Construction Update 4-21-2010

  1. 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 4/21/2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 4/19/2010 Current Activities this Week: Mass Excavation: Remaining Mass Excavation Activities are ongoing. Clarkson is working on backfilling On-Grade Seating Walls, Rock Excavation, and getting to grade. Site Utilities: Installation of the new electrical ductbank has ceased - approximately 150 linear feet is installed. Awaiting Area 2 – Rock Excavation at Column Line 13. BPU resolution on manhole tie-in. Boring of the service line and Sanitary Main Line D is complete, installation of the piping is nearly complete. Storm Sewer installation (Line 6000) has started on east side of France Family Drive. Concourse Level Area 2 – Waterline piping Foundations: installation is complete. Chlorination of Area 1 Field Level – Column Pad placement in Area 1 piping in progress. is nearly complete. Installation of North Field Walls and Intermediate Walls has started. Area 1 Mezzanine Level – Last of E-Line is being placed Today. Area 1 Concourse Level – Column Pad E-29 is being placed today. Remaining E-Line grade beam will be placed tomorrow Mezzanine Level Area 1 – Drilled Pier installation has commenced at D-Line. Building the Future
  2. 2. Area 2 Field Level – Excavation for the footings is ongoing to Column Line 16. Soil Nail Wall: Area 2 – Shotcrete installation on lifts 1-3 is complete. Rock Excavation for final lift has started. Structural Steel Erection: Field Bowl – Structural Steel Erection has started at Column Line 28. Field Level Area 1 – North Field Walls and Intermediate Walls taking shape. Deep Underground Plumbing: Sanitary piping is installed to Column Line 20. Underground Electrical: Secondary service ducts have been installed from Electrical Room 01.34.04 south past Column Line 27. Projected Activities occurring next Week: Mass Excavation: Backfilling on-grade seating walls, rock excavation and Field Level Area 1 – Structural Steel Erection Grading work will continue in Areas 1, 2 and 3. has started at Column Line 28 heading North. Site Utilities: Chlorination of relocated waterline should be completed. Installation of the Sanitary Manhole at the North end of Area 1 will begin. Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will continue. Deep Underground Plumbing: Sanitary in Area 2 will continue. Field Level Area 1 – Shot looking north from Concourse Level. Foundations: Area 2 Field Level – Placement of foundations up to Column Line 16 will continue. Building the Future
  3. 3. Area 1 Mezzanine Level – Grade Beam at D-Line Piers will begin. Area 1 Concourse Level – E-Line grade will be completed. Soil Nail Wall: Area 2 – Shotcrete wall installation on final lift will begin. Structural Steel Erection: Erection of Structural Steel Sequence 1-1 will continue to the north. Additional Photos: Concourse Level Area 1 – Backfill behind D- Mezzanine Level Area 1 – Placement of Line Wall is ongoing. reinforcing steel for D-Line Wall. Concourse Level Area 2 – Ductbank relocation on hold pending BPU Electric Field Level Area 1 – Wall Reinforcing Mats design. set in place at South East Vomitory. France Family Drive – Installation of Storm Mezzanine Level Area 1 – Waterproofing Line 6000 has started. installation at D-Line Wall. Building the Future

×