SlideShare a Scribd company logo
1 of 94
The Convention Centre Dublin



   Tuesday, 7th February 2012

   Presentation to

   The Institution of Structural
   Engineers / Engineers Ireland

   Cork Region


   Presented by:

   Ken Moriarty
   Director
   O’Connor Sutton Cronin

O’Connor Sutton Cronin & Associates Multidiscipline Consulting Engineers
Key Milestone Dates



Architect first appointed        1997
OPW (second) Tender issued       Late December 2004
PPP Co. Tender submission        May 2005
Preferred bidder appointment     December 2005
Design Team Tender Documents     December 2006
Formal Contract signing          April 2007
Start on site (Enabling works)   Late 2006
Programme duration               37 months (from Apr. 07 )
The Team


Client                    The Office of Public Works (OPW)
PPP Co.                   Spencer Dock International
                          Conference Centre Limited
Operator                  ‘The CCD’
D&C Co.                   CMPL (Sisk /Treasury JV)
Stakeholder Management    Bruce Shaw Project Management
Architect                 Kevin Roche John Dinkeloo Assoc.
Structural Engineer       O’Connor Sutton Cronin
Services Engineer         MacArdle McSweeney Assoc
Theatre Consultant        Theatre Projects
Geotechnical Consultant   Byrne Looby Partners
Steel Fabricators         Fisher Engineering
OCSC Team




            11 fulltime Staff, 3 Part-time. Total 14
Client (OPW) Brief



Table 4-3                                 Schedule of Spaces

Functional Area                                              Number or     Indicative Space          Proposed Minimum
                                                         No. of Persons    Requirement m²     Performance Standards per
                                                      (Min. anticipated)                                        Person

Main Auditorium                                                   2,000              4,400                       1.      m²
including stage area (flexible seating)

Multi-Purpose Meeting
Spaces (Boardroom Classroom layout)                              16 No.                660                      2.0-2.4 m²

Exhibition Space                                                  2,000              2,000                            1.0 m²

Banqueting Space and Kitchens                                     2,000              4,000         Kitchen: 0.2 m² per seat

Dedicated Conference Spaces                                       7 No.                                 Class room layout
                                                           ranging from              1,000                      1.8-2.4 m²
                                                         50-200 persons
Client (OPW) Brief



Specific Structural requirements:
100 Year design life for all structural elements
40 Year design life for all major replaceable components


Design Floor Loadings:

    Table 6-4     Minimum Design Floor Loadings

    Floor                             6.0 kN/m² (including 1.0 kN/m² for light weight partitions).


    Ceiling                           2.0 kN/m² for temporary exhibitors’ suspended rigging.


    Exhibition Hall Floor             12.5 kN/m² (this includes 1.0 kN/m² for light weight partitions).


    Exhibition Hall Ceiling           2.0 kN/m² for temporary exhibitors’ suspended rigging.
Floor Loading Drawings
100 Year Design Life
The Site




SPENCER
DOCK SITE




THE CCD
SITE
Architects Response to The Brief




 3-D VIEW
Architects Response to The Brief




                                   L8 ROOF
                                   L7 ROOF
                                   LEVEL 5

                                   LEVEL 4

                                   LEVEL 3


                                   LEVEL 2


                                   LEVEL 1

                                   LEVEL B1




  CROSS SECTION
Architects Response to The Brief




  ELEVATIONS
Architects Response to The Brief




  BASEMENT B1
Architects Response to The Brief




  LEVEL 1 (GROUND FLOOR)
Architects Response to The Brief




  LEVEL 2 (FIRST FLOOR)
Architects Response to The Brief




  LEVEL 3 (SECOND FLOOR, AUDITORIUM)
SITE CONSTRAINTS

GROUND CONDITIONS

TEMPORARY WORKS

FOUNDATION SYSTEM
Site Constraints




                   JANUARY 2007
Ground Conditions


The ground conditions to the south of the site are summarized as follows:

Fill                                                 0-4.0 m (metres below ground)
Soft black silt                                      4.0-5.5 m
Fine sandy gravel                                    5.5-7.0 m
Soft clayey peaty silt                               7.0-13.0 m
Medium dense coarse gravel                           13.0-15.5 m
Very stiff boulder clay                              15.5-21.6 m
Strong limestone rock                                21.6 m

The ground conditions to the north of the site are summarized as follows:

Fill                                                 0-4.2 m (metres below ground)
Soft grey silt                                       4.2-4.7 m
Medium dense coarse gravel                           4.7-7.1 m
Hard boulder clay                                    7.1-8.2 m
Medium dense coarse gravel                           8.2-8.5 m
Very hard boulder clay                               8.5-20.8 m
Strong limestone rock                                20.8 m
Ground Conditions
Temporary Works



Contractor requirements for temporary works:
1.0   Limit water ingress to site
2.0   Ground retention with minimal deflection
3.0   No obstruction to site operation


Chosen Solution:- 900 dia Secant Wall with RC
capping beam and lateral restraint anchors where
required
Foundation System


The foundation solution for The CCD is achieved using 600mm, 900mm and 1050mm
diameter Continuous Flight Auger (CFA) piles.

   The safe working load capacity of the individual piles is as follows.

   600mm diameter pile:

          Compression capacity              1800kN
          Tension capacity                  650kN

   900mm diameter pile:

          Compression capacity              3500kN
          Tension capacity                  650kN (900 kN under crane bases)

   1050mm diameter pile:

          Compression capacity              6000kN
          Tension capacity                  650kN
Foundation System




                    JULY 2007
Foundation System




                    JULY 2007
Foundation System
Material Data / Specifications


Steelwork

All structural steelwork is to be grade S275 or S355 to BS EN 10025 as noted
on the drawings.

Concrete

Concrete below (and in contact with) ground:

The grade of concrete is 35N/Sq mm (at 28 days), class DC-4 concrete in
accordance with table D1 of BRE SD 1 2005.

Concrete generally

The grade of concrete is to be 35N/Sq mm (at 28 days), in accordance with
IS EN 206-1 2002.
Steelwork: Key Facts


Approximately 7500 Tonnes of primary steel

Typical truss span at level 2 & 3 = 20m, with a structural
depth of 2.3m overall

Eight primary columns in the main exhibition spaces,
with a maximum column load of 40,000 Kn.

Roof truss over the auditorium spans 47m

Werner truss to glass drum spans 37m horizontally

Design of floor plates is governed by dynamics (natural
frequency)

Stability achieved through combined action of sway
frames and southern concrete cores.

Fire protection 90/60 minutes achieved primarily
through shop applied intumescent paint.
Steelwork Challenges



Long spans with limited depth

Indirect load path, i.e. Transfer trusses supported by
transfer trusses

Limited number of columns allowed

Significant M&E ventilation duct distribution, with M&E
design behind OCSC design

Design of floor plates governed by natural frequency +
floor response factors
Steelwork Model
Part-Basement Floor Plan
Part-Ground Floor Plan
3-D Rendered Model: Entrance Slab
Level 1M showing Level 1 below
Typical Truss Sections at Level 2
Level 2M showing Level 2 below
Level 3 Floor Plate (Auditorium)
Level 4 Floor Plate (Auditorium)
Auditorium Seating Frames
Level 5 Floor Plate (Auditorium)
Roof Plan (over Auditorium)
Section Through South Stair Core
Frame Sections: Frame at Grid L.2
Frame Sections: Frame at Grid J.4
Frame Sections: Frame at Grid G.3
Frame Sections: Frame at Grid E.2
Fire resistance drawing: Level 3
IMAGES FROM
STRAP/ROBOT/X-STEEL
Images from Strap/Robot/X-Steel
Images from Strap/Robot/X-Steel
Images from Strap/Robot/X-Steel
Images from Strap/Robot/X-Steel
Images from Strap/Robot/X-Steel




                                   UPPER AUDITORIUM FRAME MODEL




  UPPER AUDITORIUM SEATING FRAME      TRUSS 7.1 GRIDLINE G.3 (ROOF)
TEMPORARY WORKS
Temporary Works




                  MAY 2008
Temporary Works




                  MAY 2008
GLASS DRUM
Glass Drum
Glass Drum
Glass Drum
Glass Drum
Glass Drum
Glass Drum
Glass Drum
Glass Drum
Wind Tunnel Test Images
SELECTION OF
SITE PHOTOGRAPHS
Selection of Site Photographs




                                NOVEMBER 2006
Selection of Site Photographs




                                JANUARY 2007
Selection of Site Photographs




                                JULY 2007
Selection of Site Photographs




                                JULY 2007
Selection of Site Photographs




                                SEPTEMBER 2007
Selection of Site Photographs




                                DECEMBER 2007
Selection of Site Photographs




                                DECEMBER 2007
Selection of Site Photographs




                                JANUARY 2008
Selection of Site Photographs




              JUNE 2008         JUNE 2008
Selection of Site Photographs




                                JUNE 2008
Selection of Site Photographs




                                JULY 2008
Selection of Site Photographs




                                AUGUST 2008
Selection of Site Photographs




                                AUGUST 2008
Selection of Site Photographs




                                DECEMBER 2008
Selection of Site Photographs




                                MAY 2009
Selection of Site Photographs




                                NOVEMBER 2009
Selection of Site Photographs




            NOVEMBER 2009       NOVEMBER 2009
Selection of Site Photographs




                                NOVEMBER 2009
Selection of Site Photographs




                                NOVEMBER 2009
Selection of Site Photographs




                                MARCH 2010
Selection of Site Photographs




                                MAY 2010
Selection of Site Photographs




                                MAY 2010
Selection of Site Photographs




                                MAY 2010
Selection of Site Photographs




                                MAY 2010
Selection of Site Photographs




                                MAY 2010
Key Facts



Approximately 1000 piles

Total Steel (Incl. secondary steel) 9500 Tonnes

Heaviest Steel Truss 160 Tonnes, at roof level over the
auditorium

Total volume of concrete 40,000 cubic metres

Number of glass panes in the Drum: 475

Largest single concrete pour in Ireland 2375 cubic
metres in 17 hours

700 people employed on site at the peak

The CCD currently has over 200,000 delegate days
confirmed
Artists impression




                     ARTISTS IMPRESSION 2005
The finished product……




                         PHOTOGRAPHS COURTESY OF PETER
                         BARROW PHOTOGRAPHY

More Related Content

Viewers also liked

Social Portfolio_Vinfotech .pptx
Social Portfolio_Vinfotech .pptxSocial Portfolio_Vinfotech .pptx
Social Portfolio_Vinfotech .pptxRanuJain
 
Mattra Company Profile
Mattra Company ProfileMattra Company Profile
Mattra Company ProfileAizley Shahar
 
VMobileME Genealogy Form Analysis
VMobileME Genealogy Form AnalysisVMobileME Genealogy Form Analysis
VMobileME Genealogy Form AnalysisVMobile ME
 
Bon jovi power point
Bon jovi power pointBon jovi power point
Bon jovi power pointGriffingeo
 

Viewers also liked (6)

Social Portfolio_Vinfotech .pptx
Social Portfolio_Vinfotech .pptxSocial Portfolio_Vinfotech .pptx
Social Portfolio_Vinfotech .pptx
 
New grad groups 2011 112
New grad groups 2011 112New grad groups 2011 112
New grad groups 2011 112
 
Mattra Company Profile
Mattra Company ProfileMattra Company Profile
Mattra Company Profile
 
VMobileME Genealogy Form Analysis
VMobileME Genealogy Form AnalysisVMobileME Genealogy Form Analysis
VMobileME Genealogy Form Analysis
 
Bon jovi power point
Bon jovi power pointBon jovi power point
Bon jovi power point
 
Starter kit students
Starter kit studentsStarter kit students
Starter kit students
 

Similar to Ccd Talk To I Struct E 07 02 12

Design and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slabDesign and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slabDeepak Patil
 
Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Soh Shing
 
design requirement of cocrete slab
design requirement of cocrete slabdesign requirement of cocrete slab
design requirement of cocrete slabKhaliqur Rahman
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of buildingKrishnagnr
 
Design of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel BlockDesign of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel Blockjeyanthi4
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcostingimaduddin91
 
Soil nailing ppt by ankush choudhury
Soil nailing ppt by ankush choudhurySoil nailing ppt by ankush choudhury
Soil nailing ppt by ankush choudhuryAnkush Choudhury
 
IRJET- A Study on Seismic Analysis of RC Framed Structures on Varying Slo...
IRJET-  	  A Study on Seismic Analysis of RC Framed Structures on Varying Slo...IRJET-  	  A Study on Seismic Analysis of RC Framed Structures on Varying Slo...
IRJET- A Study on Seismic Analysis of RC Framed Structures on Varying Slo...IRJET Journal
 
Bstruc final report
Bstruc final reportBstruc final report
Bstruc final reportLee Yih
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAman Jain
 
Project 3 - Costing
Project 3 - CostingProject 3 - Costing
Project 3 - CostingKai Yun Pang
 
Design of multistorey building
Design of multistorey buildingDesign of multistorey building
Design of multistorey buildingSivaji Djpk
 
GCC33_Presentation_07
GCC33_Presentation_07GCC33_Presentation_07
GCC33_Presentation_07Luke Stull
 

Similar to Ccd Talk To I Struct E 07 02 12 (20)

Design and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slabDesign and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slab
 
Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Building Technology 1 (Project 1)
Building Technology 1 (Project 1)
 
design requirement of cocrete slab
design requirement of cocrete slabdesign requirement of cocrete slab
design requirement of cocrete slab
 
Alamoudi 1413034 final
Alamoudi 1413034 finalAlamoudi 1413034 final
Alamoudi 1413034 final
 
Audiotorium Calcs.pdf
Audiotorium Calcs.pdfAudiotorium Calcs.pdf
Audiotorium Calcs.pdf
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Geotechnical Investigation
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of building
 
A PPT.pptx
A PPT.pptxA PPT.pptx
A PPT.pptx
 
Design of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel BlockDesign of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel Block
 
Project
ProjectProject
Project
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcosting
 
Soil nailing ppt by ankush choudhury
Soil nailing ppt by ankush choudhurySoil nailing ppt by ankush choudhury
Soil nailing ppt by ankush choudhury
 
BIM Algorithmic Workflow Case Study - Mr. Eugenio FONTAN BIM Director and Co...
BIM Algorithmic Workflow Case  Study - Mr. Eugenio FONTAN BIM Director and Co...BIM Algorithmic Workflow Case  Study - Mr. Eugenio FONTAN BIM Director and Co...
BIM Algorithmic Workflow Case Study - Mr. Eugenio FONTAN BIM Director and Co...
 
IRJET- A Study on Seismic Analysis of RC Framed Structures on Varying Slo...
IRJET-  	  A Study on Seismic Analysis of RC Framed Structures on Varying Slo...IRJET-  	  A Study on Seismic Analysis of RC Framed Structures on Varying Slo...
IRJET- A Study on Seismic Analysis of RC Framed Structures on Varying Slo...
 
Bstruc final report
Bstruc final reportBstruc final report
Bstruc final report
 
final praveen.pptx
final praveen.pptxfinal praveen.pptx
final praveen.pptx
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha university
 
Project 3 - Costing
Project 3 - CostingProject 3 - Costing
Project 3 - Costing
 
Design of multistorey building
Design of multistorey buildingDesign of multistorey building
Design of multistorey building
 
GCC33_Presentation_07
GCC33_Presentation_07GCC33_Presentation_07
GCC33_Presentation_07
 

Ccd Talk To I Struct E 07 02 12