SlideShare a Scribd company logo
1 of 8
Download to read offline
1	
Good morning President Binder and Commission Members,
Thank you for the opportunity to address you all today – especially at the end of this very intensive
and demanding week. For the record my name is Pippa Feinstein and I am representing Swim Drink Fish
Canada/Lake Ontario Waterkeeper which has been granted intervener status in this hearing concerning the
Pickering Nuclear Generating Station’s (PNGS) licence renewal.
Waterkeeper is a non-political registered charity that uses research, education, and legal tools to
protect and restore the public’s right to swim, drink, and fish in the Lake Ontario watershed. It has been
involved in decision-making processes for the PNGS and Pickering Waste Management Facility (PWMF)
for many years, and has developed considerable expertise concerning the site’s adverse impacts on local
lake water quality and aquatic ecosystems.
Waterkeeper was provided with participant funding to examine three things: 1) the adequacy of
public information disclosure by OPG; 2) the impacts of the PNGS on local aquatic species and habitat; and
3) the impacts of the PNGS effluent and other liquid releases to local groundwater and surface water. I will
summarize some of our findings and recommendations for you in my presentation, but due to the limited
time, hope to be able to discuss these things in more depth during the question period for this intervention.
First and foremost, Waterkeeper opposes a 10-year licence renewal for the PNGS at this time.
There is insufficient information on the public record in this matter to demonstrate that the Station could
operate without significant impacts on the environment, and what little information our organization has
found on the record seems to indicate that there may be significant impacts and a lack of regulatory
oversight to ensure the facility’s compliance with relevant environmental law. As such, Waterkeeper
recommends a temporary interim licence of no longer than two years over which time OPG, CNSC staff,
and other regulators should collect and disseminate information that can demonstrate the facility’s ability to
make adequate provision for the protection of the environment. Such a decision would be consistent with a
precautionary approach which is affirmed and codified in Canadian law as well as international legal
instruments to which Canada is a signatory.
OPG and CNSC presented to the Commission on Monday, indicating that there were three robust
avenues by which members of the public could obtain information concerning the PNGS: 1) questions and
information requests during licence hearings; 2) formal Access to Information processes; and 3) OPG’s
website. I would submit each of these avenues are currently insufficient, and I will explain why.
In terms of information requests pursuant to the licence renewal hearing, our written
submissions can attest to OPG’s obfuscation and CNSC’s staff refusal1
to assist with this process. We were
																																																								
1
In our May 7th
submissions, we requested CNSC staff assistance in providing the information we had
requested, It is unclear whether staff assisted with this or to what extent they may have tried to help. CNSC
staff has informed us that they require OPG’s consent to release information about the PNGS facility and
that it is better to seek to obtain information directly from the company.
2	
almost unable to fulfill our obligations under our funding agreement after being denied crucial information
we required for our review, including groundwater monitoring reports, maps showing liquid discharge lines
from the Station, Fish Diversion System (FDS) net failure events, and cooling water temperature spikes.
None of this information was provided, nor were any reasons provided for these refusals, despite
the fact that OPG is required to provide annual impingement and entrainment reports as well as
groundwater monitoring reports to the CNSC, and the requested sampling data would have already been
completed and stored at the facility, so I would have expected these things to be provided in a timely
manner.2
This issue of insufficient disclosure at public hearings is not a new one: the Commissioners
recommended that OPG disclose more monitoring data in your last PNGS relicensing decision in 2013, as
well as your more recent PWMF relicensing decision last year. The Commission also directed staff to take
on a more active role in assisting intervenors requesting information from regulated facilities in your
PWMF decision. It is frustrating that your recommendations and directions have not been acted on.
In response to OPG’s and CNSC staff’s instance on using formal Access to Information
processes to obtain information on the PNGS, current timelines for public interventions in licence
renewal proceedings preclude this. Information requests can take several months, if not longer. Further, as
Shawn-Patrick Stensil noted to the Commission yesterday, sometimes ATIP processes can site these licence
proceedings as grounds for denying information, insisting these proceedings are the proper avenues to
obtain information about nuclear facilities.
In response to OPG’s assertions that it proactively publishes comprehensive information on
its website concerning the environmental performance of the PNGS, this is not the case. The
Environmental Risk Assessments and annual and quarterly compliance reports from OPG contain repeated
assertions that the PNGS is operating within its licence conditions and that any exceedances are not
environmentally significant, however insufficient data is provided to demonstrate the veracity of these
claims. These reports contain virtually no disaggregated data concerning any environmental monitoring
within the PNGS site boundaries. What limited data is reported concerning off-site impacts of the PNGS is
often provided in annual or quarterly averages and even then, it is inconsistently reported from year to year.
Further, monitoring methodologies employed by OPG are not comprehensively explained, frustrating
attempts to assess the significance or adequacy of sampling results that are provided.
Even with the extremely limited information available on the public record, our two scientific
experts were able to identify several areas of concern and make recommendations for their
improvement.
																																																								
2
Note: Greenpeace and Northwatch had also requested copies of OPG’s groundwater monitoring reports in
February 2018, after an OPG stakeholder meeting and were only informed in May - the week our written
interventions were due – that OPG would not provide this report. No reasons for this refusal were given.
3	
With regard to the impacts of the PNGS cooling water system on aquatic species and habitat,
Dr. Henderson found that there may be cause for concern. The PNGS cooling system extracts and
discharges a massive amount of water: up to almost five and half Olympic-size swimming pools per
minute, or what Dr. Henderson calls the flow of a small river. The plant, prior to the installation of a Fish
Diversion System (FDS) in 2009, was responsible for killing millions of fish, larvae, and fish eggs each
year due to impingement and entrainment. In 2008 the Commission directed OPG to reduce impingement
by 80%, however upon reviewing impingement data since 2010, Dr. Henderson found this 80% reduction
was only achieved in three out of the past seven years. Even the years in which OPG’s data indicates the
80% reduction was achieved, Waterkeeper urges caution as the 2003 baseline against which this reduction
is measured excludes the round goby, a fish species that has become increasingly abundant in Lake Ontario
over the last decade – Waterkeeper also cautions against the use of a single year as a baseline which is
problematic given the significant variability of certain species of fish populations around the PNGS from
year to year.
Dr. Henderson’s review of impingement data also raises concerns with OPG’s ability to comply
with its new DFO authorization. The authorization requires OPG to discuss additional follow-up
requirements if the PNGS impinges more than 3619 kg of fish in two consecutive years. Given
impingement values from 2010/11 and 2014/15 Dr. Henderson believes it’s highly likely that this 3619 kg
limit will be exceeded for two consecutive years in the future.
Further, despite high levels of entrainment, and past Commission directions to OPG to mitigate
these losses, no mitigation has taken place nor is it planned – despite the availability of sonar diversion and
the installation of full or partial closed-cycle cooling for the PNGS. OPG asserts entrainment impacts are
offset elsewhere via habitat restoration for Northern pike and Salmon restocking initiatives. However, these
offsetting measures cannot be considered appropriate as they do nothing to compensate for the loss of
species actually entrained by the PNGS, including round goby, alewife, or Diporeia.
Dr. Henderson found that elevated temperatures of discharged water at the PNGS can have adverse
effects on phytoplankton productivity and macroinvertebrate growth, adversely impact fish migrations, and
result in a loss of aquatic species diversity. He also found that spikes in thermal discharges at the PNGS are
close to thermal death points for many larger fish species in Lake Ontario.
With all this in mind, Waterkeeper is concerned that the PNGS will not be able to comply with the
current authorization. Waterkeeper is also deeply concerned that facility was permitted to operate for
decades without a permit until January 2018 – this seems like a clear violation of the Fisheries Act. Further,
Waterkeeper is concerned about the exclusion of invasive species in the current DFO authorization seems
inconsistent with the Fisheries Act protection of fish that support fisheries recognized by the Act (e.g. round
4	
goby are a significant fish of prey in Lake Ontario, comprising 86% of the food by weight consumed by
lake sturgeon).
With regard to environmental impacts of effluent and other releases to groundwater and
surface water, our other scientific expert Mr. Ruland found that there may be cause for concern.
Despite the fact that his review was limited by OPG’s refusal to disclose groundwater and stormwater
monitoring reports or data, Mr. Ruland found evidence of extremely contaminated groundwater blow the
PNGS – at one point as high as 3.96 million Bq/L of tritium – over 565 times the Ontario Drinking Water
Standard of 7000 Bq/L. This is down from the 30 million Bq/L measured underneath the PNGS between
2001 and 2005. These elevated levels of tritium are due to a series of historical leaks of the contaminant
into groundwater: a product of a significant backlog of repairs and lack of proactive facility maintenance.
While OPG claims most of this backlog has been cleared, Waterkeeper is concerned that CNSC staff may
have failed to require full remediation of this contamination, instead approving a site-specific
contamination limit of 3 million Bq/L for tritium non-potable groundwater. All of these concerns pertain to
tritium, however Mr. Ruland cautions that elevated contamination levels may be present for other
contaminants beneath the PNGS – due to OPG’s and CNSC staff’s refusal to provide groundwater
monitoring information it is impossible for Waterkeeper to know more on this point.
When examining stormwater discharges from the PNGS, Mr. Ruland found that monitoring was
sporadic and that since 1990, there appear to have been regular monitoring gaps of between three and eight
years. When monitoring was done, it did not appear to have been performed on all stormwater discharge
lines, and when it was done it often failed to take into account seasonal variation and it failed to include
follow-up monitoring in instances in which elevated contaminant levels were discovered.
This last point is particularly important legally as repeated failures of toxicity testing at specific
stormwater catchment locations may constitute another violation of the Fisheries Act. Failed toxicity tests
at these locations prove that the water tested was lethal to aquatic life. For the limited tests Mr. Ruland was
able to find sampling values for, measured zinc levels in these locations were up to 17 times higher than
Provincial Water Quality Objectives (PWQOs), copper values were over eight times higher than PWQO
limits and cadmium levels also surpassed PWQO limits. Significantly, certain stormwater catchments
contained tritium levels as high as 39,000 Bq/L which Mr. Ruland identified as possible evidence that
contaminated groundwater is leaking into stormwater infrastructure constituting an unintended pathway of
contaminated groundwater into Lake Ontario via stormwater outfalls. If this is in fact occurring, such
discharges could easily violate the Fisheries Act.
Due to time constraints, I will end my presentation there, but look forward to answering any
questions the Commission may have, and hope to be able to aske several questions of my own on the
record. Thank you.
5	
Closing statements:
The Pickering site in located in an ecologically stressed, but resilient, part of the northern shoreline
of Lake Ontario. Recently, this area has been the focus of increasing remediation and conservation efforts –
especially concerning various ecological features in this area that are unique in North America. The
Pickering site is surrounded by parks to the west and north, wetlands to the east, and the lake to the south.
Conservation areas, beaches, fishing and paddling spots, and trails also surround the site. As well as Ajax’s
drinking water intake which is located just west of the site. Of the 90 aquatic species present in Lake
Ontario, 60 have been found in the vicinity of the PNGS, including species at risk and of concern such as
sturgeon, American eel, and Atlantic Salmon.
As urban populations around the PNGS continue to rise, members of the public will become
increasingly dependent on the lake and the lake’s shoreline for sustenance and recreation.
I should emphasize, again, there is a lot of uncertainty concerning the PNGS’ impact on the
local environment – due to lack of information on the public record. The federal government’s open
data initiative – which extends to the CNSC and explicitly seeks to promote greater transparency in the
energy sector and scientific fields – requires proactive disclosure of data in accessible formats, recognizing
this is in the public interest. Access to information, including environmental monitoring data, is also a
crucial prerequisite to Ontarians’ rights to a healthful environment and Lake Ontario, as recognized in the
province’s Environmental Bill of Rights and Great Lakes Protection Act. Further, as Commissioners, the
dearth of available objective, evidence-based, and supportable information concerning PNGS’
environmental performance impacts your ability to meet your due diligence obligations. Waterkeeper
implores the Commission to require (rather than simply recommend) more disclosure from OPG and CNSC
staff in order to facilitate accountability, transparency, and the level of public scrutiny we all deserve.
The Commission has the opportunity and the duty to protect this area. You have heard extensive
testimony regarding the public concern for the environment in different kinds of hypothetical accident
scenarios. These are important to keep in mind, but just as important are the real concerns over the
environmental performance of the PNGS in the here and now.
We request a licence period of no longer than two years, over which period OPG and CNSC staff
and others should be ordered to collect and disseminate information, including raw sampling data, that can
demonstrate the facility’s ability to make adequate provision for the protection of the environment. This
additional material must be made publicly available and subject to a fulsome relicensing hearing that
facilitates public comments on the merits of OPG’s application – something that has not been possible
under the limitations of this current proceeding.
6	
Summary of all Waterkeeper recommendations
Recommendation 1: That OPG be granted a licence under the terms of its current licence, for no longer
than two years, during which time OPG, CNSC staff, the DFO and ECCC can monitor and publicly report
on the PNGS impacts to Lake Ontario’s water quality and local aquatic environments, and ensure a future
hearing to consider a longer PNGS licence on a more comprehensive evidentiary record.
Recommendation 2: When considering the current licence renewal application, the Commission Tribunal
must do so while keeping in mind the growing importance of the lake for swimming, drinking, and fishing
as well as cumulative adverse environmental impacts of lake water quality and the health of local aquatic
ecosystems.
Recommendation 3: that CNSC staff and the DFO review the use of 2003/4 data as the benchmark against
which impingement mitigation is measured, instead selecting a broader period of time that also takes into
account the current characteristics of Lake Ontario’s ecosystem.
Recommendation 4: that OPG, CNSC staff, and the DFO examine the likelihood of the PNGS exceeding
the 3,619 kg threshold for two consecutive years and publicly report their findings, including any proposed
follow-up activities.
Recommendation 5: that OPG make publicly available its monitoring reports concerning impingement
rates and net performance, including net failure events.
Recommendation 6: that entrainment monitoring commence immediately, rather than 2021.
Recommendation 7: that OPG and CNSC staff immediately develop entrainment mitigation measures to
decrease entrainment rates at the PNGS.
Recommendation 8: that OPG, CNSC staff, and the DFO consider and implement measures to ensure that
offsetting activities more effectively compensate for actual species impinged and entrained at the PNGS.
Recommendation 9: that OPG, CNSC staff, and the DFO consider and implement measures to mitigate
thermal pollution by the PNGS, taking into account the projected impacts of climate change on lake water
temperature in Lake Ontario.
Recommendation 10: that OPG makes its ECA compliance reports public, by posting them to the OPG
webpage with other compliance reports.
Recommendation 11: That OPG and CNSC staff make public their responses to the four ECCC areas in
which more information was required concerning potential adverse impacts of the PNGS on local water
quality and aquatic biota.
Recommendation 12: that an explanation from the DFO concerning the PNGS’s historical compliance
with the Fisheries Act be shared with Waterkeeper, and put on the record of the current proceedings, in
advance of the public hearings from June 25 – 29
th
, 2018, including references to any regulations or
Ministerial Orders exempting the PNGS from the application of the Fisheries Act.
Recommendation 13: that all species impinged and entrained by the PNGS be considered and added to the
DFO s. 35 permit for the PNGS, including but not limited to alewife and round goby. This approach would
be more consistent with the Fisheries Act.
Recommendation 14: that the DFO s. 35 permit itself be amended to ensure that offsetting activities
properly compensate for actual species killed by the PNGS. This approach would also be more consistent
7	
with the Fisheries Act.
Recommendation 15: that OPG be required to publicly disclose the annual compliance reports required by
the DFO permit by posting them to the OPG webpage with all other PNGS compliance reports.
Recommendation 16: That OPG and CNSC staff immediately release the following information on the
public record in this hearing process:
• a complete set of borehole logs and monitor installation details for OPG’s full network of groundwater
monitoring wells and sampling points; 

• up to date and useable groundwater level and groundwater quality monitoring data for the full network
of groundwater wells and sampling points; 

• recent annual groundwater monitoring reports for the PNGS; and 

• a map and inventory of storm sewer lines for the site, including estimates of flows and a list of how many
of these lines are being monitored on a regular basis and the 
monitoring results (for radiological
and non-radiological contaminants).
Recommendation 17: If not already included, Waterkeeper recommends that coper and zinc be included as
COPCs for groundwater below the PNGS. 

Recommendation 18: that OPG and CNSC staff publicly confirm whether a site-specific groundwater
tritium limit of 3 million Bq/L is in effect for the PNGS.
Recommendation 19: that if there is a site-specific groundwater tritium limit of 3 million Bq/L for the
PNGS, OPG and CNSC staff must publicly report: 1) when and how it was developed; the scientific basis
for its development; the extent to which it has been formally adopted by the CNSC and reasons for its
exclusion from the current and proposed licence and Licence Conditions Handbook for the PNGS; and 4)
whether any public consultation was conducted prior to establishing this elevated contamination limit.
Recommendation 20: OPG must conduct quarterly monitoring of every stormwater collection line which
is discharging to the forebay, the outfalls, or directly into Lake Ontario, 

. h) As a first step, an inventory of stormwater collection lines needs to be developed and flows of water in
those lines need to be metered. Particular attention needs to be paid to any lines which are always
flowing, as this should not be occurring in a system which is collecting only stormwater. 

. i) Toxicity testing should be done on every line for every sampling event. For lines which are
consistently showing zero mortality, the frequency of toxicity testing can be stepped down to
annually after 3 years of passing test results. 

. j) The parameter lists being used for stormwater monitoring are reasonable, however in the event of
failed toxicity testing results the scope of the testing should be increased to include:
- volatile
organic chemicals(VOCs); 

- polynuclear aromatic hydrocarbons (PAHs);
- hydrazine and morpholine; 
	
- additional radionuclides. 

. k) Adverse test results and in particular failed toxicity tests should prompt immediate further
investigation, with the goal of remediation of the issue(s) which are allowing contaminated and/or
toxic stormwater to be discharged to Lake Ontario via the stormwater collection system. 

. l) This information (including disaggregated data showing the results of this testing) should be made
publicly available in OPG’s quarterly or annual compliance reports. 

8	
Recommendation 21: Additional water quality sampling of Lake Ontario is recommended, with samples to
be taken at Beachfront Park, Frenchman’s Bay West Park, and Squires Beach and tested as follows:
-quarterly testing for copper, zinc, morpholine, and hydrazine; 

- annual testing for the full list of parameters presented on Table F.1 of the 2017 ERA Report.
. h) If not being done, then it is recommended that tritium and gross beta/ gamma be added as parameters
in the weekly testing of the PNGS outfall water quality. It is also recommended that the outfall
water quality testing should be done at a point downstream of all inputs from the PNGS. 

. i) Table A.3 of the Quarterly Environmental Emissions Data reports indicates that waterborne
radionuclide releases from the PNGS are analyzed monthly for Tritium, Gross Beta/Gamma,
Carbon-14, and Gross Alpha. It is recommended that the quarterly reports should provide a
transparent explanation for how the data being presented in Table A.3 are obtained. 

. j) It is recommended that the CNSC order OPG to provide full public disclosure of historic and current
PNGS groundwater monitoring data (including provision of full copies of Annual Monitoring
Reports if requested), commencing immediately. 

. k) It is recommended that OPG be required to fund a full, independent Peer Review of the historic and
current results of its PNGS groundwater monitoring program. The Peer Reviewer should report to
the CNSC, and their report should provide:
- an overview of historic groundwater quality monitoring results and their implications;
- recommendations on how to improve the groundwater monitoring program on 
a go-
forward basis; 

- recommendations on how to optimize the provision of transparent and 
publicly
accessible reporting of the results of the groundwater monitoring 
program. 

. l) This information (including disaggregated data showing the results of this testing, and 
additional
explanations of how this data was obtained) should be made publicly available in OPG’s quarterly
or annual compliance reports. 

Recommendation 22: The DFO and ECCC should immediately investigate the potential for stormwater
outfalls at the PNGS to be releasing deleterious substances into waters frequented by fish in contravention
of the Fisheries Act. The results of this investigation must be publicly disclosed.
Recommendation 23: OPG should better distinguish between mandatory and discretionary reporting in its
PIP and PDP and disclose the types of events that are reported in practice.
Recommendation 24: OPG should undertake to make all environmental reporting mentioned in the PIP
and PDP mandatory for the PNGS.
Recommendation 25: CNSC staff should work with OPG to create a timeline for OPG ultimately posting
comprehensive data in machine-readable formats in real time.
Recommendation 26: The webpage for reporting incidents at the PNGS should be included as a shortcut
tab on the PNGS’s homepage on opg.com.
Recommendation 27: Each incident report must include the incident date, reporting date, an exact
description of the event including actual data of any measured releases, and any applicable DRLs or ALs
so that members of the public can understand the severity of the reported incidents.

More Related Content

What's hot

Effect of Seasonal Variation on Quality of Domestic Water Sources in Central ...
Effect of Seasonal Variation on Quality of Domestic Water Sources in Central ...Effect of Seasonal Variation on Quality of Domestic Water Sources in Central ...
Effect of Seasonal Variation on Quality of Domestic Water Sources in Central ...theijes
 
5. The complex challenges of dealing with bathing waters - Prof. David Kay, A...
5. The complex challenges of dealing with bathing waters - Prof. David Kay, A...5. The complex challenges of dealing with bathing waters - Prof. David Kay, A...
5. The complex challenges of dealing with bathing waters - Prof. David Kay, A...Environmental Protection Agency, Ireland
 
Flood Early Warning System in Pakistan
Flood Early Warning System in PakistanFlood Early Warning System in Pakistan
Flood Early Warning System in PakistanDawood Jan
 
Stormwater regulations and their relationship to tmd ls
Stormwater regulations and their relationship to tmd lsStormwater regulations and their relationship to tmd ls
Stormwater regulations and their relationship to tmd lsMatthew Hahm
 
Gw01 understanding conventional and dwlr assisted water level monitoring
Gw01 understanding conventional and dwlr assisted water level monitoringGw01 understanding conventional and dwlr assisted water level monitoring
Gw01 understanding conventional and dwlr assisted water level monitoringhydrologyproject0
 
Progress report 2011 - Access the improving water information program
Progress report 2011  - Access the improving water information programProgress report 2011  - Access the improving water information program
Progress report 2011 - Access the improving water information programChristina Parmionova
 
Study Results: Delineating Injection Well Buffer Zones in Brackish Aquifers
Study Results: Delineating Injection Well Buffer Zones in Brackish AquifersStudy Results: Delineating Injection Well Buffer Zones in Brackish Aquifers
Study Results: Delineating Injection Well Buffer Zones in Brackish AquifersTexas Alliance of Groundwater Districts
 
A Case Study at Berggren Demonstration Farm - ELP
A Case Study at Berggren Demonstration Farm - ELPA Case Study at Berggren Demonstration Farm - ELP
A Case Study at Berggren Demonstration Farm - ELPAlex Burgdorfer
 
Final year project proposal
Final year project proposalFinal year project proposal
Final year project proposalDawood Jan
 
Reuse Litigation and Policy: Lyn Clancy, Jason Hill, Doug Caroom and Trey Nes...
Reuse Litigation and Policy: Lyn Clancy, Jason Hill, Doug Caroom and Trey Nes...Reuse Litigation and Policy: Lyn Clancy, Jason Hill, Doug Caroom and Trey Nes...
Reuse Litigation and Policy: Lyn Clancy, Jason Hill, Doug Caroom and Trey Nes...TWCA
 
Drought water conservation TCEQ perspective 2-3-12
Drought water conservation TCEQ perspective 2-3-12Drought water conservation TCEQ perspective 2-3-12
Drought water conservation TCEQ perspective 2-3-12The Texas Network, LLC
 
Bay-Delta Conservation Plan (BDCP) Environmental Review Process - October 24,...
Bay-Delta Conservation Plan (BDCP) Environmental Review Process - October 24,...Bay-Delta Conservation Plan (BDCP) Environmental Review Process - October 24,...
Bay-Delta Conservation Plan (BDCP) Environmental Review Process - October 24,...San Diego County Water Authority
 

What's hot (20)

WQR2014-Draft 6-15-2015
WQR2014-Draft 6-15-2015WQR2014-Draft 6-15-2015
WQR2014-Draft 6-15-2015
 
Rain harvesting
Rain harvestingRain harvesting
Rain harvesting
 
Effect of Seasonal Variation on Quality of Domestic Water Sources in Central ...
Effect of Seasonal Variation on Quality of Domestic Water Sources in Central ...Effect of Seasonal Variation on Quality of Domestic Water Sources in Central ...
Effect of Seasonal Variation on Quality of Domestic Water Sources in Central ...
 
5. The complex challenges of dealing with bathing waters - Prof. David Kay, A...
5. The complex challenges of dealing with bathing waters - Prof. David Kay, A...5. The complex challenges of dealing with bathing waters - Prof. David Kay, A...
5. The complex challenges of dealing with bathing waters - Prof. David Kay, A...
 
Flood Early Warning System in Pakistan
Flood Early Warning System in PakistanFlood Early Warning System in Pakistan
Flood Early Warning System in Pakistan
 
CLRA MSSS 2015 Walker Winnipeg
CLRA MSSS 2015 Walker WinnipegCLRA MSSS 2015 Walker Winnipeg
CLRA MSSS 2015 Walker Winnipeg
 
sea water quality
sea water qualitysea water quality
sea water quality
 
Study Results: Brackish Groundwater Comingling
Study Results: Brackish Groundwater Comingling Study Results: Brackish Groundwater Comingling
Study Results: Brackish Groundwater Comingling
 
2009-02-17 Brine Disposal Alternatives
2009-02-17  Brine Disposal Alternatives2009-02-17  Brine Disposal Alternatives
2009-02-17 Brine Disposal Alternatives
 
GCD Protest of a Texas RRC Injection Well Permit Application
GCD Protest of a Texas RRC Injection Well Permit ApplicationGCD Protest of a Texas RRC Injection Well Permit Application
GCD Protest of a Texas RRC Injection Well Permit Application
 
La Aw&Ma 2012
La Aw&Ma 2012La Aw&Ma 2012
La Aw&Ma 2012
 
Stormwater regulations and their relationship to tmd ls
Stormwater regulations and their relationship to tmd lsStormwater regulations and their relationship to tmd ls
Stormwater regulations and their relationship to tmd ls
 
Gw01 understanding conventional and dwlr assisted water level monitoring
Gw01 understanding conventional and dwlr assisted water level monitoringGw01 understanding conventional and dwlr assisted water level monitoring
Gw01 understanding conventional and dwlr assisted water level monitoring
 
Progress report 2011 - Access the improving water information program
Progress report 2011  - Access the improving water information programProgress report 2011  - Access the improving water information program
Progress report 2011 - Access the improving water information program
 
Study Results: Delineating Injection Well Buffer Zones in Brackish Aquifers
Study Results: Delineating Injection Well Buffer Zones in Brackish AquifersStudy Results: Delineating Injection Well Buffer Zones in Brackish Aquifers
Study Results: Delineating Injection Well Buffer Zones in Brackish Aquifers
 
A Case Study at Berggren Demonstration Farm - ELP
A Case Study at Berggren Demonstration Farm - ELPA Case Study at Berggren Demonstration Farm - ELP
A Case Study at Berggren Demonstration Farm - ELP
 
Final year project proposal
Final year project proposalFinal year project proposal
Final year project proposal
 
Reuse Litigation and Policy: Lyn Clancy, Jason Hill, Doug Caroom and Trey Nes...
Reuse Litigation and Policy: Lyn Clancy, Jason Hill, Doug Caroom and Trey Nes...Reuse Litigation and Policy: Lyn Clancy, Jason Hill, Doug Caroom and Trey Nes...
Reuse Litigation and Policy: Lyn Clancy, Jason Hill, Doug Caroom and Trey Nes...
 
Drought water conservation TCEQ perspective 2-3-12
Drought water conservation TCEQ perspective 2-3-12Drought water conservation TCEQ perspective 2-3-12
Drought water conservation TCEQ perspective 2-3-12
 
Bay-Delta Conservation Plan (BDCP) Environmental Review Process - October 24,...
Bay-Delta Conservation Plan (BDCP) Environmental Review Process - October 24,...Bay-Delta Conservation Plan (BDCP) Environmental Review Process - October 24,...
Bay-Delta Conservation Plan (BDCP) Environmental Review Process - October 24,...
 

Similar to Waterkeeper's PNGS hearing remarks - June 29, 2018

Submission by Lake Ontario Waterkeeper for the Darlington Nuclear Relicensing...
Submission by Lake Ontario Waterkeeper for the Darlington Nuclear Relicensing...Submission by Lake Ontario Waterkeeper for the Darlington Nuclear Relicensing...
Submission by Lake Ontario Waterkeeper for the Darlington Nuclear Relicensing...LOWaterkeeper
 
Swim Drink Fish's Preliminary Submission on Pickering Nuclear Generating Station
Swim Drink Fish's Preliminary Submission on Pickering Nuclear Generating StationSwim Drink Fish's Preliminary Submission on Pickering Nuclear Generating Station
Swim Drink Fish's Preliminary Submission on Pickering Nuclear Generating StationLOWaterkeeper
 
Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...
Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...
Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...LOWaterkeeper
 
Waterkeeper's Review of CNSC's Regulatory Oversight Report for Uranium and Nu...
Waterkeeper's Review of CNSC's Regulatory Oversight Report for Uranium and Nu...Waterkeeper's Review of CNSC's Regulatory Oversight Report for Uranium and Nu...
Waterkeeper's Review of CNSC's Regulatory Oversight Report for Uranium and Nu...LOWaterkeeper
 
Media release niagara falls water board - september 1, 2017
Media release   niagara falls water board - september 1, 2017Media release   niagara falls water board - september 1, 2017
Media release niagara falls water board - september 1, 2017Fatima Bangura
 
Lake Ontario Waterkeeper's Darlington Relicensing Hearing presentation- Novem...
Lake Ontario Waterkeeper's Darlington Relicensing Hearing presentation- Novem...Lake Ontario Waterkeeper's Darlington Relicensing Hearing presentation- Novem...
Lake Ontario Waterkeeper's Darlington Relicensing Hearing presentation- Novem...LOWaterkeeper
 
Lanteigne re: nuclear waste dump planned by Lake Huron
Lanteigne re: nuclear waste dump planned by Lake Huron Lanteigne re: nuclear waste dump planned by Lake Huron
Lanteigne re: nuclear waste dump planned by Lake Huron louisette lanteigne
 
Bay-Delta Conservation Plan: Review Update - August 22, 2013
Bay-Delta Conservation Plan: Review Update - August 22, 2013Bay-Delta Conservation Plan: Review Update - August 22, 2013
Bay-Delta Conservation Plan: Review Update - August 22, 2013San Diego County Water Authority
 
Pre production plastics and stormwater-h2 o-gtg
Pre production plastics and stormwater-h2 o-gtgPre production plastics and stormwater-h2 o-gtg
Pre production plastics and stormwater-h2 o-gtgGreg Gearheart
 
Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...
Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...
Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...LOWaterkeeper
 
NZCA submission on Next steps for fresh water April 2016
NZCA submission on Next steps for fresh water April 2016NZCA submission on Next steps for fresh water April 2016
NZCA submission on Next steps for fresh water April 2016Mark Christensen
 

Similar to Waterkeeper's PNGS hearing remarks - June 29, 2018 (20)

Submission by Lake Ontario Waterkeeper for the Darlington Nuclear Relicensing...
Submission by Lake Ontario Waterkeeper for the Darlington Nuclear Relicensing...Submission by Lake Ontario Waterkeeper for the Darlington Nuclear Relicensing...
Submission by Lake Ontario Waterkeeper for the Darlington Nuclear Relicensing...
 
Swim Drink Fish's Preliminary Submission on Pickering Nuclear Generating Station
Swim Drink Fish's Preliminary Submission on Pickering Nuclear Generating StationSwim Drink Fish's Preliminary Submission on Pickering Nuclear Generating Station
Swim Drink Fish's Preliminary Submission on Pickering Nuclear Generating Station
 
Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...
Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...
Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...
 
Waterkeeper's Review of CNSC's Regulatory Oversight Report for Uranium and Nu...
Waterkeeper's Review of CNSC's Regulatory Oversight Report for Uranium and Nu...Waterkeeper's Review of CNSC's Regulatory Oversight Report for Uranium and Nu...
Waterkeeper's Review of CNSC's Regulatory Oversight Report for Uranium and Nu...
 
Media release niagara falls water board - september 1, 2017
Media release   niagara falls water board - september 1, 2017Media release   niagara falls water board - september 1, 2017
Media release niagara falls water board - september 1, 2017
 
Lake Ontario Waterkeeper's Darlington Relicensing Hearing presentation- Novem...
Lake Ontario Waterkeeper's Darlington Relicensing Hearing presentation- Novem...Lake Ontario Waterkeeper's Darlington Relicensing Hearing presentation- Novem...
Lake Ontario Waterkeeper's Darlington Relicensing Hearing presentation- Novem...
 
2014_report
2014_report2014_report
2014_report
 
James Marsden (2011)
James Marsden (2011)James Marsden (2011)
James Marsden (2011)
 
Lanteigne re: nuclear waste dump planned by Lake Huron
Lanteigne re: nuclear waste dump planned by Lake Huron Lanteigne re: nuclear waste dump planned by Lake Huron
Lanteigne re: nuclear waste dump planned by Lake Huron
 
modelling_workshop-final_report
modelling_workshop-final_reportmodelling_workshop-final_report
modelling_workshop-final_report
 
Jeremy_Final_Thesis
Jeremy_Final_ThesisJeremy_Final_Thesis
Jeremy_Final_Thesis
 
Bay-Delta Conservation Plan: Review Update - August 22, 2013
Bay-Delta Conservation Plan: Review Update - August 22, 2013Bay-Delta Conservation Plan: Review Update - August 22, 2013
Bay-Delta Conservation Plan: Review Update - August 22, 2013
 
Sanders, Richard: The Integrated Ocean Carbon Observing System
Sanders, Richard: The Integrated Ocean Carbon Observing SystemSanders, Richard: The Integrated Ocean Carbon Observing System
Sanders, Richard: The Integrated Ocean Carbon Observing System
 
NTU is Not a University
NTU is Not a UniversityNTU is Not a University
NTU is Not a University
 
Pre production plastics and stormwater-h2 o-gtg
Pre production plastics and stormwater-h2 o-gtgPre production plastics and stormwater-h2 o-gtg
Pre production plastics and stormwater-h2 o-gtg
 
Scottish Fisheries Co-ordination Centre Talk at 2015 RAFTS Conference
Scottish Fisheries Co-ordination Centre Talk at 2015 RAFTS ConferenceScottish Fisheries Co-ordination Centre Talk at 2015 RAFTS Conference
Scottish Fisheries Co-ordination Centre Talk at 2015 RAFTS Conference
 
Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...
Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...
Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...
 
NZCA submission on Next steps for fresh water April 2016
NZCA submission on Next steps for fresh water April 2016NZCA submission on Next steps for fresh water April 2016
NZCA submission on Next steps for fresh water April 2016
 
Final_Potter_Creek
Final_Potter_CreekFinal_Potter_Creek
Final_Potter_Creek
 
4546
45464546
4546
 

Recently uploaded

办理约克大学毕业证成绩单|购买加拿大文凭证书
办理约克大学毕业证成绩单|购买加拿大文凭证书办理约克大学毕业证成绩单|购买加拿大文凭证书
办理约克大学毕业证成绩单|购买加拿大文凭证书zdzoqco
 
NL-FR Partnership - Water management roundtable 20240403.pdf
NL-FR Partnership - Water management roundtable 20240403.pdfNL-FR Partnership - Water management roundtable 20240403.pdf
NL-FR Partnership - Water management roundtable 20240403.pdfBertrand Coppin
 
Build Tomorrow’s India Today By Making Charity For Poor Students
Build Tomorrow’s India Today By Making Charity For Poor StudentsBuild Tomorrow’s India Today By Making Charity For Poor Students
Build Tomorrow’s India Today By Making Charity For Poor StudentsSERUDS INDIA
 
NO1 Certified Best vashikaran specialist in UK USA UAE London Dubai Canada Am...
NO1 Certified Best vashikaran specialist in UK USA UAE London Dubai Canada Am...NO1 Certified Best vashikaran specialist in UK USA UAE London Dubai Canada Am...
NO1 Certified Best vashikaran specialist in UK USA UAE London Dubai Canada Am...Amil Baba Dawood bangali
 
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...
Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...
Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...Christina Parmionova
 
Digital Transformation of the Heritage Sector and its Practical Implications
Digital Transformation of the Heritage Sector and its Practical ImplicationsDigital Transformation of the Heritage Sector and its Practical Implications
Digital Transformation of the Heritage Sector and its Practical ImplicationsBeat Estermann
 
ECOSOC YOUTH FORUM 2024 - Side Events Schedule -16 April.
ECOSOC YOUTH FORUM 2024 - Side Events Schedule -16 April.ECOSOC YOUTH FORUM 2024 - Side Events Schedule -16 April.
ECOSOC YOUTH FORUM 2024 - Side Events Schedule -16 April.Christina Parmionova
 
call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
2024 ECOSOC YOUTH FORUM -logistical information - United Nations Economic an...
2024 ECOSOC YOUTH FORUM -logistical information -  United Nations Economic an...2024 ECOSOC YOUTH FORUM -logistical information -  United Nations Economic an...
2024 ECOSOC YOUTH FORUM -logistical information - United Nations Economic an...Christina Parmionova
 
Professional Conduct and ethics lecture.pptx
Professional Conduct and ethics lecture.pptxProfessional Conduct and ethics lecture.pptx
Professional Conduct and ethics lecture.pptxjennysansano2
 
Canadian Immigration Tracker - Key Slides - February 2024.pdf
Canadian Immigration Tracker - Key Slides - February 2024.pdfCanadian Immigration Tracker - Key Slides - February 2024.pdf
Canadian Immigration Tracker - Key Slides - February 2024.pdfAndrew Griffith
 
ECOSOC YOUTH FORUM 2024 Side Events Schedule-18 April.
ECOSOC YOUTH FORUM 2024 Side Events Schedule-18 April.ECOSOC YOUTH FORUM 2024 Side Events Schedule-18 April.
ECOSOC YOUTH FORUM 2024 Side Events Schedule-18 April.Christina Parmionova
 
Uk-NO1 Black magic Specialist Expert in Uk Usa Uae London Canada England Amer...
Uk-NO1 Black magic Specialist Expert in Uk Usa Uae London Canada England Amer...Uk-NO1 Black magic Specialist Expert in Uk Usa Uae London Canada England Amer...
Uk-NO1 Black magic Specialist Expert in Uk Usa Uae London Canada England Amer...Amil baba
 
2024: The FAR, Federal Acquisition Regulations - Part 25
2024: The FAR, Federal Acquisition Regulations - Part 252024: The FAR, Federal Acquisition Regulations - Part 25
2024: The FAR, Federal Acquisition Regulations - Part 25JSchaus & Associates
 
澳洲UTS学位证,悉尼科技大学毕业证书1:1制作
澳洲UTS学位证,悉尼科技大学毕业证书1:1制作澳洲UTS学位证,悉尼科技大学毕业证书1:1制作
澳洲UTS学位证,悉尼科技大学毕业证书1:1制作aecnsnzk
 
2023 Ecological Profile of Ilocos Norte.pdf
2023 Ecological Profile of Ilocos Norte.pdf2023 Ecological Profile of Ilocos Norte.pdf
2023 Ecological Profile of Ilocos Norte.pdfilocosnortegovph
 
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdfIf there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdfKatrina Sriranpong
 
2024: The FAR, Federal Acquisition Regulations - Part 24
2024: The FAR, Federal Acquisition Regulations - Part 242024: The FAR, Federal Acquisition Regulations - Part 24
2024: The FAR, Federal Acquisition Regulations - Part 24JSchaus & Associates
 

Recently uploaded (20)

办理约克大学毕业证成绩单|购买加拿大文凭证书
办理约克大学毕业证成绩单|购买加拿大文凭证书办理约克大学毕业证成绩单|购买加拿大文凭证书
办理约克大学毕业证成绩单|购买加拿大文凭证书
 
NL-FR Partnership - Water management roundtable 20240403.pdf
NL-FR Partnership - Water management roundtable 20240403.pdfNL-FR Partnership - Water management roundtable 20240403.pdf
NL-FR Partnership - Water management roundtable 20240403.pdf
 
Build Tomorrow’s India Today By Making Charity For Poor Students
Build Tomorrow’s India Today By Making Charity For Poor StudentsBuild Tomorrow’s India Today By Making Charity For Poor Students
Build Tomorrow’s India Today By Making Charity For Poor Students
 
NO1 Certified Best vashikaran specialist in UK USA UAE London Dubai Canada Am...
NO1 Certified Best vashikaran specialist in UK USA UAE London Dubai Canada Am...NO1 Certified Best vashikaran specialist in UK USA UAE London Dubai Canada Am...
NO1 Certified Best vashikaran specialist in UK USA UAE London Dubai Canada Am...
 
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...
Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...
Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...
 
Digital Transformation of the Heritage Sector and its Practical Implications
Digital Transformation of the Heritage Sector and its Practical ImplicationsDigital Transformation of the Heritage Sector and its Practical Implications
Digital Transformation of the Heritage Sector and its Practical Implications
 
ECOSOC YOUTH FORUM 2024 - Side Events Schedule -16 April.
ECOSOC YOUTH FORUM 2024 - Side Events Schedule -16 April.ECOSOC YOUTH FORUM 2024 - Side Events Schedule -16 April.
ECOSOC YOUTH FORUM 2024 - Side Events Schedule -16 April.
 
call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Kirti Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
2024 ECOSOC YOUTH FORUM -logistical information - United Nations Economic an...
2024 ECOSOC YOUTH FORUM -logistical information -  United Nations Economic an...2024 ECOSOC YOUTH FORUM -logistical information -  United Nations Economic an...
2024 ECOSOC YOUTH FORUM -logistical information - United Nations Economic an...
 
Professional Conduct and ethics lecture.pptx
Professional Conduct and ethics lecture.pptxProfessional Conduct and ethics lecture.pptx
Professional Conduct and ethics lecture.pptx
 
Canadian Immigration Tracker - Key Slides - February 2024.pdf
Canadian Immigration Tracker - Key Slides - February 2024.pdfCanadian Immigration Tracker - Key Slides - February 2024.pdf
Canadian Immigration Tracker - Key Slides - February 2024.pdf
 
ECOSOC YOUTH FORUM 2024 Side Events Schedule-18 April.
ECOSOC YOUTH FORUM 2024 Side Events Schedule-18 April.ECOSOC YOUTH FORUM 2024 Side Events Schedule-18 April.
ECOSOC YOUTH FORUM 2024 Side Events Schedule-18 April.
 
Uk-NO1 Black magic Specialist Expert in Uk Usa Uae London Canada England Amer...
Uk-NO1 Black magic Specialist Expert in Uk Usa Uae London Canada England Amer...Uk-NO1 Black magic Specialist Expert in Uk Usa Uae London Canada England Amer...
Uk-NO1 Black magic Specialist Expert in Uk Usa Uae London Canada England Amer...
 
2024: The FAR, Federal Acquisition Regulations - Part 25
2024: The FAR, Federal Acquisition Regulations - Part 252024: The FAR, Federal Acquisition Regulations - Part 25
2024: The FAR, Federal Acquisition Regulations - Part 25
 
Housing For All - Fair Housing Choice Report
Housing For All - Fair Housing Choice ReportHousing For All - Fair Housing Choice Report
Housing For All - Fair Housing Choice Report
 
澳洲UTS学位证,悉尼科技大学毕业证书1:1制作
澳洲UTS学位证,悉尼科技大学毕业证书1:1制作澳洲UTS学位证,悉尼科技大学毕业证书1:1制作
澳洲UTS学位证,悉尼科技大学毕业证书1:1制作
 
2023 Ecological Profile of Ilocos Norte.pdf
2023 Ecological Profile of Ilocos Norte.pdf2023 Ecological Profile of Ilocos Norte.pdf
2023 Ecological Profile of Ilocos Norte.pdf
 
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdfIf there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
If there is a Hell on Earth, it is the Lives of Children in Gaza.pdf
 
2024: The FAR, Federal Acquisition Regulations - Part 24
2024: The FAR, Federal Acquisition Regulations - Part 242024: The FAR, Federal Acquisition Regulations - Part 24
2024: The FAR, Federal Acquisition Regulations - Part 24
 

Waterkeeper's PNGS hearing remarks - June 29, 2018

  • 1. 1 Good morning President Binder and Commission Members, Thank you for the opportunity to address you all today – especially at the end of this very intensive and demanding week. For the record my name is Pippa Feinstein and I am representing Swim Drink Fish Canada/Lake Ontario Waterkeeper which has been granted intervener status in this hearing concerning the Pickering Nuclear Generating Station’s (PNGS) licence renewal. Waterkeeper is a non-political registered charity that uses research, education, and legal tools to protect and restore the public’s right to swim, drink, and fish in the Lake Ontario watershed. It has been involved in decision-making processes for the PNGS and Pickering Waste Management Facility (PWMF) for many years, and has developed considerable expertise concerning the site’s adverse impacts on local lake water quality and aquatic ecosystems. Waterkeeper was provided with participant funding to examine three things: 1) the adequacy of public information disclosure by OPG; 2) the impacts of the PNGS on local aquatic species and habitat; and 3) the impacts of the PNGS effluent and other liquid releases to local groundwater and surface water. I will summarize some of our findings and recommendations for you in my presentation, but due to the limited time, hope to be able to discuss these things in more depth during the question period for this intervention. First and foremost, Waterkeeper opposes a 10-year licence renewal for the PNGS at this time. There is insufficient information on the public record in this matter to demonstrate that the Station could operate without significant impacts on the environment, and what little information our organization has found on the record seems to indicate that there may be significant impacts and a lack of regulatory oversight to ensure the facility’s compliance with relevant environmental law. As such, Waterkeeper recommends a temporary interim licence of no longer than two years over which time OPG, CNSC staff, and other regulators should collect and disseminate information that can demonstrate the facility’s ability to make adequate provision for the protection of the environment. Such a decision would be consistent with a precautionary approach which is affirmed and codified in Canadian law as well as international legal instruments to which Canada is a signatory. OPG and CNSC presented to the Commission on Monday, indicating that there were three robust avenues by which members of the public could obtain information concerning the PNGS: 1) questions and information requests during licence hearings; 2) formal Access to Information processes; and 3) OPG’s website. I would submit each of these avenues are currently insufficient, and I will explain why. In terms of information requests pursuant to the licence renewal hearing, our written submissions can attest to OPG’s obfuscation and CNSC’s staff refusal1 to assist with this process. We were 1 In our May 7th submissions, we requested CNSC staff assistance in providing the information we had requested, It is unclear whether staff assisted with this or to what extent they may have tried to help. CNSC staff has informed us that they require OPG’s consent to release information about the PNGS facility and that it is better to seek to obtain information directly from the company.
  • 2. 2 almost unable to fulfill our obligations under our funding agreement after being denied crucial information we required for our review, including groundwater monitoring reports, maps showing liquid discharge lines from the Station, Fish Diversion System (FDS) net failure events, and cooling water temperature spikes. None of this information was provided, nor were any reasons provided for these refusals, despite the fact that OPG is required to provide annual impingement and entrainment reports as well as groundwater monitoring reports to the CNSC, and the requested sampling data would have already been completed and stored at the facility, so I would have expected these things to be provided in a timely manner.2 This issue of insufficient disclosure at public hearings is not a new one: the Commissioners recommended that OPG disclose more monitoring data in your last PNGS relicensing decision in 2013, as well as your more recent PWMF relicensing decision last year. The Commission also directed staff to take on a more active role in assisting intervenors requesting information from regulated facilities in your PWMF decision. It is frustrating that your recommendations and directions have not been acted on. In response to OPG’s and CNSC staff’s instance on using formal Access to Information processes to obtain information on the PNGS, current timelines for public interventions in licence renewal proceedings preclude this. Information requests can take several months, if not longer. Further, as Shawn-Patrick Stensil noted to the Commission yesterday, sometimes ATIP processes can site these licence proceedings as grounds for denying information, insisting these proceedings are the proper avenues to obtain information about nuclear facilities. In response to OPG’s assertions that it proactively publishes comprehensive information on its website concerning the environmental performance of the PNGS, this is not the case. The Environmental Risk Assessments and annual and quarterly compliance reports from OPG contain repeated assertions that the PNGS is operating within its licence conditions and that any exceedances are not environmentally significant, however insufficient data is provided to demonstrate the veracity of these claims. These reports contain virtually no disaggregated data concerning any environmental monitoring within the PNGS site boundaries. What limited data is reported concerning off-site impacts of the PNGS is often provided in annual or quarterly averages and even then, it is inconsistently reported from year to year. Further, monitoring methodologies employed by OPG are not comprehensively explained, frustrating attempts to assess the significance or adequacy of sampling results that are provided. Even with the extremely limited information available on the public record, our two scientific experts were able to identify several areas of concern and make recommendations for their improvement. 2 Note: Greenpeace and Northwatch had also requested copies of OPG’s groundwater monitoring reports in February 2018, after an OPG stakeholder meeting and were only informed in May - the week our written interventions were due – that OPG would not provide this report. No reasons for this refusal were given.
  • 3. 3 With regard to the impacts of the PNGS cooling water system on aquatic species and habitat, Dr. Henderson found that there may be cause for concern. The PNGS cooling system extracts and discharges a massive amount of water: up to almost five and half Olympic-size swimming pools per minute, or what Dr. Henderson calls the flow of a small river. The plant, prior to the installation of a Fish Diversion System (FDS) in 2009, was responsible for killing millions of fish, larvae, and fish eggs each year due to impingement and entrainment. In 2008 the Commission directed OPG to reduce impingement by 80%, however upon reviewing impingement data since 2010, Dr. Henderson found this 80% reduction was only achieved in three out of the past seven years. Even the years in which OPG’s data indicates the 80% reduction was achieved, Waterkeeper urges caution as the 2003 baseline against which this reduction is measured excludes the round goby, a fish species that has become increasingly abundant in Lake Ontario over the last decade – Waterkeeper also cautions against the use of a single year as a baseline which is problematic given the significant variability of certain species of fish populations around the PNGS from year to year. Dr. Henderson’s review of impingement data also raises concerns with OPG’s ability to comply with its new DFO authorization. The authorization requires OPG to discuss additional follow-up requirements if the PNGS impinges more than 3619 kg of fish in two consecutive years. Given impingement values from 2010/11 and 2014/15 Dr. Henderson believes it’s highly likely that this 3619 kg limit will be exceeded for two consecutive years in the future. Further, despite high levels of entrainment, and past Commission directions to OPG to mitigate these losses, no mitigation has taken place nor is it planned – despite the availability of sonar diversion and the installation of full or partial closed-cycle cooling for the PNGS. OPG asserts entrainment impacts are offset elsewhere via habitat restoration for Northern pike and Salmon restocking initiatives. However, these offsetting measures cannot be considered appropriate as they do nothing to compensate for the loss of species actually entrained by the PNGS, including round goby, alewife, or Diporeia. Dr. Henderson found that elevated temperatures of discharged water at the PNGS can have adverse effects on phytoplankton productivity and macroinvertebrate growth, adversely impact fish migrations, and result in a loss of aquatic species diversity. He also found that spikes in thermal discharges at the PNGS are close to thermal death points for many larger fish species in Lake Ontario. With all this in mind, Waterkeeper is concerned that the PNGS will not be able to comply with the current authorization. Waterkeeper is also deeply concerned that facility was permitted to operate for decades without a permit until January 2018 – this seems like a clear violation of the Fisheries Act. Further, Waterkeeper is concerned about the exclusion of invasive species in the current DFO authorization seems inconsistent with the Fisheries Act protection of fish that support fisheries recognized by the Act (e.g. round
  • 4. 4 goby are a significant fish of prey in Lake Ontario, comprising 86% of the food by weight consumed by lake sturgeon). With regard to environmental impacts of effluent and other releases to groundwater and surface water, our other scientific expert Mr. Ruland found that there may be cause for concern. Despite the fact that his review was limited by OPG’s refusal to disclose groundwater and stormwater monitoring reports or data, Mr. Ruland found evidence of extremely contaminated groundwater blow the PNGS – at one point as high as 3.96 million Bq/L of tritium – over 565 times the Ontario Drinking Water Standard of 7000 Bq/L. This is down from the 30 million Bq/L measured underneath the PNGS between 2001 and 2005. These elevated levels of tritium are due to a series of historical leaks of the contaminant into groundwater: a product of a significant backlog of repairs and lack of proactive facility maintenance. While OPG claims most of this backlog has been cleared, Waterkeeper is concerned that CNSC staff may have failed to require full remediation of this contamination, instead approving a site-specific contamination limit of 3 million Bq/L for tritium non-potable groundwater. All of these concerns pertain to tritium, however Mr. Ruland cautions that elevated contamination levels may be present for other contaminants beneath the PNGS – due to OPG’s and CNSC staff’s refusal to provide groundwater monitoring information it is impossible for Waterkeeper to know more on this point. When examining stormwater discharges from the PNGS, Mr. Ruland found that monitoring was sporadic and that since 1990, there appear to have been regular monitoring gaps of between three and eight years. When monitoring was done, it did not appear to have been performed on all stormwater discharge lines, and when it was done it often failed to take into account seasonal variation and it failed to include follow-up monitoring in instances in which elevated contaminant levels were discovered. This last point is particularly important legally as repeated failures of toxicity testing at specific stormwater catchment locations may constitute another violation of the Fisheries Act. Failed toxicity tests at these locations prove that the water tested was lethal to aquatic life. For the limited tests Mr. Ruland was able to find sampling values for, measured zinc levels in these locations were up to 17 times higher than Provincial Water Quality Objectives (PWQOs), copper values were over eight times higher than PWQO limits and cadmium levels also surpassed PWQO limits. Significantly, certain stormwater catchments contained tritium levels as high as 39,000 Bq/L which Mr. Ruland identified as possible evidence that contaminated groundwater is leaking into stormwater infrastructure constituting an unintended pathway of contaminated groundwater into Lake Ontario via stormwater outfalls. If this is in fact occurring, such discharges could easily violate the Fisheries Act. Due to time constraints, I will end my presentation there, but look forward to answering any questions the Commission may have, and hope to be able to aske several questions of my own on the record. Thank you.
  • 5. 5 Closing statements: The Pickering site in located in an ecologically stressed, but resilient, part of the northern shoreline of Lake Ontario. Recently, this area has been the focus of increasing remediation and conservation efforts – especially concerning various ecological features in this area that are unique in North America. The Pickering site is surrounded by parks to the west and north, wetlands to the east, and the lake to the south. Conservation areas, beaches, fishing and paddling spots, and trails also surround the site. As well as Ajax’s drinking water intake which is located just west of the site. Of the 90 aquatic species present in Lake Ontario, 60 have been found in the vicinity of the PNGS, including species at risk and of concern such as sturgeon, American eel, and Atlantic Salmon. As urban populations around the PNGS continue to rise, members of the public will become increasingly dependent on the lake and the lake’s shoreline for sustenance and recreation. I should emphasize, again, there is a lot of uncertainty concerning the PNGS’ impact on the local environment – due to lack of information on the public record. The federal government’s open data initiative – which extends to the CNSC and explicitly seeks to promote greater transparency in the energy sector and scientific fields – requires proactive disclosure of data in accessible formats, recognizing this is in the public interest. Access to information, including environmental monitoring data, is also a crucial prerequisite to Ontarians’ rights to a healthful environment and Lake Ontario, as recognized in the province’s Environmental Bill of Rights and Great Lakes Protection Act. Further, as Commissioners, the dearth of available objective, evidence-based, and supportable information concerning PNGS’ environmental performance impacts your ability to meet your due diligence obligations. Waterkeeper implores the Commission to require (rather than simply recommend) more disclosure from OPG and CNSC staff in order to facilitate accountability, transparency, and the level of public scrutiny we all deserve. The Commission has the opportunity and the duty to protect this area. You have heard extensive testimony regarding the public concern for the environment in different kinds of hypothetical accident scenarios. These are important to keep in mind, but just as important are the real concerns over the environmental performance of the PNGS in the here and now. We request a licence period of no longer than two years, over which period OPG and CNSC staff and others should be ordered to collect and disseminate information, including raw sampling data, that can demonstrate the facility’s ability to make adequate provision for the protection of the environment. This additional material must be made publicly available and subject to a fulsome relicensing hearing that facilitates public comments on the merits of OPG’s application – something that has not been possible under the limitations of this current proceeding.
  • 6. 6 Summary of all Waterkeeper recommendations Recommendation 1: That OPG be granted a licence under the terms of its current licence, for no longer than two years, during which time OPG, CNSC staff, the DFO and ECCC can monitor and publicly report on the PNGS impacts to Lake Ontario’s water quality and local aquatic environments, and ensure a future hearing to consider a longer PNGS licence on a more comprehensive evidentiary record. Recommendation 2: When considering the current licence renewal application, the Commission Tribunal must do so while keeping in mind the growing importance of the lake for swimming, drinking, and fishing as well as cumulative adverse environmental impacts of lake water quality and the health of local aquatic ecosystems. Recommendation 3: that CNSC staff and the DFO review the use of 2003/4 data as the benchmark against which impingement mitigation is measured, instead selecting a broader period of time that also takes into account the current characteristics of Lake Ontario’s ecosystem. Recommendation 4: that OPG, CNSC staff, and the DFO examine the likelihood of the PNGS exceeding the 3,619 kg threshold for two consecutive years and publicly report their findings, including any proposed follow-up activities. Recommendation 5: that OPG make publicly available its monitoring reports concerning impingement rates and net performance, including net failure events. Recommendation 6: that entrainment monitoring commence immediately, rather than 2021. Recommendation 7: that OPG and CNSC staff immediately develop entrainment mitigation measures to decrease entrainment rates at the PNGS. Recommendation 8: that OPG, CNSC staff, and the DFO consider and implement measures to ensure that offsetting activities more effectively compensate for actual species impinged and entrained at the PNGS. Recommendation 9: that OPG, CNSC staff, and the DFO consider and implement measures to mitigate thermal pollution by the PNGS, taking into account the projected impacts of climate change on lake water temperature in Lake Ontario. Recommendation 10: that OPG makes its ECA compliance reports public, by posting them to the OPG webpage with other compliance reports. Recommendation 11: That OPG and CNSC staff make public their responses to the four ECCC areas in which more information was required concerning potential adverse impacts of the PNGS on local water quality and aquatic biota. Recommendation 12: that an explanation from the DFO concerning the PNGS’s historical compliance with the Fisheries Act be shared with Waterkeeper, and put on the record of the current proceedings, in advance of the public hearings from June 25 – 29 th , 2018, including references to any regulations or Ministerial Orders exempting the PNGS from the application of the Fisheries Act. Recommendation 13: that all species impinged and entrained by the PNGS be considered and added to the DFO s. 35 permit for the PNGS, including but not limited to alewife and round goby. This approach would be more consistent with the Fisheries Act. Recommendation 14: that the DFO s. 35 permit itself be amended to ensure that offsetting activities properly compensate for actual species killed by the PNGS. This approach would also be more consistent
  • 7. 7 with the Fisheries Act. Recommendation 15: that OPG be required to publicly disclose the annual compliance reports required by the DFO permit by posting them to the OPG webpage with all other PNGS compliance reports. Recommendation 16: That OPG and CNSC staff immediately release the following information on the public record in this hearing process: • a complete set of borehole logs and monitor installation details for OPG’s full network of groundwater monitoring wells and sampling points; 
 • up to date and useable groundwater level and groundwater quality monitoring data for the full network of groundwater wells and sampling points; 
 • recent annual groundwater monitoring reports for the PNGS; and 
 • a map and inventory of storm sewer lines for the site, including estimates of flows and a list of how many of these lines are being monitored on a regular basis and the 
monitoring results (for radiological and non-radiological contaminants). Recommendation 17: If not already included, Waterkeeper recommends that coper and zinc be included as COPCs for groundwater below the PNGS. 
 Recommendation 18: that OPG and CNSC staff publicly confirm whether a site-specific groundwater tritium limit of 3 million Bq/L is in effect for the PNGS. Recommendation 19: that if there is a site-specific groundwater tritium limit of 3 million Bq/L for the PNGS, OPG and CNSC staff must publicly report: 1) when and how it was developed; the scientific basis for its development; the extent to which it has been formally adopted by the CNSC and reasons for its exclusion from the current and proposed licence and Licence Conditions Handbook for the PNGS; and 4) whether any public consultation was conducted prior to establishing this elevated contamination limit. Recommendation 20: OPG must conduct quarterly monitoring of every stormwater collection line which is discharging to the forebay, the outfalls, or directly into Lake Ontario, 
 . h) As a first step, an inventory of stormwater collection lines needs to be developed and flows of water in those lines need to be metered. Particular attention needs to be paid to any lines which are always flowing, as this should not be occurring in a system which is collecting only stormwater. 
 . i) Toxicity testing should be done on every line for every sampling event. For lines which are consistently showing zero mortality, the frequency of toxicity testing can be stepped down to annually after 3 years of passing test results. 
 . j) The parameter lists being used for stormwater monitoring are reasonable, however in the event of failed toxicity testing results the scope of the testing should be increased to include:
- volatile organic chemicals(VOCs); 
 - polynuclear aromatic hydrocarbons (PAHs); - hydrazine and morpholine; 
 - additional radionuclides. 
 . k) Adverse test results and in particular failed toxicity tests should prompt immediate further investigation, with the goal of remediation of the issue(s) which are allowing contaminated and/or toxic stormwater to be discharged to Lake Ontario via the stormwater collection system. 
 . l) This information (including disaggregated data showing the results of this testing) should be made publicly available in OPG’s quarterly or annual compliance reports. 

  • 8. 8 Recommendation 21: Additional water quality sampling of Lake Ontario is recommended, with samples to be taken at Beachfront Park, Frenchman’s Bay West Park, and Squires Beach and tested as follows: -quarterly testing for copper, zinc, morpholine, and hydrazine; 
 - annual testing for the full list of parameters presented on Table F.1 of the 2017 ERA Report. . h) If not being done, then it is recommended that tritium and gross beta/ gamma be added as parameters in the weekly testing of the PNGS outfall water quality. It is also recommended that the outfall water quality testing should be done at a point downstream of all inputs from the PNGS. 
 . i) Table A.3 of the Quarterly Environmental Emissions Data reports indicates that waterborne radionuclide releases from the PNGS are analyzed monthly for Tritium, Gross Beta/Gamma, Carbon-14, and Gross Alpha. It is recommended that the quarterly reports should provide a transparent explanation for how the data being presented in Table A.3 are obtained. 
 . j) It is recommended that the CNSC order OPG to provide full public disclosure of historic and current PNGS groundwater monitoring data (including provision of full copies of Annual Monitoring Reports if requested), commencing immediately. 
 . k) It is recommended that OPG be required to fund a full, independent Peer Review of the historic and current results of its PNGS groundwater monitoring program. The Peer Reviewer should report to the CNSC, and their report should provide: - an overview of historic groundwater quality monitoring results and their implications; - recommendations on how to improve the groundwater monitoring program on 
a go- forward basis; 
 - recommendations on how to optimize the provision of transparent and 
publicly accessible reporting of the results of the groundwater monitoring 
program. 
 . l) This information (including disaggregated data showing the results of this testing, and 
additional explanations of how this data was obtained) should be made publicly available in OPG’s quarterly or annual compliance reports. 
 Recommendation 22: The DFO and ECCC should immediately investigate the potential for stormwater outfalls at the PNGS to be releasing deleterious substances into waters frequented by fish in contravention of the Fisheries Act. The results of this investigation must be publicly disclosed. Recommendation 23: OPG should better distinguish between mandatory and discretionary reporting in its PIP and PDP and disclose the types of events that are reported in practice. Recommendation 24: OPG should undertake to make all environmental reporting mentioned in the PIP and PDP mandatory for the PNGS. Recommendation 25: CNSC staff should work with OPG to create a timeline for OPG ultimately posting comprehensive data in machine-readable formats in real time. Recommendation 26: The webpage for reporting incidents at the PNGS should be included as a shortcut tab on the PNGS’s homepage on opg.com. Recommendation 27: Each incident report must include the incident date, reporting date, an exact description of the event including actual data of any measured releases, and any applicable DRLs or ALs so that members of the public can understand the severity of the reported incidents.