Weekly Construction Update 06-14-10

  1. 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 6.9.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 6.7.2010 Current Activities this Week: Mass Excavation: Backfilling of on-grade seating is ongoing in Area 1, Area 2 and Area 3. Site Utilities: Storm Sewer installation (Line 6000) is ongoing on Field Level Area 1 – Shallow Underground east side of France Family Drive. plumbing pipe installation has started at Men’s Field Toilet 01.32.02. Sanitary Sewer Line E installation has started on east side of France Family Dive. Foundations: Area 2 Concourse Level – E-Line footing installation is ongoing and E-Line wall installation is ongoing. Area 3 Field Level – A-Line footing (to column line 1) and wall installation (to column line 4) is ongoing. Area 3 Field Level – Installation of Drilled Piers Field Level Area 3 – A-Line footing and wall are complete. installation is ongoing up to Column Line 1. Area 4 Mezzanine Level – D-Line grade beam installation is ongoing and wall forms are being set. Concrete Flatwork: Area 1 Mezzanine – North slab on metal deck at VIP Entry concrete is placed. Area 1 Concourse – Structural Slab is placed from Column lines 33-23. Mezzanine Level Area 1 – Concrete Slab on Metal Deck at VIP Entry is placed. Building the Future
  2. 2. Structural Steel Erection: Area 1 – Steel Erection in sequence 1-5 is nearly complete is currently to Column Line 23. Seven raker pieced remain. Decking/Detailing/Studs/Edge Angle is ongoing in sequence 1-2, 1-4 and 1-5. Underground MEP: Concourse Level Area 1 – Concrete Deep Sanitary installation is ongoing in Area 3. installation taking place from Column Lines C – 33. Electrical Secondary is ongoing in Area 2 MEP Rough-in: Plumbing and Electrical rough-in for concrete decks are ongoing Suite Level. Shallow plumbing rough-in has started at Area 1 Field Level. Projected Activities occurring next Week: Mass Excavation: Backfilling of on-grade seating areas will continue in Area 3. Area 1 – Structural Steel Erection at West Site Utilities: Building is nearly complete from Column Installation of the Storm Line 6000 on the East Side (France Line 33 – 23. Family Drive) of the site will continue. Storm Line 5000 and 4000 will begin. Installation of Sanitary Line E will continue. Deep Underground Plumbing: Deep Sanitary installation in Area 3 will continue. Foundations: Area 2 Concourse Level – Footing and wall installation will continue. Area 3 Field Level – A-Line wall placement will continue. Field Level Area 2 – Backfill of on-grade Area 4 Mezzanine Level – Foundation Wall installation will seating area between column lines 21-18 is ongoing. continue. Building the Future
  3. 3. Concrete Flatwork: Area 1 Suite Level – Concrete placement will begin. Structural Steel Erection: Erection of Structural Steel in Sequence 1-3 will begin. Decking/Detailing/Studs/Edge Plates will continue in Sequence 1-5. Field Level Area 2 – Isolated footing C12 reinforcing steel being installed. Underground MEP: Deep Sanitary installation will continue in Area 3. Electrical Secondary will continue in Area 2 MEP Rough-in: Plumbing and Electrical rough-in for concrete decks will begin at Press Level. Shallow plumbing rough-in will continue at Area 1 Field Level. Shallow electrical will begin at Area 1 Field Level. Suite Level Area 1 – Concrete slab reinforcing being installed in preparation for upcoming pour. Building the Future
  4. 4. Additional Photos: Area 1 – Shot looking south showing the field walls, foundations walls, rakers and Field Level Area 2/3 – Shot looking northeast west building. showing foundations from column line 15-1. Field Level Area 1 – Secondary electrical underground is ongoing near column line Concourse Level Area 2 – Footing excavation 21. for E-Line footing is ongoing. Field Level Area 2 – Shot looking south showing southeast vomitory, south on-grade Field Level Area 1 – Electrical manhole MH-1 seating, stage and southwest vomitory. is installed. Building the Future

×