Construction Update 6-28-2010
Upcoming SlideShare
Loading in...5
×
 

Construction Update 6-28-2010

on

  • 854 views

 

Statistics

Views

Total Views
854
Views on SlideShare
712
Embed Views
142

Actions

Likes
0
Downloads
2
Comments
0

2 Embeds 142

http://www.kcwizards.com 140
http://www.sportingkc.com 2

Accessibility

Categories

Upload Details

Uploaded via as Adobe PDF

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

Construction Update 6-28-2010 Construction Update 6-28-2010 Document Transcript

  • From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 6.23.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 6.21.2010 Current Activities this Week: Mass Excavation: Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities: Storm Sewer installation (Line 6000) is ongoing on east side of France Family Drive. Storm Sewer installation Field Level Area 3 – Secondary electrical (Line 1000) has started at Village West Parkway. distribution is ongoing behind A-Line Wall. Sanitary Sewer Line E installation is ongoing on east side of France Family Dive. Foundations: Area 3 Field Level – Isolated footing installation is Ongoing and is currently to Column Line 8. Press Level Area 1 – Concrete placed for Area 4 Mezzanine Level – Excavation for D-Line footing Exterior walkway outside of the Upper Suite Is ongoing and is currently to Column Line 37. Lounge. Note the Ceremonial 1st Column in place. Concrete Flatwork: Area 1 – Mezzanine slab-on deck is complete, Main Concourse structural slab is complete, Suite Level slab on deck is complete, Press Level slab on deck is complete. Area 1 – Precast concrete treads and riser installation is ongoing between column lines 32-30. Building the Future
  • Structural Steel Erection: Area 1 –Steel Erection in sequence 1-3 is ongoing. Area 1 – Roof deck installation has started in Sequence 1-4 Underground MEP: Deep Underground Plumbing installation is ongoing in Area 3. Area 1 – 142’ long Canopy Trusses are starting to be delivered and staged in the Electrical Secondary Distribution is ongoing in Area 3. field. MEP Rough-in: Plumbing and Electrical rough-in for Field Level slab on grade is ongoing in Area 3. Projected Activities occurring next Week: Mass Excavation: Backfilling of on-grade seating areas will continue in Area 3. Area 1 – Shot of the West Building from the Site Utilities: southeast. Notice the precast risers at the Installation of the Storm Line 6000 on the East Side (France north end. Family Drive) of the site will continue. Storm Line 1000 will continue. Installation of Sanitary Line E will continue. Deep Underground Plumbing: Deep Sanitary installation in Area 3 will continue. Foundations: Area 3 Field Level – Foundation installation will continue. Area 4 Mezzanine Level – Foundation Wall installation will continue. Field Level Area 2 – Gang forms being installed for concrete placement at southeast corner. Building the Future
  • Concrete Flatwork: Area 1 Press Level – Concrete placement will begin. Structural Steel Erection: Erection of Structural Steel in Sequence 1-3 will continue. Roof decking installation on Sequence 1-4 will continue. Delivery of Roof Trusses for sequence 1-7 will continue throughout the week. Structural Precast: Field Level Area 2 – Shot looking south (from Erection of the precast risers in Area 1 will continue. Press Level Column Line 32) of Area 2. Underground MEP: Deep Sanitary installation will continue in Area 3. Electrical Secondary will continue in Area 3. MEP Rough-in: Plumbing and Electrical rough-in for Area 1 Field Level slab on grade will continue. Field Level Area 3 – Isolated footing installation is ongoing. Building the Future
  • Additional Photos: Field Level Area 3 – Shot looking south of A- Line foundation wall. Note openings in wall Rigging being installed on Canopy truss. for Supporters Section entrance. France Family Drive – Storm inlet structure installed at the west side of France Family Area 1 – Shot looking north of the West drive. Building. Note the curve of the building. Field Level Area 1 – Shotcrete wall weeps tie Press Level Area 1 – Roof Deck installation in to storm sewer is ongoing. has started in Sequence 1-4. Building the Future