Weekly Construction Update 06-06-2010

621 views
594 views

Published on

KC Soccer Stadium construction update from Turner Construction.

Published in: Sports, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
621
On SlideShare
0
From Embeds
0
Number of Embeds
83
Actions
Shares
0
Downloads
6
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Weekly Construction Update 06-06-2010

  1. 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 5.26.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 5.24.2010 Current Activities this Week: Mass Excavation: Grading is ongoing in Area 3. Backfilling of on-grade is ongoing in Area 1 and Area 2. Site Utilities: Storm Sewer installation (Line 6000) is ongoing on France Family Drive – Storm Line 6000 east side of France Family Drive. installation is ongoing. Currently at station 4+00. Foundations: Area 2 Concourse Level – E-Line footing excavation has started and is currently to Column Line 18. Area 3 Field Level – Wall Form installation is ongoing on A-Line and is currently to Column Line 9. Area 3 Field Level – Installation of Drilled Piers are ongoing. Field Level Area 2 – South East Vomitory Area 4 Mezzanine Level – D-Line grade beam excavation Wall installation is ongoing (Column Lines has begun. 11-12). Structural Steel Erection: Area 1 – Steel Erection in sequence 1-4 is ongoing and Is currently to Column Line 31. Decking/Detailing/Studs/Edge Angle is ongoing in sequence 1-2 on Mezzanine, Concourse and Suite Levels. Area 4 – Drilled Pier installation is ongoing near Column Line 1. Building the Future
  2. 2. Underground MEP: Deep Sanitary installation has started in Area 2. MEP Rough-in: Plumbing and Electrical rough-in on Concourse Level has started. Projected Activities occurring next Week: Field Level Area 2 – Deep Sanitary Line Mass Excavation: installation has started near Column Line 15. Grading at Area 3 will continue. Site Utilities: Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will continue. Storm Line 5000 and 4000 will begin. Deep Underground Plumbing: Deep Sanitary installation in Area 2 will continue. Foundations: Area 1 – Structural Steel Erection at West Area 2 Concourse Level – Footing/Grade Beam installation Building is ongoing in Sequence 1-4 (bays will begin. 28-31 shown). Area 3 Field Level – A-Line wall placement will begin Area 3 Mezzanine Level – Grade beam installation will begin. Structural Steel Erection: Erection of Structural Steel in Sequence 1-4 will continue. Decking/Detailing/Studs/Edge Plates will continue in Sequence 1-2. Field Level Area 1 – Shot looking north from Concourse Level. Building the Future
  3. 3. Additional Photos: Suite Level Area 1 – Edge plate being Concourse Level Area 1 – Plumbing rough-in installed between Column Lines 26 - 27. has started at north end. Mezzanine Level Area 4 – Grade Beam installation has started at Column Line 33 Press Level Area 1 – Steel being set in place (North Supporter’s Seating Area). that holds the precast seating tubs. Field Level Area 1 – Hydrotherapy Pit poured Field Level Area 1 – Column encasement and and backfilled. backfilling ongoing. Building the Future

×