11. 11
YellowYellow Products
% Cumulative
Sales
% Product
Range
50% 6%
95% 50%
Work to closely to align with Green products
– Piggyback with greens where
• Little change-over impact
• Differentiation happens off-line
12. 12
Yellows
• Work on reasons stopping yellows
going into green stream
• E.g.
– Changeovers
– Batch sizes
13. 13
Green stream
• Start with 6% range in fixed cycles
• Increase capacity (white space) through EOR
• Work on yellows
• Reduce barriers to being in green stream
• Move yellows into white space
• 50% product range BUT 95% volume in green
stream
14. 14
YellowYellow Products
% Cumulative
Sales
% Product
Range
50% 6%
95% 50%
– Utilize rapid improvement methodology to
remove barriers to flow
e.g.
• Grade change time, etc.
• Improve line performance
15. 15
BlueBlue Products
% Cumulative
Sales
% Product
Range
50% 6%
95% 50%
99%
• Opportunity for product or packaging
harmonization
• Product, materials and/or processing
include non-value adding complexity
17. 17
Blue SKU’s
- removing non-value adding complexity
• Facial Tissue mill
• Totally chaotic scheduling environment
• Clear bottleneck at the end of the production
process in making bundle packs
Blue opportunity – Printed Shrink Film
18. 18
EXAMPLE
Results:
• Removed Carton Orienter
• One week production cycle (now EPEW)
• Transformed a “chaotic” environment to a
smooth and “calm” one
• Focus on Multi-pack (Cyclone) bottleneck
– Output rates improved 22% two years in a row
27. 27
What about Forecasting and
Sales Variability?
Generally bigger sellers have less
variability
therefore greater predictability
28. 28
Rationalisation is NOT the only option!
It is AN option
however
there are many solutions
Red SKU’s
29. 29
Buffer tank utilization learning
Pre lean/RFS: Schedule adjustments would have occurred at three points
(creating that “vicious cycle”)
Post lean/RFS: No schedule adjustments and normal variability is
handled through the buffer tank
0
50
100
150
200
250
2/12/2006
2/19/2006
2/26/2006
3/5/2006
3/12/2006
3/19/2006
3/26/2006
4/2/2006
4/9/2006
4/16/2006
4/23/2006
4/30/2006
5/7/2006
5/14/2006
5/21/2006
5/28/2006
6/4/2006
Avg of min su Avg of max su Sum of Inv SU
GPS TCR12SR FAMILY (All) LOCCODE (All)
SUN_DT
Data
30. 30
Remove the “window” in to the
Buffer Tank…
11/27 12/4 12/11 12/18 12/25 1/1 1/8 1/15
STING8RR OK OK OK OK OK OK OK OK
STING1CAS HIGH HIGH OK OK OK OK OK HIGH
STING3RR OK OK OK OK OK OK OK OK
STING12RR OK OK OK OK OK OK OK OK
STING15RR HIGH HIGH HIGH OK OK OK OK OK
STING1MR OK OK OK OK HIGH HIGH OK OK
STING1RR OK LOW OK OK OK OK OK OK
STING24RR HIGH HIGH HIGH HIGH HIGH HIGH HIGH HIGH
STING2CAS OK OK OK OK OK OK OK OK
STING2MR HIGH HIGH HIGH HIGH OK OK OK OK
STING6RR OK OK OK OK OK OK OK OK
OK OK OK OK OK OK OK OK
31. 31
Impact on people
G’day Ian
I am sure "easy" was a word that sprang to mind when we first
started fixed cycles...there was a general view that I was insane
but having said that the crew would assassinate anyone who
now tried to take their fixed cycle away...
I'm probably a certifiable "early adopter" and the things you
are proposing seem to make so much sense.
best regards
Marty
32. 32
Impact on people
Hi Ian
Our Green Flow project started with four products that made up around 30%
of our total capacity here in Denmark. To test Green Flow’s proof-of-concept
we ran three cycles of five weeks per cycle. After fifteen weeks, the project’s
final fermentation finished followed by the standard purification, granulation
or liquid formation, QC analysis and shipping procedures.
The project has been a big success. We have reduced our lead time by 50%
for the majority of batches. Even the few batches that required some reworking
have had a 33% reduced lead time. It has been possible to hold the vast majority
of the agreed start/stop times throughout the supply chain. And lastly almost
everyone, from operators to top management, thinks the Green Flow principle
is a far better way of production than what we were doing before. We expect that
Green Flow will no longer be considered a project but an established way of
production.
Best regards,
Herman Herz
Lean Facilitator
33. 33
Impact on people
From: Graham, Jeff
Sent: Monday, February 15, 2007 10:08 AM
To: Sather, Rick
Cc: Gardhouse, Brian
Subject: RE: Huntsville Lean-RFS
Hi Rick
RFS has been a tremendous success for the Huntsville assets. Since the RFS start-up
in 2006 productivity has increase from under 15,000 cph to over 18,000 cph in January 2007.
The steady upward trend in rate of operation is a testament of the power of a frequent,
stable, predictable repeating schedule. I am a believer and would fight any efforts to go back
to the prior scheduling chaos!
We’ve been digging into the productivity improvement “toolbox” using standard techniques
fitted into the RFS structure. SMED, centerlining, TPM and equipment improvements are all
used to improve rates of operation. The approach has been practical with operations and
technical team members’ involvement. In particular, the line mechanics and electrical
Support are fully engaged making improvements regularly. Efforts have concentrated on
eliminating “rocks”, reducing equipment variables and stabilizing the process.
34. 34
A major shift in thinking is the idea of “making the cycle” versus daily rates of operation.
Instead of measuring rates of operation, we measure where we are in the cycle – ahead or
behind by hours. Also when extra hangs are made, it provides all team members a
measurable contribution to the business their efforts made especially when there are
customer service issues.
As for challenges, RFS continues to show us weaknesses in equipment, procedures and
people. Example: the facial tissue grade 280’s continues to be a challenge. Given it is run
every week; we know operating issues are independent of operating team, materials, current
procedures and equipment set-up. Plans have been developed to methodically address
observable barriers to flow to improve rates of operation. Although 280’s rates of operation
are stable and predictable, they are poor compared to other grades.
As I stated at the start, the Multifolder rates of operation continue a steady upward positive
trend in rate of operation. The stable, predictable repeating schedule contributes to
problem solving and solution implementation. I am a RFS believer.
Jeff
35. 35
Rocks or
barriers to flow
• Visible
• Hourly
• Operator led
• Focussed on achieving plan
• Problem identification
38. 38
“Normal” production variability
430
440
450
460
470
480
490
500
510
520
530
1 2 3 4 5 6 7 8 9 10 11 12
std output
actual output
Average output = 501/hr
• 501/hr average = seen as “good”
shift
•“good” hours balance “bad” hours
• little or no problem solving focus
• repeat issues not understood or
addressed
• operators get little or no resources
to help resolve their repeat issues
44. 44
Rockbusting
• Focus on all “bad” hours
(not consecutive hours or single
reoccurring issue)
• Operator led
• Visible process that triggers help
(NOT a problem solving process)
45. 45
“ROCK” Busting - Sustaining Action:
Follow-up Process for Rock Identification & Elimination
No Team Action
Needed
Decision
Point
Lean Steering
Team decides
the need for
Rock Busting in
a certain area
Gather
information
from all shifts &
perform sieve
analysis
Potential Rocks
documented on
Supervisors
Daily Shift
notes (email)
Supervisor flags
the need for Rock
Busting Team to
meet
•Rock Busting Team Members
Operator
Supervisor
Maintenance Supervisor
Quality Assurance Specialist
Engineering
Sanitation
Maintenance Techs
Report Findings and
Corrective Actions to
Distribution with
specific timeline &
person(s) responsible
Implement Corrective
Actions and continue
to monitor hourly
results
Team Gathers Data
& Executes Problem
Solving Process
(Brainstorming, etc.)
Team involves any
other necessary
resources (incl.
Corporate)
47. 47
Schedule Breaks
Example of tracking breaks
Hard
Rollover
8
Business /
Other
36
Materials
76
Customer
92
Site/Asset
113
0
20
40
60
80
100
120
2006 TOTAL FAMILY CARE RfS Schedule Breaks
Hard Rollover Business/Other Materials Customer Site/Asset
unt of Reason Description
Reason Description
48. 48
Schedule Breaks
Conclusions
• Schedule Break Log data is critical to understanding root
cause, and standardization of data is a must
• Three major barriers to flow:
– Site/Asset (36%)
– Customer (28%)
– Materials (23%)
2006 RfS Breaks - Internal or External* (%)
Customer
28%
Kimberly-
Clark
72%
49. 49
Schedule Breaks
Deeper dive – Site/Asset breaks
Site/Asset reason code breakdown (2006 totals)
0
5
10
15
20
25
30
White Space
Plan
Rates Project
Conflict
Machine
Failure
Human
Resources
Runout
51. 51
From Problem-hiding
to Problem-solving
• Focus on meeting the plan NOT line
efficiencies
• Identification of rocks & barriers to
flow
• Problem solving activity separate to
“get the line running NOW!”
53. 53
Toyota Production System
Jidoka
-Andon
-Poka-Yoke
-Visual control
-5S, etc.
Just-in-time
-continuous Flow
-Takt time
-Pull system
Customer service
Continuous
Improvement
And
Elimination of
MUDA (waste)
Lead TimeCostQuality
Stability & Standardized Work
Levelled production (heijunka)
55. 55
• Final step in the process, not how Toyota started
• What you see is different to how it was achieved
• You now know the “secret” =
EVERY PRODUCT EVERY CYCLE
56. 56
New Paradigm Supply Chain Logic
• Every Product Every Cycle is the key and
required to support production leveling
• Use the Glenday Sieve and pattern production
based on SKU categories
• Rigid cycle (start time and sequence) creates
Economies of Repetition
• Utilize “buffer tanks” to manage variability and
exceptions
– instead of always re-planning to a target
– Flexible quantity when limits are broken
57. 57
Every product Every Cycle
• A rigid disciplined PUSH process
• Leads to stability and standardisation
as a consequence
• Invest improvements in faster cycles
58. 58
Progression over time
Establish an EPEC pattern,
leverage Economies of
Repetition (EOR) & create
stability. A push flow
Fixed sequence, fixed volume
Fixed sequence, unfixed volume
Unfixed sequence, unfixed volume
Respond closer to demand,
continue to rely on EOR.
Sustain flow with some pull
Produce to demand.
True flow and pull
At this point, you will have a true Consumer Driven Supply Network
Increasingcapability,responsiveness,lowercostandcash
Faster fixed sequence, fixed volume
Maximise impact of EOR &
stability. Increase rate of flow.
Unfixed sequence, fixed volume
Break reliance on EPEC &
EOR. Pull using small fixed
volumes.
59. 59
Getting started
What – specifically – are you
going to do as a result of this forum
next week?
Write it down.