Construction Update 4-21-2010
Upcoming SlideShare
Loading in...5
×
 

Construction Update 4-21-2010

on

  • 635 views

KC Soccer Stadium construction update from Turner Construction.

KC Soccer Stadium construction update from Turner Construction.

Statistics

Views

Total Views
635
Views on SlideShare
614
Embed Views
21

Actions

Likes
0
Downloads
3
Comments
0

2 Embeds 21

http://www.kcwizards.com 17
http://www.sportingkc.com 4

Accessibility

Categories

Upload Details

Uploaded via as Adobe PDF

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

Construction Update 4-21-2010 Construction Update 4-21-2010 Document Transcript

  • From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 4/21/2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 4/19/2010 Current Activities this Week: Mass Excavation: Remaining Mass Excavation Activities are ongoing. Clarkson is working on backfilling On-Grade Seating Walls, Rock Excavation, and getting to grade. Site Utilities: Installation of the new electrical ductbank has ceased - approximately 150 linear feet is installed. Awaiting Area 2 – Rock Excavation at Column Line 13. BPU resolution on manhole tie-in. Boring of the service line and Sanitary Main Line D is complete, installation of the piping is nearly complete. Storm Sewer installation (Line 6000) has started on east side of France Family Drive. Concourse Level Area 2 – Waterline piping Foundations: installation is complete. Chlorination of Area 1 Field Level – Column Pad placement in Area 1 piping in progress. is nearly complete. Installation of North Field Walls and Intermediate Walls has started. Area 1 Mezzanine Level – Last of E-Line is being placed Today. Area 1 Concourse Level – Column Pad E-29 is being placed today. Remaining E-Line grade beam will be placed tomorrow Mezzanine Level Area 1 – Drilled Pier installation has commenced at D-Line. Building the Future
  • Area 2 Field Level – Excavation for the footings is ongoing to Column Line 16. Soil Nail Wall: Area 2 – Shotcrete installation on lifts 1-3 is complete. Rock Excavation for final lift has started. Structural Steel Erection: Field Bowl – Structural Steel Erection has started at Column Line 28. Field Level Area 1 – North Field Walls and Intermediate Walls taking shape. Deep Underground Plumbing: Sanitary piping is installed to Column Line 20. Underground Electrical: Secondary service ducts have been installed from Electrical Room 01.34.04 south past Column Line 27. Projected Activities occurring next Week: Mass Excavation: Backfilling on-grade seating walls, rock excavation and Field Level Area 1 – Structural Steel Erection Grading work will continue in Areas 1, 2 and 3. has started at Column Line 28 heading North. Site Utilities: Chlorination of relocated waterline should be completed. Installation of the Sanitary Manhole at the North end of Area 1 will begin. Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will continue. Deep Underground Plumbing: Sanitary in Area 2 will continue. Field Level Area 1 – Shot looking north from Concourse Level. Foundations: Area 2 Field Level – Placement of foundations up to Column Line 16 will continue. Building the Future
  • Area 1 Mezzanine Level – Grade Beam at D-Line Piers will begin. Area 1 Concourse Level – E-Line grade will be completed. Soil Nail Wall: Area 2 – Shotcrete wall installation on final lift will begin. Structural Steel Erection: Erection of Structural Steel Sequence 1-1 will continue to the north. Additional Photos: Concourse Level Area 1 – Backfill behind D- Mezzanine Level Area 1 – Placement of Line Wall is ongoing. reinforcing steel for D-Line Wall. Concourse Level Area 2 – Ductbank relocation on hold pending BPU Electric Field Level Area 1 – Wall Reinforcing Mats design. set in place at South East Vomitory. France Family Drive – Installation of Storm Mezzanine Level Area 1 – Waterproofing Line 6000 has started. installation at D-Line Wall. Building the Future