Your SlideShare is downloading. ×
From:    Brandon Valdez                To: David Ficklin - OnGoal
                                                        ...
Structural Steel Erection:
 Area 1 –Detailing and decking in sequence 1-3 is ongoing.
 Erection of Steel Sequence 2-1 has ...
Concrete Flatwork:
 Area 1 Field Level – Concrete placement for slab-on-grade
 will begin.

 Structural Steel Erection:
 E...
Additional Photos:




Field Level Area 1 – Shot of Player’s field   Field Level Area 3 – Field wall footing
entry.       ...
Upcoming SlideShare
Loading in...5
×

Construction Update 7-6-2010

1,058

Published on

Published in: Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
1,058
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
10
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Transcript of "Construction Update 7-6-2010"

  1. 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 6.30.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 6.28.2010 Current Activities this Week: Mass Excavation: Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities: Storm Sewer installation (Line 1000) is ongoing along Concourse Level Area 2 – Underground Village West Parkway. plumbing rough-in for the Concourse Buildings is ongoing. Storm Line Installation (Line 600 and Sanitary Sewer Line E installation is ongoing on east side of France Family Dive is ongoing. Foundations: Area 3 Field Level – Isolated footing installation is Ongoing and is currently to Column Line 6. Area 4 Mezzanine Level – Excavation for D-Line footing Is ongoing and is currently to Column Line 40. Field Level Area 1 – Vapor barrier installation from column line 32-29 is placed Concrete Flatwork: in preparation for slab-on-grade placement. Area 1 – Mezzanine slab-on deck is complete, Main Concourse structural slab is complete, Suite Level slab on deck is complete, Press Level slab on deck is complete. Preparation for 1st pour of Field Level Area 1 slab-on-grade is ongoing. Area 1 – Precast concrete treads and riser installation is nearly complete between column lines 32-24. Building the Future
  2. 2. Structural Steel Erection: Area 1 –Detailing and decking in sequence 1-3 is ongoing. Erection of Steel Sequence 2-1 has started. Area 1 – Roof deck installation for entire West Building is nearly complete. Underground MEP: Electrical Secondary Distribution is ongoing in Area 3. Area 1 –Canopy Trusses are being delivered and staged in the infield. MEP Rough-in: Area 1 – Shallow electrical and plumbing rough-in has started at Field Level in preparation for 1st slab-on-grade pour. Metal Stud Framing: Area 1 Suite Level – Metal stud framing for Suites has started. Projected Activities occurring next Week: Area 1 – Shot of the West Building from the Mass Excavation: southeast. Backfilling of on-grade seating areas will continue in Area 3. Site Utilities: Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will continue. Storm Line 1000 will continue. Installation of Sanitary Line E will continue. Deep Underground MEP: Deep Sanitary and Electrical Distribution installation in Area 3 will continue. Roof Level Area 1 – Roof decking is nearly Foundations: complete. Area 3 Field Level – Foundation installation will continue. Area 4 Mezzanine Level – Foundation Wall installation will continue. Building the Future
  3. 3. Concrete Flatwork: Area 1 Field Level – Concrete placement for slab-on-grade will begin. Structural Steel Erection: Erection of Structural Steel in Sequence 2-1 will continue. Delivery of Roof Trusses for sequence 1-7 will continue Area 2 – Shot looking south of Terrace Area throughout the week. taking shape. Structural Precast: Erection of the precast tubs in Area 1 will begin. Underground MEP: Deep Sanitary installation will continue in Area 3. Electrical Secondary will continue in Area 3. MEP Rough-in: Plumbing and Electrical rough-in for Area 1 Field Level slab on grade will continue. Field Level Area 3 – Foundation installation is ongoing. Metal Stud Framing: Area 1 Suite Level – Metal stud framing for Suites will continue. Area 1 Press Level – Metal stud framing for Suites will begin. Building the Future
  4. 4. Additional Photos: Field Level Area 1 – Shot of Player’s field Field Level Area 3 – Field wall footing entry. concrete placed at column line 4. Suite Level Area 1 – Metal stud framing for Area 1 – Subgrade preparation for on-grade suites has begun. seating risers has started. Suite Level Area 1 – Duct straps being installed in preparation for ductwork Roof Level Area 1 – Shot of steel framing for installation. Freight Elevator “High Hat”. Building the Future

×