SlideShare a Scribd company logo
1 of 3
Download to read offline
From:    Brandon Valdez                To: David Ficklin - OnGoal
                                                                         Rory O’Connor – OnGoal
                              Office: Kansas City                        Lee Turner – OnGoal
                              Date:    5.26.2010                         Andy Heitmann – Turner
                                                                         Dave Dudzik - Turner
                              Re:      Wizards Stadium Project
                                       Update – Week of
                                       5.24.2010



 Current Activities this Week:

 Mass Excavation:
 Grading is ongoing in Area 3. Backfilling of on-grade
 is ongoing in Area 1 and Area 2.

 Site Utilities:
 Storm Sewer installation (Line 6000) is ongoing on         France Family Drive – Storm Line 6000
 east side of France Family Drive.                          installation is ongoing. Currently at station
                                                            4+00.
 Foundations:
 Area 2 Concourse Level – E-Line footing excavation has
 started and is currently to Column Line 18.

 Area 3 Field Level – Wall Form installation is ongoing
 on A-Line and is currently to Column Line 9.

 Area 3 Field Level – Installation of Drilled Piers
 are ongoing.
                                                            Field Level Area 2 – South East Vomitory
 Area 4 Mezzanine Level – D-Line grade beam excavation      Wall installation is ongoing (Column Lines
 has begun.                                                 11-12).

 Structural Steel Erection:
 Area 1 – Steel Erection in sequence 1-4 is ongoing and
 Is currently to Column Line 31.

 Decking/Detailing/Studs/Edge Angle is ongoing in
 sequence 1-2 on Mezzanine, Concourse and Suite Levels.



                                                            Area 4 – Drilled Pier installation is ongoing
                                                            near Column Line 1.
Building the Future
Underground MEP:
 Deep Sanitary installation has started in Area 2.

 MEP Rough-in:
 Plumbing and Electrical rough-in on Concourse Level has
 started.

 Projected Activities occurring next Week:
                                                                Field Level Area 2 – Deep Sanitary Line
 Mass Excavation:                                               installation has started near Column Line 15.
 Grading at Area 3 will continue.

 Site Utilities:
 Installation of the Storm Line 6000 on the East Side (France
 Family Drive) of the site will continue. Storm Line 5000 and
 4000 will begin.

 Deep Underground Plumbing:
 Deep Sanitary installation in Area 2 will continue.

 Foundations:                                                   Area 1 – Structural Steel Erection at West
 Area 2 Concourse Level – Footing/Grade Beam installation       Building is ongoing in Sequence 1-4 (bays
 will begin.                                                    28-31 shown).

 Area 3 Field Level – A-Line wall placement will begin

 Area 3 Mezzanine Level – Grade beam installation will
 begin.

 Structural Steel Erection:
 Erection of Structural Steel in Sequence 1-4 will continue.
 Decking/Detailing/Studs/Edge Plates will continue in
 Sequence 1-2.
                                                                Field Level Area 1 – Shot looking north from
                                                                Concourse Level.




Building the Future
Additional Photos:




                                               Suite Level Area 1 – Edge plate being
Concourse Level Area 1 – Plumbing rough-in
                                               installed between Column Lines 26 - 27.
has started at north end.




Mezzanine Level Area 4 – Grade Beam
installation has started at Column Line 33     Press Level Area 1 – Steel being set in place
(North Supporter’s Seating Area).              that holds the precast seating tubs.




Field Level Area 1 – Hydrotherapy Pit poured   Field Level Area 1 – Column encasement and
and backfilled.                                backfilling ongoing.




Building the Future

More Related Content

More from Kansas City Wizards

More from Kansas City Wizards (6)

Memo wizards 08-25-2010
Memo wizards 08-25-2010Memo wizards 08-25-2010
Memo wizards 08-25-2010
 
Construction Update 07-28-2010
Construction Update 07-28-2010Construction Update 07-28-2010
Construction Update 07-28-2010
 
Unicorn Wizards Scouting
Unicorn Wizards ScoutingUnicorn Wizards Scouting
Unicorn Wizards Scouting
 
Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010
 
Construction Update 5-5-2010
Construction Update 5-5-2010Construction Update 5-5-2010
Construction Update 5-5-2010
 
Construction Update 4-7-2010
Construction Update 4-7-2010Construction Update 4-7-2010
Construction Update 4-7-2010
 

Recently uploaded

Project & Portfolio, Market Analysis: WWE
Project & Portfolio, Market Analysis: WWEProject & Portfolio, Market Analysis: WWE
Project & Portfolio, Market Analysis: WWEDeShawn Ellis
 
JORNADA 2 LIGA MUROBASQUETBOL1 2024.docx
JORNADA 2 LIGA MUROBASQUETBOL1 2024.docxJORNADA 2 LIGA MUROBASQUETBOL1 2024.docx
JORNADA 2 LIGA MUROBASQUETBOL1 2024.docxArturo Pacheco Alvarez
 
20240408 Bending Backwards to the Second Step Up.docx
20240408 Bending Backwards to the Second Step Up.docx20240408 Bending Backwards to the Second Step Up.docx
20240408 Bending Backwards to the Second Step Up.docxSharon Liu
 
Resultados 20 KMS "Podebrady" Walking 2024
Resultados 20 KMS "Podebrady" Walking 2024Resultados 20 KMS "Podebrady" Walking 2024
Resultados 20 KMS "Podebrady" Walking 2024Judith Chuquipul
 
Turkey Vs Georgia Vincenzo Montella's Squad Selection for Turkey's Euro 2024 ...
Turkey Vs Georgia Vincenzo Montella's Squad Selection for Turkey's Euro 2024 ...Turkey Vs Georgia Vincenzo Montella's Squad Selection for Turkey's Euro 2024 ...
Turkey Vs Georgia Vincenzo Montella's Squad Selection for Turkey's Euro 2024 ...Eticketing.co
 
DONAL88 >LINK SLOT PG SOFT TERGACOR 2024
DONAL88 >LINK SLOT PG SOFT TERGACOR 2024DONAL88 >LINK SLOT PG SOFT TERGACOR 2024
DONAL88 >LINK SLOT PG SOFT TERGACOR 2024DONAL88 GACOR
 
PPT on INDIA VS PAKISTAN - A Sports Rivalry
PPT on INDIA VS PAKISTAN - A Sports RivalryPPT on INDIA VS PAKISTAN - A Sports Rivalry
PPT on INDIA VS PAKISTAN - A Sports Rivalryanirbannath184
 
Clash of Titans_ PSG vs Barcelona (1).pdf
Clash of Titans_ PSG vs Barcelona (1).pdfClash of Titans_ PSG vs Barcelona (1).pdf
Clash of Titans_ PSG vs Barcelona (1).pdfMuhammad Hashim
 
Benifits of Individual And Team Sports-Group 7.pptx
Benifits of Individual And Team Sports-Group 7.pptxBenifits of Individual And Team Sports-Group 7.pptx
Benifits of Individual And Team Sports-Group 7.pptxsherrymieg19
 
PGC _ 3.1 _ Powerpoint (2024) scorm ready.pptx
PGC _ 3.1 _ Powerpoint (2024) scorm ready.pptxPGC _ 3.1 _ Powerpoint (2024) scorm ready.pptx
PGC _ 3.1 _ Powerpoint (2024) scorm ready.pptxaleonardes
 
BADMINTON EQUIPMENTS / EQUIPMENTS GROUP9.pptx
BADMINTON EQUIPMENTS / EQUIPMENTS GROUP9.pptxBADMINTON EQUIPMENTS / EQUIPMENTS GROUP9.pptx
BADMINTON EQUIPMENTS / EQUIPMENTS GROUP9.pptxvillenoc6
 

Recently uploaded (12)

Project & Portfolio, Market Analysis: WWE
Project & Portfolio, Market Analysis: WWEProject & Portfolio, Market Analysis: WWE
Project & Portfolio, Market Analysis: WWE
 
JORNADA 2 LIGA MUROBASQUETBOL1 2024.docx
JORNADA 2 LIGA MUROBASQUETBOL1 2024.docxJORNADA 2 LIGA MUROBASQUETBOL1 2024.docx
JORNADA 2 LIGA MUROBASQUETBOL1 2024.docx
 
20240408 Bending Backwards to the Second Step Up.docx
20240408 Bending Backwards to the Second Step Up.docx20240408 Bending Backwards to the Second Step Up.docx
20240408 Bending Backwards to the Second Step Up.docx
 
Resultados 20 KMS "Podebrady" Walking 2024
Resultados 20 KMS "Podebrady" Walking 2024Resultados 20 KMS "Podebrady" Walking 2024
Resultados 20 KMS "Podebrady" Walking 2024
 
Turkey Vs Georgia Vincenzo Montella's Squad Selection for Turkey's Euro 2024 ...
Turkey Vs Georgia Vincenzo Montella's Squad Selection for Turkey's Euro 2024 ...Turkey Vs Georgia Vincenzo Montella's Squad Selection for Turkey's Euro 2024 ...
Turkey Vs Georgia Vincenzo Montella's Squad Selection for Turkey's Euro 2024 ...
 
NATIONAL SPORTS DAY WRITTEN QUIZ by QUI9
NATIONAL SPORTS DAY WRITTEN QUIZ by QUI9NATIONAL SPORTS DAY WRITTEN QUIZ by QUI9
NATIONAL SPORTS DAY WRITTEN QUIZ by QUI9
 
DONAL88 >LINK SLOT PG SOFT TERGACOR 2024
DONAL88 >LINK SLOT PG SOFT TERGACOR 2024DONAL88 >LINK SLOT PG SOFT TERGACOR 2024
DONAL88 >LINK SLOT PG SOFT TERGACOR 2024
 
PPT on INDIA VS PAKISTAN - A Sports Rivalry
PPT on INDIA VS PAKISTAN - A Sports RivalryPPT on INDIA VS PAKISTAN - A Sports Rivalry
PPT on INDIA VS PAKISTAN - A Sports Rivalry
 
Clash of Titans_ PSG vs Barcelona (1).pdf
Clash of Titans_ PSG vs Barcelona (1).pdfClash of Titans_ PSG vs Barcelona (1).pdf
Clash of Titans_ PSG vs Barcelona (1).pdf
 
Benifits of Individual And Team Sports-Group 7.pptx
Benifits of Individual And Team Sports-Group 7.pptxBenifits of Individual And Team Sports-Group 7.pptx
Benifits of Individual And Team Sports-Group 7.pptx
 
PGC _ 3.1 _ Powerpoint (2024) scorm ready.pptx
PGC _ 3.1 _ Powerpoint (2024) scorm ready.pptxPGC _ 3.1 _ Powerpoint (2024) scorm ready.pptx
PGC _ 3.1 _ Powerpoint (2024) scorm ready.pptx
 
BADMINTON EQUIPMENTS / EQUIPMENTS GROUP9.pptx
BADMINTON EQUIPMENTS / EQUIPMENTS GROUP9.pptxBADMINTON EQUIPMENTS / EQUIPMENTS GROUP9.pptx
BADMINTON EQUIPMENTS / EQUIPMENTS GROUP9.pptx
 

Weekly Construction Update 06-06-2010

  • 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 5.26.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 5.24.2010 Current Activities this Week: Mass Excavation: Grading is ongoing in Area 3. Backfilling of on-grade is ongoing in Area 1 and Area 2. Site Utilities: Storm Sewer installation (Line 6000) is ongoing on France Family Drive – Storm Line 6000 east side of France Family Drive. installation is ongoing. Currently at station 4+00. Foundations: Area 2 Concourse Level – E-Line footing excavation has started and is currently to Column Line 18. Area 3 Field Level – Wall Form installation is ongoing on A-Line and is currently to Column Line 9. Area 3 Field Level – Installation of Drilled Piers are ongoing. Field Level Area 2 – South East Vomitory Area 4 Mezzanine Level – D-Line grade beam excavation Wall installation is ongoing (Column Lines has begun. 11-12). Structural Steel Erection: Area 1 – Steel Erection in sequence 1-4 is ongoing and Is currently to Column Line 31. Decking/Detailing/Studs/Edge Angle is ongoing in sequence 1-2 on Mezzanine, Concourse and Suite Levels. Area 4 – Drilled Pier installation is ongoing near Column Line 1. Building the Future
  • 2. Underground MEP: Deep Sanitary installation has started in Area 2. MEP Rough-in: Plumbing and Electrical rough-in on Concourse Level has started. Projected Activities occurring next Week: Field Level Area 2 – Deep Sanitary Line Mass Excavation: installation has started near Column Line 15. Grading at Area 3 will continue. Site Utilities: Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will continue. Storm Line 5000 and 4000 will begin. Deep Underground Plumbing: Deep Sanitary installation in Area 2 will continue. Foundations: Area 1 – Structural Steel Erection at West Area 2 Concourse Level – Footing/Grade Beam installation Building is ongoing in Sequence 1-4 (bays will begin. 28-31 shown). Area 3 Field Level – A-Line wall placement will begin Area 3 Mezzanine Level – Grade beam installation will begin. Structural Steel Erection: Erection of Structural Steel in Sequence 1-4 will continue. Decking/Detailing/Studs/Edge Plates will continue in Sequence 1-2. Field Level Area 1 – Shot looking north from Concourse Level. Building the Future
  • 3. Additional Photos: Suite Level Area 1 – Edge plate being Concourse Level Area 1 – Plumbing rough-in installed between Column Lines 26 - 27. has started at north end. Mezzanine Level Area 4 – Grade Beam installation has started at Column Line 33 Press Level Area 1 – Steel being set in place (North Supporter’s Seating Area). that holds the precast seating tubs. Field Level Area 1 – Hydrotherapy Pit poured Field Level Area 1 – Column encasement and and backfilled. backfilling ongoing. Building the Future