child Street (590)
• Granite Street (1,015)
• Young Street (1,300)
• Guyer Street (1,160)
• Bliss Street (370)
• Light Street (600)
General Project Overview
• New sanitary, storm, and water pipes
• Maintain esplanade configuration
• Maintain sidewalk configuration
• Retaining walls may be needed
• Add curbing and catch basins
vertical vs. sloped curb
• May modify vertical profile
• Constant roadway width
Protection of Trees
• Walkabout with arborist will be conducted.
• Invites via mailing will be forthcoming.
• Contact City staff if you have a concern about a
particular tree or planting.
Schedule
• House-To-House Inspections – January 2015
• Virtual Walkabouts – March 2015*
• CCVT/Smoke Testing – March 2015
• Project Area Survey – April 2015
• Preliminary Design – July 2015*
• 75% Design – September 2015*
• Final Construction Documents – March 2016*
• Bid Period – April 2016
• Start Construction – June 2016
• End Construction – December 2017
* Public Meeting
Project Contacts
• Christina Hall, City Engineer
Christina.Hall@lebcity.com
603.448.3112
• Mike Lavalla, Director of Public Works
Mike.Lavalla@lebcity.com
603.448.3112
• LebAlert
alert.lebnh.net
• Ryan Wingard, Wright-Pierce Project Manager
Ryan.Wingard@wright-pierce.com
603.430.3728
Small Group Sessions
Mason Street
Young to Granite
Approx. Proposed
Component Existing For Discussion
Width 25’ 24’
Esplanade yes (north) yes (north)
Sidewalk yes (north) yes (north)
Drainage CBs Vert. Curb/CBs
West Street
Young to Granite
Approx. Proposed
Component Existing For Discussion
Width 22’-25’ 22’
Esplanade yes (north) yes (north)
Sidewalk yes (north) yes (north)
Drainage CBs Vert. Curb/CBs
West Street
Granite to High
Approx. Proposed
Component Existing For Discussion
Width 20’-25’ 20’
Esplanade None None
Sidewalk None None
Drainage CBs Slope Curb/CBs
Child Street
Young to Granite
Approx. Proposed
Component Existing For Discussion
Width 18’-20’ 20’
Esplanade None None
Sidewalk None None
Drainage CBs Slope Curb/CBs
Granite Street
Mason to Mascoma
Approx. Proposed
Component Existing For Discussion
Width 20’ – 35’ 24’
Esplanade Yes (west) Yes (west)
Sidewalk Yes (west) Yes (west)
Partial (east) None
Drainage CBs Curb/CBs
Young Street
Hough to Worthen
Approx. Proposed
Component Existing For Discussion
Width 18’ – 26’ 22’
Esplanade None None
Sidewalk Partial (west) None
Drainage CBs Curb/CBs
Guyer Street
Young to Granite
Approx. Proposed
Component Existing For Discussion
Width 20’ – 22’ 22’
Esplanade Yes (north) Yes (north)
Sidewalk Yes (north) Yes (north)
Drainage CBs Curb/CBs
Guyer Street
Granite to Mascoma
Approx. Proposed
Component Existing For Discussion
Width 15’ – 20’ 20’
Esplanade None None
Sidewalk None None
Drainage CBs Slope Curb/CBs
Bliss Avenue/Street
Young to Guyer
Approx. Proposed
Component Existing For Discussion
Width 12’-16’ 16’
Esplanade None None
Sidewalk None None
Drainage CBs Slope Curb/CBs
Light Street
Granite to High
Approx. Proposed
Component Existing For Discussion
Width 10’-18’ 12’
Esplanade none none
Sidewalk none none
Drainage CBs Curb/CBs

More Related Content

What's hot

Madison Homeless Shelter Community Meeting Presentation (November 21, 2013)
Madison Homeless Shelter Community Meeting Presentation (November 21, 2013)Madison Homeless Shelter Community Meeting Presentation (November 21, 2013)
Madison Homeless Shelter Community Meeting Presentation (November 21, 2013)DC Department of General Services
 
Ohio Street Protest
Ohio Street ProtestOhio Street Protest
Ohio Street Protesth12adam
 
Benning Park Community Center - Community Meeting (September 2015)
Benning Park Community Center - Community Meeting (September 2015)Benning Park Community Center - Community Meeting (September 2015)
Benning Park Community Center - Community Meeting (September 2015)DC Department of General Services
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 finalToronto Public Consultation Unit
 
Lafayette Elementary School SIT Meeting Presentation (October 26, 2016)
Lafayette Elementary School SIT Meeting Presentation (October 26, 2016)Lafayette Elementary School SIT Meeting Presentation (October 26, 2016)
Lafayette Elementary School SIT Meeting Presentation (October 26, 2016)DC Department of General Services
 
Powell Elementary School & Twin Oaks Gardens Community Meeting Presentation J...
Powell Elementary School & Twin Oaks Gardens Community Meeting Presentation J...Powell Elementary School & Twin Oaks Gardens Community Meeting Presentation J...
Powell Elementary School & Twin Oaks Gardens Community Meeting Presentation J...DC Department of General Services
 
2010 4-14 open house
2010 4-14 open house2010 4-14 open house
2010 4-14 open housejseattle
 
Final comm meeting 3 city and committee 2017
Final comm meeting 3 city and committee 2017Final comm meeting 3 city and committee 2017
Final comm meeting 3 city and committee 2017Brian Hong
 
Rosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting PresentationRosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting Presentationknelischer
 

What's hot (14)

Madison Homeless Shelter Community Meeting Presentation (November 21, 2013)
Madison Homeless Shelter Community Meeting Presentation (November 21, 2013)Madison Homeless Shelter Community Meeting Presentation (November 21, 2013)
Madison Homeless Shelter Community Meeting Presentation (November 21, 2013)
 
Ohio Street Protest
Ohio Street ProtestOhio Street Protest
Ohio Street Protest
 
220127 gama update
220127 gama update220127 gama update
220127 gama update
 
Benning Park Community Center - Community Meeting (September 2015)
Benning Park Community Center - Community Meeting (September 2015)Benning Park Community Center - Community Meeting (September 2015)
Benning Park Community Center - Community Meeting (September 2015)
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
DWIRS public meeting 2015 March 24
DWIRS public meeting 2015 March 24DWIRS public meeting 2015 March 24
DWIRS public meeting 2015 March 24
 
Lafayette Elementary School SIT Meeting Presentation (October 26, 2016)
Lafayette Elementary School SIT Meeting Presentation (October 26, 2016)Lafayette Elementary School SIT Meeting Presentation (October 26, 2016)
Lafayette Elementary School SIT Meeting Presentation (October 26, 2016)
 
Display boards
Display boardsDisplay boards
Display boards
 
Dugway Sewer Community Update: April 1, 2014
Dugway Sewer Community Update: April 1, 2014Dugway Sewer Community Update: April 1, 2014
Dugway Sewer Community Update: April 1, 2014
 
Powell Elementary School & Twin Oaks Gardens Community Meeting Presentation J...
Powell Elementary School & Twin Oaks Gardens Community Meeting Presentation J...Powell Elementary School & Twin Oaks Gardens Community Meeting Presentation J...
Powell Elementary School & Twin Oaks Gardens Community Meeting Presentation J...
 
Dwirs community impact pres 4 4-13-v3
Dwirs community impact pres 4 4-13-v3Dwirs community impact pres 4 4-13-v3
Dwirs community impact pres 4 4-13-v3
 
2010 4-14 open house
2010 4-14 open house2010 4-14 open house
2010 4-14 open house
 
Final comm meeting 3 city and committee 2017
Final comm meeting 3 city and committee 2017Final comm meeting 3 city and committee 2017
Final comm meeting 3 city and committee 2017
 
Rosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting PresentationRosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting Presentation
 

Similar to Downtown Lebanon Visioning Study and Tunnel Project

Lebanon CSO 11 Public Meeting Presentation
Lebanon CSO 11 Public Meeting PresentationLebanon CSO 11 Public Meeting Presentation
Lebanon CSO 11 Public Meeting PresentationCity of Lebanon
 
CSO 10 Public Meeting Presentation
CSO 10 Public Meeting PresentationCSO 10 Public Meeting Presentation
CSO 10 Public Meeting PresentationCity of Lebanon
 
Final Design Presentation
Final Design PresentationFinal Design Presentation
Final Design PresentationBrian Weaver
 
NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014
NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014
NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014Island Health
 
Urban Design Quality. Church Fields, Boston Spa, a case study.
Urban Design Quality. Church Fields, Boston Spa, a case study.Urban Design Quality. Church Fields, Boston Spa, a case study.
Urban Design Quality. Church Fields, Boston Spa, a case study.Homes and Communities Agency (HCA)
 
NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014
NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014
NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014Island Health
 
Bridge Square Dec. 9 2013 open house presentation
Bridge Square Dec. 9 2013 open house presentationBridge Square Dec. 9 2013 open house presentation
Bridge Square Dec. 9 2013 open house presentationWigley and Associates
 
Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14West Central Association
 
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Davis street improvement project final2 21-13 4.16.13
Davis street improvement project final2 21-13 4.16.13Davis street improvement project final2 21-13 4.16.13
Davis street improvement project final2 21-13 4.16.13cityofevanston
 
Campbell River Community Information Meeting presentation Sept. 18, 2014
Campbell River Community Information Meeting presentation Sept. 18, 2014Campbell River Community Information Meeting presentation Sept. 18, 2014
Campbell River Community Information Meeting presentation Sept. 18, 2014Island Health
 
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood  Stormwater Improvement Preliminary Design ReviewTucker Avenue Neighborhood  Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design ReviewFairfax County
 
CMAX Cleveland Avenue BRT Public Meeting
CMAX Cleveland Avenue BRT Public MeetingCMAX Cleveland Avenue BRT Public Meeting
CMAX Cleveland Avenue BRT Public MeetingCOTA BUS
 
The Paterson Greenway Project
The Paterson Greenway ProjectThe Paterson Greenway Project
The Paterson Greenway ProjectAPA-NJ
 
Slayton Hill Road Reconstruction Presentation
Slayton Hill Road Reconstruction Presentation Slayton Hill Road Reconstruction Presentation
Slayton Hill Road Reconstruction Presentation City of Lebanon
 
Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014West Central Association
 

Similar to Downtown Lebanon Visioning Study and Tunnel Project (20)

Lebanon CSO 11 Public Meeting Presentation
Lebanon CSO 11 Public Meeting PresentationLebanon CSO 11 Public Meeting Presentation
Lebanon CSO 11 Public Meeting Presentation
 
Fairhill/MLK pre-construction public meeting 3-25-2015
Fairhill/MLK pre-construction public meeting 3-25-2015Fairhill/MLK pre-construction public meeting 3-25-2015
Fairhill/MLK pre-construction public meeting 3-25-2015
 
CSO 10 Public Meeting Presentation
CSO 10 Public Meeting PresentationCSO 10 Public Meeting Presentation
CSO 10 Public Meeting Presentation
 
Final Design Presentation
Final Design PresentationFinal Design Presentation
Final Design Presentation
 
Cold-in-Place Asphalt Recycling in the City of Highland
Cold-in-Place Asphalt Recycling in the City of HighlandCold-in-Place Asphalt Recycling in the City of Highland
Cold-in-Place Asphalt Recycling in the City of Highland
 
NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014
NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014
NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014
 
Urban Design Quality. Church Fields, Boston Spa, a case study.
Urban Design Quality. Church Fields, Boston Spa, a case study.Urban Design Quality. Church Fields, Boston Spa, a case study.
Urban Design Quality. Church Fields, Boston Spa, a case study.
 
NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014
NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014
NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014
 
Bridge Square Dec. 9 2013 open house presentation
Bridge Square Dec. 9 2013 open house presentationBridge Square Dec. 9 2013 open house presentation
Bridge Square Dec. 9 2013 open house presentation
 
Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14Fulton Market Task Force presentation #3 12.03.14
Fulton Market Task Force presentation #3 12.03.14
 
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Davis street improvement project final2 21-13 4.16.13
Davis street improvement project final2 21-13 4.16.13Davis street improvement project final2 21-13 4.16.13
Davis street improvement project final2 21-13 4.16.13
 
Campbell River Community Information Meeting presentation Sept. 18, 2014
Campbell River Community Information Meeting presentation Sept. 18, 2014Campbell River Community Information Meeting presentation Sept. 18, 2014
Campbell River Community Information Meeting presentation Sept. 18, 2014
 
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood  Stormwater Improvement Preliminary Design ReviewTucker Avenue Neighborhood  Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
 
CMAX Cleveland Avenue BRT Public Meeting
CMAX Cleveland Avenue BRT Public MeetingCMAX Cleveland Avenue BRT Public Meeting
CMAX Cleveland Avenue BRT Public Meeting
 
The Paterson Greenway Project
The Paterson Greenway ProjectThe Paterson Greenway Project
The Paterson Greenway Project
 
2015 PACAAwards
2015 PACAAwards2015 PACAAwards
2015 PACAAwards
 
Slayton Hill Road Reconstruction Presentation
Slayton Hill Road Reconstruction Presentation Slayton Hill Road Reconstruction Presentation
Slayton Hill Road Reconstruction Presentation
 
Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014Fulton Market Streetscape Public Meeting 12/10/2014
Fulton Market Streetscape Public Meeting 12/10/2014
 

Recently uploaded

Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...
Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...
Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...Amil baba
 
me3493 manufacturing technology unit 1 Part A
me3493 manufacturing technology unit 1 Part Ame3493 manufacturing technology unit 1 Part A
me3493 manufacturing technology unit 1 Part Akarthi keyan
 
sdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdf
sdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdfsdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdf
sdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdfJulia Kaye
 
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...Amil baba
 
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdfSummer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdfNaveenVerma126
 
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...amrabdallah9
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxNaveenVerma126
 
UNIT4_ESD_wfffffggggggggggggith_ARM.pptx
UNIT4_ESD_wfffffggggggggggggith_ARM.pptxUNIT4_ESD_wfffffggggggggggggith_ARM.pptx
UNIT4_ESD_wfffffggggggggggggith_ARM.pptxrealme6igamerr
 
ASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entenderASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entenderjuancarlos286641
 
Modelling Guide for Timber Structures - FPInnovations
Modelling Guide for Timber Structures - FPInnovationsModelling Guide for Timber Structures - FPInnovations
Modelling Guide for Timber Structures - FPInnovationsYusuf Yıldız
 
solar wireless electric vechicle charging system
solar wireless electric vechicle charging systemsolar wireless electric vechicle charging system
solar wireless electric vechicle charging systemgokuldongala
 
Dev.bg DevOps March 2024 Monitoring & Logging
Dev.bg DevOps March 2024 Monitoring & LoggingDev.bg DevOps March 2024 Monitoring & Logging
Dev.bg DevOps March 2024 Monitoring & LoggingMarian Marinov
 
cloud computing notes for anna university syllabus
cloud computing notes for anna university syllabuscloud computing notes for anna university syllabus
cloud computing notes for anna university syllabusViolet Violet
 
Design of Clutches and Brakes in Design of Machine Elements.pptx
Design of Clutches and Brakes in Design of Machine Elements.pptxDesign of Clutches and Brakes in Design of Machine Elements.pptx
Design of Clutches and Brakes in Design of Machine Elements.pptxYogeshKumarKJMIT
 
Test of Significance of Large Samples for Mean = µ.pptx
Test of Significance of Large Samples for Mean = µ.pptxTest of Significance of Large Samples for Mean = µ.pptx
Test of Significance of Large Samples for Mean = µ.pptxHome
 
How to Write a Good Scientific Paper.pdf
How to Write a Good Scientific Paper.pdfHow to Write a Good Scientific Paper.pdf
How to Write a Good Scientific Paper.pdfRedhwan Qasem Shaddad
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS Bahzad5
 

Recently uploaded (20)

Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...
Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...
Best-NO1 Best Rohani Amil In Lahore Kala Ilam In Lahore Kala Jadu Amil In Lah...
 
Litature Review: Research Paper work for Engineering
Litature Review: Research Paper work for EngineeringLitature Review: Research Paper work for Engineering
Litature Review: Research Paper work for Engineering
 
me3493 manufacturing technology unit 1 Part A
me3493 manufacturing technology unit 1 Part Ame3493 manufacturing technology unit 1 Part A
me3493 manufacturing technology unit 1 Part A
 
sdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdf
sdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdfsdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdf
sdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdf
 
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
 
Présentation IIRB 2024 Marine Cordonnier.pdf
Présentation IIRB 2024 Marine Cordonnier.pdfPrésentation IIRB 2024 Marine Cordonnier.pdf
Présentation IIRB 2024 Marine Cordonnier.pdf
 
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdfSummer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
 
Lecture 4 .pdf
Lecture 4                              .pdfLecture 4                              .pdf
Lecture 4 .pdf
 
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
 
UNIT4_ESD_wfffffggggggggggggith_ARM.pptx
UNIT4_ESD_wfffffggggggggggggith_ARM.pptxUNIT4_ESD_wfffffggggggggggggith_ARM.pptx
UNIT4_ESD_wfffffggggggggggggith_ARM.pptx
 
ASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entenderASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entender
 
Modelling Guide for Timber Structures - FPInnovations
Modelling Guide for Timber Structures - FPInnovationsModelling Guide for Timber Structures - FPInnovations
Modelling Guide for Timber Structures - FPInnovations
 
solar wireless electric vechicle charging system
solar wireless electric vechicle charging systemsolar wireless electric vechicle charging system
solar wireless electric vechicle charging system
 
Dev.bg DevOps March 2024 Monitoring & Logging
Dev.bg DevOps March 2024 Monitoring & LoggingDev.bg DevOps March 2024 Monitoring & Logging
Dev.bg DevOps March 2024 Monitoring & Logging
 
cloud computing notes for anna university syllabus
cloud computing notes for anna university syllabuscloud computing notes for anna university syllabus
cloud computing notes for anna university syllabus
 
Design of Clutches and Brakes in Design of Machine Elements.pptx
Design of Clutches and Brakes in Design of Machine Elements.pptxDesign of Clutches and Brakes in Design of Machine Elements.pptx
Design of Clutches and Brakes in Design of Machine Elements.pptx
 
Test of Significance of Large Samples for Mean = µ.pptx
Test of Significance of Large Samples for Mean = µ.pptxTest of Significance of Large Samples for Mean = µ.pptx
Test of Significance of Large Samples for Mean = µ.pptx
 
How to Write a Good Scientific Paper.pdf
How to Write a Good Scientific Paper.pdfHow to Write a Good Scientific Paper.pdf
How to Write a Good Scientific Paper.pdf
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
 

Downtown Lebanon Visioning Study and Tunnel Project

  • 1. City of Lebanon, NH CSO Contract 11 Community Conversation March 23, 2015 Sacred Heart Church
  • 2. Agenda • Introductions • Conversation Goals • CSO Overview • General Project Overview • Small Group Sessions • Q&A
  • 3. Conversation Goals • Collect information from residents Sewer backups Localized flooding (street, yard, basements) Sidewalk locations (current vs. desired) Pavement widths Parking needs (existing vs. desired) Curbing (vertical vs. sloped) Tree/planting/landscaping concerns Curb cuts (existing vs. desired)
  • 4. CSO Terminology CSO = Combined Sewer Overflow CB = Catch Basin CD = Consent Decree Combined Sewer = pipe w/ storm and sanitary flow Purpose of sewer separation project is to provide separate sanitary pipe and separate storm drain pipe.
  • 5. CSO Program Overview • September 1998 – Draft CSO Master Plan • 2000 – Administrative Order from EPA • December 2005 – CSO Engineering Study • April 2009 – CD Issued Nov 2018 – Complete Contract 11 Sewer Separation Dec 2020 – Eliminate All CSOs
  • 6. CSO Contract 11 Area (feet) • Mechanic Street (2,000) • Mascoma Street (840) • High Street (600) • Worthen Street (500) • Cameron Avenue (500) • Mason Street (520) • West Street (1,070) • Child Street (590) • Granite Street (1,015) • Young Street (1,300) • Guyer Street (1,160) • Bliss Street (370) • Light Street (600)
  • 7. • Bank Street Extension (1,000) • Cooper Street (250) • Bank Street Near Bank Street Extension (200)
  • 8. • Bank Street Near East Park Street (250)
  • 9. March 23, 2015 Meeting Area • Mason Street (520) • West Street (1,070) • Child Street (590) • Granite Street (1,015) • Young Street (1,300) • Guyer Street (1,160) • Bliss Street (370) • Light Street (600)
  • 10. General Project Overview • New sanitary, storm, and water pipes • Maintain esplanade configuration • Maintain sidewalk configuration • Retaining walls may be needed • Add curbing and catch basins vertical vs. sloped curb • May modify vertical profile • Constant roadway width
  • 11. Protection of Trees • Walkabout with arborist will be conducted. • Invites via mailing will be forthcoming. • Contact City staff if you have a concern about a particular tree or planting.
  • 12. Schedule • House-To-House Inspections – January 2015 • Virtual Walkabouts – March 2015* • CCVT/Smoke Testing – March 2015 • Project Area Survey – April 2015 • Preliminary Design – July 2015* • 75% Design – September 2015* • Final Construction Documents – March 2016* • Bid Period – April 2016 • Start Construction – June 2016 • End Construction – December 2017 * Public Meeting
  • 13. Project Contacts • Christina Hall, City Engineer Christina.Hall@lebcity.com 603.448.3112 • Mike Lavalla, Director of Public Works Mike.Lavalla@lebcity.com 603.448.3112 • LebAlert alert.lebnh.net • Ryan Wingard, Wright-Pierce Project Manager Ryan.Wingard@wright-pierce.com 603.430.3728
  • 15. Mason Street Young to Granite Approx. Proposed Component Existing For Discussion Width 25’ 24’ Esplanade yes (north) yes (north) Sidewalk yes (north) yes (north) Drainage CBs Vert. Curb/CBs
  • 16. West Street Young to Granite Approx. Proposed Component Existing For Discussion Width 22’-25’ 22’ Esplanade yes (north) yes (north) Sidewalk yes (north) yes (north) Drainage CBs Vert. Curb/CBs
  • 17. West Street Granite to High Approx. Proposed Component Existing For Discussion Width 20’-25’ 20’ Esplanade None None Sidewalk None None Drainage CBs Slope Curb/CBs
  • 18. Child Street Young to Granite Approx. Proposed Component Existing For Discussion Width 18’-20’ 20’ Esplanade None None Sidewalk None None Drainage CBs Slope Curb/CBs
  • 19. Granite Street Mason to Mascoma Approx. Proposed Component Existing For Discussion Width 20’ – 35’ 24’ Esplanade Yes (west) Yes (west) Sidewalk Yes (west) Yes (west) Partial (east) None Drainage CBs Curb/CBs
  • 20. Young Street Hough to Worthen Approx. Proposed Component Existing For Discussion Width 18’ – 26’ 22’ Esplanade None None Sidewalk Partial (west) None Drainage CBs Curb/CBs
  • 21. Guyer Street Young to Granite Approx. Proposed Component Existing For Discussion Width 20’ – 22’ 22’ Esplanade Yes (north) Yes (north) Sidewalk Yes (north) Yes (north) Drainage CBs Curb/CBs
  • 22. Guyer Street Granite to Mascoma Approx. Proposed Component Existing For Discussion Width 15’ – 20’ 20’ Esplanade None None Sidewalk None None Drainage CBs Slope Curb/CBs
  • 23. Bliss Avenue/Street Young to Guyer Approx. Proposed Component Existing For Discussion Width 12’-16’ 16’ Esplanade None None Sidewalk None None Drainage CBs Slope Curb/CBs
  • 24. Light Street Granite to High Approx. Proposed Component Existing For Discussion Width 10’-18’ 12’ Esplanade none none Sidewalk none none Drainage CBs Curb/CBs